Beruflich Dokumente
Kultur Dokumente
www.huawei.com
Huawei Confidential
Huawei Confidential
Page 2
0~100m
DCDU-11B
RRU3938
< 100m
Notes:
If the power cable length(between RRU and DCDU) >100m,
please contact Huawei Site Engineer for special solution
Huawei Confidential
Page 3
1) FDD LTE BBU should install under the TDD LTE BBU which already existed on the site.
2) Power cable of RRU from Sector A/B/C connected Load 3/4/5; Power cable of BBU
connected to Load 7.
3) CPRI Fiber of RRU from Sector A/B/C connected to CPRI 0/1/2 on LBBP board.
4) Transmission Fiber connected to SFP 0; Transmission Ethernet Cable connected to GE/FE 0
5) CPRI Fiber should be tied with Hook & Loop Mechanical Fastener.
6) 1 U space should be reserved between 2 BBUs.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 4
Sector A
Sector B
Sector C
Huawei Confidential
Page 5
-45
+45
ANT0
ANT1
Huawei Confidential
Page 6
2
3
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 7
Antennas Labeling
ANT_1A
ANT_1B
ANT_1C
ANT_0A
ANT_0B
ANT_0C
Sector A
HUAWEI TECHNOLOGIES CO., LTD.
Sector B
Huawei Confidential
Sector C
Page 8
RRU 0
ANT_0A
ANT_1A
Feeder Label
Huawei Confidential
Page 9
XXX
XXX
XXX
XXX
XXX
XXX
Antenna A
Antenna B
Antenna C
ANT_1C
ANT_0C
ANT_1B
ANT_0B
ANT_1A
ANT_0A
Feeder Label
Huawei Confidential
Page 10
Huawei Confidential
Page 11
Right
Notes
Safety cap is needed for the working on the site. And the safety belt is needed for working on the tower
or poles.
Huawei Confidential
Page 12
Right
Notes
1. Power cable of RRU for sector A/B/C should be connected to LOAD3/4/5, label with LTE PWR
RRU0/1/2
2. BBU should be connected to LOAD7, label with PWR BBU
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 13
Right
Notes
The black shield of the power cable near the power connector of DCDU should be cut and tied up.
Huawei Confidential
Page 14
Right
Notes
The CPRI fiber should be tied with Hook & Loop Mechanical Fastener. Dont use cable tie.
Huawei Confidential
Page 15
Wrong
Right
Notes
The redundant fiber should be circled and put on the bottom of the transmission rack. Dont put it
outside the tower or on the cable tray.
Huawei Confidential
Page 16
Right
Notes
The power cable should use the heat-shrink tube. And it should be done well.
Huawei Confidential
Page 17
Right
Notes
Ground the DCDU on the Transmission cabin. ( Use 6mm grounding cable. )
Huawei Confidential
Page 18
Right
Notes:
Follow the label on the bracket assembly carefully. And make sure the bracket assembly of the RRU is
installed on the right direction.
Huawei Confidential
Page 19
Right
Notes
The metal shield of RRU power cable should be cut and grounding on clip inside RRU cabling cavity. The
metal shield can not be cut too long and it go outside the cabling cavity.
Huawei Confidential
Page 20
Right
Notes
The water plugs should be filled in the vacant troughs of the RRU cabling cavity.
Huawei Confidential
Page 21
Wrong
Wrong
Right
Notes
Use Label ANT_0A and ANT_1A for Sector A;
Use Label ANT_0B and ANT_1B for Sector B;
Use Label ANT_0C and ANT_1C for Sector C.
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Confidential
Page 22
Wrong
Right
Notes
Oil paint of tower is not removed on earth grounding point.
electric ability surge protection will be decreased.
Huawei Confidential
Page 23
Right
Notes The power cables of the RRU should be grounded by the grounding clip on the grounding bat
before routed into the Roxtec.
Huawei Confidential
Page 24
Right
Notes
BBU and DCDU should be fixed with screws. Cable ties is forbidden to use for fixing equipment.
Huawei Confidential
Page 25
Right
Notes Keep the environment of the site neat and clean. Dont leave any boxes, cables, bottles
inside and outside the shelter. Take all the garbage away the site.
Huawei Confidential
Page 26