Republic of the Philippines

ZAMBOANGA CITY WATER DISTRICT


Pilar Street, Zamboanga City
I.

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Project Title
Proposed Production Well & Collection Center
Gov. Ramos Avenue, Zamboanga City,

II.

Background
2.1This project is a supplementary payment facility that is
proposed to facilitate ZCWD customers in paying their bills
which aims to reduce the struggles of long queues and
anticipates providing comfort to the customers while waiting
for their turn.
2.2The proposed project is set to utilize the area where existing
Production Well Facility is located. It is primarily situated at
Lot 3-B-2, Gov. Ramos Avenue, Barangay Sta. Maria,
Zamboanga City having total lot area of 359 square meters.
The area encloses existing generator set with steel canopy,
production well borehole system with concrete shelter and
concrete fence with steel gate.
2.3The proposed 140 square meters floor area facility
encompasses Security Area, Operators Room, Collectors
Area, Concessionaires Lounge, Supervisors Cubicle, Rest
Area/File Storage/Janitorial Area and toilets. This proposal
covers the parking area, relocation of existing discharge pipe,
relocation of front fence and relocation of generator set with
newly fabricated generator set concrete pad/foundation.
Furniture, appliances specified in the proceeding item of
works is covered in this proposal.
2.4This project has been submitted for initial review by the
Zamboanga City Planning Office in conformity to the setback
requirement.

III.

Purpose and Objectives


3.1The proposed Payment Facility project will mainly serve the
ZCWD (Zamboanga City Water District) customers for
barangays nearly located with the proposed facility or any
customer who would wish to transact with this proposed
payment facility.
3.2The facility may help alleviate the inconvenience that many
customers experience when they are unable to pay on
schedule due to long queues and heavy traffic going to
ZCWD Main Payment Center at city proper.

1 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
IV.

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

General
4.1 PERMITS AND CLEARANCES:
The Contractor shall bear the preparations and payments of all the
necessary permits and clearances of the different agencies; this
include the conduct of lot relocation to established the required
boundary, and other forms of works necessary for the commencement
of the project.

4.2WORK INCLUDED:
Lot Relocation, staking out of building, establishment of lines, grades
and benchmark. All excavation works including all necessary shoring
bracing, and drainage of storm water from site. All backfilling, filling
and grading, removal of excess material from site Protection of
property, work and structures, workmen, and other people from
damage and injuries.
4.3 LINES, GRADES, BENCHMARKS:
Stake out accurately the lines of the building and of the other
structures included in the contract, and establish grades therefore after
which secure approval by Engineer before excavation work
commenced. Erect basic batter boards and basic reference marks, at
such places where they will not be disturbed during the construction of
the foundations.
4.4 DISPOSAL OF SURPLUS MATERIALS:
Any excess materials remaining after hauling and spreading shall be
disposed of after the completion of the earthwork to ZCWD Property in
Lupong Road, Cabatangan, Z.C.. Excavated material deposited in spoil
areas shall be graded to a uniform surface.

V.

Scope of Works/ Item Description/Specifications


5.1Structure Excavation
2 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

General
This pertains to Item 103(1)a, standards set by the Department
of Public Works and Highways (DPWH) latest edition of the
Bluebook. Procedures, manpower and equipment to be used
shall comply with the DPWH Bluebook Standards. Excavation
works shall cover all necessary pit digging for Building footing,
Wall footing, Generator set concrete pad, and pipe laying
excavation for the relocation of discharge pipe.
Except when specifically provided to the contrary, excavation
shall include the removal of materials of whatever nature
encountered, including all obstructions of any nature that would
interfere with the proper execution and completion of the work.
The removal of said materials shall conform to the lines and
grades shown or ordered. Unless otherwise provided, the entire
construction site shall be stripped of all vegetation and debris,
and such materials shall be removed from the site prior to
performing any excavation or placing any fill. The contractor
shall furnish, place and maintain all supports and shoring that
may be required for the sides of the excavations, and all
pumping, ditching, or other approved measures for the removal
or exclusion of water, including taking care of storm water and
waste water reaching the site of the work from any source, so as
to prevent damage to the work or adjoining property.
The walls and faces of all excavations in which workers are
expose to danger from unstable ground shall be guarded against
by a shoring system, sloping of the excavation, or some other
acceptable method. The Contractor shall furnish, install, and
maintain such sheeting, bracing, etc., as may be necessary to
protect the workers and to prevent any movement of earth
which could injure or delay the work or endanger adjacent
structures. In excavation where workers may be required to
enter, excavated or other materials shall be effectively stored
and retained at least 600mm or more from the edge of the
excavation. All excavation and trenching operations shall
conform with any and all national, provincial, and local safety
requirements.

5.1.1 Excavation Beneath Proposed Structures


Except where otherwise specified for a particular
structure or ordered by the Engineer, excavation shall
be carried to the grade of the bottom of the footing or
slab. Where shown or ordered, areas beneath proposed
structures shall be over-excavated. When such over3 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

excavation is shown on the Drawings, both overexcavation and subsequent backfill to the required
grade shall be performed by the Contractor at his own
expense. When such over-excavation is not shown but
is ordered by the Engineer, such over-excavation and
any resulting backfill will be paid for under a separate
unit price bid item if such bid item has been
established, otherwise, payment will be made in
accordance with the negotiated prices. After the
required excavation or over-excavation has been
completed, the exposed surface shall be scarified to a
depth of 150mm (6 in.) brought to optimum moisture
content, and rolled with heavy compaction equipment
to ninety-five percent (95%) of maximum density.

5.1.2 Excavation Beneath Areas to be Paved


Excavation under areas to be paved shall extend to the
bottom of the aggregate base, if such base is called
for, otherwise, it shall extend to the bottom of paving.
After the required excavation has been completed, the
exposed surface shall be scarified, brought to optimum
moisture content, and rolled with heavy compaction
equipment to ninety percent (90%) of maximum
density.

5.1.3 Disposal of Excess Excavated Material


The Contractor shall remove and dispose all excess
excavated material at ZCWD Property in Lupong Road,
Cabatangan, Z.C. in a manner approved by the
Engineer, the cost thereof shall be made chargeable to
the contractor.

5.1.4 Excavation in Vicinity of Trees


Except where trees are shown on the drawings to be
removed, trees shall be protected from injury during
construction operation; and no tree is to be removed
without written permission from the Engineer. No tree
roots over 50 mm (2 in.) in diameter shall be cut
without the permission of the Engineer. Trees shall be

4 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

supported during excavation as may be directed by the


Engineer.
5.2Foundation Fill
General
This pertains to Item 103(3), standards set by DPWH
Department of Public Works and Highways latest edition of the
Bluebook. Excavated materials that were acquired earlier during
excavation can be used to fill the excavated area, however
during compaction, the materials maybe insufficient to fill the
excavated area entirely. It is the responsibility of the contractor
to provide additional filling materials to make use of.

Backfill shall not be dropped directly upon any structure or pipe.


Materials used for backfill shall be selected material, free from
grass, roots, brush or other vegetation, or rocks having
maximum dimension larger than 150 mm (6 in.). material placed
within 150 mm (6 in.) of any structure or pipe shall be free of
rocks or unbroken masses or earth materials having maximum
dimension larger than 75 mm (3 in.). Backfill shall not be placed
around or upon any structure until the concrete has attained
sufficient strength to withstand the loads imposed.
5.2.1 Backfill Around and Beneath Proposed Structures
and Paved Areas
Except where otherwise specified for a particular
structure or ordered by the Engineer, backfill
placed around and beneath proposed structures
and paved areas, shall be placed in horizontal
layers not to exceed 200 mm (8 in.) in thickness,
as
measured
before
compaction,
where
compaction is attained by means of sheep foot
rollers, pneumatic type rollers or any heavy
compaction equipment approved by the
Engineer. Where the use of heavy compaction
equipment is impractical, the layers shall not
exceed 150 mm (6 in.) in thickness before
compaction, and compaction shall be attained
by means of hand-operated power driven
tampers. The backfill shall be brought up evenly,
with each layer moistened and compacted by
mechanical means to ninety-five percent (95%)
of
maximum
density
beneath
proposed
structures, and ninety percent (90%) of
maximum density around the sides of structures
and beneath proposed paved area.
5 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

5.2.2 Embankment Fill


The area where an embankment is to be
constructed shall be cleared of all vegetation,
roots and foreign materials. Following this, the
surface shall be moistened, scarified to a depth
of 150 mm (6 in.) and rolled or otherwise
mechanically compacted to ninety percent
(90%)
of
maximum
density
elsewhere.
Embankment fill shall be placed in horizontal
layers not to exceed 200 mm (8 in.) in thickness,
as
measured
before
compaction,
where
compaction is attained by means of sheep foot
rollers, pneumatic type rollers or any approved
heavy compaction equipment. Where the use of
these equipment is impracticable, the layers
shall not exceed 150 mm (6 in.) in thickness
before compaction, and compaction shall be
attained by means of hand-operated powerdriven tampers. The backfill shall be brought up
evenly with each layer moistened and
compacted by mechanical means to ninety-five
percent (95%) of maximum density under
proposed structures, and ninety percent (90%)
of maximum density elsewhere. The top 500
mm (20 in.) of backfill or embankment shall
consist of loamy earth free of rocks larger than
25 mm (1 in.) in maximum dimension.

5.3Demolition Works (Masonry & Concrete)


Demolition Works covers the existing concrete fence at the
faade of the perimeter fence, including the dismantling of
existing steel gate, and the borehole concrete shelter. Only
masonry and concrete structures for demolition are measured
per square meter and deemed for payment. Any dismantling
works related to the structure is part of the contractors scope at
no extra charge.
5.4Reinforced Concrete
This pertains to Item 405, standards set by DPWH Department of
Public Works and Highways latest edition of the Bluebook. This
item covers all the structural element of the proposed building.
Exteriors Ground Slabs such as ramp/parking area, driveway or
6 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

perimeter area outside the building covers at 200mm thickness.


Thickness may vary upon actual implementation at site. The use
of bagger mixer/transit mixer and concrete vibrator is required
for concreting and shall conform to the ideal materials tested as
per DPWH Standards. Concrete Sampling for material testing
shall comply with the standard procedures set by DPWH
Bluebook for proper guidance. It is obligatory to use the Class
A concrete mix for all the structural elements of the building.
The work to be undertaken under this Section shall include all
labor, materials, equipment, plant and other facilities and the
satisfactory performance of all work necessary to complete all
concrete work shown on the Drawings and specified herein. All
work included under this Section shall be subject to the General
Conditions accompanying these specifications. The Contractor is
required to refer especially thereto.

5.4.1 MATERIALS
Cement
Except as may be otherwise provided in these
specifications, cement shall conform with the
Standard Specifications for Portland Cement
(ASTM C- 150 Latest Revision) and shall be
Type I. The cement shall be of one brand and
shall not be more than three (3) months from
date of manufacture.
Concrete-Aggregates
Concrete aggregates shall be well-graded, clean,
hard particles of gravel or crushed rock
conforming with the Standard Specifications
for Concrete Aggregates (ASTM C-33 Latest
Edition).
The maximum size of the aggregates shall not
be larger than one-fifth (1/5) of the narrowest
dimension between forms and not larger than
three-fourths (3/4) of the minimum clear spacing
between individual reinforcing bars, or bundles
of bars, and in no case larger than 38 mm (1-1/2
in.) in diameter except that larger diameters
may be allowed in massive concreting with
written permission from the Engineer.
Water used in mixing concrete shall be clean
and free from injurious amounts of oils, acids,
alkali, organic materials, or other substances
that may be deleterious to concrete or steel.

7 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Reinforcing Steel
All reinforcing steel bars used shall be of
deformed type, new, free from rust, oil, defects,
Greases, or kinks. They shall conform with the
latest edition of National Structural Code for
Buildings with a minimum grade equal to 275
Mpa unless otherwise shown on the plans.

5.4.2 STORAGE OF MATERIALS


Cement and aggregates shall be stored in such a
manner as to prevent deterioration or intrusion
by foreign matter. Any material which has
deteriorated or which has been damaged shall
not be used for concrete. Steel shall be stored
under cover or otherwise prevented from
rusting.

5.4.3 TESTING OF MATERIALS


The Owner or his duly authorized representative
or the Engineer shall periodically order the test
of any material supplied by the Contractor
entering into concrete or reinforced concrete to
determine its suitability for the intended
purpose. Such tests shall be in accordance with
the standard of the American Society for Testing
and Materials, as noted elsewhere in this
Specification. Samples shall be provided by the
Contractor without cost to the Owner. Expenses
for the testing and cost of transporting samples
to testing laboratory shall be borne by the
Contractor. Compressive strength specimen for
tests of concrete during construction shall be
according to Making and Curing of Concrete
Compression
and
Flexural
Strength
Test
Specimens in the Field (ASTM C-31).

5.4.4 CONTROLLED STREGTH OF CONCRETE


Concrete for structural elements, including slabs
on grade within water-retaining structures and
shall develop minimum 28-day compressive
cylinder strength of 20.68 mega Pascal (3,000
psi), unless otherwise specified in the plans.
Concrete for non-structural elements such as
cradles, un-reinforced encasements, thrust
blocks, and partition walls shall develop a
8 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

minimum of 28-day cylinder strength of 17.25


MPa (2,500 psi), unless otherwise specified in
the plans.

5.4.5 EXCLUSION OF WATER


No concrete shall be placed in any structure
until all water entering the space to be filled
with concrete has been properly cut off or has
been diverted by pipes, or other means, and
carried out of the forms, clear of the work. No
concrete shall be deposited under water without
the explicit permission of the Engineer, and then
only in strict accordance with his decisions, nor
shall the Contractor, without explicit permission,
allow still water to rise on any concrete until the
concrete has attained its initial set. Water shall
not be permitted to allow over the surface of any
concrete in such manner and at such velocity as
will injure the surface finish of the concrete.
Pumping or other necessary dewatering
operations for removing ground water, if
required, will be subject to the approval of the
Engineer.

5.4.6 MIXING CONCRETE


Hand mixing is allowed only in mixing
aggregates and cement for plastering and
mortar purposes. No hand mixing shall be
allowed pouring of concrete on monolithic
structures except in emergency such as mixer
breakdown during concreting operations and
this shall stop as soon as the pour is completed,
at a construction joint shown or otherwise
designated by the Engineer. All concrete shall be
machine mixed for at least one and one- half (11/2) minutes after all materials, including water,
are in the mixing drum.
The mixer shall of an approved size and type
which will ensure a uniform distribution of
material throughout the mass. It shall be
equipped with a device for accurately measuring
and controlling the amount of mixing water in
such batch.

9 | Page

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

The first batch of concrete materials placed in


the mixer shall contain a sufficient excess of
cement, sand, and water to coat the inside of
the drum without reducing the cement of the
mix to be discharged.
Re-tempering, i.e, remixing with the addition of
water to concrete that has been partially
hardened will not be permitted.

5.4.7 PREPARATION OF STRUCTURE FOR CONCRETE


Earth surfaces shall be thoroughly wetted by
sprinkling prior to the placing of any concrete,
and these surfaces shall be kept moist by
frequent sprinkling up to the time of placing
concrete thereon.
Concrete surfaces upon or against which
concrete is to be placed, where the placement of
old concrete has been stopped or interpreted so
that, in the opinion of the Engineer, the new
concrete cannot be incorporated integrally with
that previously placed, are defined as
construction joints. The surfaces of the
horizontal joints shall be leveled with a wooden
float to provide a reasonably smooth surface. A
surface consisting largely of coarse aggregate
shall be avoided. Except where the drawings call
for joint surfaces to be painted, the joint
surfaces shall be cleaned of all laitance, loose or
defective concrete, and foreign material. Such
cleaning shall be accomplished by sandblasting
followed by thorough washing. All pools of water
shall be removed from the surface of
construction joints before the new concrete is
placed. After the surfaces have been prepared to
the
satisfaction
of
the
Engineer,
all
approximately horizontal construction joints
shall be covered with a layer of mortar
approximately 25 mm (1 in.) thick.
The mortar shall have the same proportion of
cement and sand as the regular concrete
mixture, unless otherwise directed by the
Engineer. The water-cement ratio of the mortar
in place shall not exceed that of the concrete to
be placed upon it, and the consistency of the
10 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

mortar shall be spread uniformly and shall be


worked thoroughly into all irregularities of the
surface, and wire brooms shall be used where
possible to scrub the mortar into the surface.
Concrete shall be placed immediately upon the
fresh mortar.
When the placing of concrete is to be
interrupted long enough for the concrete to take
a set, the working face shall be given a shape by
the use of forms or other means that will secure
proper union with subsequent work, provided
that construction joints shall be made only
where approved by the Engineer.

5.4.8 PLACING CONCRETE


Concrete which upon or before placing is found
not to conform with the requirements specified
herein shall be rejected and immediately
removed from the work. Concrete which is not
placed in accordance with these specifications,
or which is of inferior quality, as determined by
the Engineer, shall be removed and replaced by
and at the expense of the Contractor. No
concrete shall be placed except in the presence
of a duly authorized representative of the
Engineer. Prior to placing any concrete, the
Contractor shall give the Engineer twenty-four
(24) hours written notice.
Concrete shall be deposited in its final position
without segregation, re-handling, or flowing.
Placing shall be done in preferably with buggies,
buckets, or wheelbarrows. No chutes will be
allowed except to transfer complete from
hoppers to buggies, wheelbarrows, or buckets in
which case, they shall not exceed six (6) meters
(20 ft.) in aggregate length.
Placing of concrete with a free drop or fall more
than 1.20 meters (4 ft.) shall not be allowed,
except when approved by the engineer and
when approved sheet metal conduits, pipes, or
elephant
trunks
are
employed.
When
employed these conveyors shall be kept fall of
11 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

concrete and the ends kept buried in newly


placed concrete as pouring progresses.
Concrete in forms shall be deposited in uniform
horizontal layers not deeper then 450mm (18in.)
and care shall be taken to avoid inclined layers
or incline contraction joints except where such
are required for slopping members. Each layer
shall be placed while the previous layers are still
soft. The rate of placing concrete in forms shall
not exceed 1.5mtrs. (5ft.) of vertical rise per
hour.

5.4.9 FORMS
The Contractor shall provide forms to confine
the concrete and shape it to the repaired lines.
Plastering, in general, shall not be allowed. The
Contractor shall assume full responsibility for the
adequate design of all forms. However, forms
which in the opinion of the Engineer are unsafe
or inadequate in any respect may at any time be
condemned by the Engineer, and the Contractor
shall promptly remove the condemned forms
from the work and replace them at his own
expense. A sufficient number of forms of each
kind shall be provided to permit the required
rate of progress to be determined.
Whenever, in the opinion of the Engineer,
additional forms are necessary to maintain the
progress schedule, such additional forms shall
be provided by the Contractor at his own
expense. The design and inspection of concrete
forms, false work, and shoring shall comply with
the applicable safety regulations, and as may be
specified in the General Conditions of these
Specifications.

5.4.9.1

Materials

Except as otherwise expressly approved by the Engineer, all lumber


brought at the job site for use as forms, shoring, or bracing shall be
new material.
All forms shall be smooth surface forms and shall be of the following
materials:
Walls

steel or plywood panels


12 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
Columns
Slab

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

steel, plywood or surface lumber

plywood

All other work -

steel panels, plywood or surface lumber

Column forms shall be checked for plumb ness before concrete is


deposited. Hand holes shall be provided in column forms at lowest
points of pour lifts to render this space accessible for cleaning.
All girder, beam, and slab centerlines shall be crowned at least 6.4mm
(1/4 in.) in all directions for every 4.57 meters (15 ft.) span. However,
cambers from all cantilevers shall be as indicated on the plans or
obtained from the Engineer by the Contractor.
The following are the tolerance limits for formwork:
Variation from plumb:
In lines and surface of columns, piers, walls and risers:
In 3.05 m (10 ft)

6.3 mm (1/4 in.)

6.10 m (20 ft)

9.5 mm (3/8 in.)

12.20 m (40 ft)


or more

19.0 mm (3/8 in.)

For exposed corner columns and/or piers, control joint grooves and
other conspicuous lines:
In any bay 6.10 m
(20 ft) max.

6.3 mm (1/4 in.)

In 12.20 m (40 ft)


or more

13.0 mm (1/2 in.)

Variations in cross-sectional dimensions of columns and piers, beams,


and thickness of walls and slabs:
Minus
Plus

6.3 mm (1/4 in.)


13.0 mm (1/2 in.)
13 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Footings
Variations in dimensions on drawings (applied to concrete only and not
to reinforcing bars or dowels):

Minus
Plus

13.0 mm (1/2 in.)


50.0 mm (2 in.)

Misplacement of eccentricity, two percent (2%) of the footings


width in the direction of misplacement but not to exceed 50.0
mm (2 in.)

Reduction in thickness - five percent (5%) at specified thickness

5.4.9.2

Design

All forms shall true in every respect to the required shape and size,
shall conform with the established alignment and grade, and shall
be of sufficient strength and rigidity to maintain their position and
shape under the loads and operations incident to placing and
vibrating the concrete. Suitable and effective means shall be
provided on all forms for holding adjacent edges and ends of panels
and sections tightly together and in accurate alignment so as to
prevent the formation for ridges, fins, or offsets, or similar surface
defects in the finished concrete. Plywood, 16.0 mm (5/8 in.) and
greater in thickness, may be fastened directly to studding if the
studs are close enough to prevent visible deflection marks in
concrete.
The forms shall be tight so as to prevent the loss of water, cement,
and fins during placing and vibrating of the concrete. Adequate
clean-out holes shall be provided at the bottom of each lift of forms.
The size, number, and location of such clean-outs shall be subject to
the approval of the Engineer.
Concrete construction joints will not be permitted on locations other
than those shown or specified, except as may be approved by the
Engineer. When a second lift is placed on hardened concrete,
special precaution shall be taken in the way of the number, location,
and tightening of ties at the top of the old lift and bottom of the new
to prevent any unsatisfactory effect whatsoever on the concrete.
Pipe stubs and anchor bolts shall be set in the form where required.

14 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Unless otherwise shown, exterior corners in concrete members shall


be provided with 19.0 mm (3/4 in.) chamfers. Re-entrant corners in
concrete members shall not have fillets unless otherwise shown
All vertical surfaces of concrete members shall be formed, except
where placement of the concrete against the ground is called for on
the drawings or explicitly authorized by the Engineer. Not less than
25mm (1 in.) of concrete shall be added to the thickness of the
concrete member as shown where concrete is permitted to be
placed against trimmed ground in lieu of forms. Such permission will
be granted only for members of comparatively limited height and
where the character of the ground is such that it can be trimmed to
the required lines and will stand securely without caving or
sloughing until the concrete has been placed.

5.4.9.3

Maintenance of Forms

Forms shall be maintained at all times in good condition, particularly as


to size, shape, strength, rigidity, tightness, and smoothness of surface.
Forms, when in place, shall conform with the established alignment and
grades. Before concrete is placed, the forms shall be thoroughly
cleaned. Forms may be reused if in good condition and if approved by
the Engineer. Light sanding between uses will be required wherever
necessary in the opinion of the Engineer to obtain uniform surface
texture on all exposed concrete surfaces. Exposed concrete surfaces
are defined as surfaces which are permanently exposed to view. In the
case of forms for the inside wall surfaces of hydraulic structures,
unused tie rod holes shall be covered with metal caps or shall be filled
by other methods approved by the Engineer.

5.4.9.4

Removal of Forms

Directions of the Engineer concerning the removal of forms shall be


strictly followed, and this work shall be done with care so as to avoid
injury to the concrete, and this work shall be done with care so as to
avoid injury to the concrete. No heavy loading on green concrete will
be permitted. In the case of roof slabs and above-ground floor slabs,
forms remain in place until test cylinders for the roof concrete attain a
minimum compressive strength of 15.52 MPa (2,250 psi) provided that
no forms shall be disturbed or removed under an individual panel or
unit before the concrete in the adjacent panel or unit has attained a
strength of 15.52 MPa (2,250 psi) and has been in place for a minimum
of seven (7) days. The time required to establish said strength will be
determined by the Engineer who will make several test cylinders for
this purpose from concrete used in the first group of roof panels placed.
If the time so determined is more than the seven-day minimum, then it
shall be used as the minimum length of time. Forms for all vertical
15 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

walls and columns shall remain in place at least three (3) days after the
concrete has been placed. Forms for all parts of the work not
specifically mentioned herein shall remain in place for periods of time
as ordered by the Engineer.
50 mm (2 in.) clearance between said items and any part of the
concrete reinforcement. Securing such items in position by wiring or
welding them to the reinforcement will not be permitted.

5.4.10ORDER OF PLACING CONCRETE


The order of placing concrete in all parts of the
work shall be subject to the approval of the
Engineer. In order to minimize the effects of
shrinkage, the concrete shall be placed in units
as bounded by construction joints shown on the
drawings. The placing of the units shall be done
by placing alternate units in a manner such that
each unit place shall have cured at least seven
(7) days before the contiguous unit or units are
placed, except that vertical walls shall be placed
until wall footings have cured at least fourteen
(14) days, and the corner sections of vertical
walls shall not be placed until all the adjacent
wall panels have cured at least fourteen (14)
days.
The surface of the concrete shall be level
whenever a run of concrete is stopped. To insure
a level, straight joint on the exposed surface of
walls, a wood strip at least 19.0mm (0.75in.)
thick shall be tacked to the forms on these
surfaces. The concrete shall be carried about
13.0mm (0,50in.) above the underside of the
strip. About one hour after the concrete is
placed, the strip shall be removed and any
irregularities in the edge formed by the strip
shall be leveled with s trowel and laitance shall
be removed.

5.4.11TAMPING AND VIBRATING


As concrete is placed in the forms or in
excavations, it shall be thoroughly settled and
compacted through-out the entire depth of the
layer which is being consolidated, into a dense,
homogeneous mass, filling all corners and
angles,
thoroughly
embedding
the
16 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

reinforcement, eliminating rock pockets, and


bringing only a slight excess of water to the
exposed surface of concrete during placement.
Concrete in walls shall be internally vibrated and
at the same time rammed, stirred, or worked
with suitable appliances, tamping bars, shovels,
or forked tools until it completely fills the forms
or excavations and closes snugly against all
surfaces. Subsequent layers of concrete shall
not be placed until the layers previously placed
have been worked thoroughly as specified.
Except in special cases where their use is
deemed impracticable by the Engineer, the
contractor shall use internally vibrated, high
speed power vibrators not less than 8000 rpm of
an approved immersion type in sufficient
numbers, with standby units as required, to
accomplish the results herein specified within
fifteen (15) minutes after concrete of the
prescribed consistency is placed in the forms.
The vibrating head shall be kept from contact
with the surfaces of the forms. Care shall be
taken not to vibrate concrete excessively or to
work it in any manner that causes segregation of
its face.

5.4.12CARE AND REPAIR OF CONCRETE


The Contractor shall protect all concrete against
injury or damage from excessive heat, lack of
moisture, overstress, or any other cause until
final acceptance by the Owner. Particular care
shall be taken to prevent the drying of concrete
and to avoid roughening or otherwise damaging
the surface. Any concrete found to be damaged
or which may have been originally defective, or
which becomes defective at any time prior to
the final acceptance of the concrete work, or
which departs from the established line or
grade, or which for any other reason does not
conform with the Specifications, shall be
satisfactorily repaired or removed and replaced
with acceptable at the Contractors expense.

5.4.13FINISH OF CONCRETE SURFACES

17 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

All finished or formed surfaces shall conform


accurately with the shape, alignment, grades
and sections as indicated on the plans or as
prescribed by the Engineer. Surfaces shall be
free
from
fins,
bulges,
ridges,
offsets,
honeycombing, or roughness of any kind, and
shall present a finish, smooth, continuous hard
surface.
Except as otherwise provided herein, unformed
top surfaces of concrete shall be brought to
uniform surfaces and worked suitable tools to a
reasonably smooth wood flat finish. Excessive
floating of surfaces while the concrete is plastic
will not be permitted. All surfaces shall be
placed monolithically with the base slab. Dusting
of dry cement and sand on the concrete surface
to absorb excess moisture will not be permitted.
Floor slabs and exposed tops of walls and curbs
shall be given a steel trowel finish. At the
Contractors option, the above mentioned floor
slabs may be finished with a power float after
screenings. Subsequent to the aforementioned
finish, all sloping surfaces of concrete
pavements for diveways shall be lightly
broomed to provide a skid-resistant surface.

5.4.14TREATMENT OF SURFACE DEFECTS


As soon as forms are removed, all exposed
surfaces shall be carefully examined at any
irregularities shall be immediately rubbed or
ground in a satisfactory manner in order to
secure a smooth, uniform, and continuous
surface. Plastering or coating of surfaces to be
smooth will not be permitted, No repairs shall be
made until after inspection by the Engineer, and
then only in strict accordance with his directions.
Concrete containing voids, holes, honeycombing,
or similar depression defects shall be completely
removed and replaced; provided that where
required or approved by the Engineer, defects
shall be repaired with gunite or with cement
mortar placed by an approved compressed air
mortar gun. In no case will extensive patching of
honeycomb concrete be permitted. All repairs
and replacements herein specified shall be
promptly executed by the Contractor at his own
expense.
18 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Defective surfaces to be repaired as specified in


Subsection (a) hereon, shall be cut back from
true line a minimum depth of 13.0mm (1/2in.)
over the entire area. Feathered edges shall be
avoided. Where chipping or cutting tools are not
required in order to deepen the area properly, the
surface shall be prepared for bonding by the
removal of all laitance or soft material, and not
less than 0.79mm (1/32in.) depth of the surface
film from all hard portions, by means of an
efficient
sandblast.
After
cutting
and
sandblasting, the surface shall be wetted
sufficiently in advance of shooting with guide or
with cement mortar so that while the repair
material is being applied, the surfaces under
repair will remain moist, but not so wet as to
overcome the section upon which a good bond
depends. The material used for repair purposes
shall consist of mixture of one (1) bag of cement
to 0.08 m3 (3 ft3) of sand. For exposed walls, the
cement shall contain such a proportion of white
Portland cement as is required to make the color
or patch match the color of the surrounding
concrete.
Holes left by the tie-rod cones shall be reamed
with suitable toothed reamers so as to leave the
surfaces of the holes clean and rough. These
holes then shall be repaired in an approved
manner with dry-packed mortar. Holes left by
form-typing devices having a rectangular crosssection and other imperfections having a depth
greater than their least surface dimension, shall
not be reamed but shall be repaired in an
approved manner with dry-packed mortar.
All repairs shall be built up and shaped in such a
manner that the completed work will conform
with the approved methods which will not disturb
the bond, cause sagging or horizontal fractures.
Surfaces of said repairs shall receive the same
kind and amount of curing treatment as required
for the concrete in the repaired section.
Prior to filling any structure with water, any
cracks that may have developed shall be veed
as shown on the drawings and filled with sealant.

5.4.15PLACING REINFORCEMENTS
19 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

All reinforcement shall be placed in accordance


with the plans furnished by the Engineer. In case
of any doubt or ambiguity in placing of steel, the
Contractor shall consult with the Engineer whose
decision shall be final in such cases.
All loose rust or scale, all adhering materials,
and all oil or other materials which tend to
destroy bond between the concrete and the
reinforcement shall be removed before placing
the steel and before concreting begins.
Metal reinforcement shall be accurately placed
and adequately secured by using annealed iron
wire ties or suitable clips at intersections and
shall be supported by concrete or metal
supports, spacers, or metal hangers. The
minimum clear distance between parallel bars
shall be one and one-half (1-1/2) times the
diameter for round bars, and twice the side
dimension for square bars. In no case shall the
clear distance between bars be less than 25mm
(1in.) nor less than one and one-third (1-1/3)
times the maximum size of the coarse
aggregate. Where bars are used in two or more
layers, the bars in the upper layers shall be
placed directly above those in the lower layers
at a clear distance of not less than 25mm (1in.).
Bends for stirrup and ties shall be made around
a pin having a diameter not less than six (6)
times the minimum thickness of the bar, except
that for bars larger than 25mm (1in.), the pin
shall not be less than eight (8) times the
minimum thickness of the bar. All bars shall be
bent cold.
Reinforcement steel shall not be straightened or
relent in a manner that will injure the material.
Bars with kinks or bends not shown on the
drawings shall not be used. Heating of the
reinforcement will be permitted only when
approved by the Engineer.

5.4.16OFFSETS AND SPLICES IN REINFORCEMENTS

20 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

In slabs, beams, and girders, splices or


reinforcement at points of maximum stress shall
be generally avoided, and may be allowed only
upon written approval of splice detail of the
Engineer. Splices shall provide sufficient lap to
transfer stress between bars by bonding shear
or by butt-welding to develop in tension at least
one hundred twenty-five percent (125%) of the
specified yield strength of the reinforcing bar.
Splices in adjacent bars shall be generally
staggered.
Where changes in the cross-section of a column
occur, the longitudinal bars shall be offset in a
region where lateral support is afforded. Where
offset, the slope of the incline portion of the bar
with the axis of the column shall not be more
than one in six, in the case of tied columns, the
ties shall be spaced not over 76mm (3in.) on
center for a distance of 300mm (12in.) below
the actual point of offset unless otherwise shown
on the plans.

5.5Masonry Works
This item shall cover all the perimeter and partition walls in
accordance with the provided BOQ (Bill of Quantities) and plans.
All perimeter and partition walls are specified to use 4 thick
CHB (Concrete Hollow Blocks). Wire Meshes on existing
perimeter fence shall be removed and replaced with 4 CHB. All
wall footing requires 6 CHB making the footing tie beam in
place. Reinforcements for the masonry walls and zocalo footing
should correspond to the provided detailed drawings.
5.5.1 Laying
All masonry shall be laid plumb, true to line, with
level and accurately spaced course, and with
each course breaking joint with the course
below. Bond shall be kept plumb throughout,
corners shall be plumb and true. Units with
greater than 12% absorption shall be wetted
before laying. Work required to be built in with
masonry, including anchors, wall plugs and
accessories shall be built in as the erection
progresses.
21 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Masonry units - each course shall be solidly


bedded in Portland cement mortar. All units shall
be damped when laid; units shall be showed into
place not laid in full bed of un-furrowed mortar.
All horizontal and verticals points shall be
completely filled with mortar when aid in full bed
of un-furrowed mortar. All horizontal and vertical
points shall be bonded at corners and
intersections. No cells shall be left open in face
surfaces. All cells shall be filled up with mortar
for exterior walls. Units terminating against
beams or slab shall be wedged tied with mortar.
Do not lay cracked, broken or defaced block.

Lintels shall be of concrete and shall be


reinforced as shown on the drawings. Lintels
shall have a minimum depth of 0.20 (8") and
shall extend at least 0.20(8") on each side of
opening.

5.5.2 Workmanship and Installation


Plastering: Clean and evenly wet surfaces. Apply
scratch coat with sufficient force to form good
keys. Cross scratch coat upon attaining its initial
set: Keep damped. Apply brown coat after
scratch coat has set at least 24 hours after
scratch coat application. Apply lightly scratch
brown coat, Keep moist for 2 days, and allow
drying out. Do not apply finish until brown coat
has seasoned for 7 days. Just before applying
coat, wet brown coat again. Float finish coat to
22 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

true even surface, trowel in a manner that will


force sand particles down into plaster with final
trawling, leave varnished smooth, free from
rough areas, trowel marks, checks, other
blemishes. Keep finish coat moist for at least
two (2) days, thereafter protect against rapid
drying until properly, thoroughly cured.

5.5.3

Scaffoldings
Provide all scaffoldings required for masonry
work, including cleaning down after completion.

5.6Plastering Works
Plastering Works requires minimum 12mm thickness with Class
mixture of 1:3 for internal wall plastering and 1:3 for external
wall plastering (Cement and Fine Sand Ratio). This covers both
sides of the walls having smooth surface finish ready for
painting.
5.7Roof Framing Works
5.7.1 Rafter
Top and Bottom Chord are specified as double
angle of 38mm x 38mm x 6mm thickness. Web
Members are specified as 12mm, plain round
bars welded unto the top and bottom chord.
Application of anti-corrosion paint is mandatory.
Refer to drawings for details.
5.7.2 Purlins
Ga. 16 50mm x 100mm C channel purlins
spaced at 0.60m 10mm deformed bars bracing
support. Application of anti-corrosion paint is
mandatory. Refer to drawings for details.
5.8Roofing Works

23 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Metal roofing sheets shall be of Rib Type design with effective


coverage of 1070mm at any variant of pre-painted royal blue
color. The Contractor shall verify the correct gauge of the metal
sheet with caliper upon actual inspection of materials witnessed
by ZCWD resident engineer. All bended accessories such as end
flashings and ridge rolls shall be of Ga. 26 matching the
specified color of the metal roof sheet. It shall all conform to the
detailed drawings provided. All areas covered with metal roofing
sheet must have 20mm thick Aluminized Polyethylene (P.E.)
foam for insulation. The insulation must have metal wire cross
meshing to avoid it from sagging.
5.9Ceiling Works
5.9.1 Ceiling Frames
All carrying channels, hangers and ceiling joist
are specified to be 0.4mm x 13mm x 50mm
Aluminum Metal Furring fastened and joined
with blind rivets
5.9.2 Boards
The specified ceiling board is Fiber Cement type
having 3.50mm bare thickness.
5.9.3 Mouldings
Ceiling Mouldings shall have a size of 3 and 5
floor mouldings/baseboards.
5.10

Plumbing Works

Plumbing specifications shall conform to the provided detailed


plans adhering to the National Plumbing Code of the Philippines.
5.10.1Plumbing Fixtures
Water Closets - One piece, jet flush water closets
with complete fittings and accessories
Lavatory at Toilets with faucet Pedestal Type
Lavatory (Oval Shaped) with complete fittings
and accessories.
Kitchen Sink with faucet - Brushed Finish
Stainless steel single bowl with dish drain
Soap Holder/ Toilet Paper Holder Brushed Finish
Stainless steel
24 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Bidet Spray Plastic Bidet spray with chrome


coating and stainless flexible hose.
5.11

Sealed Septic Vault (3.50m x 1.20m x 2.45m)

The specifications of the septic vault shall conform to the


provided detailed plans adhering to the standards of the National
Plumbing Code of the Philippines. Waterproofing admixture shall
be applied to concrete mixture and as well as bituminous
membrane torched and applied to the inside surface of the
septic vault.

5.12

Tile Works
5.12.1Concessionaires Area, Collectors Area,
Supervisors Cubicle,
Rest Area, Security
Area, Operators Room
These areas shall have 600mm x 600mm
Granite Tiles with application of 25mm Floor
topping before tile installation. Tiles are installed
at 2.5mm spaces where application of tile grout
is expected. Tile Grout shall conform to the color
of the granite tiles
5.12.2Toilet Area (Floors)
Flooring for the toilet area shall be of 300mm x
300mm Ceramic tiles with application of 12mm
floor topping before tile installation. Tile grout
color shall conform to the color of ceramic tiles.
5.12.3Toilet Area (Walls)
Walls for the toilet area shall be of 300mm x
300mm Ceramic tiles with application of 12mm
floor topping before tile installation. Tile grout
color shall conform to the color of ceramic tiles.
5.12.4Faade Area (Security Area)
25 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Faade Walls at Security area shall be of 400mm


x 400mm Ceramic tiles (Stone Design) with
application of 12mm topping before tile
installation. Tile grout color shall conform to the
color of ceramic tiles.
5.12.5Faade Area (Main Entrance Area)
Faade Walls at Main Entrance shall be of
300mm x 600mm Ceramic tiles (Stone Design)
with application of 12mm topping before tile
installation. Tile grout color shall conform to the
color of ceramic tiles.
5.13

Supply and Installation of Jalousie Windows

All jalousie windows shall have 2 x 6 Window Jambs with 6mm


thick bronze smoked glass blades with Aluminum frames. Actual
sizes of the windows shall be verified at site for accuracy in
measurement upon installation.
5.14 Supply and Installation of PVC Doors with complete
Accessories (0.60m x 2.10m)
Prefabricated PVC doors are of 600mm x 2100mm size with
bottom louver. PVC doors are mainly utilized for toilets.
5.15

Supply and Installation of Flush Type Door (0.80m x 2.10m)

Flushed Type Doors are to be fabricated except for its window


jambs. Dimensions and measurement shall conform to the
provided detailed plans. The preferred good lumber to be used
for flushed type door is Mahogany.
5.16

Tubular Type Window Assembly (2.870m x 1.80m)

This window opening is aesthetically designed to remain open


for the entire daily operation. The tubular design shall consist of
1.2mm x 50mm x 50mm B.I. (Black Iron) Square Hollow Section.
12mm dowel is welded unto the main frame to be anchored
and welded to existing masonry walls. Measurement and exact
dimensions for the tubular design are specified in the provided
drawing details. These window types are primarily located at the
faade of the building.

26 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
5.17

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Iron Grille Type Window Assembly

This window type is located at the rear part of the building which
allows natural light at the rear area of the building. It shall
consist of 16mm plain round bar design with dimensions and
measurements as per provided detailed drawing.
5.18

Supply and Installation of Manual Operated Roll-Up Door

Roll-Up Doors will use at the Glass Main Door Entrance and the
tubular type windows. It shall conform to the following
specifications:

5.18.1Slats
The slats are formed in as cold-rolled process in
continuous
lengths
of
galvanized
steel
interlocked to form curtains.
5.18.2Gauge
The rolled-up door gauge is specified to be Ga.
24 or higher.
5.18.3Endlocks
End locks are fitted to each end of alternate
slats to achieve slat alignment and to serve as a
wearing surface
5.18.4Galvanizing
Zinc Coated
5.19

Supply and Installation of Aluminum and Glass Works


5.19.11.20m x 1.25m Glass Sliding Window
The frames shall be of FD100 Analok Aluminum
Frames with 12mm Bronze Glass. Dimensions
and Measurements, to verify at site.
5.19.22.10m x 2.20m Glass Sliding Window
The frames shall be of FD100 Analok Aluminum
Frames with 12mm Bronze Glass with push
plate, pull bar and other accessories necessary.
Dimensions and Measurements, to verify at site.
27 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

5.19.3Counter Security Glass (6.07m x 1.00m)


The counter security glass shall be using 6mm
thick clear glass on SOB Moulding with 1 x 2
Anodized Rectangular section. Provision of
speak hole and money hole are with specified
positions and dimensions indicated in the
provided detailed plan.

5.20

Electrical Works

The proposed project shall be undertaken in accordance with the


established standards set by the Local Electric Cooperative,
Zamboanga City Electric Cooperative (ZAMCELCO), and shall be
done in conformity with Philippine Electrical Code (PEC).
Signing & sealing of plans shall be at the expense of the
contractor to include the necessary and other incidental charges
thereof.
5.20.1Safety
5.20.1.1
Ensure that safety, security and
housekeeping guidelines are issued and
implemented by the Contractor.
5.20.1.2
Regularly conducts walk-through
inspection
on
the
jobsites
and
immediately calls attention to unsafe
practices and work conditions.
5.20.1.3
Every personnel working in the
project must equip with protective gear
and gadgets for safety precautions.
5.20.2System & Energization
5.20.2.1
Ensure the proper tests and all
pertinent electrical system specifications
of the Project. This includes the tests of
(2) units of Air Condition units and (3)
units of Industrial orbit fan. The supply for
the same is part of Contractors scope.
28 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

5.20.2.2
The Contractor will be responsible
for energization to the electrical lines
including initial energy deposit, to cover
also the documentation requirements. The
ZCWD personnel must be informed ahead
of the scheduled energization works.
5.20.3Post Completion Phase
5.20.3.1
Upon completion of project work,
an inspection must be conducted together
with the ZCWD and the Contractor.
5.20.3.2
Immediate commission must
done after approval of
inspection.

be

5.20.3.3
A final inspection must be done by
the ZCWD Inspection Committee.
5.20.4Construction Phase
5.20.4.1 Distributing Poles
The distributing poles to be provided by
the Agency shall be factory made 35
Footer and 45 Footer Round Centrifugal
Pre-stressed Concrete or Galvanized Steel
Poles with Minimum Break Load of 500
Kg.; 140mm and 268mm Top and Butt
Diameter respectively, that shall conform
to National Electrification Administration
(NEA) and Local Power Co./Cooperatives
Standards.
5.20.5Pole Setting
5.20.5.1 The minimum depth for setting poles
shall be as follows:
Length of Poles

Setting in Soil

(feet)

(feet)

Setting in Solid
Rock
(feet)

35

6.0

4.0
29 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
45

6.5

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City
4.5

5.20.5.2
Setting in Soil specifications shall
apply:
-Where the poles are to be set in soil.
-Where there is a layer of soil of more
than two (2) feet in depth over solid rock.
-Where the hole in solid rock is not
substantially vertical or the diameter of
the hole at the surface of the rock
exceeds
approximately
twice
the
diameter of the pole at the same level.
5.20.5.3
"Setting
in
All
Solid
Rock"
specifications shall apply where poles are
to be set in solid rock and where the hole
is substantially vertical, approximately
uniform in diameter and large enough to
permit the use of tamping bars the full
length of the hole.
5.20.6

Grading of Line

When using high poles to clear obstacles such as


buildings, foreign wire crossings, railroads, etc.,
there shall be no up strain on pin-type insulators in
grading the line each way to lower poles.
5.20.7

Guys and Anchors


Guys shall be placed before the conductors are
strung and shall be attached to the pole as
shown in the Construction Drawings.
All anchors and rods shall be in line with the strain
and shall be so installed that approximately six (6)
inches of the rod remain out of the ground. In
cultivated fields or other locations, as deemed
necessary, the projection of the anchor rod above
earth may be increased to a maximum of twelve
(12) inches to prevent burial of the rod eye. The
backfill of all anchor holes must be thoroughly
tamped the full depth.
When a cone anchor is used, the hole, after the
anchor has been set in place, shall be backfilled with
30 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

coarse crushed rock for two feet above the anchor,


tamping during the filling with the remainder the
hole to be backfilled and tamped with dirt.
5.20.8

Locknut
A locknut shall be installed with each nut or other
fastener on all bolts or threaded hardware such as
insulator pins, upset bolts, double arming bolts, etc.

5.20.9

Conductors
All conductors to be used for low voltage
transmission must be made of copper. Conductors
must be handled with care. Conductors shall not be
trampled on nor run over by vehicles. Each reel shall
be examined and the wire shall be inspected for
cuts, kinks, or other injuries. Injured portions shall be
cut out and the conductor spliced. The conductors
shall be pulled over suitable rollers or stringing
blocks properly mounted on pole or crossarm if
necessary to prevent binding while stringing.
The neutral conductor should be maintained on one
side of the pole (preferably the road side) for
tangent construction and for angles not exceeding
thirty degrees (30O). With pin-type insulators the
conductors shall be tied in the top groove of the
insulator on tangent poles and on the side of the
insulator away from the strain at angles. Pin-type
insulators shall be tight on the pins and on tangent
construction the top groove must be in line with the
conductor after tying in.
For neutral and secondary conductors on poles,
insulated brackets (Material Item) may be
substituted for the single and double upset bolts on
angles of 0 to 5 in locations known to be a subject
to considerable conductor vibration.
All conductors shall be cleaned thoroughly by wire
bushing before splicing or the installation of
connectors, clamps or tapping armor rods.
A
suitable inhibitor shall be used on aluminum
conductors
before
splicing,
before
applying
connectors, clamps or before installing tapping
armor rods.

31 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Equipment grounding conductors shall be UL 83


insulated stranded copper, except that sizes 6 mm
(10 AWG) and smaller shall be solid copper.
Insulation color shall be continuous green for all
equipment grounding conductors, except that wire
sizes 25 mm (4 AWG) and larger shall be permitted
to be identified per PEC.
Bonding conductors shall be ASTM B8 bare stranded
copper, except that sizes 6 mm (10 AWG) and
smaller shall be ASTM B1 solid bare copper wire.
All electrical works including equipment grounding,
bonding and color coding of conductors must
conform to the provisions of the Philippine Electrical
Code.
5.20.10

Splices and Deadends

Conductors shall be spliced and dead ended as shown


on the construction drawings. There shall be not more
than one splice per conductor in any span and splicing
sleeves shall not be located near conductor support.
Maintain ten feet or more separation between the
splice and the conductor support. NO splices shall be
located in Grade B crossing spans and preferably not
in the adjacent spans. A high-grade Hydraulic
Crimping tool must be used in the termination of
conductors.
5.20.11

Taps and Jumpers

Jumpers and other leads connected to line conductors


shall have sufficient slack to allow free movement of
the conductors. Where slack is not shown on the
construction drawings it will be provided by at least
two bends in a vertical plane, or one in a horizontal
plane, or the equivalent. In areas where aeolian
vibration occurs, special measures to minimize the
effects of jumper breaks shall be used as specified.
All leads on equipment: such as transformers,
reclosers, etc., shall be a minimum of #6 copper
conductivity.
5.20.12

Hot-Line Clamps and Connectors

32 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Connectors and hot-line clamps suitable for the


purpose shall be installed as shown on Guide
Drawings. On all hot-line clamp installations, the clamp
and jumper shall be so installed so that they are
permanently bonded to the load side of the line,
allowing the jumper to be de-energized when the
clamp is disconnected. This applies in all cases, even
where the line layout is such that the tap line is in
actuality the main back to the power source.
Do not install hot-line clamps directly to ACSR
conductors. Use tapping armor rods or tap saddles.
Before installing hot line clamps to the surface of
tapping armor rods thoroughly clean by wire bushing
and apply a suitable inhibitor to the area of the tapping
armor rod coming into contact with the hot-line clamp.
5.20.13

Lighting Arrester Gap Settings

The external gap electrodes of lightning arresters,


combination arrester cutout units, and transformermounted arresters shall be adjusted to the
manufacturers' recommended spacing. Care shall be
taken, that the adjusted gap is not disturbed when the
equipment is installed.
5.20.14

Conductor Ties

Ties shall be in accordance with Construction


Drawings. Hot-line ties shall not be used at Grade "B"
crossings.

5.20.15

Sagging of Conductors

Conductors shall be sagged in accordance with the


conductor
manufactures
recommendations.
All
conductors shall be sagged evenly. A certified etched
glass thermometer shall determine the air temperature
at the time and place of sagging.
The sag of all conductors after stringing shall be in
accordance with the conductor manufacturers'
recommendations, except that a maximum increase of
three inches of the specified sag in any span will be
acceptable. However, under no circumstances will a
decrease in the specified sag be allowed.
33 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

5.20.16

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Secondaries and Service Drops

Secondary conductors may be bare or covered wires or


multi-conductor service cable. The conductors shall be
sagged in accordance with manufacturers'
recommendations.
Conductors for secondary under build on primary lines
will normally be bare except in those instances where
prevailing conditions may limit primary span lengths to
the extent that covered wires or service cables may be
used. Service drops shall be covered wire or service
cable.
Secondaries and service drops shall be so installed as
not to obstruct climbing space. There shall not be more
than one splice per conductor in any span, and splicing
sleeves shall not be located near the conductor
support. Maintain ten feet or more separation between
the splice and the conductor support. Where the same
covered conductors or service cables are to be used for
the secondary and service drop, they may be installed
in one continuous run.
Retapping to the new 3-Phase power supply of the
existing single phase and all other existing electrical
connections shall be done prior for testing and
commissioning of the project.
All convenience outlet must be of 3 Gang (with
ground) universal type with ground and childlock protection.
AFCI (Arc Fault Circuit Interrupter) for Main and
Branches Circuit Breaker are required.
For circuits located in moist conditions, the same
must be of GFCI-type (Ground Fault Circuit
Interrupter)

5.20.17

Grounds

Electrical systems that are grounded shall be


connected to earth in a manner that will limit the
voltage imposed by lighting, line surges or
unintentional contact with higher voltage lines and that
34 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

will stabilize the voltage to earth during normal


operation.
Non-current carrying conductive materials enclosing
electrical conductors or equipment, or forming parts of
such equipment, shall be connected to earth so as to
limit the voltage to ground on these materials.
Bonding of electrical equipment for non-current
carrying conductive materials, equipment or forming
parts shall be connected together in a manner that
establishes an effective ground-fault current path.
Effective ground-fault current path shall be installed in
a manner that creates a permanent, low impedance
circuit facilitating the operation of the overcurrent
device for high impedance grounded system capable of
carrying the maximum ground-fault current imposed
on it.
Ground rods shall be driven in undisturbed earth in
accordance with the Construction Drawings. Where
aluminum ground wire is used, it must be terminated
above ground at a galvanized ground rod or spliced by
a compression connector to a copper or steel ground
wire - extension to the ground rod, of which the top of
the ground rod shall be 12 inches or more below the
surface of the earth. The ground wire shall be attached
to the rod with a clamp and secured to the pole with
staples. The staples on the ground wire shall be spaced
two feet apart except for a distance of eight feet above
the ground rod and eight feet down from the top of the
pole where they shall be six inches apart.
All equipment shall have at least two connections from
the frame, case or tank to the multi-grounded neutral
conductor.
The equipment: ground, neutral wires, and lightningprotective equipment shall be interconnected and
attached to a common ground wire.
5.20.18

Crossarms

All crossarms to be used shall be made of Galvanized


Steel material.
5.20.19

Electrical Equipment
35 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Distribution Transformers
The transformers shall be oil-immersed, self-cooled,
double bushing pole mounted-type with the following
specifications:
No. of units
KVA Rating
Primary Voltage, KV
Secondary Voltage
Temperature Rise, Degree Centigrade
Frequency, HZ
: 60
Percentage Tolerance
B.I.L.
Min. Insulation Resistance, Mega ohm

: 3
: 25 KVA/unit
: 7620V/13200V
: 120V/240V
: 65C
: +/- 10%
: 95-115 KV
: 2

Notes:
1. The units shall conform to ZAMCELCOs maximum allowable
copper and core losses.
2. Expenses for the calibration/testing of meter and
transformers and its protective devices shall be borne by the
Contractor.
The transformers shall be oil-immersed, self-cooled,
double bushing pole mounted-type with the following
specifications:
Each transformer shall be furnished with 2-no-load
manual winding taps at 2 1/2% above and below
normal voltage. It shall have grounding pads located
diagonally on opposite comers of the tank base,
mounting lugs of transformer pole mounting bracket
cluster. The core and winding of the transformer shall
be designed and constructed to give the minimum core
loss and shall be designed, fabricated and tested in
strict compliance to an applicable standards prior to
delivery, installation and acceptance Required fuse-cut
outs and arresters assemblies shall be supplied by the
Contractor.

5.20.20

Distribution Fuse-Cut-Out

Three (3) units of open-type distribution fuse cutouts


complete with NEMA type K or T fuse link as defined in
the latest ANSI C 37.43 standard shall be provided for
36 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

each Pump Station. Cutouts shall be suitable for pole


cross-arm mounting rated 15 KV with fuse link of the
required rating.
5.20.21

Distribution Lighting Arrester

Distribution Lighting Arrester shall be provided for each


distribution transformer for equipment surge voltage
protection. Each unit shall be of the valve type rated
10 KV suitable for transformer close coupling.
5.20.22

Kilowatt-hour Meter and Accessories

Kilowatt hour/Demand meter shall be of Self-contained


type 3-phase, 3-wire, of the socket type, 120-480 V to
be installed with complete accessories and grounding
system employing a minimum of 5.5mm2 THW Copper
ground wires. The unit shall be complete with a meter
socket and weatherproof steel enclosure. The stator
unit shall be calibrated, installed and sealed by the
Local Power Cooperative The unit should be GE-KV 2C
Electronic Meter, FM 12S, 3 phase, 4 wires, 110v480v,
class 200 with Test Block 7 terminals and metering
box.
5.20.23

Current Transformer

The Current Transformers to be provided must outdoor


type with secondary terminal sealing provision and a
basic insulation level of 600 Volts and CTR of 200/5
ratio, which must be brand new and approved by the
Local Electric Cooperative, enclosed in a Current
Transformer Box.
5.20.24

Safety

Ensure that safety, security and housekeeping


guidelines are issued and implemented by the
Contractor.
Regularly conduct walk-through inspection on the
jobsites and immediately call attention to unsafe
practices and work conditions.
Every personnel working in the project must equip with
protective gear and gadgets for safety precautions.
5.20.25

System Testing and Energization


37 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Ensure the proper tests and all pertinent system


specifications of the Project.
The Contractor will be responsible for energization to
the electrical lines including initial energy deposit, to
cover also the documentation requirements. The
ZCWD personnel must be justified during energization.
5.20.26

Post-Completion Phase

Upon completion of project work, an inspection must


be conducted to the Project together with the ZCWD
and the Contractor.
Immediate commission must be doane after approval
of inspection.
Ensure that necessary clearances are obtained from
government agencies.
A final inspection must be done by the ZCWD
Inspection Committee.
Prepare necessary documents needed and recommend
ZCWD for the release of final payment and retention.

5.20.27

Turnover

Recommend and validate documents needed by the


ZCWD for the issuance of a Certificate of Acceptance
and Occupancy.
Submit the Final Project Evaluation Report to the
ZCWD.
5.20.28
-

Minimum Personnel Requirement


Project Engineer
Stand as the team leader, in charge of the project
Must be a licensed Electrical Engineer and at least
of five years of experience in the field of work.
Must be also present at all times in the duration of
the project.
Foreman Electrician
38 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City
-

5.20.29

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

Acts as the lead man


Reports to the project engineer
Eligible and responsible to handle the group at work
Must be at least Registered Master Electrician
Prepare daily activity reports
Line Man
Reports to the foreman
Responsible in staking of primary lines, splicing of
tapping points, connection and all other electrical
works in the construction
Must be at least TESDA graduate or graduate of any
technical schools
Well experience of at least five years in the field of
work
Laborer
Reports to the foreman
Acts also as Ground Man
Responsible of bore holing and setting the post on
the ground
Can perform any task assigned to him by the
foreman

Proposal Evaluation

Bids will be evaluated base on the lowest complying


responsive bid following the tenets of RA 9184.
5.2 Provision of Tubular Type Shed at Genset Area
The generator set area shall be covered with a tubular framed
roofing system mainly sloped at the rear edge of the perimeter
wall. The composition of the genset cover shall be as follows:
(See Section Detail A at Sheet No. 5)
5.21.1100mm x 50mm B.I. Tubular Section
5.21.23mm Fiber Cement Board
5.21.320mm thick Aluminized Polyethylene
(P.E.) foam
5.21.4Ga. 26 G.I. Rib Type Roofing
5.3 Main Entrance Canopy with Tubular Trellis/Rails
39 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

The trellis design of the main entrance canopy aesthetically


designed with 100mm x 50mm B.I. Tubular Sections, covered
with 6mm thick. x 1.20m x 5.0m Polycarbonate Roofing (with
Polycarbonate H-Strips for joints).

5.4 Supply and Delivery of Office Chairs


5.23.1

Concessionaires Chair (5-Seater - Gang


Chair)
5.23.1.1
Seat/ Seat Side/ Arms & Legs
Stainless Steel (SS201) with Brushed
Finish System
Note: Gang Chair Legs requires 3 pairs,
having 1 pair at the center support.
5.23.1.2
Beam Support
80mm x 40mm Rectangular Steel Tube
with Anti-Rust Finish System
5.23.1.3
Overall Dimensions (5-Seater,
Gang Chair)
(L X D X H) - 2690mm x 670mm x
790mm

5.23.2

Tellers, Security, Operators, Supervisors


Chair
360 Swivel Chair, Mesh Back Support with Fixed
Arm Rest, Pneumatic Height Adjustment Seat,
Chrome Plate Frames (1 Seater)

5.23.3

Visitors Chair/ Conference Chair


50cm (H) x 48cm (w) x 50cm (L), Stainless Steel
Frame, Leather Surface

5.5 Carpentry Works (Drawers, Partition, Hanging Shelves, Long Table)

40 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

All counter drawers, partitions, hanging shelves and long table


are fabricated. Material specifications and detailing shall be in
accordance with the detailed plans provided.
5.24.1

Materials
Quality of lumber: Lumber shall be the approved
species. Lumber shall be of the respective kinds
for the various parts of the work, well-seasoned,
thoroughly dry, and free from large, loose or
unsound knots saps, shakes, and other
imperfections impairing the strength, durability
or appearance. All finishing lumber to be used
shall be completely dry and shall not contain
more than 14% moisture. All flooring, tongue
and groove shall be well seasoned or kiln dried.

5.24.2

Treatment of Lumber
Surface in contact with masonry and concrete shall
be coated with creosote or its equivalent.

5.24.3

Doorsashes
All door sashes shall be well-seasoned, flush
type, semi-hollow core and solid core. Tanquile
plywood veneers on both sides. Exterior doors
shall be of kiln dried Yakal panel boards.

5.24.4

Kind of Lumber
All unexposed lumber for framings shall be of
yakal wood. All windows and doorjambs shall be
of yakal wood.

5.24.5

Workmanship
Execute rough carpentry in best, substantial,
41 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

and workmen like manner. Erect framing true to


line and dimensions, squared, aligned, plumbed
and well spliced, nailed and adequately braced,
properly fitted using mortise and tenon joint.

Millwork-accurately milled to details, clean cut


moldings, profiles, lines, scrape, sand smooth,
mortise and tenon splice joints, block, screw,
bolt together as approved in a manner to allow
free play of panels, avoid swelling, shrinkage,
ensure work remaining in place without warping,
splitting opening of joints. Do not install millwork
and case until concrete and masonry have been
cured and will not release moisture harmful to
wood work.

Secure work to grounds; otherwise fasten in


position to hold correct surface lines and levels.
Make finished work flat, plumb, true.
5.6 Provision of Granite Counter (Tellers Counter)
Edges of the Granite slab shall be Full Bullnose or Half Bullnose.
The granite slab must have smooth finish using polishing
abrasives. The preferred color for granite is black.
5.7 Supply and Delivery Fire Proof Metal Filing Cabinet (4 Drawer)
Four-Drawer cabinet, 3 section slider, central locking, 2 sets of
keys, provision of file hanger bar, heavy duty smooth and quiet
drawer suspension mechanism, anti-tilt and suitable for legal, A4
or letter file sizes.
5.8 Construction of Steel Fence
The steel fences are primarily located near the security area
which is to be fabricated with 50mm x 50mm x 4mm thick G.I.
42 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

square tube section (Framings) and 38mm x 38mm x 6mm thick


with complete barrel bolt assembly at the bottom and mid area
of the opening fence. It shall comply with the discretion of ZCWD
resident engineer.
5.9 Supply and Installation of Metal Build-Up Signage at Faade
Metal Built-Up Signage is of brass material with urethane clear
paint and 3mm diameter spike stand on each letter. The
350mm ZCWD logo, (brass material with urethane clear paint)
shall have vinyl graphic sticker.
5.10

Carpentry Works (Drawers, Partition, Hanging Shelves, Long


Table)
The cubicle partition at the Supervisors area shall comprise of
4mm thick of 50mm x 75mm Metal Stud as wall joists at 600mm
clear spacing from the face of the stud. The double wall covering
will be 10mm Gypsum Board riveted/screwed unto the metal
stud frames.

5.11

Fabrication of Temporary Parking Barricades


Parking barricades will be fabricated with specified materials at
the provided detailed drawings. The stanchion frames shall be
38mm G.I. pipe. The 4.50mm BI steel matting shall be framed
with 2-25mm x 12mm flat bar that will be welded unto the main
frames. The parking barricades shall require 6 units of 2.16m x
1.35m enough to cover the front ramp of the property.

5.12

Relocation of Discharge Pipe


The existing borehole system shall remain at its original position.
Its existing discharge pipeline that is located at near the
proposed genset area will be relocated by closing it permanently.
The new discharge pipeline will be tapped from the borehole
system with appropriate gate valves and catch basin. The new
discharge pipe line (8 PVC pipe) goes to existing drainage. (See
provided detailed plan.)

5.13

Painting Works

5.13.1

Concrete Surfaces

43 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

For concrete surfaces, the initial application of


concrete neutralizer is set to purposely clean
and even the surface before applying paint.
Solvent-based Acrylic Primer is then applied to
the concrete surface. Body filler and Solvent
based acrylic cast is then applied on cracks and
uneven surfaces which will be then undergo
abrasive polishing (sand paper). After the
surface has been smoothen and free from dusts
specks, solvent based acrylic primer is reapplied
before the solvent based Acrylic paint top coat
is applied as final finish.

5.13.2

Gypsum Board/ Fiber Cement Board


Similar procedure to that of concrete surfaces is
being applied to these types of surfaces except
for the application of concrete neutralizer.
Cleaning of the surface will be the initial
procedure before

5.13.3Metal Surfaces
Formations of rusts are removed by using steel
brush. Red oxide primer is being applied rust
proofing the all metal surface. Final finish shall
be the Flat wall enamel paint as top coat.

5.13.4Wooden Surface
Clean any wooden surface, making it free form
dust and any other agent that makes the
wooden surface unsmooth. Apply Enamel Primer
to the surface by either roller or brush. Putty
filler /Body Filler are then applied to bulges
caused by rivets, screws, finishing nails and
even joints. After which, abrasive polishing using
sand paper is then treated making the surface

44 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

even. Quick Drying Enamel (Semi-Gloss) will


serve as the final coat of the wooden surface.

VI.

Time Frame/ Project Duration:


Calendar Days)

VII.

Manpower Schedule

(129) One Hundred Twenty Nine

Technical Personnel Required


Description
Construction Foreman/
Electrical Engineer
Steelman
Mason
Carpenter
Plumber
Electrician
Painter
Welder
Laborer

No.
1
3
3
3
1
2
1
3
15

PREPARED BY:

REVIEWED & SUBMITTED BY:

CAROLYN M. TORINO
Senior Engineer (C.E.)

EDITO M. BAUSTISTA, JR.


Officer in-Charge
Design Division

FELIX FEDERICO N. MENDOZA


Senior Engineer (E.E.)

APPOVED BY:
IMPLEMENTATION:

RECOMMENDING PROJECT

MARLI P. ACOSTA-DEFIESTA
Officer in-Charge
Engineering & Construction Department

ARNULFO A. ALFONSO
Assistant General Manager
for Technical Services

Approved for Project Implementation

45 | P a g e

Republic of the Philippines


ZAMBOANGA CITY WATER DISTRICT
Pilar Street, Zamboanga City

Proposed Production Well & Collection


Center
Gov. Ramos Avenue, Zamboanga City

LEONARDO REY D. VASQUEZ


General Manager

46 | P a g e