ARCELORMITTAL TUBULAR PRODUCTS PROJECT

AL - JUBAIL, KINGDOM OF SAUDI ARABIA


Additional Works Carried by NSH Due to CISDI Drawing Revisions:

NSH Submitted
Claim
(SR)

S. No.

Description

Drawing Reference No.

Dismantling Work at Preceding Billet Saw


Foundation

10010001DR5003ST002-C2 (Old)
10010001DR5003ST002-D2 (New)

3,074.69

Dismantling Work at Detection Foundation

100110001DR5006ST005-B

12,226.99

Dismantling Work at 115 / 13.8KV Sub


Station Foundation

10010001DR5054ST002-A2 (Old);
100110001DR5054ST002-2/C (New)

3,569.35

Additional Works for Cooling Bed


Foundation

10010001DR5005ST015-6A &
10010001DR5005ST015-6B

11,370.42

Additional Works for Hot Mill Equipment


Foundation (Due to Revision)

10010001DR5005ST004-2

8,011.60

10010001DR5008ST002-11 A
10010001DR5008ST002-15 A
6

Charges For Rebar Wastage at


Intermediate Foundation 1/7 due to
drawing revision.

10010001DR5008ST002-20 A
10010001DR5008ST002-11 B

4,183.25

10010001DR5008ST002-15 B
10010001DR5008ST002-20 C
7

Rectification work for Intermediate


Transportation Foundation (3/7)

10010001DR5008ST002-A8 (Old)
10010001DR5008ST002-B8 (New)

32,814.28

Rectification work for QA Line Foundation

10010001DR5008ST004-4B

3,440.25

Rectification work for Crane Rail


Foundation

10010001DR5003ST009-2

2,279.27

10

Additional Work - Rectification of Sand


Filter Foundation due to drawing revision.

10010001DR5050ST002-A (Old)
10010001DR5050ST002-B(New)

4,824.61

11

Additional Rebar Installation for 115 / 13.8


KV Sub Station Columns.

10010001DR5054ST002-2/C (Old)
10010001DR5054ST002-3(A-D)

2,700.00

12

Additional Work - Installation of additional


rebar for cantilever beam at Cooling Bed
Foundation.

10010001DR5005STC-015-9

16,695.30

13

Additional Work - Installation of additional


10010001DR5008ST002-B; (RFI: 2617
rebar at Intermediate Transportation (3/7
- Rev. 02 dated 24 Oct. 2010 & RFI:
& 4/7) Foundation due to changes in
2693 Rev.03 dated 01 Nov. 2010)
drawing by CISDI.

14

Additional Work - Modification of Anchor


Box due to drawing revision.

15

Additional Work - Rectification works at


Piling and Binding Foundation - OCTG - 1

11,760.00

10010001DR5005ST005-14B (Old)
10010001DR5005ST005-14C(New)

4,275.00

10010001DR5008ST0098A,9A,10A,13A & 16A (Old)


10010001DR5008ST0098B,9B,10B,13B,& 16B (New)

4,470.09

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to CISDI Drawing Revisions:

S. No.

Description

Drawing Reference No.


10010001DR5008ST014-4-A (Old)
10010001DR5008ST014-4-B(New)

NSH Submitted
Claim
(SR)

16

Additional Work - At OCTG - 2 due to


drawing revision.

17

Additional Works - Main Utility Electrical


Room due to drawing revision.

18

Additional Work - Rectification work at


Zone - 4 Equipment Platform Foundation
due to drawing revision.

10010001DR5005ST006-3A (Old)
10010001DR5005ST006-3B(New)

28,351.87

19

Additional Work - At Q.A. Line Foundation


" Core Cutting" as per reveised drawing

10010001DR5005ST004-4-C (Old)
10010001DR5005ST004-4-D(New)

15,110.00

20

Modification work at Hot Mill (Zone -2) to


accommodate steel column structure.

21

Additional Work - At Sliding Chain


Foundation due to drawing revision.

22

Pile rectification works at Piling , Binding


and transfer for LPL area due to drawing
revision

23

7,563.53

54,461.95

Opening as per drawing is 890mm x


3000mm but in actual column size is
about 1400mm x 3150mm in
dimension.

22,331.88

10010001DR5008ST008-12-C

6,916.00

Pile Cut - Off level revision

5,937.65

Additional Work at Sand Filter Bank


Foundation due to drawing revision

10010001DR5050ST022-6-C (Old)
10010001DR5050ST022-6-D (New)

2,602.28

24

Breaking of Column Sizing Mill Plate


(Zone - 8) due to drawing revision.

10010001DR5050ST017-C (Old)
10010001DR5050ST017-D (New)

3,166.28

25

Hot Mill Zone - 3 Foundation: Rectification 10010001DR5005ST005-12-B (Old)


work due to drawing revision.
10010001DR5005ST005-12-C (New)

22,312.89

26

Additional Work - Main Utility Electrical


Room Modification Work due to drawing
revision.

10010001DR5050ST016-4-A (Old)
10010001DR5050ST016-4-B (New)

55,320.00

27

Additional Work - Main Utility Electrical


Room Breaking of concrete wall for cable
entry due to drawing revision.

10010001DR5050ST016-4-A (Old)
10010001DR5050ST016-4-B (New)

7,724.00

28

Add'l. Work - Core Cutting at Detection


Fdn. No. 1 & Tube Collection Fdn. for
Pockets

10010001DR5006ST004-11-B
10010001DR5006ST006-11-C

4,800.00

29

Add'l. Work - After Phospating No. 2 Breaking of existing concrete foundation


and making extension as per revised
drawing.

10010001DR5008ST017-10-A
10010001DR5008ST017-10-B

35,501.29

30

ER 06 - Rectification Works- Breaking of


Cable Trench due received revised
drawing from CISDI

10010001DR5006ST007-3-A
10010001DR5006ST014-3-A

48,756.95

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to CISDI Drawing Revisions:

S. No.

Description

Drawing Reference No.

NSH Submitted
Claim
(SR)

31

Additional Works at Quenching Pit and


OCTG - 1 Foundation. Changes in
elevation.

10010001DR5008ST013-A (Old)
10010001DR5008ST017-B (New)

4,930.00

32

Additional Works at Quenching Pit due to


drawing revision. Changes in wall
elevation.

10010001DR5050ST007- B (Old)
10010001DR5050ST007-D (New)

4,668.44

33

Sacrificial Sheet Pile for the construction


of Water Tunnel due to late issuance of
drawings and without any prior notice to
hold the construction of adjacent
structure. (Ref. Variation Order No. 11)

909,764.00

34

Removable Sheet Pile for the same


reason above.(Ref. Variation Order No.
11)

133,596.00

TOTAL AMOUNT (SAR)

1,499,510.11
Percentage of Acceptance

AMTPJ
Approved (SR)

Ref. CCF No.

Remarks

2,412.40

CCF/033

CCF Approved

8,935.71

CCF/033

CCF Approved

2,162.69

CCF/033

CCF Approved

7,001.00

CCF/032

CCF Approved

3,355.60

CCF/032

CCF Approved

4,183.25

CCF/074

CCF Approved

12,613.46

CCF/074

CCF Approved
Not Accepted by
AMTPJ

2,050.52

CCF/067

CCF Approved

2,855.54

CCF/067

CCF Approved

1,890.00

CCF/074

CCF Approved

8,649.37

CCF/074

CCF Approved

8,820.00

CCF/074

CCF Approved

4,275.00

CCF/055

CCF Approved

4,470.00

CCF/055

CCF Approved

AMTPJ
Approved (SR)

Ref. CCF No.

Remarks

7,563.53

CCF/055

CCF Approved

50,121.56

CCF/055

CCF Approved

23,078.47

CCF/058

CCF Approved

14,320.00

CCF/058

CCF Approved

15,400.46

CCF/062

CCF Approved

4,940.00

CCF/067

CCF Approved

4,539.63

CCF/067

CCF Approved

2,602.28

CCF/067

CCF Approved

2,746.46

CCF/081

CCF Approved

3,206.28

CCF/088

CCF Approved

35,471.81

CCF/089

CCF Awaiting
Approval

6,925.10

CCF/104

CCF Approved

4,800.00

CCF/105

CCF Approved

32,729.79

CCF/110

CCF Approved

37,290.89

CCF/119

CCF Approved

AMTPJ
Approved (SR)

Ref. CCF No.

Remarks

3,174.46

CCF/121

CCF Approved

3,580.69

CCF/131

CCF Approved

108,000.00

CCF/109

CCF Approved

776167.57

CCF/109

CCF Approved

1,210,333.52
80.72%

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to CISDI Drawing Revisions / Errors:

S. No.

Description

CCF Ref.

CCF Amount
(SAR)

Modification Works Due To Drawings Revisions / Errors:

Dismantling Work at Preceding Billet Saw Foundation

CCF/033

3,074.69

Dismantling Work at Detection Foundation

CCF/033

12,226.99

Dismantling Work at 115 / 13.8KV Sub Station Foundation

CCF/033

3,569.35

Additional Works for Cooling Bed Foundation

CCF/032

11,370.42

Additional Works for Hot Mill Equipment Foundation (Due to


Revision)

CCF/032

8,011.60

Charges For Rebar Wastage at Intermediate Foundation 1/7 due to


drawing revision.

CCF/074

4,183.25

Rectification work for Intermediate Transportation Foundation (3/7)

CCF/074

32,814.28

Rectification work for Crane Rail Foundation

CCF/067

2,279.27

Additional Work - Rectification of Sand Filter Foundation due to


drawing revision.

CCF/067

4,824.61

10

Additional Rebar Installation for 115 / 13.8 KV Sub Station Columns.

CCF/074

1,890.00

11

Additional Work - Installation of additional rebar for cantilever beam


at Cooling Bed Foundation.

CCF/074

16,695.30

12

Additional Work - Installation of additional rebar at Intermediate


Transportation (3/7 & 4/7) Foundation due to changes in drawing by
CISDI.

CCF/074

11,760.00

13

Additional Work - Modification of Anchor Box due to drawing


revision.

CCF/055

4,275.00

14

Additional Work - Rectification works at Piling and Binding


Foundation - OCTG - 1

CCF/055

4,470.00

15

Additional Work - At OCTG - 2 due to drawing revision.

CCF/055

7,563.53

16

Additional Works - Main Utility Electrical Room due to drawing


revision.

CCF/055

50,121.56

17

Additional Work - Rectification work at Zone - 4 Equipment Platform


Foundation due to drawing revision.

CCF/058

28,351.87

18

Additional Work - At Q.A. Line Foundation " Core Cutting" as per


reveised drawing

CCF/058

15,110.00

19

Modification work at Hot Mill (Zone -2) to accommodate steel column


structure.

CCF/062

22,331.88

20

Additional Work - At Sliding Chain Foundation due to drawing


revision.

CCF/067

6,916.00

21

Pile rectification works at Piling , Binding and transfer for LPL area
due to drawing revision

CCF/067

5,937.65

22

Additional Work at Sand Filter Bank Foundation due to drawing


revision

CCF/067

2,602.28

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to CISDI Drawing Revisions / Errors:

S. No.

Description

CCF Ref.

CCF Amount
(SAR)

23

Plate Load Bearing Test

CCF/079

37,800.00

24

Breaking of Column Sizing Mill Plate (Zone - 8) due to drawing


revision.

CCF/081

3,166.28

25

Installation of additional rebar for cantilever beam at Cooling Bed


Foundation

CCF/074

16,695.30

26

Rectification work for Intermediate Transportation Foundation (3/7)

CCF/074

32,814.28

27

Installation of additional rebar at Intermediate Transportation (3/7 &


4/7) Foundation.

CCF/074

11,760.00

28

Hot Mill Zone - 3 Foundation: Rectification work due to drawing


revision.

CCF/088

22,312.89

29

Additional Work - Main Utility Electrical Room Modification Work due


to drawing revision.

CCF/089

55,320.00

30

Additional Work at Hot Mill Zone 3 Slab -Construction Joint.

CCF/098

31,533.95

31

Additional Work - Main Utility Electrical Room Breaking of concrete


wall for cable entry due to drawing revision.

CCF/104

7,724.00

32

Add'l. Work - Core Cutting at Detection Fdn. No. 1 & Tube Collection
Fdn. for Pockets

CCF/105

4,800.00

33

Core Cutting for Bolt Pocket at Q.A. Line Foundation.

CCF/107

12,310.00

34

Add'l. Work - After Phospating No. 2 - Breaking of existing concrete


foundation and making extension as per revised drawing.

CCF/110

35,501.29

35

ER 06 - Rectification Works- Breaking of Cable Trench due received


revised drawing from CISDI

CCF/119

48,264.76

36

Additional Works at Quenching Pit and OCTG - 1 Foundation.


Changes in elevation.

CCF/121

4,930.00

37

Additional Works at Quenching Pit due to drawing revision. Changes


in wall elevation.

CCF/131

4,668.44

38

Block work in luie of mass concrete platform.

CCF/092

939,948.00

39

Backfilling for Steel Structure Erection due to wrong sequence of


work at Scale Flume Channel; RHF Inner Side and Water Tunnel
Area.

CCF/100

172,706.56

40

Backfilling Works at Water Tunnel and Main Plant Building along grid
D/E - 7/13 to serve as platform in the erection of steel structure.

CCF/112

186,932.94

41

Additional Work at Quenching Pit and OCTG - 1 Foundation due to


drawing revision.

CCF/131

4,668.44

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to CISDI Drawing Revisions / Errors:

S. No.

Description

CCF Ref.

CCF Amount
(SAR)

42

Cost Difference Of 20mm dia. To 12mm dia. MS Rebar At Main


Building

CCF/165

50,225.00

43

Hilti Hit Anchor Bolt For Main Substation

CCF/170

55,535.00

44

Cable Trench construction inside Main Substation Building as per


drawing revision.

CCF/174

5,097.97

45

Core cutting / drilling at Water Tunnel Top Slab for pipe sleeves and
duct opening as per revised drawing..

CCF/176

5,350.00

46

Additional Work at Billet Saw Foundation 2/3 - Core drilling for


additional anchor bolts pockets not shown in previous IFI drawing.

CCF/217

5,733.35

47

Blast Resistant Door"Single Leaf" For Main substation And Electrical


Room ER05

CCF/225

49,628.20

48

Modification of shear key and pockets at Cooling Bed # 2 as per


Mechanical drawing to equipment erection. (Drawing mistake from
CISDI)

CCF/228

3,200.00

49

Concete breaking around electrical conduits to create small trench to


reroute its location due to descripancy between mechanical and civil
drawing .

CCF/230

5,964.00

50

Additional Work at Charging Platform Foundation - Diamond core


drilling for anchor bolts pockets & shear keys new locations.

CCF/232

14,880.00

51

Core cutting / drilling for new anchor bolts location at Cooling Bed 1
& 2 and at Straightener Foundation No. 2 HT due to conflict between
civil and mechanical drawings.

CCF/238 Rev.1

170,664.86

52

Modification work - Slab thickening to accommodate anchor bolts


height at Hot Mill Area as per TQ SRFTI-0983. Chipping of existing
foundation and drilling holes for providing rebar and fixing with
chemical bond as per TQ SRFTI-1380. All oof these were due to
errors on CISDI issued drawings.

CCF/243

28,635.38

53

Various additional works at different locations:


a Core cutting at Scale Flume Channel wall for pipe sleeves as per TQ
) SRFTI No. 1353

CCF/247

1,420.00

b Core cutting of two pockets at QA Line as per revised drawing by


) CISDI as per TQ SRFTI No. 1416.

CCF/247

953.67

Breaking the concrete hollow block wall for 200 mm dia. pipe
c sleeves (6 nos.) and 120 mm dia. curing in transformer room
) concrete wall for 3 x 4 nos. PVC conduit pipe at Main Substation as
per TQ SRFTI No. 1419 & No. 1391.

CCF/247

2,458.00

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to CISDI Drawing Revisions / Errors:

S. No.

Description

CCF Ref.

CCF Amount
(SAR)

Core cutting for additional pipe sleeves at Physical Lab. Building as


d
per revised drawing (Reference: Dwg. no. 1001000DR5058ST001-9)
C & 1001000DR5058ST001-9-D).

CCF/247

2,768.00

Concrete foundation breaking (portion only) to accommodate trench


e
at Main Plant Area (Reference: Dwg. no. 1001000DR5008ST020-4)
C & TQ SRFTI 1334 dated 17/12/2011).

CCF/247

1,800.00

f Wall breaking for cable trench opening at Sea Water Cooling System
) as per TQ SRFTI No. 1345.

CCF/247

3,673.31

g Breaking of Foundation base for motor erection as per SCF No.


) MEIP-038 & TQ SRFTI MEC No. 073

CCF/247

1,900.00

TOTAL AMOUNT (SAR)

2,304,123.40

NFA Ref.

NFA Amount
(SAR)

N/A

2,412.40

N/A

8,935.71

N/A

2,162.69

N/A

7,001.00

N/A

3,355.60

N/A

4,183.25

N/A

12,613.46

N/A

2,050.52

N/A

2,855.54

N/A

1,890.00

N/A

8,649.37

N/A

8,820.00

N/A

4,275.00

N/A

4,470.00

N/A

7,563.53

N/A

50,121.56

N/A

23,078.47

N/A

14,320.00

N/A

15,400.46

N/A

4,940.00

N/A

4,539.63

N/A

2,602.28

NFA Ref.

NFA Amount
(SAR)

N/A

37,800.00

N/A

2,746.46

N/A

8,649.37

N/A

12,613.46

N/A

8,820.00

N/A

3,206.28

N/A

35,471.81

N/A

10,250.27

N/A

6,925.10

N/A

4,800.00

N/A

12,310.00

N/A

32,729.79

N/A

37,290.89

N/A

3,174.46

N/A

3,580.69

N/A

939,948.00

N/A

73,838.79

N/A

186,932.94

N/A

3,580.69

NFA Ref.

NFA Amount
(SAR)

NFA No. 289

50,225.00

NFA No. 307

55,535.00

NFA No. 285

4,844.23

NFA No. 285

5,350.00

NFA No. 476

5,733.35

NFA No. 482

46,937.01

NFA No. 482

2,288.00

NFA No. 476

13,693.40

NFA Ref.

NFA Amount
(SAR)

1,805,515.46

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to CISDI Drawing Revisions / Errors:

S. No.

Description

CCF Ref.

CCF Amount
(SAR)

Additional Works due to wrong Drawing Sequense issuance:

45

Sacrificial Sheet Pile for the construction of Water Tunnel due to late
issuance of drawings and without any prior notice to hold the
construction of adjacent structure. (Ref. Variation Order No. 11)

CCF/109

108,000.00

46

Removable Sheet Pile for the same reason above.(Ref. Variation


Order No. 11)

CCF/109

776,167.57

TOTAL AMOUNT (SAR)

884,167.57

NFA Ref.

NFA Amount
(SAR)

N/A

108,000.00

N/A

776,167.57
884,167.57

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by NSH Due to SID Drawing Revisions / Errors:

S. No.

Description

Amount
(SR)

Modification Works Due To Drawings Revisions / Errors:

Casting of pumps pedestals for pump installation at Main Pump


House Building. This was due to wrong assignment of drawing.

Drilling for 32 nos. 28mm diameter for chemical anchor bolts at WTP
Area 100 as per AMJ instruction SI - P - 018 due to wrong SID civil
assignment drawing.

1,920.00

Core cutting for opening of 500mm diameter at 700mm thick wall on


WTP Area 100 as per SCF No. MEIP - 053

2,137.00

Core cutting to accommodate 1100mm diameter pipe sleeve at


300mm thick wall of Sea Water Cooling System as per drawing
revisions.
TOTAL AMOUNT (SAR)

20,291.79

20,367.75

44,716.54

Ref. CCF No.

NFA Ref.

NFA Amount
(SAR)

Reason / Remarrks

CCF/228

Cost Subject to Negotiation


w/ NSH

CCF/238 Rev.1

Cost Subject to Negotiation


w/ NSH

CCF/245

Cost Subject to Negotiation


w/ NSH

CCF/245

Cost Subject to Negotiation


w/ NSH

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by IBSF Due to CISDI Drawing Revisions / Errors:

S. No.

Description

CCF Ref.

CCF Amount
(SAR)

Modification Works Due To Drawings Revisions / Errors:

Rectification Works of Frame Columns AAD-7 & AAD-8.

CCF/054

131,280.00

Rectification of Purlin CB1441 & CB1310.

CCF/063

35,675.00

Rectification of Column Bracket and Plates to Installed Roof Beam.

CCF/073

19,860.00

Rectification of Column Bracing and Frame Column (AAg-1).

CCF/077

4,825.00

Cradle Frame for Lifting of Box Girder (BAD-20 & BAC-23).

CCF/096

180,290.00

Rectification of Column Bracings and Frame Columns (AAc-6,AAc-9 &


AAc-10).

CCF/101

3,435.00

Rectification Works of Frame Columns (ST003&ST007), Purlin


(ST005), Auxilliary Truss (ST006).

CCF/123

17,328.00

Rectification Works for Eave & Valley Gutter at Site.

CCF/164

115,500.00

10

Rectification of Frame Column (AAC-26) and Roof Beams (CA2.31 &


CA2.36)

CCF/192

16,325.00

11

Rectification of Frame Column (AAC-7 & AAC-8),Column Bracing


(AZF-14,AZF-19 & AZF-17) and Roof Beams (CA3.44)

CCF/203

26,029.00

12

Rectification of Purlin (CB1477),Additional of Roof Panel and


Removal of Roof Sheeting & Bracing.

CCF/210

55,873.00

13

Rectification of Handrail (G.L. A/1-13 & G.L. A/14-18).

CCF/213

76,400.00

14

Rectification of Column (AAK-20),Stair No.263LA-1(G.L. K/30) and


Removal of Roof Sheeting & Bracing for MEIP Works.

CCF/221

54,126.00

15

Rectification of Stairs @ G.L. D (Steel Ladder to Crane Service Platform 1)

CCF/222

86,280.00

16

Relocation of the Installed Steel Ladders.

CCF/240

70,781.00

17

Rectification of columns to install the visit platform

CCF/242

299,020.00

18

Removed and Reinstalled chequered plates and column bracing for


chimney opening.

CCF/244

72,800.00

19

Modification of Wall Frame at G.L. A/7-8.

CCF/246

14,020.00

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA
Additional Works Carried by IBSF Due to CISDI Drawing Revisions / Errors:

S. No.

20

Description

Modification of Gutter DE-7 at G.L. A/13-14 and Additional Support at


G.L. A/14 as per latest revision.

TOTAL AMOUNT (SAR)

CCF Ref.

CCF Amount
(SAR)

CCF/258

30,180.00

1,310,027.00

NFA Ref.

NFA Amount
(SAR)

76,659.00

32,255.00

16,760.00

4,425.00
154,442.00
3,135.00
NFA/354

14,868.00

NFA/312

50,795.00

NFA/318

12,125.00

NFA/354

26,029.00

NFA/386

25,073.00

NFA/467

73,400.00

NFA/447

4,026.00

NFA/447

86,280.00

NFA Ref.

NFA Amount
(SAR)

580,272.00

ARCELORMITTAL TUBULAR PRODUCTS PROJECT


AL - JUBAIL, KINGDOM OF SAUDI ARABIA

Summary For Back-Charged Amount To CISDI


S. No.

Description

Final Back-Charged Amount


($)

(SAR)

NSH - Modification Works Due To Drawings Revisions / Errors:

481,470.79

1,805,515.46

NSH - Additional Works due to wrong Drawing Sequense issuance:

235,778.02

884,167.57

IBSF - Modification Works Due To Drawings Revisions / Errors:

154,739.20

580,272.00

871,988.01

3,269,955.03

TOTAL BACK-CHARGED AMOUNT

ck-Charged Amount To CISDI


Remarks