Beruflich Dokumente
Kultur Dokumente
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
Article information:
To cite this document:
S. Mahdi Hosseinian David G. Carmichael , (2014),"An optimal target cost contract with a risk neutral
owner", Engineering, Construction and Architectural Management, Vol. 21 Iss 5 pp. 586 - 604
Permanent link to this document:
http://dx.doi.org/10.1108/ECAM-01-2013-0003
Downloaded on: 14 June 2015, At: 07:42 (PT)
References: this document contains references to 57 other documents.
To copy this document: permissions@emeraldinsight.com
The fulltext of this document has been downloaded 137 times since 2014*
Access to this document was granted through an Emerald subscription provided by emerald-srm:534288 []
For Authors
If you would like to write for this, or any other Emerald publication, then please use our Emerald for
Authors service information about how to choose which publication to write for and submission guidelines
are available for all. Please visit www.emeraldinsight.com/authors for more information.
The current issue and full text archive of this journal is available at
www.emeraldinsight.com/0969-9988.htm
ECAM
21,5
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
S. Mahdi Hosseinian
School of Civil and Environmental Engineering,
The University of New South Wales, Sydney,
Australia and Bu-Ali Sina University, Hamedan, Iran, and
586
David G. Carmichael
School of Civil and Environmental Engineering,
The University of New South Wales, Sydney, Australia
Abstract
Purpose Target cost contracts are commonly used to share the monetary outcome of work or a
project. However, discussion is ongoing, as to what constitutes optimal sharing. The purpose of this
paper is to examine optimal sharing and derives a result for defined risk assumptions on the owner
(risk neutral) and contractor (risk-averse ranging to risk neutral).
Design/methodology/approach The derivation is based on solving a constrained maximization
problem using ideas from principal-agent theory. Practitioners were engaged in a designed exercise in
order to validate the approach and propositions. The influence of the contractors level of risk aversion,
the cost uncertainty and the contractors effort effectiveness are examined.
Findings The paper shows that, at the optimum, the sharing ratio between contractor and owner
needs to reduce and the fixed fee needs to increase when the contractor becomes more risk-averse, the
level of the cost uncertainty increases, or the effectiveness of the contractor effort decreases.
Practical implications The papers findings provide practitioners with a useful benchmark for
outcome sharing in target contracts.
Originality/value Existing work on outcome sharing in target contracts is limited to being qualitative
and anecdotal in nature. This paper extends existing knowledge by providing a quantitative treatment of
optimal sharing.
Keywords Construction, Contracts
Paper type Research paper
Introduction
Target cost contracts attempt to establish cooperative behaviour between the contracting
parties by sharing any project gains/losses or reward/risk, and to motivate the parties to
work towards the same project cost goal or target (Carmichael, 2000; Lahdenpera, 2010;
Love et al., 2011). A desire for cost savings, enhanced teamwork and the elimination
of adversarial behaviour lead an owner to use a target cost contract (Chan et al., 2011a),
with a desired result of a successful project (Carmichael, 2000; Turner and Simister, 2001;
Broome and Perry, 2002).
However, concerns exist about the design of appropriate outcome sharing
arrangements (Ward and Chapman 1994; Badenfelt, 2008), which are seen as central
to achieving project goals (Rahman and Kumaraswamy, 2002; El-Sayegh, 2008;
Lahdenpera, 2010). In construction projects with large risk (Lahdenpera, 2010),
inappropriate sharing arrangements may create an atmosphere of hostility that can
reduce a contractors performance (Bresnen and Marshall, 2000), generate disputes
(Rahman and Kumaraswamy, 2005) and promote a reluctance to tender for future work
(Zaghloul and Hartman, 2003; Chan et al., 2011b). Previous research has highlighted
that a sharing arrangement should be tailored to particular project circumstances, and
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
should fairly distribute risks and rewards between the parties, though how fair and
unfair are defined is not stated. (Bower et al., 2002; Love et al., 2011; Badenfelt, 2008).
A number of researchers have examined outcome sharing. However, the underlying
justification for any recommendations made is not always clear. Badenfelt (2008) notes
that outcome sharing in projects is often established in an arbitrary way and not based
on scientific evidence or mathematical modelling. Hughes et al. (2012) and Badenfelt
(2008) recommend that future studies develop appropriate sharing arrangements. Tang
et al. (2008), Broome and Perry (2002) and Uher and Toakley (1999) share a similar
perception about the lack of research in outcome sharing arrangements tailored to
the construction industry. Despite a current trend towards the use of target contracts
(Chan et al., 2011b), only a few studies have looked at optimal sharing arrangements.
This paper fills part of this gap in knowledge, by investigating the outcome sharing
problem in contracts with defined risk assumptions on the owner and contractor.
The term outcome, in this paper, refers to a projects monetary outcome expressed
relative to a target that is desired by the owner, for example, with respect to cost
underruns/overruns. The term risk neutral is used here in the sense of Clemen
and Reilly (2001) and Kraus (1996) to refer to those who do not care about risk, and
can disregard risk associated with different alternatives in decision making. The term
risk-averse is used here in the sense of Clemen and Reilly (2001) to refer to those who
avoid risk, are afraid of risk, or are sensitive to risk. The term risk is used here in
the sense of Al-Bahar and Crandall (1990) and Carmichael (2004) to mean exposure
to the chance of occurrence of events adversely or favourably affecting the project
as a consequence of uncertainty.
The derivation presented here is based on solving a constrained maximization
problem using ideas from principal-agent theory. The paper looks at the influence on
the optimal outcome sharing of the contractors level of risk aversion, cost uncertainty
and the contractors effort effectiveness.
The paper is original and will be of interest to academics and practitioners (owners,
contractors and design consultants) interested in the design of target contracts. It
proposes a solution to the problem of optimal sharing of a projects outcome between a
risk-neutral owner and a contractor (risk-averse ranging to risk neutral). As well, the
paper casts new light on establishing optimal sharing arrangements in the construction
industry and it provides those who design target contracts with recommendations on
outcome sharing. By exploring optimal sharing, both theoretically and empirically, the
paper contributes an enhanced understanding of the nature of optimal outcome sharing
within projects, over that currently existing. The paper also contributes to principalagent theory by expanding its applicability to construction contracts, and beyond its
traditional home of sales, advertising and the like (Lal and Srinivasan, 1993; Zhao, 2005).
The paper is organized as follows. First, existing approaches to outcome sharing
and the background to principal-agent theory are given. Discussion on optimal
outcome sharing arrangements is then given. Applying the results to construction
projects leads to the development of the papers propositions, which are assessed based
on a designed exercise.
Literature review
A number of publications address sharing arrangements in construction contracts. For
example, Al-Subhi Al-Harbi (1998) uses utility theory to explain how owners and
contractors determine the best sharing arrangement. Badenfelt (2008), via interviews
with construction clients and contractors, finds that any outcome sharing arrangement
An optimal
target cost
contract
587
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
588
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
effective in curbing agent opportunism (Shavell, 1979; Weitzman, 1980; Holmstrom and
Milgrom, 1987). Such contracts align the agents interests with those of the principal,
but at the price of transferring risk to the agent.
Based on principal-agent theory thinking, the following section looks at a constrained
maximization problem expressed in terms of a projects outcome, the contractors fee, and
the utilities of the owner and contractor. The solution of the optimization problem leads
to the optimal outcome sharing result for target contracts.
Theoretical development
Consider an owner contemplating engaging a contractor. The owner is not able to fully
monitor the contractors effort, but the owner is able to measure the monetary outcome
of the work. The problem examined is how this outcome should be shared between the
owner and the contractor.
The works monetary outcome, x, is affected by the contractors effort, e, and events
which are outside of the contractors influence, denoted by e. e is assumed to be
normally distributed with a mean of zero and variance s2 (Holmstrom and Milgrom,
1987). For convenience, x is assumed to be a linear function of the contractors effort:
x ke e
Here n is a sharing ratio distributing the outcome between the contractor and the owner,
defined as the proportion going to the contractor, and taking values in the range 0-1.
The owner is assumed to be risk-neutral and its utility (or payoff), in monetary
units, is the difference between the works monetary outcome received and the fee paid.
Using Equations (1) and (2), the owners expected utility is given by:
EU o Ex Fee
1 nkeF
An optimal
target cost
contract
589
ECAM
21,5
The contractor wishes, through choice of effort e, to maximize its expected utility
or its certainty equivalent. A certainty equivalent is a fee that is the same in the
contractors mind to a corresponding situation that involves uncertainty, and equals
expected fee minus the cost of its effort, C(e), minus a risk premium:
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
590
Risk premium is defined as the cost compensating the contractor for the risk borne
(Clemen and Reilly, 2001) and is given by:
Risk Premium
n2 rs2
2
The expected fee to the contractor can be obtained by substituting Equation (1) into
Equation (2), while noting that E[e] 0:
EFee F nke
Following Holmstrom and Milgrom (1987, 1991), the contractors cost function C(e) is
assumed to increase with e at an increasing rate. The simplest functional form that
meets this requirement can be written as:
b
Ce e2
2
Optimization
The owners problem is to offer a contract with a fee defined as in Equation (2), in order
to maximize its expected utility:
Max1 n keF
n;F
10
This contract needs to include a minimum fee, MinFee, required by the contractor to
motivate the contractor to agree to the contractual arrangement:
b
n2 rs2
F nke e2
XMinFee
2
2
11
The contractor selects the effort level that maximizes its certainty equivalent. As a
consequence, the effort level the owner favours needs to maximize the contractors
certainty equivalent:
b
n2 rs2
Max F nke e2
e
2
2
12
Maximizing expression (12) with respect to e yields the optimal level of effort:
k
e n
b
13
An optimal
target cost
contract
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
The optimal value of F is such that expression (11) holds as an equality, that is:
b
n2 rs2
F MinFee nke e2
2
2
591
14
Substituting Equations (13) and (14) into (10), the owners problem can be restated as:
Max
n
k2
k2
n2 rs2
n MinFee n2
b
2b
2
15
Differentiating expression (15) with respect to n and setting to zero, the optimal sharing
ratio is obtained by:
n
1
1 rs2 b=k2
16
Substituting Equations (13) and (16) into (14) provides the optimal fixed fee:
F MinFee
1
k2
rs2
n2
2
b
17
18
19
where n* and F* are obtained from Equations (16) and (17), respectively. Similar
optimal target formulae can be developed based on target durations and target quality.
In practice, a risk cap may be set by some contracts so that a small return margin or
zero loss is guaranteed to the contractor; however, this can lead to extra cost to the
owner (Carmichael, 2000).
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
The cost of the risk borne by the contractor (risk premium) is directly affected by
the contractors risk attitude, level of uncertainty and contractor effectiveness, based on
Equations (16) and (17):
.
The sharing ratio needs to increase and the fixed fee needs to reduce as a
contractor becomes less risk-averse. As the level of risk aversion continues to
increase, the risk premium becomes too large, forcing the owner to reduce
the sharing ratio and to increase the fixed fee in order to retain the contractor.
The sharing ratio needs to increase and the fixed fee needs to reduce as the
effectiveness, k, of the contractors effort towards the actual cost increases;
the opposite occurs when the contractors effort effectiveness decreases.
592
The results presented here are applicable provided the following assumptions hold:
.
The works final cost is normally distributed. The central limit theorem supports
this assumption where the works final cost is comprised of the sum of many
component costs (Ang and Tang, 1975).
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
P3. With increasing effectiveness of the contractors effort towards the actual
cost: (P3a) the sharing ratio needs to increase, and (P3b) the fixed fee needs to
decrease.
Empirical study outline
To support the above findings an empirical outcome sharing study was carried out. This
was based on a designed interview of a sample of 60 construction contractors.
The contractors involved in the empirical study were from mid-sized companies,
typically pursuing projects in the range of $5M-$15M. The participants were instructed
to act as corporate decision makers, not as private individuals dealing with their own
funds, and to make decisions based on usual practice, workload and economic conditions
(Hosseinian and Carmichael, 2013b). This was so because the economic situation may
have affected their responses (Willenbrock, 1973). Before starting the interviews proper,
a pilot study was conducted with a number of experienced contractors, in order to fine
tune and validate the study.
An optimal
target cost
contract
593
Contractor sample
The backgrounds of the participants are shown in Table I. Approximately 43.3 per cent
of the interviewees were project managers, 26.7 per cent were contract managers,
21.7 per cent were executive directors and 8.3 per cent were construction managers.
The number of projects in which the participants have been involved is considerable as
shown in Table I; approximately 43 per cent of the contractors were engaged in more
than 26 projects, and 47 per cent of the contractors between 5 and 25 projects.
Approximately 46 per cent of the contractors had more than 21 years of experience in
the construction industry, and 33 per cent of the contractors between 11 and 20 years as
illustrated in Table I. Because the experience of the participants in the construction
industry is quite extensive, induction based on their responses could be regarded as
very persuasive.
Interview parts
The interview questions were based on this papers theoretical findings, and consisted
of three parts: first, contractor risk attitudes and levels of risk aversion; second, the
influence on the sharing ratio, n, and the fixed fee, F, of level of contractor risk
aversion; and third, the influence on the sharing ratio and the fixed fee of actual cost
uncertainty and contractor effort effectiveness towards the actual cost.
(i). Contractor risk attitudes and levels of risk aversion. The participants utility
functions and levels of risk aversion were established using the method of certainty
equivalence (Clemen and Reilly, 2001). This involved offering each contractor a series
of hypothetical, uncertain contracts (choice 1) with a 50-50 chance of either gaining
b1Tc or gaining/losing b2Tc; where Tc is the target cost estimate of the work. Given
Age (years)
o30
30-35
35-40
40-45
45-50
50-55
55-60
460
%
1.7
6.7
20.0
16.7
20.0
16.7
10.0
8.3
Experience (years)
o5
5-10
11-15
16-20
21-25
26-30
31-35
435
%
3.3
16.7
21.7
11.7
20.0
8.3
10.0
8.3
Number of projects o5
5-15
16-25
26-35
36-45
46-55
455
%
10.0
26.7
20.0
16.7
11.7
6.7
8.3
Position
Project manager Contract manager Executive director Construction manager
%
43.3
26.7
21.7
8.3
Table I.
Age, experience,
involvement in projects,
and positions of the
participants in the study
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
594
Table II.
Cost variances for
different scenarios due to
events outside of the
contractors influence
b1 and b2, the participants were required to evaluate the values of their certainty
equivalents (CEs) (choice 2) such that they would be indifferent between (choice 1) and
(choice 2). The contractors utility function is then inferred from the choices made.
To frame the size of the work and complexity, contractors were asked to make their
decisions in scenarios similar to that in which they would usually operate. A target cost
of $10 M, representing the approximate mid-point value of the projects for the sample
of contractors, was used.
The level of risk aversion was obtained by asking the contractors to consider a
hypothetical contract that has equal chances of gaining aTc or losing half of that
amount. a is a constant, which varies between 0 and 1. The value of a is adjusted
during the study. The largest value of aTc is approximately equal to the decision
makers risk tolerance. The inverse of the risk tolerance equals the level of risk aversion
(Clemen and Reilly, 2001).
(ii) Effect of risk aversion on sharing ratio and fixed fee. For a fee, defined as in
Equation (18), the contractors were asked to choose the preferred value of n. To keep
the fixed fee, F, constant, the participants were asked to decide on the value of n, where
F equals 0.1Tc. The target cost, Tc, was kept the same as in part (i). The contractors
were told to consider the level of uncertainty in the actual cost of the project similar to
the uncertainty in the projects that they usually carry out.
To examine the impact of the level of risk aversion on the fixed component of the
contractors fee (for a fee defined as in Equation 1), the sample contractors were asked
to choose a minimum amount for F as their tendered fee, such they would not agree to
the contractual arrangement for any lesser amount. Keeping the sharing ratio, n,
constant at 0.5, the contractors were asked to decide on the value of tendered F. The
target cost, Tc, was kept the same. In order to limit the contractors response, the
contractors were required to select the preferred value of tendered F between 0.05Tc to
0.15Tc. This mentioned range covers the fee amount that the contractors commonly
receive from their usual projects, although fees outside this range can occur, depending
on the industry sector and the type, size and complexity of the project.
(iii) Effect of cost uncertainty on sharing ratio and fixed fee. For a fee defined as in
Equation (18), the contractors were asked to choose the value of n and the tendered
F for five different scenarios. Each scenario provided the contractors with different
levels of uncertainty in the actual cost of the work due to events outside of the
contractors influence, as shown in Table II. As an example, in Scenario 3 the
contractors were told that the optimistic, most likely and pessimistic actual cost values
equalled 0.90Tc, Tc and 1.10Tc, respectively. The contractors were asked to consider
the level of uncertainty in the projects that they regularly carry out as the usual
uncertainty mentioned in Table II. In this table the actual cost variances are calculated
using the PERT-style approximation based on optimistic (a) and pessimistic (c) values,
Scenario
Uncertainty level
1
2
3
4
5
No
Very low
Low
Usual
High
Optimistic
Project cost
Pessimistic
1.00Tc
0.95Tc
0.90Tc
0.85Tc
0.75Tc
1.00Tc
1.05Tc
1.10Tc
1.15Tc
1.25Tc
Most likely
s2/Tc2
Tc
0.0000
0.0003
0.0011
0.0025
0.0070
An optimal
target cost
contract
595
C3-C8
6.7
C9-C16
8.3
C17-C26
10
C27-C32
12.5
C33-C36
14.3
C37-C40
16.7
C41-C44
20
C45-C46
25
Table III.
High
Ranking risk attitudes of
C47-C48 the sample of contractors;
33.3
Ci refers to contractor i
C1 and C2
C3 to C8
0.8
Utility
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
namely, [(ca)/6]2 (Carmichael, 2006). Similarly to above, keeping the fixed fee, F,
constant, the contractors were asked to select the value of n, where F equals 0.1Tc.
Keeping the sharing ratio, n, constant at 0.5, the contractors were asked to decide on
the value of tendered F. The target cost, Tc, value of $10 M was kept the same.
(iv) Influence of the effectiveness of the contractors effort towards the actual cost, on
sharing ratio and fixed fee. For a fee defined as in Equation (18), the contractors
were asked to choose the value of n and the tendered fee, F, for a scenario where
the effectiveness of the contractors effort towards the actual cost increases.
The contractors chose the value of n and the tendered fee when the effectiveness
of their effort towards the actual cost was more than that of their usual projects.
The contractors were asked to make their decisions based on projects where early
involvement of the contractor is required. Here projects with early involvement of the
contractor represent projects where the contractors effort effectiveness towards
the actual cost increases. Similarly to above, keeping the fixed fee, F, constant, the
contractors were asked to select the value of n where F equals 0.1Tc. Keeping
the sharing ratio, n, constant at 0.5, the contractors were asked to decide on the value
of the tendered fee, F. The target cost, Tc, value of $10 M was kept the same.
C9 to C16
C17 to C26
0.6
C27 to C32
0.4
C33 to C36
C37 to C40
0.2
C41 to C44
C45 and C46
0
0
0.05
0.1
0.15
0.2
0.25
Figure 1.
Utility functions for
contractors
596
1.0
0.15
0.8
0.12
0.6
0.09
0.4
0.06
Fixed fee / Tc
Figure 2.
The relation between fixed
fee (F) and sharing ratio
(n) as a function of level of
risk aversion; data and
best-fit curves
Sharing ratio
0.03
0.2
Sharing ratio Fixed fee
0.00
0.0
0
10
15
20
25
30
35
r = 5.0/Tc
1.0
r = 6.7/Tc
r = 8.3/Tc
0.8
Sharing ratio
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
r = 10.0/Tc
r = 12.5/Tc
0.6
r = 14.3/Tc
0.4
r = 16.7/Tc
r = 20.0/Tc
Figure 3.
Influence of uncertainty in
the actual cost of the work
on sharing ratio
0.2
0.0
0.000
r = 25.0/Tc
r = 33.3/Tc
0.002
0.004
0.006
0.008
Influence of the effectiveness of the contractors effort towards the actual cost, on sharing
ratio and fixed fee
Figure 5 shows the average value of the sharing ratio selected by the contractors where
the effectiveness of the contractors effort towards the actual cost increases, called
higher effectiveness in Figure 5. It compares these results with those obtained for
projects that the contractors usually carry out without any need for early involvement
of the contractor, called usual effectiveness in Figure 5.
Figure 5 supports the validity of the theoretical results in terms of the relationship
between the sharing ratio and the effectiveness of the contractors effort towards the
actual cost (Equation (2)). It shows that an increase in the value of the sharing ratio, n,
follows from an increase in the effectiveness of the contractors effort towards the
actual cost. This supports P3a.
Figure 6 shows the equivalent results for the fixed fee selected by the contractors.
It supports the validity of the theoretical results in terms of the relationship between the
tendered fixed fee, F, and the effectiveness of the contractors effort towards the actual cost
(Equation (3)). It shows that a decrease in the value of the fixed fee follows from an increase
in the effectiveness of the contractors effort towards the actual cost. This supports P3b.
0.16
r = 33.3/Tc
0.14
r = 25.0/Tc
Fixed fee / Tc
An optimal
target cost
contract
597
r = 20.0/Tc
0.12
r = 16.7/Tc
0.10
r = 14.3/Tc
0.08
r = 12.5/Tc
0.06
r = 10.0/Tc
0.04
r = 8.3/Tc
0.02
r = 6.7/Tc
r = 5.0/Tc
0.00
0.000
0.004
0.002
0.006
0.008
Figure 4.
Influence of actual
cost uncertainty on
the fixed fee
0.9
0.8
Higher effectiveness
0.7
Sharing ratio
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
Figure 4 shows that an increase in the fixed fee follows from an increase in the level of
cost uncertainty, reflecting the contractors concern about uncertainty in the actual cost
of the work. This supports P2b.
Usual effectiveness
0.6
0.5
0.4
0.3
0.2
0.1
0.0
0
10
15
20
25
30
35
Figure 5.
Influence of the
effectiveness of the
contractors effort towards
the actual cost, on the
sharing ratio
598
Recommendations
The data derived from the participants can be used to develop a set of recommendations
for outcome sharing. In the cumulative frequency plot of the Table IV data, the level of
risk aversion of the sample contractors has been classified into three groups low,
medium and high. The results that follow are relatively insensitive to the choice of
boundaries between these classifications. By calculating the average sharing ratios
presented in Figure 3, for the risk aversion classification, recommended values of sharing
ratios can be obtained Table IV for three levels of cost uncertainty (low, usual and high)
as defined in Table II.
In Table IV the sharing ratio varies from 0.75 to 0.20. The highest sharing ratio
needs to be used in work with low cost uncertainty where a low risk-averse contractor
is engaged. By contrast, the lowest sharing ratio needs to be offered to a high riskaverse contractor in high cost uncertainty work.
Where there is little or no information about both the cost uncertainty and the
contractors level of risk aversion, the average value of the sharing ratio is recommended.
This average equals 0.45, which is obtained from data presented in Table IV.
Using the data presented in Figure 4, for a sharing ratio of 0.5, the averages of the
fixed fee selected by the sample contractors for different levels of cost uncertainty and
contractor risk attitude are summarized in Table V. The lowest fixed fee corresponds to a
low risk-averse contractor, with low cost uncertainty in the work; the highest fixed fee
corresponds to a high risk-averse contractor, with high cost uncertainty in the work.
Based on data presented in Figure 5, Table VI presents the recommend values of
sharing ratios for projects with early and usual contractor involvement. The highest
sharing ratio (n 0.8) needs to be used in work with early involvement of the
contractor where a low risk-averse contractor is engaged. By contrast, the lowest
sharing ratio (n 0.25) needs to be offered to a high risk-averse contractor in non-early
contractor involvement.
0.14
0.12
Fixed fee / Tc
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
Figure 6.
Influence of the
effectiveness
of the contractors effort
towards the actual cost,
on the fixed fee
Table IV.
Recommended values of
sharing ratios for different
levels of uncertainty and
contractor risk attitude
0.10
0.08
Usual effectiveness
0.06
Higher effectiveness
0.04
0.02
0.00
0
10
20
30
40
Cost uncertainty
Low
High
Low
Usual
High
0.75
0.55
0.40
0.60
0.45
0.35
0.40
0.25
0.20
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
Based on the data presented in Figure 6, using a sharing ratio of 0.5, Table VII presents
the averages of the fixed fee selected by the sample contractors for early contractor
involvement and usual contractor involvement. According to Table VII, the lowest fixed
fee needs to be used for a low risk-averse contractor with early involvement. By contrast,
the highest fixed fee needs to be offered to a high risk-averse contractor with no early
contractor involvement.
Discussion
The above findings highlight the influence on the optimal outcome sharing of the
contractors level of risk aversion, cost uncertainty and the contractors effort effectiveness,
and how they should be acknowledged in any outcome sharing arrangement. Al-Subhi
Al-Harbi (1998) suggests that the contractor needs to be open about its risk attitude and,
in particular, its level of risk aversion. This will assist the owner and contractor in
reaching agreement on the optimal outcome sharing. In practice, it may be difficult to
assess the contractors level of risk aversion, because of commercially and politically
sensitive issues. In the situation where there is little or no information about the
contractors level of risk aversion, practitioners will find Tables IV-VII useful for selecting
an appropriate outcome sharing. Ignoring the optimal outcome sharing may translate into
an unattractive risk for contractors, resulting in a conflict of interest between the
contracting parties and perhaps putting the projects success at stake. Barnes (1983)
claims that owners in such situations have problems getting their work completed to a
satisfactory standard without substantial additional costs.
It is acknowledged that there may exist parameters affecting the selection of the
optimal sharing ratio and fixed fee other than those considered in this paper, and this
could be the subject of future research. Considering together all parameters that may
affect an optimal outcome sharing would lead to a complicated analysis, the results of
An optimal
target cost
contract
599
Cost uncertainty
Low
Risk aversion
Medium
High
Low
Usual
High
0.08
0.10
0.11
0.09
0.11
0.12
0.12
0.13
0.14
Table V.
Average values of
Fixed fee/Tc
Table VI.
Recommended values of
sharing ratios for early
and usual contractor
involvement vs different
levels of contractor risk
attitude
Contractor involvement
Low
Risk aversion
Medium
High
Early
Usual
0.80
0.55
0.65
0.45
0.40
0.25
Contractor involvement
Low
Risk aversion
Medium
Early
Usual
0.08
0.10
0.09
0.11
Table VII.
Comparison between
High
average values of Fixed
fee/Tc for work with early
and usual contractor
0.12
involvement
0.13
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
600
which may be difficult for practitioners to use. Petersen (1993) argues that few
owners or contractors would contemplate taking the advice offered by very
complicated models. Although some assumptions are considered in deriving an
optimal outcome sharing, the insight gained from the results does address the problem
of the selection of the optimal sharing ratio and fixed fee. Weitzman (1980) argues
that economic models may operate in accordance with some simplification of reality,
but these models usually lead to significant insights into the nature of the problems
that they address.
This paper does not attempt to describe the way in which owners and contractors
make decisions in selecting a sharing arrangement. Rather, the paper indicates what
a rational decision maker would do. In construction projects with a high level of
uncertainty, the papers findings have a valuable role to play for decision makers
(owners, contractors) who are familiar with the concept of utility, expected utility and
optimization. Accordingly, the papers derived results give useful insight into the
outcome sharing problem. Knowing the factors that influence the optimal form
of sharing ratio and fixed fee can facilitate the process of negotiation between the
owner and the contractor to reach an agreement on the form of the optimal target
arrangement. The authors do not regard the derived results as a perfect solution to the
outcome sharing problem. Instead, it is more sensible to think of the derived results as
providing a better understanding of the sharing problem in construction.
Conclusions
This paper derives a result for the optimal outcome sharing in target cost contracts
under defined risk assumptions on the contractor (risk-averse ranging to risk neutral)
and the owner (risk neutral), and fills a knowledge gap in the literature. The paper
proposes an original solution to the problem of establishing optimal parameters in
target relationships; thereby, contributing to knowledge on target cost contracts. It is
found that the sharing ratio needs to reduce and the fixed fee needs to increase for
increasing contractor level of risk aversion. It is also found that the sharing ratio needs
to reduce and the fixed fee needs to increase for increasing actual cost uncertainty and
reducing contractor effort effectiveness towards the actual cost. The optimization
results presented in this paper may be used by contracting parties in the design of their
contracts, or as optimal benchmarks by which contracts designed differently, may be
compared. Although this paper refers primarily to construction projects, the solutions
presented here apply equally to related project types.
Limitations
The results presented in this paper are applicable provided the following assumptions,
discussed in the body of the paper, hold: the contractor is risk-averse and the owner is
risk-neutral; potential contractors have appropriate skills, and a projects final cost is
normally distributed.
The. theoretical results and the papers propositions were supported through
conducting an empirical study based on interviewing a sample of risk-averse
contractors. The study was based on a group of medium-sized contractors in the
commercial and building fields, and hence the support for the theoretical results
is limited to similar situations, until further data are assembled. Similarly, the
recommended values of the sharing ratio and the fixed fee are based on the data
collected from a group of medium-sized contractors, and hence their validity is limited
to similar situations.
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
References
Al-Bahar, J.F. and Crandall, K.C. (1990), Systematic risk management approach for construction
projects, Journal of Construction Engineering and Management, Vol. 116 No. 3,
pp. 533-546.
Al-Subhi Al-Harbi, K.M. (1998), Sharing fractions in cost-plus-incentive-fee contracts,
International Journal of Project Management, Vol. 16 No. 2, pp. 73-80.
Ang, A.H.S. and Tang, W. (1975), Probability Concepts in Engineering Planning and Design, Vol. I,
John Wiley and Sons, New York, NY.
Badenfelt, U. (2008), The selection of sharing ratios in target cost contracts, Engineering,
Construction and Architectural Management, Vol. 15 No. 1, pp. 54-65.
Baiman, S. (1990), Agency research in managerial accounting: a second look, Accounting,
Organizations and Society, Vol. 15 No. 4, pp. 341-371.
Barnes, M. (1983), How to allocate risks in construction contracts, International Journal of
Project Management, Vol. 1 No. 1, pp. 24-28.
Bower, D., Ashby, G., Gerald, K. and Smyk, W. (2002), Incentive mechanisms for project
success, Journal of Management in Engineering, ASCE, Vol. 18 No. 1, pp. 37-43.
Bresnen, M. and Marshall, N. (2000), Motivation, commitment and the use of incentives in
partnerships and alliances, Construction Management and Economics, Vol. 18 No. 5,
pp. 587-598.
Broome, J. and Perry, J. (2002), How practitioners set share fractions in target cost contracts,
International Journal of Project Management, Vol. 20 No. 1, pp. 59-66.
Bubshait, A. (2003), Incentive/disincentive contracts and its effects on industrial projects,
International Journal of Project Management, Vol. 21 No. 1, pp. 63-70.
Carmichael, D.G. (2000), Contracts and International Project Management, A. A. Balkema,
Rotterdam.
Carmichael, D.G. (2004), Project Management Framework, A. A. Balkema, Rotterdam.
Carmichael, D.G. (2006), Project Planning, and Control, Taylor and Francis, Oxford.
Chan, D.W.M., Chan, A.P.C., Lam, P.T.I. and Wong, J.M.W. (2011a), An empirical survey of the
motives and benefits of adopting guaranteed maximum price and target cost contracts in
construction, International Journal of Project Management, Vol. 29 No. 5, pp. 577-590.
Chan, J.H.L., Chan, D.W.M., Lam, P.T.I. and Chan, A.P.C. (2011b), Preferred risk allocation in
target cost contracts in construction, Facilities, Vol. 29 Nos 13/14, pp. 542-562.
Clemen, R.T. and Reilly, T. (2001), Making Hard Decisions with Decision Tools, Duxbury/
Thomson Learning, Pacific Grove, CA.
Coughlan, A.T. and Sen, S.K. (1989), Salesforce compensation: theory and managerial
implications, Marketing Science, Vol. 8 No. 4, pp. 324-342.
Eisenhardt, K.M. (1989), Agency theory: an assessment and review, The Academy of
Management Review, Vol. 14 No. 1, pp. 57-74.
El-Sayegh, S.M. (2008), Risk assessment and allocation in the UAE construction industry,
International Journal of Project Management, Vol. 26 No. 4, pp. 431-438.
Hauck, A., Walker, D., Hampson, K. and Peters, R. (2004), Project alliancing at National
Museum of Australia collaborative process, Journal of Construction Engineering and
Management, Vol. 130 No. 2, pp. 143-152.
Holmstrom, B. (1979), Moral hazard and observability, The Bell Journal of Economics, Vol. 10
No. 1, pp. 74-91.
Holmstrom, B. and Milgrom, P. (1987), Aggregation and linearity in the provision of
intertemporal incentives, Econometrica, Vol. 55 No. 2, pp. 303-328.
An optimal
target cost
contract
601
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
602
Hosseinian, S.M. and Carmichael, D.G. (2013b), An optimal incentive contract with a risk-neutral
contractor, ASCE Journal of Construction Engineering and Management, Vol. 139 No. 8,
pp. 899-909.
Hosseinian, S.M. and Carmichael, D.G. (2013c), An optimal outcome sharing arrangement in
construction contracts with a consortium of contractors, Journal of Civil Engineering and
Management (in press).
Hosseinian, S.M. and Carmichael, D.G. (2013d), An optimal multiple outcomes sharing
arrangement in construction target contracts, Journal of Financial Management of
Property and Construction (in press).
Hughes, D., Williams, T. and Ren, Z. (2012), Is incentivisation significant in ensuring successful
partnered projects?, Engineering, Construction and Architectural Management, Vol. 19
No. 3, pp. 306-319.
Jensen, M.C. and Meckling, W.H. (1976), Theory of the firm: Managerial behaviour,
agency costs and ownership structure, Journal of Financial Economics, Vol. 3 No. 4,
pp. 305-360.
Kirkwood, C.W. (2004), Approximating risk aversion in decision analysis applications, Decision
Analysis, Vol. 1 No. 1, pp. 51-67.
Kraus, S. (1996), An overview of incentive contracting, Artificial Intelligence, Vol. 83 No. 2,
pp. 297-346.
Lahdenpera, P. (2010), Conceptualizing a two-stage target-cost arrangement for competitive
cooperation, Construction Management and Economics, Vol. 28 No. 7, pp. 783-796.
Lal, R. and Srinivasan, V. (1993), Compensation plans for single-and multi-product salesforces:
an application of the Holmstrom-Milgrom Model, Management Science, Vol. 39 No. 7,
pp. 777-793.
Love, P.E.D., Davis, P.R., Chevis, R. and Edwards, D.J. (2011), Risk/reward compensation model
for civil engineering infrastructure alliance projects, Journal of Construction Engineering
and Management, Vol. 137 No. 2, pp. 127-136.
McGeorge, D. and Palmer, A. (2002), Construction Management New Directions, 2nd ed., Blackwell
Science, Oxford.
Perry, J.G. and Barnes, M. (2000), Target cost contracts: an analysis of the interplay between fee,
target, share and price, Engineering, Construction and Architectural Management, Vol. 7
No. 2, pp. 202-208.
Petersen, T. (1993), The economics of organization: the principal-agent relationship, Acta Sociologica,
Vol. 36 No. 3, pp. 277-293.
Rahman, M.M. and Kumaraswamy, M.M. (2002), Risk management trends in the construction
industry: moving towards joint risk management, Engineering Construction and
Architectural Management, Vol. 9 No. 2, pp. 131-151.
Rahman, M.M. and Kumaraswamy, M.M. (2005), Assembling integrated project teams
for joint risk management, Construction Management and Economics, Vol. 23 No. 4,
pp. 365-375.
Ross, J. (2003), Introduction to project alliancing, available at: www.pci-aus.com/files/resources/
Alliancing_30Apr03_F.pdf (accessed 15 December 2012).
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
Sakal, M.W. (2005), Project alliancing: a relational contracting mechanism for dynamic projects,
Lean Construction Journal, Vol. 2 No. 1, pp. 67-79.
Sappington, D.E.M. (1991), Incentives in principal-agent relationships, Journal of Economic
Perspectives, Vol. 5 No. 2, pp. 45-66.
Shavell, S. (1979), Risk sharing and incentives in the principal and agent relationship, The Bell
Journal of Economics, Vol. 10 No. 1, pp. 55-73.
Tang, W., Qiang, M., Duffield, C.F., Young, D.M. and Lu, Y. (2008), Incentives in the Chinese
construction industry, Journal of Construction Engineering and Management, Vol. 134
No. 7, pp. 457-467.
Turner, J.R. and Simister, S.J. (2001), Project contract management and a theory
of organization, International Journal of Project Management, Vol. 19 No. 8,
pp. 457-464.
Uher, E.T. and Toakley, R.A. (1999), Risk management in the conceptual phase of a project,
International Journal of Project Management, Vol. 17 No. 3, 161-169.
Ward, S. and Chapman, C. (1994), Choosing contractor payment terms, International Journal of
Project Management, Vol. 12 No. 4, pp. 216-221.
Weitzman, M.L. (1980), Efficient incentive contracts, The Quarterly Journal of Economics,
Vol. 44 No. 1, pp. 719-730.
Willenbrock, J.H. (1973), Utility function determination for bidding models, Journal of the
Construction Division, ASCE, Vol. 99 No. 1, pp. 133-153.
Wong, A.K. (2006), The application of a computerized financial control system for the decision
support of target cost contracts, Journal of Information Technology in Construction,
Vol. 11, Special Issue, pp. 257-268.
Zaghloul, R. and Hartman, F. (2003), Construction contracts: the cost of mistrust, International
Journal of Project Management, Vol. 21 No. 6, pp. 419-424.
Zhao, H. (2005), Incentive-based compensation to advertising agencies: a principal-agent
approach, International Journal of Research in Marketing, Vol. 22 No. 3,
pp. 255-275.
Further reading
Banker, R.D. and Thevaranjan, T. (1997), Accounting earnings and effort allocation,
Managerial Finance, Vol. 23 No. 5, pp. 56-71.
Eriksson, P. (2006), Procurement and governance management development of a conceptual
procurement model based on different types of control, Management Review, Vol. 17 No. 1,
pp. 30-49.
Eriksson, P. and Laan, A. (2007), Procurement effects on trust and control in client-contractor
relationships, Engineering, Construction and Architectural Management, Vol. 14 No. 4,
pp. 387-399.
Feltham, G.A. and Xie, J. (1994), Performance measure congruity and diversity in multi-task
principal/agent relations, The Accounting Review, Vol. 69 No. 3, pp. 429-453.
Sharma, A. (1997), Professional as agent: knowledge asymmetry in agency exchange, Academy
of Management Review, Vol. 22 No. 3, pp. 758-799.
About the authors
Dr S. Mahdi Hosseinian is a Graduate of the Shiraz University (BSc) and Isfahan University of
Technology (MSc), where he achieved maximum marks among his cohorts. This paper forms
part of his PhD research at The University of New South Wales. Before joining The University of
New South Wales, he worked at the Buali Sina University.
An optimal
target cost
contract
603
Downloaded by KWAME NKRUMAH UNIVERSITY OF SCIENCE AND TECHNOLOGY At 07:42 14 June 2015 (PT)
ECAM
21,5
604