Beruflich Dokumente
Kultur Dokumente
IOPF 2008
October 29-30, 2008, Houston, Texas, USA
IOPF2008-922
DEEPWATER PIPE-IN-PIPE (PIP) QUALIFICATION TESTING FOR 350F SERVICE
Paul Jukes, PhD CEng.
J P Kenny, Inc.
Houston, Texas, USA.
Francois Delille
J P Kenny, Inc.
Houston, Texas, USA.
Gary Harrison
BP America, Inc.
Houston, Texas, USA.
ABSTRACT
Development of future deep water oil reservoirs in the Gulf of
Mexico (GoM), where the flowline product temperatures are
approaching 350F (177C), water depths approaching 10,000ft
(3050m), and tie-backs in the order of 40 miles (64.4km), requires the
appropriate material selection for key pipe-in-pipe (PIP) components.
These extreme flowline temperatures, water depths and distances,
restrict the choices in PIP component materials, and present real
challenges to the design of centralizers, waterstops seals, thermal
insulation and loadshares. These challenging conditions warrant
qualification testing to be undertaken on PIP components to ensure
structural integrity and long-term thermal and structural performance.
This paper describes a qualification testing programme for the
testing of PIP components for 350F (177C) service, and includes the
testing of centralizers, waterstop seals, thermal insulation and
loadshares. The following qualification tests are proposed: (i)
Centralizers tests: Slippage tests, creep tests, abrasion tests, bolt
relaxation and aging tests are undertaken. Structural integrity testing
under installation loads and in-service conditions is undertaken to
ensure no long-term creep or degradation of the material due to
temperature. (ii) Waterstop seal tests: Load test, hydrostatic pressure
test, elevated temperature tests and material aging tests are
undertaken. The material selection for the waterstop seals are
undertaken to examine the integrity of the seal at temperature. (iii)
Thermal insulations tests: A number of tests undertaken on aerogel
materials to evaluate the effect of prolonged exposure to temperature
on thermal conductivity and mechanical integrity. Tests include
checking thermal conductivity, compressive strain recovery, long-term
exposure to high-temperature and aging effects on thermal
conductivity and mechanical integrity. (iv) Load-share tests: A
mechanical radial clamp load-share is tested to ensure performance
under sustained installation loads.
Each test planned and performed, testing rationale and results are
presented within the paper. Conclusions are drawn on the suitability
of these qualification tests for high-temperature applications. The
successful qualification testing of the components extends the
KEY WORDS
Aerogel, Annulus, Centralizer, Deep Water, Extra High-Pressure
High-Temperature (XHPHT), Flowlines, Load-share, Nanogel,
Overall Heat Transfer Coefficient (OHTC), Pipe-in-Pipe (PIP),
Pipelines, Spacers, Thermal Insulation, Waterstop.
INTRODUCTION
Pipe-in-pipe (PIP) is increasingly being used for the transportation of
hydrocarbons. Pipe-in-pipe flowline systems are frequently used in
the GoM for subsea tie-backs where there is a requirement for high
thermal performance. A PIP system consists of the inner pipe carrying
the fluid encased within a larger diameter outer pipe. Figure 1 shows
a typical PIP system configuration.
PIP COMPONENTS
Centralizers, waterstops, thermal insulation and loadshares
make up a PIP system. The function of each component is briefly
described, and issues associated with high temperatures are addressed.
Centralizers
Depending on the thermal insulation type, centralizers are
placed between the inner and outer pipes at regular intervals. The
function of the centralizers in a PIP system are to support the inner
pipe centralized within the outer pipe, prevent possible damage to the
PIP thermal insulation between the inner and outer pipes, and to
transfer loads between the inner and outer pipes.
The distance between the spacers will depend on the loading to
which the section of the PIP will be subjected. This spacing may be
two meters for reeled pipelines, and four to six meters for S-lay and Jlay installation methods. The presence of centralizers provides heat
loss paths and can present cold spots, reducing the overall thermal
performance of the PIP system. For high-temperature flowlines, the
temperature can reduce the structural integrity of the centralizers, and
lead to deformations that could crush the thermal insulation.
Ability to undertake the functions of the centralizers
successfully at high temperatures requires the spacer material to
tolerate high temperatures without excessive deflections and maintain
structural integrity. Compression loads on centralizers are a key
aspect in their design.
Centralizer Tests
Centralizers are used to avoid the loading that could crush the
thermal insulation. Installation loads can be particularly large during
reeling, and the centralizers are tested in compression for the
maximum loads seen during the reeling process.
Operational conditions need to be considered, and degradation
of the material due to temperature, long-term creep, and structural
integrity are all issues related to the performance of the centralizer.
These high temperatures severely restrict the material selection
available for pipe-in-pipe centralizers. Based on the temperature, a
modified Polyphenylenesulphide (PPS) material was selected for
testing, based on its characteristics of having high thermal mechanical
strength, high hardness and rigidity, high creep strength and excellent
wear characteristics.
The type of tests undertaken when testing centralizers are as
follows:
Slippage Tests;
Abrasion Test;
Creep Tests;
Aging Test.
Pressure Tests. A further requirement of the seal is to provide leakfree sealing of the large pressures that occur in the PIP annulus if the
outer pipe is breached. The purpose of this test is to verify the
pressure and sealing capacity of the waterstop seal. The seal was
enclosed in a special pressure test rig consisting of bolted end flanges.
The seal was tested to 375bar (37.5MPa), which includes a safety
factor of 1.25. A pressure based on water-depth of 10,000ft (3050m)
was applied. The seal was examined after the test, and no permanent
seal damage was observed. Below is a picture of the pressure test
apparatus and setup.
Load Tests
levels
of
Thermal conductivity;
Hydrophobic threshold;
Lightweight
Highly porous
ACKNOWLEDGMENTS
The author would like to thank all that have provided input into
this work, especially BP, Cabot Corporation, TEKMAR and Devol
Engineering Ltd.
REFERENCES
[1] Jukes, P and Harrison, G. An XHPHT Pipe-in-Pipe Design for
Installation By S-lay, J-lay and Reel-lay Methods, Proceedings
of IOPF2006-16, Houston, Texas, USA, October 24-25, 2006.
[2] J P Kenny Inc., Extra High-Pressure High-Temperature Pipe-InPipe Design Study, Internal Report, Rev. 0, July 2006.
[3] J P Kenny Inc., XHPHT Pipe-In-Pipe Design Study: sensitivity
for additional water depths (7,750ft and 10,000ft), Internal
Report, Rev. 0, July 2006.
[4] Harrison, G. and McCarron, W. Potential Failure Scenario for
High-Temperature, Deepwater Pipe-in-Pipe, Proceedings of
Offshore Technology Conference, OTC# 18063, May 2006.
[5] Jukes, P., A Design Philosophy for Lateral Buckling in
Deepwater, Proceeding of ASME International Petroleum
Technology Institute, IOPF# 2006-002, Oct. 2006.
[6] Jukes, P., Wang, J., Eltaher, A., and Harrison, G. A General
Flowline Thermal Expansion Design Philosophy Employing
Buckle Initiators and Piles, Proceeding of IOPF, Houston Texas,
USA, October 23-25, 2007.
[7] J P Kenny Inc., XHPHT Component Testing & Further FEA Local Loadshare FE Study, Internal Report, Rev. B, June 2007.
CONCLUSIONS
This paper describes a qualification testing programme for the
testing of PIP components for 350F (177C) service, and includes the
testing of centralizers, waterstop seals, thermal insulation and
loadshares. Conclusions from the testing program are;
[8] Sun, J.J., Jukes, P and Eltaher, A., Finite Element Analysis of
Loadshare for the Installation of Pipe-in-Pipe Flowline by S-lay
and J-lay Methods, Oceans 07 MTS/IEEE Conference,
Vancouver, Canada, 29th Sept-4th Oct, 2007.
[9] Devol Engineering Ltd, HPHT Pipe-in-Pipe Centralizer
Evaluation, Document No. CDT 6676 CR, Feb. 2008
[10] TEKMAR, 8/12 pipe-in-pipe waterstop seal development
programme test report, 7th Issue, 6th Oct. 2008.
[11] Cabot Corporation, Nanogel Aerogel Material Qualification
Testing Report, June 2007.