Description
ID FAN
ID fan outlet & inlet expansion bellow flange rope, bolt &
nuts to be fixed. And All hardwares tightness to be done.
ID fan Inside cleaning to be done.
ID fan inlet TE & PT cable lying and termination to be
done.
ID fan DE & NDE shaft sealing plate to be fixed
ID Inlet damper bolt & nut to be fixed. And all hardwares
tight ness to be done.
ID fan DE & NDE Plummer block grease nipples to be fixed
ID fan Suction damper power cylinder erection and
grouting work to be done
ID suction damper power cylinder air connection tubing
work to be done.
ID fan DE & NDE cooling fan to be fixed
ID fan Coupling guard to be fixed.
ID fan, Suction and discharge duct insulation and gladding
sheet work to be completed.
FD FAN
FD fan inside cleaning to be done.
FD fan DE & NDE shaft sealing plate to be fixed.
FD Fan Suction duct erection to be done.
FD fan Suction damper power cylinder election to be
done.
FD flow transmitter cable lying and termination to be
done.
FD fan discharge & bypass damper handle to be provided.
FD Fan Discharge and bypass dampers bolt and nuts
tightness to be done
FD fan Discharge and bypass damper flanges gaskets to
be removed and rope will be provided.
FD fan discharge & bypass damper before duct small
cutting to be done to check the open /Close for damper.
FD fan discharge & bypass damper open & close marking
to be done.
FD HDR expansion bellow temp. Locks to be removed.
FD fan outlet DG to be fixed.
FD fan outlet pressure transmitter cable lying and
termination work to be done.
FD fan coupling guard to be done.
PA FAN
PA fan suction casing erection to be done.
Status
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
110
111
112
113
124
125
126
127
128
129
130
131
132
133
134
COMMISSIONING INPUTS:
S.NO.
1.
2.
3.
DESCRIPITION
Fire wood
Bed material
Char Coal
STATUS
Not available
Not available
Not available
Chemical
DM water
Electrical power
Husk handling system
8.
Cooling water
9.
Available
DM plant erection work was U/P
Start- up power required.
Grizzly hopper & gantry erection were
completed. Belt laying & plant
commissioning is pending.
Cooling tower erection work under
progress
Vessel & conveying line erection work
70% completed. And inst. airline work
to be completed. Ash silo erection
work under progress.