Beruflich Dokumente
Kultur Dokumente
SUPPLY
CONTRACT
V - 6730
Purchaser
and
Page - -
Table of content
1.
DEFINITIONS... 3
21.
Subject of the Contract
63
23.
Terms of delivery and delivery dates...
84
43.
Contract Price....
114
45.
Terms of payment.1.
15
6.
Variations and SUSPENSION... 12
57.
Risk of
loss.13. 5
86.
Warranty...14 6
97.
Acceptance..
615
108.
Overall limitation of
Liability...17 8
11.
TERMINATION OF THE CONTRACT....18
129.
Force Majeure.
819
13.
OFFICIAL APPROVALS.. 20
14.
REPRESENTATIVES... 20
150.
Collateral agreements and effectiveness of the Contract..
920
161.
Applicable law and Jurisdiction
921
17.
TAXES. 21
18.
PATENTS AND USE OF DOCUMENTATION. 22
19.
ASSIGNMENT AND SUB_LETTING. 22
20.
EFFECTIVE DATE OF CONTRACT22
LIST OF Annexes
Annex
SERVICESSUPERVISION
Annex II Technical Description TD | 6730 | i1 | 2008
Annex III .Form of Letter of Credit
Annex IV Acceptance Parameters
Annex V..Battery Limit
Annex VIProject Time Schedule
Annex VIIContract Price and Terms of Payment
Annex VIII.Engineering
Annex IX.Commissioning Procedure
Annex XSpare Parts
Annex XI...Performance Bond
Page - -
Preamble
I
II.
III.
IV.
1.2
APPLICABLE RULES Shall mean IEC codes, standards and regulations as far
as this CONTRACT provides for their application to the performance of the
CONTRACT and Laws and Regulations being in force in Pakistan to the extent
they are mandatory for the performance of the CONTRACT.
1.3
1.4
Page - -
1.5
1.6
CONTRACT Shall mean all the terms and provisions appearing in the Articles
of this document and Annexes hereto.
1.7
1.8
1.9
4.5;
1.17 PERFORMANCE AND RELIABILITY TESTS - Shall mean test executed
according to Clause 9.7 below and Commissioning Procedure (Annex IX).
1.18 PROJECT TIME SCHEDULE (Annex VI) - Shall mean the schedule for delivery
performance of the GENSETS.
1.19 PRODUCT(S) Shall mean electrical power as the context may provided,
specified and guaranteed in Appendix IV for the industrial/commercial use in the
Industry.
Page - -
1.20 PROVISIONAL TAKE OVER Shall mean the successful completion of the
COMMISSIONING, START UP and Test Run.
1.21 PURCHASER Shall mean RUPALI POLEYSTER LIMITED
1.22 RISK Shall mean as defined per DELIVERY term and Incoterms 2000.
1.23 SITE Shall mean the actual place where the GENSETS is to be erected.
1.24 SPARE PARTS Shall mean those items which are mutually agreed between the
SUPPLIER and the PURCHASER to be the replacement parts of the GENSETS as
per Appendix X.
1.25 SUB-SUPPLIER(S) Shall mean all persons and companies and their employees,
used by the SUPPLIER in accordance with the CONTRACT to perform the
GENSETS supply.
1.26 INSTALLATION
1.27 SUPERVISION Shall mean the technical services, direction, instructions, advise,
guidance, and supervision for the purposes of ERECTION, MECHANICAL TESTS,
MECHANICAL COMPLETION, COMMISSIONING, START-UP, operation and
conduct of PERFORMANCE and RELIABILITY TESTS of the GENSETS till
PROVISIONAL TAKE OVER as specified in Article 9.7.
1.28 SUPPLIER Shall mean DEUTZ Power Systems Gmbh.
1.29 WARRANTY PERIOD Shall mean the period defined in Article 7.2.
1.30 WORK or WORKS Shall mean all the GENSETS and any services to be
supplied by the SUPPLIER under this CONTRACT.
1.31 CFR shall mean Cost and Freight as is further specified as per INCOTERMS
2000;
1.32 CPT shall mean Carriage Paid To as is further specified as per INCOTERMS
2000;
1.33 DDP shall mean Delivered duty paid as is further specified as per INCOTERMS
2000;
1.34 DDU shall mean Delivered duty unpaid as is further specified as per
INCOTERMS 2000;
1.35 EXW shall mean Ex Works as is further specified as per INCOTERMS.
12.
2.1
Subject to the terms and conditions of this Supply Contract, the SUPPLIER agrees to
supply to the PURCHASER, the SUPPLIER design, know-how, basic and detail engineering in
the
form
of
technical
documentation,
manufacture
and
deliver
the
EQUIPMENTGENSETSSUPERVISION ERECTION and installation of the EQUIPMENTthe
engines with additional equipment (hereinafter referred to as GENSETS) and to perform the
Page - -
The SUPPLIER shall ensure that the GENSETS is designed to meet all the physical
conditions at SITE, including, but not limited to the kind of climate and utilities etc.
available thereon.
Unless otherwise provided for in this Contract, this Supply Contract shall be executed
based on the standards of the SUPPLIERS and according to the relevant technical
standards, codes and regulations existing and applying in the Federal Republic of
Germany on the date of signature of the Contract.
2.4
Unless otherwise provided for in this Contract, the SUPPLIERS obligation to perform
according to Clause 1.1 is conditioned upon the PURCHASER ensuring:
a)
That the employees of the SUPPLIER have safe and unrestricted access to the
site on which the GENSETS are to be installed and operated.
b)
That all necessary work to be performed by the PURCHASER or other
contractors of PURCHASER prior to the performance of the SERVICES by the
SUPPLIER have been successfully and entirely completed.
c)
That all tools, equipmentGENSETS, materials and manpower, which are
necessary for the performance of the SERVICES according to Clause 1.1 that
the SUPPLIER does not provide under this Contract are provided free of charge
and at the risk of the PURCHASER.
d)
That the PURCHASER provides suitable and lockable storage rooms for
equipmentGENSETS and apparatus of the SUPPLIER.
That the PURCHASER provides all in connection with this Contract necessary
permissions or licences as long as this is not clear defined as duty of the SUPPLIER in
Annex I.
That the PRCHASER confirms at least four weeks before the schedule date of
commissioning, that the installation works of the GENSETS is finished and that the
plant is ready for commissioning.
In case the PURCHASER does not meet the aforesaid conditions the PURCHASER
shall be deemed to be in default and the SUPPLIER shall be entitled to reject the
performance of the SERVICES according to Clause 1.1 until the PURCHASER has
Page - -
remedied such default to the reasonable satisfaction of the SUPPLIER. The periods
stipulated in Clause 2.2 shall be executed accordingly. Any additional costs of the
SUPPLIER resulting from such default of the PURCHASER shall be borne by the
PURCHASER who shall indemnify the SUPPLIER for such additional costs.
2.5 The SUPPLIER shall, in accordance with this CONTRACT and with due care and diligence,
deliver the GENSETS within the PROJECT TIME SCHEDULE (APPENDIX VI).
2.6
SUPPLIER shall supply the consumables SPARE PARTS for up to ______ hours of
plant operation along with COMMISSIONING spares as defined in Appendix X and the
purchaser shall rely on the list of such SPARE PARTS supplied by the SUPPLIER.
2.7.2
2.7.3
2.7.4
2.7.5
2.7.6
During the whole period of SUPERVISION the GENSETS shall be under the
charge of the INSTALLATION ADVISORSUPERVISOR and the PURCHASER
shall not act in any manner contrary to the instructions, guidance and advice
issued by the INSTALLATION ADVISORSUPERVISOR in writing
2.7.7
2.7.8
2,8
2.8.1 The PURCHASER is responsible for providing required information for the SUPPLIER to
fulfill his obligations according to Project Time ScheduleDocument Submittal
Schedule, as specified in the Annex XVI.
Page - -
2.8.2. The SUPPLIER will send Technical Description of the GENSETS in accordance with
Project Time ScheduleDrawing Submittal Schedule (Annex XVI). Any comments the
PURCHASER might have to these drawings shall be remitted within fourteen (14) days
after receipt, otherwise they are be deemed to be approved.
2.8.3 The SUPPLIER shall be responsible for any discrepancies, errors and omissions in his
drawings and information, whether the PURCHASER has approved them or not.
2.8.4 The PURCHASER shall be responsible for the drawings and information supplied in
writing by the PURCHASER.
2.8.5
2.9
INSPECTION
2.9.1 The PURCHASER is entitled to physically review relevant progress of the manufacture of
the GENSETS. For this purpose the PURCHASER having provided reasonable notice to
the SUPPLIER shall have access to the said workshop during normal business hours,
but without interfering with the progress of the GENSETS manufacture.
2.9.2 The SUPPLIER shall give the PURCHASER notice in writing at least two (2) weeks
before any FACTORY TEST of the GENSETS that are subject to FACTORY TEST and
which must be at least one (1) month before the dispatch EXW.
2.9.3
23.
3.1
Delivery of the GENSETS will be effected in accordance with and be subject to CFR
Sea Port Karachi, Pakistan condition according to INCOTERM.
3.2
3.3
Compliance with the Project Time Schedule (Annex VI) delivery times by the
SUPPLIER is conditioned upon PURCHASERS fulfilling its contractual obligations
under this Contract.
3.4
In the event the SUPPLIER fails to deliver the GENSETS on the delivery dates due to
the negligence of the SUPPLIER and the PURCHASER sustains damages because of
such delay, the PURCHASER shall be entitled to claim liquidated damages for delayed
delivery at a rate of 0.250% of the CONTRACT PRICE price of the part of the of the
complete scope of GENSETS actually delayed for every full week of delay, but no more
than an aggregate of 2.5% of the price of such part of the scope of GENSETS, which
can not be used due to the delay. After reaching the maximum liquidated damages for
delay the PURCHASER shall grant the Supplier a reasonable extension of delivery
time. If the delivery of the GENSETS is delayed beyond twelve weeks (12) the
Page - -
PURCHASER shall have the right to terminate the CONTRACT. The payment of
liquidated damages shall not absolve the SUPPLIER from its obligations to deliver the
delayed portion of the GENSETS (Annex I) and/or Technical Description (Annex I).
3.5 The SUPPLIER must ensure that the EQUIPMENTGENSETS shall be packed to as per
export standard sea worthy packing which is fit for the purpose for transport of such like
equipmentGENSETS. An international inspection company, acceptable to the SUPPLIER
will supervise the packaging procedure. A report regarding the quality of the packaging
procedure and completeness of the GENSETS will be forwarded to the PURCHASER. All
costs arising from these services shall be borne by the SUPPLIER.
3.6 SUPPLIER shall provide the following documentation commercial invoice, packing list,
European Certificate of Origin (if required) Bill of Lading and any other documents required
by the PURCHASER for the importation of the GENSETS.
3.7 If the SUPPLIER is responsible for any shortages or errors in GENSETS as specified in
Annex I, the SUPPLIER shall deliver the missing parts DDP SITE Pakistan.
3.8 The PURCHASER shall inform SUPPLIER in writing two weeks after the signing of
CONTRACT of its requirements as regards the format and contents of the packing lists and
shipping invoices and on any important matters to be taken into consideration in this
respect. SUPPLIER shall prepare the packing lists and shipping invoices accordingly and
shall send to the PURCHASER by courier service or telefax the packing lists and shipping
invoices prepared by SUPPLIER for shipment actually dispatched as soon as practical, but
in any event prior to submission of these documents to the bank.
3.9
3.12
Page - - 10
Page - - 11
Page - - 12
factory test and which must be at least one (1) month before the
dispatch ex works.
3.16.5The SUPPLIER shall be responsible for any discrepancies, errors and
omissions in his drawings and information, whether the PURCHASER
has approved them or not.
3.16.6The PURCHASER shall be responsible for the drawings and
information supplied in writing by the PURCHASER, and shall pay any
additional cost incurred by the SUPPLIER due to alterations of the
GENSETS, which result from incorrect or incomplete drawings and
information.
3.16.7The PARTIES to the CONTRACT shall use SI-units in documentation
and correspondence.
34.
Contract price
43.1 The PURCHASER agrees to buy from the SUPPLIER and the SUPPLIER agrees to
supply, sell and render the PURCHASER the GENSETS, SPARE PARTs,
SUPERVISION and other required services to be rendered by the SUPPLIER as
per the Scope of Supply and Technical Descriptions for the The total contract price
for the GENSETS and the SERVICES isof EURO xxx.xxx.00 (in words:
xxxxxxxxxxxxxxxxxxxxxxxxxx).
4.2
The CONTRACT PRICE is fixed and not subject to escalation.This price is valid for
deliveries of GENSETS or performance of SERVICES until the end of the year,
according to Clause 2.2. if the delivery or performance of SERVICES are delayed due
to circumstances, the SUPPLIER is not responsible for, the contract price for the
delayed part of GENSETS or performance of SERVICES increased by 1% for each
quarter of the year or part thereof.
4.3
The prices stipulated in clause 3.1 do not include VAT. In case VAT incurred, it shall be
added in the amount according to legal regulations.
4.4
The contract price for the GENSETS and the SERVICES does not include any taxes,
customs, duties, including re-export duties, fees on equipment and tools levied by the
PURCHASERS government or the country of the place of the delivery, social security
contribution, stamp duties, or any other dues. All such expenses are to be borne by the
Purchaser who shall indemnify and hold the SUPPLIER harmless accordingly. The
CONTRACT PRICE excludes any duties, taxes or levies except those
withholding taxes which the PURCHASER is bound by law of Pakistan to
deduct.
4.5
45.
Terms of payment
Page - - 13
45.1
Payment of the CONTRACT PRICE shall be effected by the PURCHASER as set out
below.
100% of the CONTRACT PRICE shall be paid out of an irrevocable and confirmed
documentary sight letter of credit.
45.2
For the payments specified in this clause 4.1 an irrevocable and confirmed
documentary sight letter of credit, acceptable to the SUPPLIER and according to the Annex
III, shall be prepared by the PURCHASER and handed over to the SUPPLIER within 20
calendar days after the effective date of this ContractCONTRACT. The letter of credit shall
be confirmed by a first class PakistaniGerman bank and shall be valid at least 3 month
after the date of delivery according to Clause 3.
4.3
In the event the PURCHASER fails to prepare the letter of credit as provided for in
Clause 4.2 above in time the SUPPLIER will extend the delivery dates specified in Clause 2.2
accordingly. The SUPPLIER shall be also entitles to claim liquidated damages for delayed
payment or issue of the letter at a rate of 0.5% of the delayed payment or letter of credit for
every full week of delay, but no more than an aggregate of 5% of the amount of the delayed
payments and/or letter of credit. After reaching the maximum liquidated damages for delay the
SUPPLIER shall grant the PURCHASER a reasonable extension for the payment or the issue
of the letter of credit. If such extension expires and the PURCHASERS has not made the
delayed payments or opened the letter of credit due to the PURCHASERS negligence, the
SUPPLIER shall have the right to terminate the Contract by giving a written notice to the
PURCHASER. The PURCHASER has to indemnify the SUPPLIER from any costs resulting
from performance of this Contract which can not be compensated otherwise.
45.4
All bank charges, duties, fees and taxes or other charges and fees in
connection with the payments to be made hereunder and / or the preparation of
the letter of credit shall be borne and paid by PUCHASER, unless otherwise
agreed in this CONTRACT. All L/C charges outside the country of SUPPLIER shall
be on PURCHASER account except for confirmation charges, which are on
SUPPLIER account.
6.
6.2
The PURCHASER may place CHANGE ORDER (S) at any time, provided such
changes are technically feasible and acceptable to the SUPPLIER. No CHANGE
ORDER shall, together with any change/modification already ordered, involve a net
addition to or reduction from the CONTRACT PRICE of more than 15% unless the
SUPPLIER and PURCHASER agree in writing.
6.3
6.4
Within three (3) weeks after receipt of such CHANGE ORDER the SUPPLIER shall
offer in writing an AMENDMENT to this CONTRACT, defining the necessary
changes to the GENSETS, the PROJECT TIME SCHEDULE (APPENDIX VI) and
any other terms of this CONTRACT and the additional price for such changes, if
any.
6.5
Within further two (2) weeks the PARTIES shall agree in writing upon an
AMENDMENT incorporating the changes.
Page - - 14
6.8
6.6
Until an AMENDMENT is agreed upon, the SUPPLIER shall proceed with the
GENSETS supply as if no changes were implied.
6.7
SUSPENSION
6.8.1 The PURCHASER may for its convenience or for any other reason whatsoever
suspend the carrying out of the manufacture of the GENSETS by the SUPPLIER in
whole or in part, at any time, by giving written notice thereof to the SUPPLIER
specifying the nature, effective date and anticipated duration of such suspension
and the SUPPLIER shall without undue delay give full effect to and comply with
such notice of suspension.
6.8.2 The SUPPLIER shall be entitled to suspend the carrying out of the manufacture of
the GENSETS in whole or in part by giving written notice thereof to the
PURCHASER in the event any payments to the SUPPLIER are not effected within
30 days of the due date as per Article 4. Upon receipt of the amount(s) due from
the PURCHASER, the SUPPLIER shall resume the carrying out of the manufacture
of the GENSETS forthwith.
6.8.3 In the event of suspension as per Articles 6.8.1 and 6.8.2 above, the PURCHASER
shall pay to the SUPPLIER all additional costs and expenses demonstrably
accruing to the SUPPLIER as consequence of the cessation and resumption of the
manufacture of the GENSETS including costs for proper protection and
maintenance of the GENSETS. The PURCHASER shall pay such costs and
expenses monthly against invoices provided by the SUPPLIER.
6.8.4
In the event of suspension as per Articles 6.8.1 and 6.8.2 above liquidated damages for
late delivery shall not be due and payable for the period of the suspension.
57.
Risk of loss
7.1
Risk of loss and damage to the GENSETS shall be transferred to the PURCHASER
when the GENSETS is delivered at Site.
7.2
Title to the GENSETS shall be transferred to the PURCHASER when the delivered at
SITE.
7.3 In case of any damage to the GENSETS or any part thereof the
SUPPLIER shall up to FINAL ACCEPTANCE arrange for the repair of the
GENSETS or part concerned, or deliver replacement for such GENSETS
or part thereof DDP SITE at its own cost and expense as specified in
the CONTRACT. In case of any shortage or discrepancy the SUPPLIER
shall clarify the same. In case of any short shipment or wrong
shipment of the GENSETS or any part thereof SUPPLIER shall deliver
such short shipped or wrongly shipped GENSETS or part thereof up to
acceptance DDP SITE at its own cost and expense as specified in the
CONTRACT. However, SUPPLIER may include any such short shipped or
wrongly shipped GENSETS or part thereof in the next scheduled
shipment (DDU) Karachi if this does not have any adverse effect on the
ERECTION schedules.
Page - - 15
7.4 PURCHASER will accept the repair of the GENSETS only under the
following conditions:
7.5
a)
The repair does not effect the overall life time of the GENSETS.
b)
7.6 The SUPPLIER shall continue to perform its obligations under the
CONTRACT during the time required for replacement of the lost
relevant GENSETS or part thereof.
By way of clarification it is agreed that the transfer of risk and
ownership of the GENSETS shall not in any manner, absolve the
SUPPLIER of its other obligations and liabilities under the CONTRACT.
5.1 The risk of loss passes to the PURCHASER in accordance with Incoterms 2000 conditions
as stated in Clause 2.1, irrespective of whether only a part of the goods to be supplied are
ready for dispatch or shipped or whether the SUPPLIER is required to render additional
services under the contract, such as transportation or installation. The SUPPLIER, at the
PURCHASERS expense, shall obtain such insurance as the PURCHASER may request in
writing, covering losses which are at the PURCHASERS risk arising out of theft, breakage,
transportation, fire and water damage, as well as out of such other insurable casualties as
the PURCHASER may specify.
5.2 In the event of delay in shipment for which the PURCHASER is responsible, the risk of loss
passes to the PURCHASER as of the date the goods are ready for dispatch. From this date
on the GENSETS will be stocked on account and at the risk of the PURCHASER. The
SUPPLIER shall, however, upon request and expense of the Purchaser, contract the
insurance requested by the PURCHASER.
86.
WARRANTY
86.1
Page - - 16
86.2
The SUPPLIER shall at its own expenses shall and at the sole option of the
SUPPLIER, exchange, replace or repair such parts of the GENSETS which have failed or
which have essential impact on their usability during a period of 24 months after the date of
commissioning of the GENSETS or and 360 months after the transfer of perils to the
PURCHASER, whichever period expires first, solely as a result of a substantial deficiency
which was inherent in the GENSETS or the part thereof before transfer of perils and due
faulty design, faulty material or bad workmanship.
86.32 The PURCHASER must promptly notify the SUPPLIER in writing of obvious defects or
deficiencies after detection thereof. Replaced parts shall become the property of the
SUPPLIER upon request of the SUPPLIER.
86.4
The SUPPLIER is not liable for defects or deficiencies which are resulting from the
following reasons, as long as they are not resulting from a default of the SUPPLIER;
Importer, unsuitable or negligent use, handling and/or operation of the GENSETS by the
PURCHASER or third parties; improper or faulty installation respectively commissioning by
the PURCHASER or third parties; use of spare parts other than Genuine DEUTZ Power
Systems Parts; normal wear and tear; use of unsuitable consumables (such as, fuel, oil,
cooling liquid or any other consumables), particularly the use of consumables not
conciliated in the operation manuals; improper building ground; chemical; electro-chemical
or electric influences.
86.5
The SUPPLIER shall at its own costs and expense rectify defects for which the
SUPPLIER is responsible according to this Article, within one month or other such time to
be agreed in advance between the SUPPLIER and the PURCHASER. During such period
the SUPPLIER shall be liable to pay the PURCHASER liquidated damages of @ 0.50 % of
the CONTRACT PRICE for each full week which on aggregate shall not exceed in any
event 5% of the CONTRACT PRICE during which the SUPPLIER carried out the repairs. If
the SUPPLIER fails to rectify such defects within such time period, the PURCHASER may
grant an extension of time to SUPPLIER to rectify such defects and charge liquidated
damages at the rate mentioned herein above or the PURCHASER may terminate the
CONTRACT and shall be entitled to compensation as mentioned in Article 10.7. The costs
for the rectifying the defects shall be born by the SUPPLIER. If the SUPPLIER neglects to
rectify such defects within the agreed time, the PURCHASER is entitled to execute the
work necessary to rectify the defect at cost and risk to the SUPPLIER, by giving fourteen
(14) days written notice to that effect and charge liquidated damages at the rate mentioned
herein during the rectification period. The PURCHASER shall be obliged to allow after
agreement with the SUPPLIER the required time and opportunity for all repairs and
replacements necessary in SUPPLIERS sole discretion, otherwise the SUPPLIER shall be
exempt from his obligations.
86.5
The PURCHASE shall be entitled to remove any defects or deficiencies by himself or
third parties and to claim from the SUPPLIER compensation or necessary costs only in
urgent case of threat of operational reliability and for defence of out of scale of damages, in
which cases the SUPPLIER shall be informed immediately, respectively if the SUPPLIER is
behind the schedule with rectification of deficiencies.
86.76 During the WARRANTY PERIOD, the SUPPLIER shall have the rights of access to the
EQUIPMENTGENSETS, provided that he has informed the PURCHASER duly in
advance.The SUPPLIER shall bear insofar as the complaint is legitimate out of all costs
directly arising from repair or replacement only the costs for the spare parts including the
delivery costs and the reasonable costs for removal and minting, as well, if this can be fairly
required in the individual case, the costs for eventual necessary mechanics and back staff
of PURCHASER. Other costs shall be borne by the PURCHASER.
86.87 The initial warranty period of the GENSETS will not be extended due to repair or
replacement of parts.If, during the WARRANTY PERIOD, any part of the
Page - - 17
8.9.2
8.10.2
79.
Acceptance
9.1
9.2
Page - - 18
shall inform the SUPPLIER in writing about the date of readiness of START UP and
COMMISSING by giving thirty days notice in advance. Five days before STARTUP and
COMMISSIONING the PURCHASER shall send to the SUPPLIER the completed
installation check list, confirming that the mounting and installation of the
EQUIPMENTGENSETS has been finalized according to SUPPLIERS Technical
Description (Annex II) and project related documentation and that all SITE facilities
necessary for EQUIPMENTGENSETS operation are ready for continuous and
uninterrupted operation.
9.3
9.4
97.51 The PARTIES agree that directly after the commissioning a performance test shall be
executed. For the execution of a performance test the following applies;
a) This Supply Contract and the description of scope of supply for the GENSETS may
include many different performance parameters and technical data related to the
GENSETS. However the PRTIES agree that the only critical performance
parameters related to the GENSETS are electrical output and fuel consumption to
the extent each is specified in Annex IV (hereinafter referred to as ACCEPTANCE
PARAMETERS).
ab) The PURCHASER has to inform the SUPPLIER about the execution of the
performance test in such due time, at least two weeks before the test should be
executed, that the SUPPLIER or his representative are able to participate.
b) Regarding the performance test a protocol will be furnished and signed by
PURCHASER and SUPPLIER or their representatives. This protocol will specify
the PROVISIONALTAKE OVER of the EQUIPMENTGENSETS. The
EQUIPMENTGENSETS will be considered PROVISIONAL TAKE OVER by the
PURCHASER if the Performance ParametersACCEPTANCE PARAMETERS
(Annex IV) are achieved during the PERFORMANCE and RELIABILITY
TEST.acceptance of the GENSETS or the conditional acceptance of the
GENSETS. In the latter case possible defects claimed by the PURCHASER have
to b included in the protocol. The GENSETS will be considered as as
PROVISIONAL TAKE OVERaccepted, if the ACCEPTANCE PARAMETERS are
achieved during the performance test PERFORMANCE and RELIABILITY TEST.
c) If and when tested the EQUIPMENTGENSETS fails to achieve the performance
parametersACCEPTANCE PARAMETERS as per APPNDIX IV the SUPPLIER
shall be afforded a period of one month or such other period as otherwise agreed
between the PARTIES, during which the SUPPLIER at its own costs and expenses
can repair, correct and/or adjust the EQUIPMENTGENSETS, at its own cost and
expense,
so
the
EQUIPMENTGENSETS
achieve
the
performance
parametersACCEPTANCE PARAMETERS as per APPENDIX IV. During such
period the SUPPLIER shall be liable to pay the PURCHASER liquidated damages
of @ 0.50 % of the CONTRACT PRICE for each full week which on aggregate shall
not exceed in any event 5% of the CONTRACT PRICE during which the
SUPPLIER carried out the repairs. If the SUPPLIER fails to rectify such defects
within such time period, the PURCHASER may grant an extension of time to
SUPPLIER to rectify such defects and charge liquidated damages at the rate
mentioned herein above or the PURCHASER may terminate the CONTRACT and
shall be entitled to compensation as mentioned in Article 11.7. The costs for the
Page - - 19
The contractual tolerances and the tolerances of the meausirng system applies in
favour of the SUPPLIER.
b) fuel consumption
Page - - 20
The total of all liquidated damages is limited to a total of 5% of the contract price of
deficient gensets.
79.54
The liability of the SUPPLIER for meeting the ACCEPTANCE PARAMETERS expires;
a)
b)
c)
79.65
Any other claims of the PURCHASER resulting from faults of the GENSETS, in
particular any claim of compensation of damages, not occurring on the GENSETS
themselves are exhausted. The PURCHASER shall without delay give his FINAL
ACCEPTANCE of the EQUIPMENTGENSETS after the expiration of the WARRANTY
PERIOD, after which all obligations of the PARTIES under this CONTRACT will come to an
end.
9.7 PERFORMANCE AND RELIABILITY TESTS\
9.7.1 Precondition:
During all test runs SUPPLIERs GENSETS will run parallel with existing generators of the
PURCHASER.
Test run in speed mode: with all GENSETS, PURCHASER provides load sharing signal
according to interface list and electrical overview from SUPPLIER. In case of a mechanical
governor on the PURCHASERS engines, test run with droop cooperation (lower frequency on
full load).
Test run in power mode: with all GENSETS of SUPPLIERs (All SUPPLIERS GENSETS are
set to a fixed value of 90-100% of nominal power) and fluctuation will be covered with existing
engines of PURCHASER.
In case less electrical load or natural gas is available, the PERFORMANCE TEST(S) should be
accomplished on a unit by unit basis. Time for testing must be notified by SUPPLIER to
PURCHASER at least two (2) weeks in advance.
Note: Only possible if PURCHASERs engines are able to run with load sharing line, power
mode.
(According to the precondition in the Technical Descriptions)
9.7.2 Performance Test Run
Testing of the GENSETS shall include a SUPPLIERs guided [72] hours non-stop test run
(excluding oil consumption), operated by PURCHASERs personnel in order to show
performance mentioned in item ________ of this CONTRACT. COMMISSIONING engineer of
the SUPPLIER is only obliged to stay [8 hours] per day at SITE, which is up to him when he will
be available. If the engine fails to perform at the test run, COMMISSIONING engineer has [6]
hours time to solve the problem, without that the test period counts from zero again. If
Page - - 21
COMMISSIONING engineer needs more than [6] hours, then the test run will be started again.
If any of the GENSETS are not able to fulfil the test run due to any other reason, which is not
caused by the SUPPLIER, COMMISSIONING engineer is not obliged to wait until the test run
can be carried out. If test run should be carried out at later stage, PURCHASER bears cost for
travel to the SITE and the accommodation costs in advance unless postponement is caused
due SUPPLIERs fault. After successful test run the SUPPLIER and PURCHASER will sign the
Form of GENSETS Acceptance Report.
9.7.3 RELIABILITY TEST Run:
This RELIABILITY TEST run will last [15 days] and will take place immediately after the [72]
hours PERFORMANCE TEST run. This RELIABILITY TEST Run will be supervised by the
SUPPLIER. During the last (3) three days of this RELIABILITY TEST Run GENSETS data
can be collected.
108.
8.1 The SUPPLIER shall not be liable to the PURCHASER for any indirect or consiquental loss
or damage whatever of which legal ground, including, but not limited to, loss of profit, loss
of use, loss of production or loss of contracts.
8.2 Without prejudice to the limitations and exclusions of liability in favour of the SUPPLIER the
aggregate liability of the SUPPLIER to the PURCHASER, whether under the Supply
Contract or under Law is limited to 7.5% of the total contract price according to Clause 3.1.
10.1
The SUPPLIER shall be liable to the PURCHASER for any physical loss of or damage
to the EquipmentGENSETS or property of the PURCHASER caused directly or
indirectly by the fault of the SUPPLIER during the performance of the SUPPLIERS
obligations under the CONTRACT.
10.2
The SUPPLIERS liability shall not, in any circumstances, exceed 30% of the
CONTRACT PRICE. If the SUPPLIER incurs liability exceeding the said amount, the
PURCHASER shall indemnify, defend and hold the SUPPLIER harmless.
10.3
The limit as specified section 10.2 above shall not include SUPPLIERs liability
a)
b)
c)
d)
10.4 Any liability of the SUPPLIER shall cease at the end of the respective WARRANTY
PERIOD, applicable for the part of works due to which the damage was caused.
10.5
The limitations and exclusions stated under this Article shall apply
for any liability of the SUPPLIER under the CONTRACT, in tort, under
any theory of strict liability or otherwise. The limitations and
exclusions stated under this Article do, however, not apply to
damages or loss caused by wilful act on the part of the SUPPLIER. Nor
Page - - 22
11.1
The PURCHASER shall at any time until delivery be entitled to terminate the
CONTRACT for its convenience with immediate effect upon notice thereof to the
SUPPLIER, whereupon the SUPPLIER shall take all steps to cease all further work
and performance under the CONTRACT, on the date of termination specified by
the PURCHASER in his notice and to terminate all SUBSUPPLIERS, orders or
contracts with Suppliers on the best terms possible.Following such termination by
the PURCHASER, the PURCHASER shall become liable to pay to the SUPPLIER
all incurred and committed costs.
11.2
The PURCHASER shall have the right to terminate the CONTRACT for any
material breach by the SUPPLIER by giving thirty (30) days prior written notice to
the SUPPLIER of its intention to terminate the CONTRACT in order to allow the
PARTIES to reach a mutually beneficial solution thereof, if one of the following
conditions has occurred due to reasons other than Force Majeure:
11.3
11.4
11.5
If, for the reasons attributable to SUPPLIER, SUPPLIER fails to perform any or all
of the PERFORMANCE and RELIABILITY TESTS within a maximum period of
[01 months] in respect of the EQUIPMENTGENSETS in order to meet the
PRODUCT Performance ParametersACCEPTANCE PARAMETERS as specified in
Annex IV including Minimum Performance as per Article 9.5 (d) and Annex IV then
the PURCHASER shall be entitled to terminate the CONTRACT.
11.6
11.7
Page - - 23
11.8
The carrying out of the CONTRACT has been suspended by the SUPPLIER for
more than three (3) months and the payments have not been effected by the
PURCHASER during the said period; or
11.9
11.10
11.112
129.
Force Majeure
12.1
12.2
"Force Majeure" for the purpose of this Article 12 shall mean the
actual happening and not mere therat or apprehension of happening in
Paksitan near relevant PLANTGENSETSs SITE of any and all
events or fortuitous circumstances which directly affect
SELLERUPPLIER
and/or
its
subcontractors,
or
BUYERPURCHASER's and/or his contractors in their
implementation of their respective obligations under or in connection
with the CONTRACT and completion of the relevant
PLANTGENSETS as per the Project Time Schedules in respect of
the PLANTGENSETS as attached at ANNEX 6__ and shipment
schedule and which are beyond their respective control, such as but
not limited to, strike, lockout, labour disputes, fire, explosion, nuclear
catastrophes, transportation accidents, natural disaster, earthquake,
riot, rebellion, war, government seizures, laws, or other regulations of
any authority.
12.3
The aggrieved party will notify the other party in writing of any event
of Force Majeure within [fourteen (14)] days of its occurrence (or if
this cannot be done for reason of Force Majeure, as soon as possible
thereafter), and as soon as possible of the consequences of such an
event. Thereupon, both parties will discuss and agree in good faith
how to overcome the consequences of the Force Majeure occurred.
12.4
Page - - 24
OFFICIAL APPROVALS
13.1 The EQUIPMENTGENSETS shall comply with applicable regulations and
requirements of the authorities within the country of construction of the
EQUIPMENTGENSETS, valid on the effective date of this CONTRACT.
13.2 The SUPPLIER shall provide the applicable documentation related to the
EQUIPMENTGENSETS in accordance with Project Time ScheduleDocument
Submittal Schedule (Annex XVI). The PURCHASER is responsible for obtaining all
necessary approvals, permits, licences within the country of construction of the
EQUIPMENTGENSETS.
14.
REPRESENTATIVES
14.1
For the EQUIPMENTGENSETS supply phase of the project the SUPPLIER and
PURCHASER shall name Project Managers for the project co-ordination.
150.
150.1This Contract shall become effective from the date of signature thereof by both PARTIES.
150.2Collateral agreements and changes of the Contract shall be valid only when executed In
writing.
150.3Previous agreements on the subject matter of this Contract shall become invalid upon
signature of the Contract.
150.4in the event that individual provisions of the Contract have become or become invalid
upon conclusion or during the term of this Agreement, the remaining provisions shall,
nevertheless remain valid. The PARTY will make efforts to agree on new provisions instead
of the invalid ones which will be legally effective, correspond to the tenor of this Contract
and approach the purpose of the invalid provision as much as possible.
150.5In the event the down payment or payments guarantees according to Clause 4 are not
executed within 12 months after the date of effectiveness of the contract, the Contract will
be automatically cancelled.
10.6 In the event of any inconsistency or conflict between the terms and
conditions of this Contract and the annexes to this Contract, the documents
should prevail each other in the following order.
Page - - 25
a)
b)
10.7
If one or several provisions of this Contract should be legally invalid for any
reason whatsoever, the validity of the remaining provisions shall not be
affected thereby. In such case, the PARTIES shall replace the invalid
contractual provision by such other provision coming as close as possible to
the legal and economic purpose of the Contract. The same shall apply
mutatis mutandis to any nuclear provision contained in this Contract. If the
PARTIES fail to meet their duty to replace or complete any such provision,
the above mentioned requirements of this Contract.
161.
161.1 All dispute and differences which may arise out of or in connection wit the
present CONTRACTAgreement, or the breach thereof, which cannot be settled
amicably between the PARTIES shall be finally settled, excluding any other
jurisdiction but for enforcement of the arbitral award, by arbitration under the
Pakistan Arbitration Act 1940Rules of arbitration of the international chamber of the
commerce (icc, paris) by an arbitration committee of three arbitrators.
161.2 The place of arbitration proceedings shall be Lahore, PakistanGeneva,
Switzerland. The language of arbitration shall be the English language.
116.3 The arbitration award shall be final and binding on both Parties and subject
to no appeal and shall deal with the question of the costs of arbitration and all
matters relating thereto.
161.4 The PARITES agree that this Agreement shall be governed by and construed
in accordance with the laws of Switzerland, with the exception of the United Nations
Conventions on the International Sale of Goods (CISG).
The CONTRACT shall be construed and interpreted in all respects in accordance with its own
provisions and all agreements concluded between the PARTIES in connection
therewith, and, subsidiary, in accordance with Pakistani law and the exclusive
jurisdiction of the Pakistani Courts.
17.
TAXES
17.1
Any taxes, duties, fees, and other fiscal charges, including customs duties, directly or
indirectly levied by any authority or country outside Pakistan in connection with the
CONTRACT, its conclusion or its execution shall be borne and directly paid by
SUPPLIER.
17.2
Except as specifically otherwise agreed in the CONTRACT , any taxes, duties, fees,
and other fiscal charges, including customs duties, directly or indirectly levied by the
authorities of Pakistan, including government appointed surveyors, in connection with
the CONTRACT, its conclusion or its execution (hereinafter collectively referred to as
"Impositions") shall be borne and directly paid by PURCHASER over and above the
agreed prices stated or referred to in the CONTRACT.
17.3
The all or any income tax due towards the SUPPLIER in relation to this
CONTRACT whether in Pakistan or outside Pakistan shall be sole
responsibility of the SUPPLIER.
17.4
If SUPPLIER shall effectively obtain a credit against any German taxes payable on the
basis of taxes paid by PURCHASER on behalf of SUPPLIE in Pakistan, which are
evidenced by tax receipts, in the English language, handed over to SUPPLIER, then
Page - - 26
SUPPLIER shall pass on to PURCHASER the net benefit of such tax credit and
reimburse to PURCHASER the corresponding amount of such tax credit.
17.5
18.
18.1
18.2
19.
19.1
Either PARTY shall not assign the CONTRACT unless mutually agreed between the
Parties. The SUPPLIER shall be responsible for all EquipmentGENSETS supplied by
all SUB-SUPPLIERS.
20.
20.1
The CONTRACT shall become valid upon the formal execution (signing) by
duly authorised officers of the PARTIES.
IN WITNESS WHEREOF, the parties hereto have caused this document to be executed and
signed as follows on the day and date first above written.
Page - - 27
_____________________________
Place
______________________________________
Date
____________________________________________________________________
for Rupali Polyester Ltd.
_____________________________
Place
______________________________________
Date
____________________________________________________________________
for DEUTZ Power Systems Gmbh
Witness:
__________________________
Name: ____________
Witness:
_________________________
Name: ____________