Beruflich Dokumente
Kultur Dokumente
$2500.00
$3500.00
$2200.00
VARIABLE
$45 / UNIT
$30 / UNIT
$40 / UNIT
The selling price of the product is $70 and the company wishes
to find a location with an expected volume of 1200 per year.
The equation to be used for each is:
TOTAL COST = FIXED COSTS + VARIABLE COSTS
(VOLUME)
$56,500
$39,500
$50,200
Cost-volume analysis
Data
Cost Type. Each type of cost must be identified as either a fixed cost or a variable cost.
The default is that the first cost in the list is fixed and that all other costs are variable.
These values can be changed by using the usual dropdown box.
Costs. The specific cost for each option gets listed in the two columns in the table.
Volume. If a volume analysis is desired then enter the volume at which this analysis
should be performed. The volume analysis will compute the total cost (revenue) at the
chosen volume. If the volume is 0 then no volume analysis will be performed other
than for the breakeven point. We have asked for a volume analysis at 250 units.
The solution screen is very straightforward. In the screen above there are 5 costs with
some of them being fixed and some of them being variable. The program displays the
following four outputs.
Total Fixed Costs. For each of the two options the program takes the fixed costs, sums
them up and lists them below the table. In this example the total fixed costs for option
1 are $1300 (800+500) while the total fixed costs for option 2 are $900 (700+200).
Total Variable Costs. The program identifies the variable costs, sums them up and lists
them. In this example the total variable costs for option 1 are $10 per unit while for
option 2 they are $12 per unit.
Break even point in units. The breakeven point is the difference between the fixed
costs divided by the difference between the variable costs and this is displayed in
units. In the example it is 200 units.
Break even point in dollars. The breakeven point can also be expressed in dollars.
A volume analysis has been performed for a volume of 250 units. The total fixed costs
and total variable costs have been computed for each option and these have been
summed to yield the total cost for each option.
A graph is available as shown below.
Breakeven analysis
Example 2 - Using Breakeven Analysis with prices
One standard type of break even analysis has revenue versus cost.
Data entry for this option is slightly different in that the program creates a column for
costs and a column for revenues. The fixed and variable costs get entered in the cost
column and the revenue per unit is placed in the revenue column.
We have used three types of cost to set up the table. The first is for the fixed cost of
$10,000, the second is for the variable cost of $20 per unit and the third is for the
(variable) revenue of $25 per unit. The program will compute a break-even volume of
2000 units or $50,000 (not shown).
Example 3 - Breakeven point with three options
The break even module can perform a breakeven analysis for two or three options.
Below we demonstrate the output for a 3 option breakeven. Of course, while there are
three breakeven points only two of them are relevant.
budgeted fixed
varianc
e
=(
budgeted production
units produced
overhead
=(
units produced
budgeted fixed
overhead
Since
budgeted fixed
overhead factory
capacity = budgeted
rate
overhead
overproduce, because as
production increases, the per-unit
cost decreases. Similarly,
calculating the volume variance
using budgeted production in the
denominator of the overhead rate
can provide managers short-run
incentives to overproduce,
because as production exceeds
budget, the volume variance
becomes increasingly favorable.
For this reason, some companies
choose not to allocate fixed
overhead at all. However, the use
of factory capacity in the
denominator of the fixed overhead
rate accomplishes the same
objective, because it isolates the
volume variance such that the
performance reports of these
managers need not be affected by
it.
We have assumed, throughout this
section, that fixed overhead is
allocated based on units of output.
However, we saw in the chapter
on activity-based costing that
units of production is often a poor
choice of allocation base in a
multi-product factory, and many
companies that use standard
costing systems use allocation
bases that are more sophisticated,
such as direct labor hours or direct
materials dollars. The question
might arise, how does the use of a
different allocation base, such as
direct labor hours, affect the
calculation of the volume
variance? The answer is: Not at
Comprehensive Example of
Fixed Overhead Variances:
The Coachman Company makes
pencils. The pencils are sold by
the box. Following is information
about the companys only factory:
Number of boxes
Direct labor hours
Machine hours
Fixed overhead
Budget
10,000
200
500
$40,000
Actual
12,000
250
650
$42,000
Capacity
20,000
or equivalently:
volume variance = $2.00 per box
x (12,000 boxes 20,000 boxes)
= $16,000 unfavorable
If the company uses a standard
costing system, the amount
of overallocated or underallocated
fixed overhead is the difference
between actual fixed overhead
incurred, and fixed overhead
allocated to product, calculated as
follows:
actual fixed
overhead fixed
allocated
overhead
=
$42,000 ($2.00
per box x 12,000 boxes)
= $42,000 $24,000
$18,000 underallocated
or equivalently:
volume variance = $4.00 per box
x (12,000 boxes 10,000 boxes)
= $8,000 favorable
If the company uses a standard
costing system, the amount
of overallocated or underallocated
fixed overhead is the difference
between actual fixed overhead
incurred, and fixed overhead
allocated to product, calculated as
follows:
actual fixed
overhead fixed
allocated
overhead
=
$42,000 ($4.00
per box x 12,000 boxes)
= $42,000 $48,000
$6,000 overallocated
January 2013
Let's begin by determining the standard cost of variable manufacturing overhead for the good output
that DenimWorks produces in January 2013:
Recall that there were 50 actual direct labor hours in January. Let's assume that the actual cost for
the variable manufacturing overhead (electricity and manufacturing supplies) during January is $90.
Our analysis will look like this:
Variable Manufacturing Overhead Analysis for January 2013:
Notice that for the good output produced in January, the actual cost of variable manufacturing
overhead was $90 and the total standard cost of variable manufacturing overhead cost allowed for
the good output was $84. This unfavorable difference of $6 agrees to the sum of the two variances:
The additional 8 hours no doubt caused the company to use additional electricity and supplies.
Measured at the originally estimated rate of $2 per direct labor hour, this amounts to $16 (8 hours x
$2). This is referred to as anunfavorable variable manufacturing overhead efficiency variance.
Variable Manufacturing Overhead Spending Variance
In the analysis above, item 2 shows that based on the 50 direct labor hours actually used, electricity
and supplies could reasonably add up to $100 instead of the standard of $84. (If the good output
took 8 actual direct labor hours more than the standard hours to cut and sew the denim, the
company will likely have additional electricity and supplies costs since it is operating the machines
for an additional 8 hours.) We find, however, that the actual cost of the electricity and supplies is $90,
not $100. This $10 favorable variance indicates that the company did not spend the planned $2 per
direct labor hour. (Perhaps electricity rates were lower than the rates anticipated when the standard
costs were established.)
Actual variable manufacturing overhead costs are debited to overhead cost accounts. The credits are
made to accounts such as Accounts Payable. For example:
Another entry records how these overheads are assigned to the product based on standard costs:
As our analysis notes above and these entries illustrate, DenimWorks has an actual variable
manufacturing overhead of $90, but only $84 (the standard amount) was applied to the products.
The $6 difference is "explained" by the two variances:
February 2013
Recall that in February 2013 the company produced 200 large aprons and 100 small aprons. We use
that good output to compute the standard cost of variable manufacturing overhead for February
2013:
Given that there were 75 actual direct labor hours in February and assuming that the actual cost for
the variable manufacturing overhead in February was $156, our analysis will look like this:
Variable Manufacturing Overhead Analysis for February 2013:
The favorable difference between the actual cost of $156 and the standard cost of $160 agrees to
the sum of the two variances:
Actual variable manufacturing overhead costs are debited to overhead cost accounts. The credits are
made to accounts such as Accounts Payable. For example:
Another entry records how these overheads are assigned to the product:
As our analysis notes above and as these entries illustrate, even though DenimWorks had actual
variable manufacturing overhead of $156, the standard amount of $160 was applied to the products.
For the month of February 2013 the company applied more variable manufacturing overhead to its
products than it actually incurred.
We will discuss later how to report the balances in the variance accounts under the heading"What
To Do With Variance Amounts".
property tax bill was not dependent on the number of units produced or the number of machine
hours that the plant operated. Other examples include the depreciation or rent on production
facilities; salaries of production managers and supervisors; and professional memberships and
training for personnel in the manufacturing area. Although the fixed manufacturing overhead costs
present themselves as large monthly or annual expenses, they are, in reality, a small part of each
product's cost.
DenimWorks has two fixed manufacturing overhead costs:
A small amount of these fixed manufacturing costs must be allocated to each apron produced. This
is known as absorption costing and it explains why some accountants say that each product
must "absorb" a portion of the fixed manufacturing overhead costs.
A simple way to assign or allocate the fixed costs is to base it on things such as direct labor hours,
machine hours, or pounds of direct material. (Accountants realize that this is simplistic; they know
that overhead costs are a result ofor are driven bymany different factors.) Nonetheless, we will
assign the fixed manufacturing overhead costs to the aprons by using the same method we used for
variable manufacturing overheadby using direct labor hours.
We can do that from the information given earlier (and repeated here):
Step 3.
Compute the standard fixed manufacturing rate to be used in 2013.
Note:
One of the reasons a company develops a predetermined annual rate is so that the rate
is uniform throughout the year, even though the number of units manufactured may
fluctuate month by month. For example, if the company used monthly rates, the rate
would be high in the months when few units are manufactured (monthly fixed costs of
$700 100 units produced = $7 per unit) and low when many units are produced
(monthly fixed costs of $700 350 units = $2 per unit).
Fixed Manufacturing Overhead Budget Variance
The difference between the actual amount of fixed manufacturing overhead and
the estimated amount (the amount budgeted when setting the overhead rate prior to the start of the
year) is known as the fixed manufacturing overhead budget variance.
In our example, we budgeted the annual fixed manufacturing overhead at $8,400 (monthly rents of
$700 x 12 months). If DenimWorks pays more than $8,400 for the year, there is an unfavorable
budget variance; if the company pays less than $8,400 for the year, there is a favorable budget
variance.
This analysis shows that the actual fixed manufacturing overhead costs are $8,700 and the fixed
manufacturing overhead costs applied to the good output are $8,440. This unfavorable difference of
$260 agrees to the sum of the two variances:
Actual fixed manufacturing overhead costs are debited to overhead cost accounts. The credits are
made to accounts such as Accounts Payable or Cash. For example:
Another entry records how these overheads are assigned to the product:
This model is used to balance workloads on an assembly line. Five heuristic rules can
be used for performing the balance. The cycle time can be given explicitly or the
production rate can be given and the program will compute the cycle time. This model
will not split tasks. Task splitting is discussed in more detail in a later section.
The Model
The general framework for assembly line balancing is dictated by the number of tasks
which are to be balanced. These tasks are partially ordered as shown for example in
the precedence diagram below.
Precedences. Enter the precedences, one per cell. If there are two precedences they
must be entered in two cells. Do not enter 'a,b'. In fact, a comma will not be accepted
Notice that in the precedence list we have typed both 'a' and 'A'. As mentioned
previously, the case of the letters is irrelevant.
Example 1
In this example we have 6 tasks named a through f. The precedence diagram for this
problem appears above. The time to perform each task is above the task. Also, note
that the tasks which are ready at the beginning of the balance are
tasks a and b. Finally, in this first example we use a cycle time of 10.
Solution
The screen above contains the solution to our first example. The solution screen will
always have the same appearance and contain the same information regardless of the
rule which is chosen for the balance. The information is as follows.
The cycle time. The cycle time which was used appears below the balance. This cycle
time was either given directly or was computed. In this example the cycle time was
given directly as 10 seconds.
Station numbers. The station numbers appear in the far left column. They are printed
only for the first task which is loaded into each station. In this example three stations
are required.
Task names. The tasks which are loaded into the station are listed in the second
column. In this example tasks b, e and a are in station 1, tasks d and c are in station 2
and task f is in station 3.
Task times. The length of time for each task appears in this column.
Time left. The length of time which remains at the station is listed in this column. The
last number at each station is of course the idle time at that station. For example, there
is 1 second of idle time at station 1, 1 second at station 2, and 2 seconds at station 3
for a total of 4 seconds of idle time per cycle.
Ready tasks. The tasks which are ready appear here. A ready task is any task which
has had its precedences met. We emphasize this because some books do not list a task
as ready if its time exceeds the time remaining at the station. Also, if the number of
characters in the ready task list is very long you might want to widen that column.
Time allocated. The total time allocated for making each unit is printed. This time is
the product of the number of stations and the cycle time at each station. In this
example we have 3 stations each with a cycle time of 10 seconds for a total work time
of 30 station-seconds.
The time needed to make one unit. This is simply the sum of the task times. In the
example we have 1 + 5 + 2 + 7 + 3 + 8 = 26 seconds.
Idle time. This is the time needed subtracted from the time allocated. This example
has 30 - 26= 4 which matches the 4 seconds found in the column of time left.
The efficiency. Efficiency is defined as the time needed divided by the time allocated.
In this example the efficiency is computed as 26/30 which is .8667
The balance delay. The balance delay is the percentage of wasted time or 100% - the
efficiency. In this example it is 4 (the idle time)/30 or .1333 which is also determined
by 1-.8667.
Minimum theoretical number of stations. This is the total time to make one unit
divided by the cycle time and rounded up to the nearest integer. In this example we
have 26 seconds required to make one unit divided by a 10 second cycle time for an
answer of 2.6. which we round up to 3 stations.
The precedence graph can be displayed as well as a bar graph indicating how much
time was used at each station. These are shown at the end of this section. In addition,
if there is idle time at every station then a note will appear at the top indicating that
the balance can be improved (by reducing the cycle time).
Example 2 - computing the cycle time
Suppose that for the same data we require a production of 2250 units in 7.5 hours.
We assume full minutes and hours and compute the cycle time as
(7.5 hrs/2,250units)*60 min/hr*60 sec/min = 27,000/2,250 = 12 seconds
as illustrated in the balance in the screen below.
Other rules
A common way to choose tasks is by using the task with the most tasks following.
Notice from the diagram that a has three tasks following it and b has 2 tasks following
it. Therefore the first task scheduled is task a when using this rule.
Ranked positional weight method
The ranked positional weight computes the sum of the task and all tasks which follow.
For example, for task a the ranked positional weight is 1 + 2 + 7 + 8 = 18 while for
task b the weight is 5 + 3 + 8 =16. The task with the largest weight is scheduled first
(if it will fit in the remaining time). Notice that e has a higher ranked positional
weight than c.
Shortest operation time
Another rule that is used sometimes is to give priority to the task which takes the least
amount of time.
Least number of followers
Some books and some software do not apply the longest operation time rule properly.
If the task with the longest time will not fit into the station then the task with the
second longest time should be placed in the station if it will fit.
In the screen below we present data for 8 tasks. Notice that tasks b and c follow
task a.
The balance appears above for a cycle time of 5 seconds. After task a is completed
tasks b and c are ready. Task b is longer but will not fit in the 4 seconds which remain
at station 1. Therefore, task c is inserted into the balance. We caution you that if the
answer in your book differs from the program to check if the book has neglected to
put in the task with the longest operation time that will fit.
Example 4 - Splitting Tasks
If the cycle time is less than the amount of time to perform a specific task then there is
a problem. We perform what is termed task splitting but in reality is actually
duplication. For example, suppose that the cycle time is 2 minutes and a task takes 5
minutes. Then we have the task performed three times (by three people at three
machines independent of one another). The effect is that three units will be done every
5 minutes which is equivalent to one unit every 1.33 minutes which fits into the 2
minute cycle.
Now, the actual way that the three people work may vary. While other programs will
split tasks the assumptions vary from program to program. Rather than making
assumptions we leave it to you to split the tasks by dividing the task time
appropriately.
Suppose that in Example 1 we wanted to use a cycle time of 6 seconds. Then it is
necessary to replicate both tasks d and f since they will not fit in the cycle time. The
approach to use is to solve the problem by dividing the task times by two since this
replication is needed. We present the results below
Graphs
Two different graphs are available. The first is a precedence graph as shown below.
Please note that there may be several different ways to draw a precedence graph.
The second graph is of time used at each station. In a perfect world these would all be
the same (a perfect balance)
Chapter Contents:
Cost Variances for Variable Overhead
Cost Variances for Fixed Overhead
The Fixed Overhead Spending Variance
The Fixed Overhead Volume Variance
Additional Issues Related to the Volume Variance
Comprehensive Example of Fixed Overhead Variances
Cost Variances for Variable Overhead:
The formulas for splitting the flexible budget variance for variable overhead into a
price variance and an efficiency variance are the same as the formulas for direct
materials and direct labor explained in Chapter 6. The price variance for variable
overhead is called the variable overhead spending variance:
Spending variance = PV = AQ x (AP SP)
Efficiency variance = EV = SP x (AQ SQ)
Where AP is the actual overhead rate used to allocate variable overhead, and SP is the
budgeted overhead rate. The Qs refer to the quantity of the allocation base used to
allocate variable overhead, so that AQ is the actual quantity of the allocation base
used during the period, and SQ is the standard quantity of the allocation base. The
standard quantity of the allocation base is the amount of the allocation base that
should have been used (i.e., would have been budgeted) for the actual output units
produced.
Given the use of the allocation base in these formulas for the cost variances for
variable overhead, the meaning of these variances differs fundamentally from the
interpretation of the variances for direct materials and direct labor. Consider a
company that allocates electricity using direct labor as the allocation base. A negative
variable overhead efficiency variance does not necessarily mean that the factory used
more electricity than the flexible budget quantity of kilowatt hours for the actual
outputs produced. Rather, the negative variance literally means that the factory used
more direct labor than the flexible budget quantity for direct labor. If there is a causeand-effect relationship between the allocation base and the variable overhead cost
category (i.e., if more direct labor hours implies more electricity used), then the
negative efficiency variance suggests that more electricity was used than the flexible
budget quantity, but the efficiency variance does not measure kilowatts directly.
Similarly, a negative spending variance for variable overhead does not necessarily
mean that the cost per kilowatt-hour was higher than budgeted. Rather, a negative
spending variance for variable overhead literally states that the actual overhead rate
was higher than the budgeted overhead rate, which could be due either to a higher cost
per kilowatt-hour, or more kilowatt hours used per unit of the allocation base. Hence,
what one might think should be included in the efficiency variance (kilowatt hours
required per direct-labor-hour being higher or lower than budgeted) actually gets
included as part of the spending variance.
=(
X units produced
budgeted fixed
overhead
The term in parenthesis equals the amount of fixed overhead that would be allocated
to production under a standard costing system, when budgeted production is the
denominator-level concept.
Since
budgeted fixed overhead budgeted production = budgeted overhead
rate
the above expression for the volume variance is algebraically equivalent to the
following formula:
volume =
variance
This formula for the volume variance illustrates the statement above; that the volume
variance attaches a dollar amount to the difference between two production levels. In
this case, the two production levels are actual production and budgeted production.
The interpretation of the volume variance, when budgeted production is used in the
denominator of the overhead rate, is the following. When actual production is less
than budgeted production, the volume variance represents the fixed overhead costs
that are not allocated to product because actual production is below budget. In this
case, the volume variance is unfavorable. When actual production is greater than
budgeted production, then the volume variance represents the additional fixed
overhead costs that are allocated to product because actual production exceeds budget.
In this case, the volume variance is favorable.
The intuition for when the volume variance is favorable and when it is unfavorable is
the following. If the company can produce more units of output using the same fixed
assets (i.e., the resources that comprise fixed overhead), then assuming those
additional units can be sold, the company is more profitable. When fixed overhead is
allocated to production, this greater profitability is reflected in a lower per-unit
production cost, because the same amount of total fixed overhead is spread over more
units. On the other hand, if fewer units are produced than planned, then the same fixed
overhead is spread over fewer units, the per-unit production cost is higher, and the
company is less profitable. This higher or lower profitability that arises from changes
in production levels is not an artifact of the accounting system. Even if the company
uses Variable Costing, and expenses fixed overhead as a lump-sum period cost, when
the company makes and sells fewer units than planned using the same fixed overhead
resources, it really is less profitable than was budgeted, and when the company makes
and sells more units than planned using the same fixed overhead resources, it really is
more profitable than was budgeted.
The volume variance with factory capacity in the denominator of the O/H rate:
Next we use factory capacity to calculate the volume variance. In this case:
volume
varianc
e
=(
units produced
budgeted fixed
overhead
Since
budgeted fixed overhead factory capacity = budgeted overhead rate
the above expression for the volume variance is algebraically equivalent to the
following formula:
volume = (units produced factory capacity) x budgeted overhead rate
variance
The interpretation of the volume variance, when factory capacity is used in the
denominator of the overhead rate, is the following. Actual production is almost always
below capacity. The volume variance represents the fixed overhead costs that are not
allocated to product because actual production is below capacity. Hence the volume
variance represents the cost of idle capacity, and this variance is
typically unfavorable. For this reason, this volume variance is sometimes called
the idle capacity variance. In the unlikely event that the factory produces above
capacity (which can occur if the concept of practical capacity is used, and actual
down-time for routine maintenance, etc., is less than expected), then the volume
variance represents the additional fixed overhead costs that are allocated to product
because actual production exceeds capacity. In this case, the volume variance
is favorable.
the cost of this strategic decision, and the cost reports of factory managers and the
product profitability statements of product managers are negatively affected by this
unused capacity. Some companies prefer to isolate the cost associated with this
strategic decision, and to either show the cost of idle capacity as separate line-items
on the cost reports and profit statements of the factory manager and product managers,
or remove this cost entirely from these performance reports, and report it only at the
corporate level.
Allocating fixed overhead using actual production can provide managers short-run
incentives to overproduce, because as production increases, the per-unit cost
decreases. Similarly, calculating the volume variance using budgeted production in the
denominator of the overhead rate can provide managers short-run incentives to
overproduce, because as production exceeds budget, the volume variance becomes
increasingly favorable. For this reason, some companies choose not to allocate fixed
overhead at all. However, the use of factory capacity in the denominator of the fixed
overhead rate accomplishes the same objective, because it isolates the volume
variance such that the performance reports of these managers need not be affected by
it.
We have assumed, throughout this section, that fixed overhead is allocated based on
units of output. However, we saw in the chapter on activity-based costing that units of
production is often a poor choice of allocation base in a multi-product factory, and
many companies that use standard costing systems use allocation bases that are more
sophisticated, such as direct labor hours or direct materials dollars. The question
might arise, how does the use of a different allocation base, such as direct labor hours,
affect the calculation of the volume variance? The answer is: Not at all. Because of
the way in which standard costing systems work, the amount of fixed overhead that
will be allocated to product does not depend on the choice of allocation base.
For example, assume that a one-product company budgets two direct labor hours to
make each unit, and assume that if fixed overhead is allocated based on output units,
the budgeted fixed overhead rate is $10 per unit. Then using direct labor hours as the
allocation base, the budgeted fixed overhead rate is $5 per direct labor hour. Because
of the mechanics of standard costing systems, no matter whether the $10-per-unit rate
is used, or the $5-per-direct-labor-hour rate is used, $10 of fixed overhead will be
allocated to every unit produced, no matter how many direct labor hours are actually
used per unit. (If this fact is not obvious to you, refer back to Chapter 10 on standard
costing.) Therefore, for the purpose of calculating the volume variance, we might as
well use the easiest allocation base, which is units-of-output.
Budget
10,000
200
500
$40,000
Actual
12,000
250
650
$42,000
Capacity
20,000
The outputs here are boxes of pencils. The inputs are direct labor hours and machine
hours. First we calculate a fixed overhead rate using actual amounts, and output units
as the allocation base:
$42,000 12,000 boxes = $3.50 per box.
Using this overhead rate, every box of pencils is costed at the variable cost of
production plus $3.50 in allocated fixed overhead.
Next we calculate a fixed overhead rate using budgeted costs, and budgeted output
units as the denominator-level concept:
$40,000 10,000 boxes = $4.00 per box.
Next we calculate a fixed overhead rate using budgeted costs, and factory capacity as
the denominator-level concept (expressed in terms of output units).
$40,000 20,000 boxes = $2.00 per box.
The advantage of using capacity in the denominator is that this denominator-level
concept shows how low the fixed cost per unit can go, and hence, how low the total
cost per unit can go, as production increases.
Yield (finance)
This article needs additional citations for verification. Please help improve this
article by adding citations to reliable sources. Unsourced material may be challenged and
Finance
Financial markets[show]
Financial instruments[show]
Corporate finance[show]
Personal finance[show]
Public finance[show]
Financial regulation[show]
Standards[show]
Economic history[show]
V
T
E
In finance, the term yield describes the amount in cash (in percent terms) that returns to the owners
of a security. Normally, it does not include the price variations, at the difference of the total return.
Yield applies to various stated rates of return on stocks (common and preferred, and convertible),
fixed income instruments (bonds, notes, bills, strips, zero coupon), and some other investment type
insurance products (e.g. annuities).
The term is used in different situations to mean different things. It can be calculated as a ratio or as
an internal rate of return (IRR). It may be used to state the owner's total return, or just a portion
of income, or exceed the income.
Because of these differences, the yields from different uses should never be compared as if they
were equal. This page is mainly a series of links to other pages with increased details.
Contents
[hide]
2 Preferred shares
4 Common shares
5 Annuities
9 See also
10 References
Preferred shares[edit]
Like bonds, preferred shares compensate owners with scheduled payments which resemble interest.
However, preferred "interest" is actually in the form of a dividend. This is a significant accounting
difference as preferred dividends, unlike debt interest, are charged after taxes and below net
income, therefore reducing net income and ultimately earnings per share. Preferred shares may also
contain conversion privileges which allow for their exchange into common stock.
The dividend yield is the total yearly payments divided by the principal value of the preferred share.
The current yield is those same payments divided by the preferred share's market price.
If the preferred share has a maturity (not always) there can also be a yield to maturity and yield to
call calculated, the same way as for bonds.
Common shares[edit]
Common shares will often pay out a portion of the earnings as dividends. The dividend yield is the
total dollars (RMB, Yen, etc.) paid in a year divided by the spot price of the shares. Most web sites
and reports are updated with the expected future year's payments, not the past year's.
The price/earnings ratio quoted for common shares is the reciprocal of what is called the earnings
yield. EarningsPerShare / SharePrice.
Annuities[edit]
The life annuities purchased to fund retirement pay out a higher yield than can be obtained with
other instruments, because part of the payment comes from a return of capital. $YearlyDistribution /
$CostOfContract.
estimated rental value (ERV) less costs that are incurred along the way. The discount rate used to
calculate the net present value (NPV) of the DCF to equal zero is the equivalent yield, or
the IRR.Initialyield.com (May 2012). "Glossary, Equivalent Yield". Equivalent Yield. Retrieved May
2012.
The calculation not only takes into account all costs, but other assumptions including rent reviews
and void periods. A trial and error method can be used to identify the equivalent yield of aDCF, or if
using Excel, the goal seek function can be used.
See also[edit]
Ecological yield
Yield curve
30-day yield
Nominal yield
Bond (finance)
the country, general region, small number of community alternatives, and site alternatives.
Several factors that influence location positioning include the location of raw materials, proximity to the
market, climate, and culture. Models for evaluating whether a location is best for an organization consist
of cost-profit analysis for locations, the center of gravity model, the transportation model, and factor
rating.
This chapter discusses the decision to relocate a facility by considering costs and benefits. If you are
planning on moving or acquiring a new facility, there are many factors to consider: the size, the
geographic area, culture, transportation costs and others. After a location or locations have been chosen
a cost-profit-volume analysis is done.
The main factors that affect location decisions include regional factors, community
considerations, and site-related factors. Community factors consist of quality of life,
services, attitudes, taxes, environmental regulations, utilities, and development support.
EVALUATING LOCATION ALTERNATIVES (Page 385)
There are three specific analytical techniques available to aid in evaluating location alternatives:
1.
1.
1.
2.
3.
4.
5.
2.
1.
1.
Factor Rating
This method involves qualitative and quantitative inputs, and evaluates alternatives
based on comparison after establishing a composite value for each alternative. Factor Rating consists of
six steps:
1.
2.
3.
4.
5.
Adjust score using weights (multiply factor weight by score factor); add up scores
for each alternative.
6.
The alternative with the highest score is considered the best option.
2.
Minimum scores may be established to set a particular standard, though this is not
necessary.
2.
o
face after a location move. Culture shock can have a big impact on employees which might
affect workers productivity, so it is important that mangers look at this.
v IDENTIFYING A COUNTRY
o A decision maker must understand the benefits and risks as well as the probabilities of
them occurring
v IDENTIFYING A REGION- 4 major considerations
o Location to Raw Materials: The three most important reasons for a firm to locate in a
particular region includes raw materials, perishability, and transportation cost. This often
depends on what business the firm is in.
o Location to Markets: Profit maximizing firms locate near markets that they want to serve as
part of their competitive strategy. A Geographic information system(GIS) is a computer
based tools for collecting, storing, retrieving, and displaying demographic data on maps.
o Labor Factors : Primary considerations include labor availability, wage rates, productivity,
attitudes towards work, and the impact unions may have.
o Other : Climate is sometimes a consideration because bad weather can disrupt operations.
Taxes are also an important factor due to the fact that taxes affect the bottom line in some
financial statements.
v IDENTIFYING A COMMUNITY
o There are many important factors for deciding upon the community in which move a
business. They include facilities for education, shopping, recreation and transportation
among many others. From a business standpoint these factors include utilities, taxes, and
environmental regulation.
v IDENTIFYING A SITE
o The main considerations in choosing a site are land, transportation, zoning and many
others. When identifying a site I]it is important to consider to see if the company plans on
growing at this location. If so, the firm must consider whether or not location is suitable for
expansion. There are many decisions that go into choosing exactly where a firm will establish its
operations. First, a company must determine the driving factors that will influence which areas are
suitable locations. After these factors have been determined, the company will identify potential countries
and examine the pros and cons of establishing operations in these countries. After looking at pro and
cons of the different countries and deciding on a country, then decision makers will identify a region within
the country. When identifying a region, decision makers must take the four major factors explained above
into consideration. The last two stages of the search include choosing a community and a site.
Note: The above part is way too lengthy for this assignment.
Summary below..
Summary : There are several ways that are very helpful in evaluating location alternatives, such as
locational cost-profit-volume analysis, factor rating, and the center of gravity method. First, let's take a
look at Location Cost-Profit-Volume Analysis.
This analysis can be done numerically or graphically. The procedure for locational cost-profit-volume
Total cost = Fixed cost + Variable cost per unit * Quantity or volume of output
Total profit = Quantity(Revenue per unit - Variable cost per unit) - Fixed cost
In most situations, other factors besides cost must also be considered. We will now consider another kind
of cost often considered in location decisions: transportation costs.
Transportation costs sometimes play an important role in location decisions. The company can include
the transportation costs in a locational cost-volume analysis by incorporating the transportation cost per
unit being shipped into the variable cost per unit if a facility will be the sole source or destination of
shipments. When there is a problem with shipment of goods from multiple sending points to multiple
receiving points, and a new location is to be added to the system, the company should undertake a
separate analysis of transportation. In this case, transportation model of linear programming is very
helpful. The model is used to analyze each of the configurations considered, and it reveals the minumum
costs each would provide. Then the information can be included in the evaluation of location alternatives.
1.
Specialization involved in this strategy usually results in economies of scale and, compared to
multipurpose plants, lower operating costs.
The plant locations may either be widely scattered or placed relatively close to one another.
The individual plants can produce either most, or all of the company's products and supply a
limited geographical area.
The operating costs of this strategy are often times higher than those of product plants, but
savings on shipping costs for comparable products can be made.
This strategy is useful when shipping costs are high due to volume, weight, or other factors.
It can also bring the added benefits of faster delivery and response times to local needs.
This strategy is most useful when products have numerous components; separating the
production of components results in less confusion than if all the production were done in the same
location.
A major issue with this strategy is the coordination of production throughout the system, and it
requires a highly informed, centralized administration in order to be an effective operation.
It can bring about additional shipping costs, but a key benefit is that individual plants are highly
specialized and generate volumes that brings economies of scale.
It allows for a quick response to products and market changes, but can be less productive than a
more focused approach.
A benefit to this approach is the increase in learning opportunities that happens when similar
operations are being done in different plants. Solutions to problems as well as improvements made at one
plant can be shared with the other plants
Question 1:
From a company standpoint, which factors determine the desirability of a community as a place for its
workers and managers to live?
A) The amount of parking spaces
B) Retail stores
C) Schools
D) Locals attitudes towards the company.
E) Both C and D.
Answer: E. Page 380.
Question 2:
What is NOT a risk a corporation must consider when planning a location?
A) Political
B) Exporting
C) Economic
D) Cultural
E) Economic
Answer: B. Pages 373-374.
Question 3:
What do banks, fast-food chains, supermarkets, and retail stores view locations as?
A) One in many intricate decisions for their organizations
B) A crucial part of the marketing strategy.
C) An easier way to distribute their product or service.
D) New ideas for future investments.
E) A second home.
Answer: B. Page 369
Question 4:
What is the third step when making location decisions?
A) Evaluate the alternatives and make a selection.
B) Identify important factors.
C) Decide on criteria for evaluating alternatives.
D) Develop location alternatives.
E) None of the above.
Answer: D. Page 376.
Question 5:
What is the center of gravity method?
A) A method that determines the location of a facility that will minimize shipping cost and travel time to
various destinations.
B) A method that determines the location of a facility closest to the most number of consumers.
C) A method that determines the location of a facility closest to the main supplier
D) A method that determines the location of a facility in the middle-point of all suppliers.
E) none of the above
Answer: A. Page 388
1.) Location analysis assumes that both qualitative and quantitative factors are important in determining
an ideal location when using:
a. The Transportation Model
b. The Center of Gravity Method
c. Factor Rating
d. Cost-Profit Analysis
e. None of the above
Page 379 9th Ed.
2.) The transportation model can be applied to solve factors including:
I. Cost
II. Profit
III. Capacity
IV. Management
a. I only
b. I and II only
c. I, II, and III only
d. II, III, and IV only
e. II and IV only
Page 391 9th Edition
3.) The Transportation Model uses the following information to determine costs:
a. A list of shipping origins
b. Demand of destinations
c. Unit costs
d. None of the above
e. All of the above
5) Method for locating a distribution center that minimizes the distribution costs.
A.Location cost-pofit-volume analysis
B. Method for finding balance between company culture and geographic culture.
C. Method that compares costs to benefits
D. All of the above.
E. None of the above
Answer: A
1. Which of these is a computer-based tool for collecting, storing, retrieving, and displaying
demographic data on maps?
A. Geographic Data System
B. Geographic Information System
C. Demographic Data System
D. CAM
E. none of the above
Answer: B page 379
2. Which is a major consideration when choosing to operate in a region?
A. the minimum wage rate
B. identifying a community
C. location to raw materials
D. possible sites available
E. none of the above
Answer: C page 378
3. Considering global expansion, decision makers need to be absolutely clear on the benefits and risks
and the likelihood of their occurrences when deciding upon identifying:
A. a continent
B. a site
C. a community
D. a country
E. none of the above
Answer: D page 378
4. A dominant factor that influences the location decision of a manufacturing firm is:
A. Climate changes
B. Location to competitors
C. Proximity to markets
D. Transportation cost
E. none of the above
Answer: D page 376
5. Which of the following is Not a primary consideration when identifying a site for operations?
A. Land
B. Transportation
C. Zoning
D. Future expansion
E. All of the Above
Answer: E page 381
1 . When using the Center of Gravity Method, what are the two differing variables for equal and unequal
quantities shipped, respectively?
a. n 1 ; n 2
b. n;Q
c. n; n i
d. e; u e
e. n; Q i
Answer: e ( pages 388-89 )
2. Which location alternative technique involves viewing the problem in economic terms?
a. Factor Rating
b. CVP
c. GIS
d. Center of Gravity
e. Transportation Model
Answer: b ( page 385 )
3. When considering foreign locations, crime, and the threat of terrorism fall under which category?
a. Safety
b. Cultural Differences
c. Market
d. Financial
e. Customer Preferences
Answer: a ( page 378 )
4. When using the factor rating method of location alternative evaluation, which of the following could be
considered relevant factors?
a. Location of market
b. Water supply
c. Parking facilities
d. Revenue potential
e. All of the above
Answer: e ( page 387 )
5. Which of the following is not a step in the general procedure for making location decisions?
a. Develop location alternatives
1. What is the name of the computer-based tool used for collecting, storing, retrieving, and displaying
demographic data on maps?
A: Geographic Information System (GIS)
2. True or False: Most organizations try to find the one best location.
A: False
3. What are the three primary regional factors involved in location decision making?
A: raw materials, markets, and labor considerations
4. Name three trade agreements mentioned in this chapter.
A: North American Free Trade Agreement (NAFTA), the General Agreement on Tariffs and Trade
(GATT), and the U.S. China Trade Relations Act
5. What are five disadvantages to having global operations?
A: Transportation costs, security costs, unskilled labor, import restrictions, and criticisms.
6. Suppose that the operating costs of a company has a weight of .20. There are three possible location
choices. The first location has a score of 60/100. The second location has a score of 50/100. The third
location has a score of 80/100. What are the weighted scores of each location possibility?
A:
Location 1: .20(60) = 12
Location 2: .20(50) = 10
Location 3: .20(80) = 16
7. What are some benefits associated with a company moving it's operation's globally?
A: Market expansion, financial savings, legal, etc.
8. What is the center of gravity method used for?
A: Locating a distribution center that minimizes distribution costs.
9. Find the center of gravity with the information provided below.
Destination
L1
L2
L3
L4
A:
x = 21/4 = 5.25
y = 15/4 = 3.75
The center of gravity is located at (5.25, 3.75)
10. Determine the center of gravity based on the following information:
Destination
Weekly Quantity
L1
700
L2
500
L3
800
L4
600
L5
200
Total
28
21
2,800
A:
x = [7(700) + 5(500) + 8(800) + 6(600) + 2(200)] / 2,800 = 6.36
y = [6(700) + 3(500) + 6(800) + 4(600) + 2(200)] / 2,800 = 4.75
11. Use the table below and the cost-profit-volume analysis to determine the B Superior range
approximation.
Location
$250,000
$20
$150,000
$50
$350,000
$25
$225,000
$40
A:
Total Cost of C = Total Cost of B
350,000 + 25Q = 150,000 + 50Q
200,000 = 25Q
Q = 8,000
12. Use the table from Question 12 and the cost-profit-volume analysis to find the C Superior range
approximation.
A:
Total Cost of A = Total Cost of C
250,000 + 20Q = 350,000 + 25Q
5Q = 100,000
Q = 20,000
Use the following information to answer question 1-3.
A firm paid $2000 for rent, $300 for maintenance fee in January. They sold 2000 units in the month and
the cost per unit was $5. The price for the product is $10 per unit.
1. What is their total costs for the month?
a. $2300
b. $10000
c. $12300
d. $2000
e. none of the above
Answer: c. page 376
2. What is the firms total revenue for the month?
a. $20000
b. $10000
c. $2300
d. $2000
e. none of the above
Answer: a. page 378
3. What is the firms profit for the month ?
a. $20000
b. $10000
c. $12300
d. $7700
e. none of the above
Answer: d. page 378
4. If two alternatives yield comparable annual costs, management would be indifferent in choosing
between the two in terms of _.
a. total revenue
b. total costs
c. total profit
d. total variable costs
e. total fixed costs
Answer b. page 378
5. The transportation cost must be converted into cost per unit of in order to correspond to other variable
costs if raw materials are involved.
a. input
b. output
c. initial input
d. both a& b
e. none of the above