Beruflich Dokumente
Kultur Dokumente
Sheet: 1 of 7
Date: October 2000
Revision: R0
1
2
3
4
5
6
7
8
9
10
11
Area (A)
=
1032.4 sq km
Length of the longest stream (L)
=
61.37 km
Length of the longest stream from a point opposite
C.G. Of catchment to point of study (L=
32.46 km
Equivalent stream slope (S)
R.D. Starting R.L. Of
Length of
Height
Di-1+Di Li.(Di-1+Di)
From Bridge River Bed
Each
Above
Site
Segment (Li)Datum (Di)
(km)
(m)
(km)
(m)
(m)
(km.m)
0.00
10.80
19.01
31.24
38.19
40.34
46.19
53.73
55.16
58.44
61.37
11.50
20.00
40.00
60.00
80.00
100.00
120.00
300.00
500.00
700.00
900.00
0.00
10.80
8.21
12.22
6.95
2.15
5.85
7.54
1.43
3.28
2.93
Total
Note:
S=
0.00
8.50
28.50
48.50
68.50
88.50
108.50
288.50
488.50
688.50
888.50
0.00
8.50
37.00
77.00
117.00
157.00
197.00
397.00
777.00
1177.00
1577.00
61.37
0.00
91.80
303.94
941.17
813.56
337.08
1153.09
2994.57
1108.78
3857.32
4624.16
16225.46
4.3081
,Say
4.308 m/km
time from the centre of rainfall excess duration to the U.G.peak (hr)
0.376{(L.Lc) /( S^0.5)}^0.
7.4038
,Say
7.5 hr
1.215/(tp)^0.
0.30193
,Say
0.302 cumec/sqkm
2.211/(qp)^1.
7.961
,Say
8.0 hr
1.312/(qp)^1.
4.360
,Say
4.4 hr
Sheet: 2 of 7
Date: October 2000
Revision: R0
width of the rising limb of U.G. Measured at 50% of peak discharge ordinate (hr)
0.808/(qp)^1.
2.851
,Say
2.9 hr
width of the rising limb of U.G. Measured at 50% of peak discharge ordinate (hr)
0.542/(qp)^0.
1.721
,Say
1.7 hr
26.741
,Say
27.0 hr
7.621(tp)^0.6
tp+tr/2
8.0
8.0 hr
qp*A
311.80
,Say
312.0 cumec
2867.90 cumec.hr
Where
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
Total
1032.4
1
1
Sq km
cm
hr
1-hr U. G. Ordinate
(cumec)
0.0
6.0
20.0
45.0
85.0
150.0
220.0
300.0
312.0
300.0
260.0
215.0
180.0
150.0
125.0
105.0
90.0
75.0
60.0
49.0
39.0
30.0
22.0
15.0
8.0
5.0
2.0
0.0
300.0
250.0
Discharge (cum e c)
Time
(hr)
A=
d=
tr=
200.0
150.0
100.0
50.0
0.0
0
10
15
20
25
30
Tim e (hr)
2868.0
In case the Sum (Qi.ti) for the unitgraph drwn is higher or lower than the volume worked out by the above formula, then the
falling limb and/ or rising limb may be suitably modified to get the correct volume under the hydrograph, taking care to get
the smooth shape of the hydrograph.
Sheet: 3 of 7
Date: October 2000
Revision: R0
8.25
hr
,Say
8.0
hr
26.00
= cm
Hence,
50-yr, 8-hr areal rainfall
15.21
=
Step-7 Time Distribution for Areal Rainfall and Estimation of Effective Rainfall Units
50-yr, 8-hr areal rainfall15.21
(Ir) =
(Refer: Table A-3 of Flood Estimation Report for Eastern Coast Region (Sub-zone - 4a))
Design Loss rate of 0.75 cm/hr under section 3.11 of Flood Estimation Report has been adopted. The following table
shows the computation of 1-hr effective rainfall units in coloumn {4} by substracting the design loss rate in column {3}
from 1-hr rainfall increament in column {2}.
Duration Distribution
Storm 1-hr RainfallDesign Loss
1-hr Effective
Coefficient
Rainfall Increament
Rate
Rainfall
(hr)
(cm)
(cm)
(cm/hr)
(cm)
{1)
{2}
{3}={2}*Ir
{4}
{5} {6}={4}-{5}
1
2
3
4
5
6
7
8
0.50
0.68
0.78
0.86
0.91
0.96
0.99
1.00
7.605
10.343
11.864
13.081
13.841
14.602
15.058
15.210
7.605
2.738
1.521
1.217
0.761
0.760
0.456
0.152
0.750
0.750
0.750
0.750
0.750
0.750
0.750
0.750
6.855
1.988
0.771
0.467
0.011
0.010
0.000
0.000
Sheet: 4 of 7
Date: October 2000
Revision: R0
Direct
Runoff
(cumec)
{4}
596.3
2138.8
231.3
121.4
3087.8
14.7
3102.4
cumec
3100.0
cumec
Sheet: 5 of 7
Date: October 2000
Revision: R0
14.523 m
(Cross-Section At Bridge Site)
Actual Modified
Average Horizontal
Chainage H.F.L Bed Level
Bed Level Height Height Distance
(m)
(G.T.S)
(m)
(m)
h
h'
x
1
2
3
4
5
6
7
0.000
1.000
3.680
20.089
42.848
64.842
81.236
86.343
92.398
93.398
14.523
12.830
12.829
10.682
10.695
10.951
10.853
10.898
11.218
13.357
13.400
14.523
12.829
10.682
10.695
10.951
10.853
10.898
11.218
13.357
14.523
0.000
1.694
3.841
3.828
3.572
3.670
3.625
3.305
1.166
0.000
0.847
2.768
3.835
3.700
3.621
3.648
3.465
2.236
0.583
1.000
2.680
16.409
22.759
21.994
16.394
5.107
6.055
1.000
Total
Area of Cross-Section, A
Wetted Perimeter, P
Hydraulic Mean Depth, R =
Longitudinal Slope, S
Velocity of Stream, V
Discharge, Q = A x V
=
=
=
=
=
=
Say,
Area
6x7
8
0.847
7.417
62.920
84.208
79.640
59.797
17.696
13.536
0.583
Difference Wetted
in h
Perimeter
h"
sqrt(7*7+9*9)
9
10
1.694
2.147
0.013
0.256
0.098
0.045
0.320
2.139
1.166
###
326.645 Sq m
96.034
m
3.401
m
0.0008
2.092 m/sec (Manning's coeff., n
1.967
3.434
16.409
22.760
21.994
16.394
5.117
6.422
1.536
96.034
0.030 )
683.273 m3/sec
680.000 cumec
15.000
14.000
R L (m)
13.000
12.000
11.000
10.000
Column P
Sheet: 6 of 7
Date: October 2000
Revision: R0
Recommendation
A)
Now, these discharges have been compared. Final design discharge has been taken as the
highest of the two discharges but if higher discharge is greater than 1.5 times of the other, the
design flood discharge has been limited to 1.5 times of the lower discharge. (Ref: IRC, SP-13)
Therefore,
Design flood discharge, Qd 1.5 x 680.000 cumec
Recommended Design Flood Discharge, Qd= 1020.0 cumec
B)
15.516
12.830
12.829
10.682
10.695
10.951
10.853
10.898
11.218
13.357
13.400
15.516
12.829
10.682
10.695
10.951
10.853
10.898
11.218
13.357
15.516
0.000
2.687
4.834
4.821
4.565
4.663
4.618
4.298
2.159
0.000
1.344
3.761
4.828
4.693
4.614
4.641
4.458
3.229
1.080
Total
Area of Cross-Section, A
Wetted Perimeter, P
Hydraulic Mean Depth, R =
Longitudinal Slope, S
Velocity of Stream, V
Discharge, Qd = A x V
=
=
=
=
=
=
1.000
2.680
16.409
22.759
21.994
16.394
5.107
6.055
1.000
Area
6x7
8
1.344
10.078
79.214
###
###
76.076
22.767
19.549
1.080
Difference Wetted
in h
Perimeter
h"
sqrt(7*7+9*9)
9
10
2.687
2.147
0.013
0.256
0.098
0.045
0.320
2.139
2.159
###
### Sq m
###
m
4.279
m
###
2.438 m/sec (Manning's coeff., n
### m3/sec
2.867
3.434
16.409
22.760
21.994
16.394
5.117
6.422
2.379
97.777
0.030 )
### m
Sheet: 7 of 7
Date: October 2000
Revision: R0
16.000
15.000
R L (m )
14.000
13.000
12.000
11.000
10.000
10.000
30.000
50.000
70.000
90.000
0.000
20.000
40.000
60.000
80.000
100.000
R D (m )
Original x-section
Column P