Huawei LTE eNodeB Site Solution &


Installation Key Point
V1.0

www.huawei.com

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

LTE Network Topology


CONTENTS
Chapter1: Site Solution

Chapter2: Installation Key Point and Mistake

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 2

RRU Power Cable Solution

0~100m

DCDU-11B

RRU3938
< 100m

Notes:
If the power cable length(between RRU and DCDU) >100m,
please contact Huawei Site Engineer for special solution

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 3

BBU and DCDU install on the Transmission Cabinet

1) FDD LTE BBU should install under the TDD LTE BBU which already existed on the site.
2) Power cable of RRU from Sector A/B/C connected Load 3/4/5; Power cable of BBU
connected to Load 7.
3) CPRI Fiber of RRU from Sector A/B/C connected to CPRI 0/1/2 on LBBP board.
4) Transmission Fiber connected to SFP 0; Transmission Ethernet Cable connected to GE/FE 0
5) CPRI Fiber should be tied with Hook & Loop Mechanical Fastener.
6) 1 U space should be reserved between 2 BBUs.
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 4

RRU installed on Tower


RRU and antenna
can be installed as
back to back.
RRU can be installed
on a pole near the
pole for antenna.
RRU should be
grounded on tower.

Sector A

Sector B

HUAWEI TECHNOLOGIES CO., LTD.

Sector C

Huawei Confidential

Page 5

Cable connection for RRU

-45
+45

ANT0
ANT1

1) ANT0 of RRU should connected to port +45 of the Antenna. .


2) ANT1 of RRU should connected to port -45 of the Antenna.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 6

Cable connection inside RRU cabling cavity.

1) CPRI fiber is connected to CPRI 0;


2) The metal shield of RRU power cable should
be cut and grounding on clip inside RRU
cabling cavity;
3) The water plugs should be filled in the vacant
troughs of the RRU cabling cavity.

2
3
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 7

1) Label of ANT_0A, ANT_0B, ANT_0C is connected to +45


2) Label of ANT_1A, ANT_1B, ANT_1C is connected to -45

Antennas Labeling

ANT_1A

ANT_1B

ANT_1C

ANT_0A

ANT_0B

ANT_0C

Sector A
HUAWEI TECHNOLOGIES CO., LTD.

Sector B
Huawei Confidential

Sector C
Page 8

RRU Feeder Label and Color Feeder Mark Rules

RRU 0

ANT_0A

ANT_1A

Color Feeder Mark

Feeder Label

RRU Label Rules


Sector: A BC
RRU Path: 01
Color Feeder Mark: A(Red)B(yellow)C(Blue); all with two while ring code to separate with
TDD
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 9

Antenna Feeder Label and mark rules


XXX
XXX
XXX

XXX
XXX
XXX

XXX
XXX
XXX

Antenna A

Antenna B

Antenna C

RCU +45 -45 -45 +45 RCU

RCU +45 -45 -45 +45 RCU

RCU +45 -45 -45 +45 RCU

ANT_1C

ANT_0C

ANT_1B

Make mark with color ring

ANT_0B

ANT_1A

ANT_0A

Make mark use alphabet

Feeder Label

RRU Label Rules


Sector: A BC
Path: 0123
Color Ring: A(Red)B(yellow)C(Blue); all with two while ring code to separate with TDD
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 10

LTE Network Topology


CONTENTS
Chapter1: Site Solution

Chapter2: Installation Key Point and Mistake

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 11

Safety belt and cap is extremely needed.


Wrong

Right

Notes
Safety cap is needed for the working on the site. And the safety belt is needed for working on the tower
or poles.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 12

Connect the power cable to the right port


Wrong

Right

Notes
1. Power cable of RRU for sector A/B/C should be connected to LOAD3/4/5, label with LTE PWR
RRU0/1/2
2. BBU should be connected to LOAD7, label with PWR BBU
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 13

Remove the shield of the power cable near connector


Wrong

Right

Notes
The black shield of the power cable near the power connector of DCDU should be cut and tied up.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 14

The CPRI fiber should be tied.


Wrong

Right

Notes
The CPRI fiber should be tied with Hook & Loop Mechanical Fastener. Dont use cable tie.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 15

Put the redundant fiber on the Transmission Rack


bottom

Wrong

Right

Notes
The redundant fiber should be circled and put on the bottom of the transmission rack. Dont put it
outside the tower or on the cable tray.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 16

The heat-shrink tube is used and shrink well.


Wrong

Right

Notes
The power cable should use the heat-shrink tube. And it should be done well.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 17

Ground the DCDU on the Transmission Cabin


Wrong

Right

Notes
Ground the DCDU on the Transmission cabin. ( Use 6mm grounding cable. )

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 18

Installed the bracket assembly on the right


direction
Wrong

Right

Notes:
Follow the label on the bracket assembly carefully. And make sure the bracket assembly of the RRU is
installed on the right direction.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 19

The metal shield of RRU power cable is wrongly


cut.
Wrong

Right

Notes
The metal shield of RRU power cable should be cut and grounding on clip inside RRU cabling cavity. The
metal shield can not be cut too long and it go outside the cabling cavity.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 20

The waterproof plugs are filled in the vacant


troughs

Right

Notes
The water plugs should be filled in the vacant troughs of the RRU cabling cavity.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 21

Wrong

Labeling the Jumpers of the RRU with the correct


Label

Wrong

Right

Notes
Use Label ANT_0A and ANT_1A for Sector A;
Use Label ANT_0B and ANT_1B for Sector B;
Use Label ANT_0C and ANT_1C for Sector C.
HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 22

Remove the oil paint of the tower for grounding


point

Wrong

Right

Notes
Oil paint of tower is not removed on earth grounding point.
electric ability surge protection will be decreased.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 23

The power cable are grounded beside the Roxtec


Wrong

Right

Notes The power cables of the RRU should be grounded by the grounding clip on the grounding bat
before routed into the Roxtec.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 24

BBU and DCDU should be fixed with screws.


Wrong

Right

Notes
BBU and DCDU should be fixed with screws. Cable ties is forbidden to use for fixing equipment.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 25

Keep the environment of the site neat and clean


Wrong

Right

Notes Keep the environment of the site neat and clean. Dont leave any boxes, cables, bottles
inside and outside the shelter. Take all the garbage away the site.

HUAWEI TECHNOLOGIES CO., LTD.

Huawei Confidential

Page 26