Sie sind auf Seite 1von 8

BORED PILING METHOD STATEMENT

RED PILING

METHOD

BORED PILING METHOD STATEMENT.

WORK

PROCEDURE

Ref No. FOUN/04


PROJECT:
PAGE 1 OF 2
SECTION:

DATE

FOUNDATIONS
SUBJECT:

Dec 2012
BY:

OF

ISSUE

QA/QC ENGINEER
APPROVED

BY:

BORED PILING
QEHS MANAGER
ACTION
1.

SCOPE

Project

VERIFY
Method

The scope of this procedure covers the Manager Statement


control of installation of Bored Cast-inSitu Concrete piles executed by a subSubApproved
contractor.
contractor
2.

.1

Project

Construction
Programme

Manager

Approval

PROCEDURE

Method

Statement:

A method statement shall be submitted


by the piling Sub-contractor for approval Subcon/
which
shall
include:

i)

Construction

ii)

Pile

iii)

Testing

design

FCC
procedure. Surveyor

with

calculations.

procedure.

iv) Documentation
to
be
maintained during the execution of

Field Book

work.

v)

Mix

design

for

concrete.

vi) Specification for reinforcement steel


and
bentonite
clay.

vii)
the

.2

Any other information required by


specification.

Construction

Programme:

The sub-contractor shall submit a


programme for approval based on the
Contract Programme. The subcontractor
shall also indicate the mobilisation time of
plant, equipment, materials and work
force.

.3

Piling

Sequence:

Approval of piling sequence will be given


prior to commencement of piling by the
Subcontractor.

.4

Setting-Out:

HEE will execute pre-piling setting out


and offer for cross-checking by
Subcontractors
Surveyor
and

Consultants Representative.

WORK

PROJECT:

PROCEDURE

Ref No. FOUN/04


PAGE 2 OF 2

SECTION:

DATE OF ISSUE

FOUNDATIONS

Dec 2012
BY:

SUBJECT:
QA/QC ENGINEER
APPROVED

BY:

BORED PILING
QHSE MANAGER
ACTION
.5

Source

Certificates: Project
Engineer

Reinforcement steel and Bentonite


test certificates if required shall be Project
obtained from the Subcontractor and, Engineer/
submitted for approval by the
Consultant.
Labtech.
.6

Concrete

Cube

VERIFY
Source
certificate

Test result,
FOUN/04/A

Pile testing
record

Testing:
Subcon.
Checksheet

Cube results will be assessed and


retained. The cube test reports shall QA/QC
be clearly identified with the location
of pour by reference to the
QA/QC
checksheet.

.7

Testing

of

Piles:

The Subcontractor shall carry out a

Non-

Conformity
Report

load test
specified

and
in

integrity test as
the
Contract.

.8 Inspection
Work/Checksheet:

of

The work shall be inspected using


the attached checksheet as Appendix
FOUN/04/A which shall be completed
as verification and record of
compliance.

.9

Non-Conformity:

Non-conforming workmanship shall


be notified to the Subcontractor as
Appendix 7/3/6/A and corrective
action taken in accordance with good
working practice and Consultants
approval.

PROJECT:

SITE NO.:

CHECK SHEET FOR BORED PILING

SUBCONTRACTOR:

Sheet No.

FATAYERJI

SECTION OF WORK ____________________________LOCATION


_________________

Checke
d
STAGE

ITEM
by

PREPARATION

1. Subcontractors
method statement
PE
approved.
2. Materials approved by
PE
the consultant.
3. Cross-check location
SU
of Pile.

APPROVAL TO
PROCEED
4. Check borehole to be
filled with Bentonite
INSTALLATION

QA/QC

GF
slurry at all times.
5. Check cleaning of
bottom of borehole.
6. Check reinforcement
cage.
7. Check minimum cover
while lowering cage into
the borehole.
8. Check slump of
concrete.
9. Check cut-off level +
location.
APPROVAL TO
PROCEED WITH PILE
CAP.

,CM Construction Manager


,QA/QC Quality Assurance/Quality Control
,PE Project Engineer

GF
SE
GF
Lab
SU
CM

DATE

,SE Site Engineer


,GF General Foreman
,SU Surveyor
Lab Laboratory Technician

Das könnte Ihnen auch gefallen