Beruflich Dokumente
Kultur Dokumente
Project Proposal
Project Summary
Project Name : Railway Infrastructure Design
Project owner: Metal and Engineering Corporation
Subcontractor: Woldia University
Country: Ethiopia
Contact Person:
Name: Woldia University
Address: Woldia, North Wollo
Telephone: +251 335400683
Fax: +251 335400674
Email : ahaduhiz@gmail.com
CONTENTS
LIST OF FIGURES.......................................................................................................................................... v
1.
EXECUTIVE SUMMARY...................................................................................................................... 1
2.
3.
4.
5.
PROJECT GOAL..................................................................................................................................... 3
6.
8.
DESIGN TASKS...................................................................................................................................... 5
8.1.
Project organization.......................................................................................................................... 5
8.1.1.
8.1.4.
8.1.5.
8.1.6.
8.1.7.
8.1.8.
8.2.
8.2.1.
8.2.2.
8.2.3.
8.2.4.
8.2.5.
Specifications ......................................................................................................................... 15
8.2.6.
Material/Equipment Selection................................................................................................ 15
8.2.7.
Concept Drawing.................................................................................................................... 15
8.3.
8.3.1.
8.3.2.
8.3.3.
8.3.4.
8.3.5.
8.3.6.
8.4.
8.4.1.
8.4.2.
Technology selection.............................................................................................................. 24
8.4.3.
8.4.4.
9.
9.1.
Civil Work...................................................................................................................................... 26
9.2.
9.3.
10.
10.1.
10.2.
Per diem...................................................................................................................................... 29
10.3.
Transportation Fee......................................................................................................................30
10.4.
10.5.
iv
LIST OF FIGURES
Figure 1: Project location and probable route (in blue).................................................................................... 4
Figure 2 : Earth quake and volcano distribution in the project area................................................................. 5
Figure 3: Project Management Hierarchy ....................................................................................................... 6
Figure 4: Nominated railway line...................................................................................................................15
Figure 5: Section of railway track (Wikipedia)..............................................................................................16
Figure 6: The power supply layout ................................................................................................................19
Figure 7: Cross-section of the pole of the contact line..................................................................................23
1.
EXECUTIVE SUMMARY
WU & METEC
Page 1
station designs, bridge designs and related works with the up-to-date cost estimation. The
design approach of the project will be to meet the minimum design life.
These trains are powered by electric power which entails second part of the project which is
detail design of traction power supply and distribution system with BOM.
The communication system design is the 3rd component of the design. Trains carry large loads
resulting in higher traffic capacity since trains move on specific tracks which require to be fully
guided and there is no arrangement of steering, so there is a need to provide control on the
movement of trains in the form of Railway signals which indicate to the drivers to stop or move
and also the speed at which they can pass a signal. Since the load carried by the trains and the
speed which the trains can attain are high, they need more braking distance before coming to
the stop from full speed. Without signal to be available on the route to constantly guide the
driver, accidents will occur.
3. BENEFIT OF THE PROJECT
The significance of railway transportation systems d e s i g n a n d d e v e l o p m e n t in our
country is paramount. The project as a whole has a number of economic, social, institutional and
political significances. Specifically the design and consultation project as a component of the
whole project has advantages of:
Technology and knowledge transfer and localization which pushes our country in the
chain of global technology.
The emerging man power from universities will gain practical education from the
project.
Creating job opportunities to professionals and laborers during site investigation and on
the design process.
Page 2
A new railway track infrastructure subsystem design which extends from Dallol t o
Semera. This includes:
study the properties of the subsoil layer in the route and stations
equipment selection
Signaling and communication system and preparation of state- of- the art
bill of
5. PROJECT GOAL
Complete infra-structure, electrification, signaling system design and accompanying material bill
for the Dalol-Semera freight train infra structure development project.
WU & METEC
Page 3
C qualify the Afar Depression as one of the most unique features on earth. Apart
from this Dalol is one of the few places where abundant potash deposits are found at the
surface. The deposit is estimated to cover an area of 1150 km2 with an estimated accumulation of
about 150 million ton.
WU & METEC
Page 4
WU & METEC
Page 5
Top
Management
Project
Coordinator
Team leader
Submit the problems occurred to management bodies of the two institutions and seek
appropriate solutions
8.1.3.
submit project progress report to the management body of the two institutions
Team leader
WU & METEC
Page 6
Team centre engineering PDM (Product data management) software, using Unigraphics
3D modeling Design software and Teamcentre 8.3, NX 7.5 versions. These software
all used for modeling, clearance analysis , dimensional analysis, cable routing
,piping harnessing design modification , system integration and load analysis.
WU & METEC
Page 7
structural software
Automatic Level
Total Station
Digital camera
Vehicles
Compass
Meter tape
Geological hammer
Stereo ploter
8.1.8.
Humanitarian Facilities
Transportation service
Accommodation
Preliminary investigation
- Proposed route selection
- Reconnaissance survey
Detail survey
- Survey data collection
- Final route selection
WU & METEC
Page 8
Geometric design criteria (both vertical and horizontal alignments, gradients of the area
the grade requirement is within the limit 1.7%)
WU & METEC
Page 9
Safety of the route such as the existence of steep and gentle grades.
Then once the best three or four routes are selected, detailed route selection will be done through
feasibility study.
ii.
Reconnaissance survey
Before commencing the Finalization of the route selection and detailed field investigation work,
site reconnaissance is carried out. It includes
Review of existing regional, site and sub surface information from existing geotechnical
and geological reports prepared for the site or nearby areas, topographic maps, site plans,
geologic maps, air photos, construction plans, surveys and geological data.
Gathering information regarding ground water level near the project site and data on
seismic aspects, such as ground motion, liquefaction potential, and site amplification.
Visual inspection of site and collecting data regarding it accessibility, over head space
limitation, identification of underground utilities, nature of above ground structures,
traffic condition and control during investigation and construction.
Inspection and visualization of the natural hazards such as volcanoes and the natural
schemes like lakes, rivers, forests that can be affected or can affect the construction of
the new transportation system.
After a detail review of existing ground information and reconnaissance survey, the appropriate
alignment (route) is selected. The most appropriate route to be selected is the one with minimum
overall cost.
WU & METEC
Page 10
iii.
Detail survey/investigation
After the successful accomplishment of the preliminary survey and route selection, detail
investigation and data collection along the selected alignment will be carried out. This is the
stage where the required survey and areal data, subsoil properties, geological characteristics and
other related datas of the project area are specified and identified for the design.
8.2.2. Site design
The site design to be carried out for the new railway line from Dalol to Semera contains the
architectural and structural design of station.
i. Station Design
The station shall enable a safe, reliable, cost-effective and customer oriented transport system.
The stations of the new railway are designed to fulfill the requirements of the railway facilities.
Transit way stations fulfill two primary functions: they provide access to the transit way and
transit information to customers. To fulfill these functions, the following should be carefully
considered in each station; facilities provided, facility sizing, components and transit way
information included, and materials used. Thus, the station design should ensure each station fits
with and enhances the neighborhood surrounding it in terms of both function and aesthetics.
ii. Station Facilities
One of the primary functions of transit way stations is the provision of facilities so that transit
patrons can access the transit way. All transit way stations should provide:
Facilities that support access for customers of all ages and abilities
Facilities that support access for pedestrians and people using wheelchairs or bicycles,
including providing bicycle parking
Station platform(s)
Waiting shelters for all public transit routes serving the station
Stations may also include facilities for additional functions. The factors to consider in deciding
which additional facilities to provide at each station, if any, are existing and future passenger
demand, market needs; transit service plans (transit way and other transit services); capital,
WU & METEC
Page 11
operating, and maintenance costs, available rightofway; and consistency with surrounding
development plans and land use policies.
Generally the Design and selection criteria for terminal and intermediate stations will be based
on;
a. Existing highway infrastructure impacts (capacity and accessibility)
b. Platform requirements
c. Further expansion capabilities of the city in which the stations will be constructed (due
to mining) as well as the expansion capabilities of the station itself.
d. Access to utilities (electric power, water, geographic nature, gas etc.)
e. Population density of the area
f. Future Industrialization of the area
g. The existing railway of the area
h. Cost of the stations
i. Environmental conditions (forest, natural hazards)
j. Existing structures
8.2.3. Geotechnical and geological investigations
As mentioned above, a detailed geotechnical investigation will be performed to identify
subsurface conditions, soil type, geological conditions, bearing capacity of the area which will
dictate much of the design work of the roads, foundations, buildings, tunneling and stations.
Typically, the geotechnical investigation involves a drill rig for major foundations such as
bridges which bores to the engineers required depths (typically 10cm diameter drill to 7-10 m
deep) and an open pit excavation to identify the subsurface soil and rock types and strength
properties by sampling and lab testing. A geotechnical investigation will generally be performed
throughout the path of the selected route. It also will be conducted at the terminal and
intermediate stations etc.
In addition, Geological investigations are conducted to know the geological structures, geo
hazards and other related factors which can threaten the project area. These include faults, folds,
earth quake, volcanoes, etc.
i. Soil test
a) Field tests
WU & METEC
Page 12
Field tests will be done actually in the site. These tests include Standard penetration test, van
shear test and other related field tests which are going to be carried out to determine the bearing
capacity and CBR test of the soil in the site.
b) Laboratory tests
These tests are to be done in the Laboratory to know the characteristics of the soil in the site.
The soil samples to be brought can be disturbed and undisturbed depending on the tests and
outcome required. So direct shear test, cone penetration test, CBR test and other related tests are
going to be done for the sub grade and the under bed of the station sites.
8.2.4. Railway civil works
In addition to those mentioned above, the civil works involved in the construction of a new
railway line also includes.
a) Earthwork and bridges
b) Structural and geometrical design of track components
c) Estimation of project cost
a) Earthwork for Formation
The formation may be in an embankment or a cutting depending upon the rail level and general
contour of the area. A formation in an embankment is normally preferred from the point of view
of good drainage. The height of the embankment also depends on the high flood level of the area
and a reasonable free board is provided above this level.
In the alignment there may be areas where there are both cuttings and embankments. So the
earth from the cuttings should be used for the embankments up to an economical lead. The
economical lead of moving earth in the longitudinal direction is determined by the masshaul
curve.
b) Bridges
Bridges should be designed for the heaviest locomotive likely to pass the section. Depending
upon the topography of the country and the type of stream to be crossed, pipe culverts,
reinforced cement (RCC) slab bridges, plate girders or pre stressed concrete (PRC) girder
WU & METEC
Page 13
bridges or steel bridges, are designed. Bridges, being important structures, are normally made
for double-line tracks, even in single-line sections, with a view to plan for future expansion. For
the construction of important bridges, separate tenders are called, with design and construction
details included in the tender documents. Minor bridges and culverts are normally included in
the earthwork zones mentioned above.
c) Rails
The new railway line should be equipped with the acceptable rails so as to access the feasible
transit. Rail shall be inclined at 1:40 to the vertical towards the track center line except
at switch and crossing areas where the rail shall be vertical. All rails shall be continuously
welded.
Premium rail shall be used in all horizontal curves with radii less than 700m, including the
transition spirals at each end. These requirements shall also apply to siding tracks and crossover
tracks in the mainline.
In the design, the rails need to be well spaced so that they can be able to withstand and safely
transfer the load from the train. The spacing is also determined from the aspects of the standard
gauge measurements and code recommendations as of broad gauge, narrow gauge etc. Standard
rail shall be used in all depot tracks.
d) Concrete Ties (Sleepers)
Railway sleepers can be made up of wood, steel or concrete. A concrete sleeper is a railroad tie
made out of steel reinforced concrete. They are made of pre-stressed concrete containing
reinforcing steel wires. These are ties used to hang the rail in position and to transfer the train
load safely to the ballast. Even though there are different ties, concrete ties are gaining
acceptance for heavy haul mainline use, both track and turnouts, as well as for curvature greater
than 2. An insulator clip is also placed between the contact point of the elastic fastener used to
secure the rail to the tie and the contact point on the base of the rail.
The concrete sleepers have to be placed on the well-designed ballast (in thickness and side
slope) in which this layer is needed to be lied on recommended sub ballast and sub grade.
WU & METEC
Page 14
8.2.5.
Specifications
The railway track infrastructure from Dallol to Semera is double track system throughout its
length. And the track system is required to be designed to overcome the maximum load from the
train and mineral carrying wagons which has an expected weight of 25 ton per axle or 150 ton
locomotive with six axles in addition to the transportation load.
The maximum grade requirement is within the limits of -1.7%to 1.7% so that the load transport
and relevant speed can be acquired with lesser energy consumption. Also the designed speed of the
railway infrastructure is 120Km/hr.with a track gauge of 1435mm.
8.2.6. Material/Equipment Selection
Equipment procurement will be undertaken using the project site specifications. Based on the
design basis approach the Project will be designed and constructed to meet the minimum design
life.
8.2.7. Concept Drawing
WU & METEC
Page 15
WU & METEC
Page 16
AC system is used for long distance and DC for short distance. This makes AC an ideal
medium for electric railways power transmission.
It is easier to boost the voltage of AC than that of DC, so it is easier to send more power
over transmission lines with AC.
DC, on the other hand was the preferred option for shorter lines, urban systems and
tramways. However it needed a heavier transmission medium, a third rail or a thick wire, to
carry the power and it lost a fair amount of voltage as the distance between supply
connections increased.
For minimizing power loss it needs placing substations at close intervals, nowadays two or
three on a 750 volt system which is very close and uneconomical compared with a
minimum of 20 kilometers for a 25 kV AC line.
WU & METEC
Page 17
Due to the above reason the plan in this design is to use AC transmission system. These
advantages and other advantages and also the hindrances that will come from the environmental
conditions of the area will be analyzed and solutions will be proposed in the preliminary study.
Among AC systems the 25kV, 50Hz system is widely used nowadays because of the following
advantages:
i. Supply layout
Electric power is supplied to moving trains with a (nearly) continuous conductor running along the
track that usually takes either overhead (catenary) which is suspended from poles or towers along
the track or from structure or tunnel ceilings or a third rail which is mounted at track level and
contacted by a sliding "pickup shoe". Both overhead wire and third-rail systems usually use the
running rails as the return conductor but some systems use a separate fourth rail for this purpose.
Due to the selection of AC system for the transmission third rail system is not applicable due to
higher skin effect voltage drops. The proposal is to use overhead catenary system. In catenary
system there are two wires: contact wire and messenger wire.
power to the train through pantograph whereas the messenger wire serves two purposes. Firstly,
it supports the contact wire vertically between structures by use of hangers.
Secondly, it
WU & METEC
Page 18
Applied where maximum train weight and speed are very low. Consists of a contact wire only.
b. Simple Catenary
Used for speeds upto 160 km/h where two wires are ample for the required current capacity.
c. Stitched Catenary
Used for speeds up to 300km/h with single pantograph where two wire are ample for the
required current capacity
Is similar to simple catenary but with a stitch or bridle included between the two main wires in
the area of the supports
WU & METEC
Page 19
d. Compound Catenary
Used for all speeds where the current capacity requires inclusion of a third wire and for
medium and high speeds where progressively larger numbers of pantographs are operated on a
single train.
Consists of a main messenger with an auxiliary wire suspended beneath it on hangers, which in
turn has a contact wire suspended on clamps or hangers beneath it.
voltage flicker,
WU & METEC
Page 20
harmonic distortion that may result from the addition of the highly fluctuating, single
phase, and non-sinusoidal traction loads.
train power demand in this case 2 trains X 6400kW X 1hour= 12,800 kWh ,
During substation design, the task of substation layout design, substation equipment selection,
location as well as configuration will be done.
The traction power substation equipment selection includes the following major item of
equipment:
Power transformers:
transformer size will be selected according to the maximum expected load and possibility of
future expansions. And then the transformers may be selected from the commercially
available standard power transformer ratings to supply the present and future loads.
Switchgear equipment
-
Measurement instruments
WU & METEC
Page 21
Power cables, control cables, and low voltage auxiliary power wiring
Insulation and grounding systems, raceways, conduits, duct banks, and other
miscellaneous equipment
Due to the large electrical clearances required, high voltage equipment of traction power
substations is typically installed outdoors. Each item of equipment is delivered to the site
separately and installed on prepared foundation or footings.
iii) Substation location
The following considerations are taken into account in determining the location off traction
substations.
Site access: all weather heavy vehicles access for construction and future maintenance
requirements
Security consideration
WU & METEC
Page 22
WU & METEC
Page 23
Page 24
After gathering the informations regarding to the number of trains, number of routes,
environment factors, and selecting the technology we will design a system which will be cost
effective, efficient, reliable and suitable for the site of Dalol -Samara-Djibouti.
8.4.4. Preparation of state-of-the-art of bill of materials
After designing the signaling and communication systems and make a review by expertise, the
next step will be writing the state of the art of bill of materials. And since we will design
depending on the availabilities of materials and cost-effectiveness of the material we will use,
this part will be also taken in to account during design.
WU & METEC
Page 25
9.2.
WU & METEC
Page 26
9.3.
WU & METEC
Page 27
Descriptio
n
Sub description
Route
Details
Qty
Per
month No
(Birr)
months
20,000
10
13,000
20
10,000
20,000
2.5
20,000
20,000
4.5
10
20,000
3.5
20,000
20,000
4.5
20,000
selection Office
analysis
Total
and
and
Reconnaissance
locations
480,000.00
survey
Surveyor
Topographi
c study
Staff man
Data collection
Data processing
Geological study
GIS
Architectural design
50,000.00
600,000.00
180,000.00
Site design
Structural design
Geometrical
1,200,000.00
Geological map,
structures analysis
Station design
780,000.00
Rail
way Structural
alignment
480,000.00
900,000.00
design
civil works
Drainage
WU & METEC
700,000.00
400,000.00
Page 28
20,000
20,000.00
14
1,960,000.00
20,000.00
12
1,680,000.00
240,000.00
Electrification
system Design
designs
traction substation design
Signaling
and carry
Design
out
the
system
of material formulation
Coordinator Fees
6
7500
16
120,000.00
5,000
16
240,000.00
Sub Total
9,650,000.00
Description
Place
Per
No
diem
days
500
20
30000.00
10
500
30
150000.00
Labour)
15
500
30
225000.00
14
500
55
385000.00
Labour)
10
600
55
330000.00
175000.00
Qty
Addis Ababa
of Total
Bahirdar
35
5000
Project area
15000 -
60000.00
500
350,000.00
Field Visits
WU & METEC
Project
area
&
Addis 7
100
Page 29
Ababa
Communication and Signaling System Design
7
Field visits
Project
area
&
Addis 5
500
70
175,000.00
Ababa
Sub Total
1,880,000.00
Description
Per Expected
Total
Km
L(Birr/Lit)
Total Km
(Birr)
Cost
0.15
20
76800
230,400
20
4000
12,000
20
50800
152,400
46800
140,400
and to labs
Electrification System Design
3
0.15
Sub Total
WU & METEC
0.15
20
535,200
Page 30
Item
Unit
Qty
Total (birr)
Pack
100
100.00
10,000.00
Rim
57
2500.00
142,500.00
No
40
6500.00
260,000.00
Design Manuals
No
15
11000.00
165,000.00
Pen, pencil
Pack of 50
200.00
600.00
Stapler (20mm)
No
400.00
1,600.00
Stapler
No
80.00
400.00
stapler pen
Pack
15
20.00
300.00
Note book
Dozen
500.00
1,500.00
10
No
25
450.00
11,250.00
11
Software
No
20
15000.00
300,000.00
893,150.00
Sub Total
10.5.
Cost Summary
No
Budget Type
Amount
1.
Professional fee
9,650,000.00
2.
Per diem
1,880,000.00
3.
Transportation
535,200.00
4.
Material Cost
893,150.00
Total
12,958,350.00
1,295,835.00
1,295,835.00
Total
15,550,020.00
Contingency (10%)
1,555,002.00
Grand Total
17,105,022.00
WU & METEC
Page 31
Name
Qualification
Remark
Team Leader
Aregawi Tekle
Girma Moges
Mulugeta Fentaw
Leulseged Birrara
Haileleul Temesgen
Abreha G/ zher
Aniley Mitikie
Birhanu Teshome
Abebaw Meseret
10
Birhanemeskel Taye
11
Gebremikael Haile
12
Gedey Tsegaye
13
Tsegaye Gashaw
14
Bisrat Assefa
15
Lemlemu Abebe
16
Aklilu Ayalew
17
Seid Ahmed
18
Millashu Sisay
19
Shambel Addisie
20
Ayene Assefa
21
Yitbarek Firew
B.Sc. in Architecture
22
Gizachew Zelalem
23
Kahsu G/meskel
24
Shewit Kassaye
25
Zewdu Maru
M.Sc. in Hydraulics
WU & METEC
Page 32
26
Asrat Hibu
27
Mihreteab Aregawi
28
Melese Baye
29
Mitiku Kiros
B.Sc. in Geology
30
Belay Anberber
B.Sc. in Geology
31
Wolday G/ Hiwot
B.Sc. in Geology
2. Mintesenot Kassa
3. Ahadu Hillawie
4. Kelemwork Aregawi
5. Dagemawi Demerew
Team Leader
Project Coordinator
Medhanye Melese
2.
Kibrom Berihu
Team Leader
engineering)
3.
Tesfaye Hailu
4.
Abera Gesese
5.
Ali Yemam
WU & METEC
Page 33