Beruflich Dokumente
Kultur Dokumente
execution method
Driven Piles
Drilled/Bored Piles
Driven piles
Pile driving is the process by way of which a pile is forced or
driven into the ground without excavation or boring
Driven piles are considered to be displacement piles. In the
process of driving the pile into the ground, soil is moved radially
as the pile shaft enters the ground. There may also be a
component of movement of the soil in the vertical direction.
There are several types of pile driving method in the piling
construction, type of pile driving method used is depending on
the condition of soil and location of the site. However, different
piling machine will be used with different pile driving methods
too.
Driven Piles
Bored piles
Bored piles (Replacement piles) are generally considered to be
non- displacement Piles: a void is formed by boring or
excavation before piles is produced.
Piles can be produced by casting concrete in the void.
Drilled/Bored piles
Also called drilled piers or Cast-in-drilled-hole piles (CIDH piles) or Cast-in-Situ piles.
Rotary boring techniques offer larger diameter piles than any other piling method and
permit pile construction through particularly dense or hard strata. Construction
methods depend on the geology of the site. In particular, whether boring is to be
undertaken in 'dry' ground conditions or through water-logged but stable strata - i.e.
'wet boring'.
Boring is done until the hard rock or soft rock layer is reached in the case of end
bearing piles. If the boring machine is not equipped with a rock auger, then socketing
of the hard rock layer is done with the help of a heavy chisel which is dropped from a
height of about 1.5 metres (depends on the weight of the chisel and design
requirements) by suspending it from a tripod stand attached to a winch crane. The
socketing is carried out until the desired depth within the rock layer has been
attained. Usually, the required depth within the rock layer is considered to be equal to
the diameter of the pile in hard rock layers and is taken to be equal to 2.5 times the
diameter of the pile in soft rock layers.
'Dry' boring methods employ the use of a temporary casing to seal the pile bore
through water-bearing or unstable strata overlying suitable stable material. Upon
reaching the design depth, a reinforcing cage is introduced, concrete is poured in the
bore and brought up to the required level. The casing can be withdrawn or left in situ.
'Wet' boring also employs a temporary casing through unstable ground and is used
when the pile bore cannot be sealed against water ingress. Boring is then
undertaken using a digging bucket to drill through the underlying soils to design
depth. The reinforcing cage is lowered into the bore and concrete is placed by
tremmie pipe, following which, extraction of the temporary casing takes place.
The reinforcement cage may need to be lapped with another cage if the depth of
the pile exceeds 12 metres as that is the standard length of reinforcement bars of
diameter 16mm and above.
In some cases there may be a need to employ drilling fluids (such as bentonite
suspension) in order to maintain a stable shaft. Rotary auger piles are available in
diameters from 350 mm to 2400 mm or even larger and using these techniques,
pile lengths of beyond 50 metres can be achieved.
Such piles commonly fail due to the collapse of the walls of the shaft resulting in
the formation of a reduced section which may not be able to bear the loads for
which it had been designed. Hence at least a third of piles in projects with a large
number of piles are tested for uniformity using a "Pile Integrity Tester". This test
relies on the manner in which low intensity shock waves are affected as they pass
through the pile and are reflected to judge the uniformity and integrity of the pile.
A pile failing the integrity test is then subjected to a pile load test
Drilled Piles
Bored pile is a cast-in-place concrete pile where the bored piles have to
be cast on construction site.
Bored piling is cast by using bored piling machine which has specially
designed drilling tools, buckets and grabs, its used to remove the soil
and rock. Normally it can be drilling into 50metres depth of soil. The
advantage of bored piling is its drilling method, little vibration and
lower noise level.
Usually bored pile is used for those tall buildings or massive industrial
complexes, which require foundations which can bear the load of
thousands of tons, most probably in unstable aor difficult soil
conditions.
The method of drilling bored pile is different from RC Square pile or
spun pile which are using driving method, the piling machine to be used
will be different too.
Bored piling works required specialist bored piling contractor to follow
up instead of hiring general piling contractor.
There is a simple step-by-step method on how to drill the bored pile in
construction site.
1.The first step is to drill a hole of the require diameter into the
ground.
2.When the design depth or foundation bearing layer is
reached, drilling stopped.
3.The hole is then cleaned.
4.Steel reinforcement cage is lowered into the hole.
5.Concrete is then poured into the hole until the designed cutoff level of the pile.
6.After Step5, the construction of bored pile is completed.
Thus it can be seen that bored piles are constructed by first
drilling into ground. Drilling is one of the most important step
in bored pile construction. Only successful drilling can lead to
the next construction step to be carried out. Thus drilling
requires experience and the use of the right tools and
equipment.
1) Adjust the piling machine on the pile axis2) Start drilling until the auger is filled.
and haul with the auger to the drilling
place.
The drilling rig is a power unit that rotates the Kellybar which in turn
rotates the auger. The power unit is normally diesel powered. The
Kellybar is slotted through the power unit at the front end known as
the Table. Horizontal rotation of the diesel engine is converted to
vertical rotation which rotates the Kellybar.
There is also a pair hydraulic arms at the table. These arms can
clamped to the Kellybar and are use to raise or lower the the
it slowly over a short lenght. Rotation can be either anticlockwise or
clockwise. The whole power unit, Kellybar and auger assembly is
then mounted onto a base crane.
Drilling starts by pressing and rotating the auger at the same time.
Once the initial hole is formed and depending on the soil material,
the weight of the Kellybar pushes the drilling deeper.
The Kellybar is raised and lowered into the hole by a separate lifting
cable of the base crane. This enables the Kellybar and auger to be
lifted up quickly to the surface to dispose of the drilled material and
later lowered back again to the hole to continue drilling. This
processes is repeated until the desired depth is reached.
Name of Parts
1
KellyBar
2
Auger
3
Diesel Powered Drilling Rig
4
Base Crane
5
Table
6
Hydraulic arms
After completing the concreting and the auger had been removed, a
reinforcing cage is pushed down the shaft while the concrete has not
set. It is not uncommon to push down cage length of 12m. Thus it
can be seen that the final steps of bored piles construction by CFA is
different from the Kellybar and auger process.
However if the drilled hole depth is shallow and the ground stable (
the drilled hole does not collapse), the CFA can be completely
removed. In this case, the concreting can be carried out like those of
the Kellybar and auger method.
Modern drilling rigs can drill bored piles of diameters ranging from
600mm to 4000mm. Due to the convenience of the rotary drilling
rigs, they have become more common nowadays as compared to
the crane mounted drilling rigs. Rotary drilling rigs are self-mounting
and also easily transportable. On the whole this capability which
reduces cost of mobilization.
Single Piles
Pile Groups
Piled Wall