FOR
STORM WATER
QUALITY MANAGEMENT
AS
ADOPTED AUGUST 21, 2001
AMENDED SEPTEMBER 25, 2001
EFFECTIVE OCTOBER 1, 2001
AMENDED APRIL 13, 2004
AMENDEND MAY 1, 2011
HARRIS COUNTY
PUBLIC INFRASTRUCTURE DEPARTMENT
ENGINEERING DIVISION
ARTHUR L. STOREY, JR., PE
COUNTY ENGINEER
JACKIE L. FREEMAN, PE
ENGINEERING DIVISION DIRECTOR
In General
Authority
Area Covered by Regulations
Purpose
Construction of Regulations
Abrogation and Greater Restrictions
Remedies Not Exclusive
Access to Facilities
Severability
Definitions
Accessory Structure
Applicant
As-Built Certification
Best Management Practices (BMP)
Certificate of Compliance
Certificate of Non-Compliance
Certificate of Proper Operation
CFR
Clean Water Act
Commercial Use
County Engineer
Development
Discharge
Discharger
Dwelling Unit
EPA
Express Plan Review Sheet
Harris County Pollution Control
Hearing Examiner
Impervious Surface
Industrial Activity Certification
Industrial Manager
Multi-Family Residential
Municipal Separate Storm Sewer System (MS4)
New Development
Non-Structural Controls
Notice of Change (NOC)
Notice of Intent (NOI)
Notice of Termination (NOT)
NPDES
NPDES Permit
One-Stop Shop
Parcel
Permittee
Person
1
1
1
1
2
2
2
2
3
3
3
3
3
4
4
4
4
4
4
5
5
5
5
5
5
5
6
6
6
6
6
6
7
7
7
8
8
8
8
8
8
8
9
2.36
2.37
2.38
2.39
2.40
2.41
2.42
2.43
2.44
2.45
2.46
2.47
2.48
2.49
2.50
2.51
2.52
2.53
2.54
2.55
2.56
2.57
2.58
Pollutant(s)
Pollution
Property Owners Association
Representative Storm Event
Sewage
Significant Redevelopment
Single-Family Residential
Storm Water Discharges Associated with Construction Activity
Storm Water Discharges Associated with Industrial Activity
Storm Water Pollution Prevention Plan (SWPPP)
Storm Water Quality Engineer
Storm Water Quality Features
Storm Water Quality Management Plan (SWQMP)
Storm Water Quality Permit (SWQ Permit)
Structural Control
TCEQ
TPDES
TPDES Permit
Type 1 Facility
Type 2 Facility
Unincorporated Area
Waters of the United States
Wetlands
9
9
9
9
10
10
10
10
10
11
11
11
11
11
11
11
12
12
12
12
12
12
13
13
13
14
14
15
15
16
17
17
17
17
19
19
19
20
21
21
Section 5
5.01
5.02
5.03
Section 6
6.01
6.02
6.03
6.04
6.05
Section 7
7.01
Section 8
8.01
Section 9
9.01
9.02
22
23
23
25
25
26
26
26
27
27
28
28
In General
Administration by County Engineer
Compliance with Permit
Submission of NOI
Submission of NOT
Inspections
Inspection Procedures
Civil Enforcement
Civil Enforcement
Certificate of Non-Compliance
28
29
29
29
30
30
31
In General
Administration
Unpermitted Discharges Prohibited
Submission of NOI
Submission of NOC
Submission of NOT
Designation as a Type 1 or Type 2 Facility
Monitoring
Monitoring Required
No Exposure Certification
Reporting of Monitoring Results
Intermittent Discharges
iii
31
31
32
32
32
32
33
35
35
36
36
In General
Administration
Non-Storm Water Discharges Prohibited
Spills into the MS4
Appeals and Hearing Procedures, Variances, and Review by
Commissioners Court
Appeals
Hearing Before the Examiner
Filing of Examiners Decision
Review by Commissioners Court
Variances
Compliance Monitoring
Compliance Monitoring
Civil Enforcement
Civil Enforcement
APPENDIX A
iv
37
37
39
39
40
40
40
41
41
42
The
authority of Harris County to adopt these Regulations and the contents hereof is derived from
Texas Local Government Code, Section 422, as amended, and these Regulations may be
amended at any time by a majority of Commissioners Court as approved by the appropriate
federal authorities.
The Code Construction Act of Texas (Texas Government Code, Chapter 311) applies for
construing these rules unless an alternative instruction, definition, or application is
contained herein.
(b)
The word shall is mandatory and not discretionary as used in these Regulations.
(c)
These Regulations are to be liberally construed to give affect to its purpose and intent.
(d)
All terms used in the masculine shall refer to the feminine and vice versa.
Where these
Regulations and other legal requirements conflict or overlap, whichever imposes the more
stringent restrictions shall prevail.
Section 2 Definitions
The following words and terms, when used in these Regulations, shall have the following
meanings, unless the context clearly indicates otherwise.
Multi-family
Control District, and designed or used for collecting or conveying storm water and which is not
used for collecting or conveying sewage.
more of one single-family dwelling unit and one or more accessory structures; however, if the
use of the property excluded under the foregoing exception at any time changes to a commercial
use, including further subdividing of the property, the owner of the property shall comply with
all applicable requirements of these Regulations;
(2)
projects constructed within waters of the United States and not associated with
Notice of change or NOC means a written submission that is required by the TCEQ or EPA
from a permittee authorized under a general permit who has submitted a Notice of Intent on
which information must be corrected or changed.
10
11
12
could affect interstate or foreign commerce; all impoundments of waters otherwise defined as
waters of the United States under this definition; all tributaries of water identified in this
definition; all wetlands adjacent to the waters identified in this definition; and any other waters
within the federal definition of waters of the United States in Section 122.2 of Title 40 of the
Code of Federal Regulations; but not including any waste treatment systems, treatment ponds, or
lagoons designed to meet the requirements of the federal Clean Water Act.
Wetlands
13
If any portion of a project drains directly into a Municipal Separate Storm Sewer System owned
by Harris County or the Harris County Flood Control District, that project must have a SWQ
Permit issued by Harris County. The granting of a SWQ Permit does not imply that federal or
state storm water management criteria have been met and is in addition to any other development
permit required in Harris County.
Any project that has, prior to October 1, 2001, received a completed and
unexpired application for a preliminary or final subdivision plat on file with a
municipality provided the project is substantially underway by October 1, 2003;
(b)
Any project that has an initial construction plan review from Harris County by
October 1, 2001, or in the case of a project not receiving an initial construction
plan review, has submitted a valid development permit application to Harris
County by October 1, 2001, provided the project is substantially underway by
October 1, 2003;
(c)
For toll road projects, if there is a preliminary or approved master drainage plan
associated with the project prior to October 1, 2001; or
(d)
For Harris County or Harris County Flood Control District channel, basin,
roadway, or bridge projects, if the date of authorization or notice to proceed with
the preliminary engineering report from Harris County or the Harris County Flood
Control District to the consultant is prior to October 1, 2001; or
14
(e)
A copy of the application for an individual permit from the TCEQ or EPA for
Storm Water Discharges Associated with Industrial Activity at the facility;
(b)
A copy of the permit issued by the TCEQ or EPA for Storm Water Discharges
Associated with Industrial Activity at the facility;
(c)
A copy of the NOI for coverage under a general permit for Storm Water
Discharges Associated with Industrial Activity issued by the TCEQ, or the noexposure certification referenced in Part D, Section 2.02;
(d)
(e)
A statement of commitment to file a NOI for coverage under a general permit for
Storm Water Discharges Associated with Industrial Activity issued by the TCEQ.
15
(b)
A fee in the amount of $300.00 paid in cash, cashiers check, personal check, or
money order. Checks shall be made out to Harris County Treasurer;
(c)
If a bond is required by the Regulations of Harris County, Texas for the Approval
and Acceptance of Infrastructure, the amount of the bond shall be increased by an
amount equal to the cost of constructing the Storm Water Quality Features. A
copy of the bond shall be submitted with the application;
(d)
(e)
water control and improvement district, a fresh water supply district, or any other
utility or water district created pursuant to state law;
(f)
2.
3.
The County Engineer may require the submission of additional information, drawings,
specifications or documents to determine whether a SWQ Permit shall be issued from the
information submitted.
SECTION 1.07 DETERMINATION OF PERMIT ELIGIBILITY
After the application is filed, the County Engineer shall:
(a)
Issue the SWQ Permit if he is satisfied that that applicant has met all the
requirements of Part B, Section 1.06; or
(b)
Return the application and supporting data to the applicant if any provision of
these Regulations is not met. The County Engineer shall notify the applicant in
writing of items required for further review of the plans.
16
(b)
(c)
(d)
A renewal fee in the amount of $150.00, together with any outstanding inspection
or other fees, paid in cash, cashiers check, personal check, or money order.
Checks shall be made payable to the Harris County Treasurer.
All outstanding inspection or other fees owed Harris County shall be paid prior to renewal of the
SWQ Permit. Harris County shall not renew a SWQ Permit if such fees are outstanding.
SECTION 1.09 TERM OF PERMITS
Development activity under the SWQ Permit must start within 180 days from the date of
issuance. Failure to initiate development activity shall result in the SWQ Permit becoming
invalid. Upon written request, the County Engineer may grant two (2) six-month extensions.
17
(a)
The SWQMP shall be prepared in accordance with the Storm Water Management
Handbook for Construction Activities and the Storm Water Quality Management
Guidance Manual or the Storm Water Quality Guidance Document for New
Development/Redevelopment Projects. If applicable to the BMP selected, the
SWQMP shall incorporate features from the Minimum Design Criteria for
Implementation of Certain Best Management Practices for Storm Water Runoff
Treatment Options as set forth in Appendix A. Alternate techniques and methods
not mentioned in the Storm Water Quality Management Guidance Manual, Storm
Water Quality Guidance Document for New Development/Redevelopment
Projects, Storm Water Management Handbook for Construction Activities, or the
Minimum Design Criteria for Implementation of Certain Best Management
Practices for Storm Water Runoff Treatment Options shall be reviewed on a caseby-case basis.
(b)
(c)
Any preliminary drawings or plans altered or marked by the Storm Water Quality
Engineer shall be resubmitted along with the corrected original drawings for
signature. If further corrections are required, the package shall be returned to the
applicant for resubmittal upon completion of revisions.
(d)
Drawings shall meet the same standards as far as size, line weight, etc., as
outlined in the Rules, Regulations and Requirements Relating to the Approval and
Acceptance of Improvements in Subdivisions or Resubdivisions and/or the Harris
County Flood Control Criteria Manual.
18
(e)
The Storm Water Quality Feature shall remain with the owner unless there is a
transfer pursuant to Part B, Section 4.04.
(b)
If Harris County or the Harris County Flood Control District accepts the Storm
Water Quality Features for maintenance, the permit holders requirements for the
SWQ Permit and permit renewal with respect to that feature as set forth in Part B,
Sections 1.02 and 1.08 terminate. All other permit requirements continue to
apply.
19
(b)
Remove all soil deposits resulting from runoff or from vehicular construction traffic
and/or from site operations from the road adjacent roadside ditch on a daily or more
frequent basis, or as specified in the Storm Water Quality Management Plan;
(c)
Post the SWQ Permit on the job site in a place visible from the nearest road or street
during the construction phase; and
(d)
Allow the County Engineer to inspect the work pursuant to a permit. The County
Engineer may make as many scheduled or unscheduled inspections as he may deem
necessary to enforce these Regulations and shall have access to any building or
premise at any reasonable time. If no specific inspection standards are set by any
part of these Regulations, the inspection shall only be to determine that the drawings
and specifications furnished with the SWQ Permit application are met.
When the Storm Water Quality Features are complete and ready for use, a
professional engineer licensed in the state of Texas must inspect and certify that the
Storm Water Quality Features were completed in accordance with the approved
plans. The permittee shall then submit an As-Built Certification form supplied by
the County Engineer.
professional engineer licensed in the State of Texas indicating that the Storm Water
Quality Features were completed in accordance with the approved plans.
20
(b)
Once the As-Built Certification and any certification authorized by the SWQMP are
submitted to the County Engineer's office, the County Engineer will issue or deny a
Certificate of Compliance.
applicable certifications were not provided, or the provisions of Part B, Section 1.06
of these regulations were not followed, then enforcement procedures such as SWQ
Permit revocation or civil enforcement may commence. The County Engineer may
deny a Certificate of Compliance if he determines that the Storm Water Quality
Features were not constructed in accordance with approved plans.
(c)
Should the County Engineer have to make additional inspections or conduct survey
work due to non-compliance with these Regulations, additional fees may be assessed
as outlined in Part B, Section 8.
The obligation to comply with the SWQ Permit requirements shall be recorded by
the permittee in the Real Property Records of Harris County, Texas for the
affected parcel and will apply to all subsequent owners of all or a portion of the
parcel. The recordation shall note that no structural or non-structural controls on,
or for the parcel, may be changed from the plans and technical specifications in
the SWQ Permit for the parcel. If there are substantial changes in the structural or
non-structural controls then the procedures as outlined in Part B, Section 1.06
shall be followed. For Storm Water Quality Features that are not accepted by the
Harris County Flood Control District for maintenance, the recordation shall
reflect that the features are private and must be properly maintained by the owner
in accordance with the SWQMP.
(b)
For new development that includes the platting of a reserve tract, a notation shall
be placed on the subdivision plat that a SWQ Permit must be obtained before the
21
issuance of any development permit for a structure on all or a part of the reserve
tract.
(c)
(d)
The applicant, or if the SWQ Permit has already been issued, the permittee, shall
pay all recording fees required by the county clerks office.
The SWQ Permit may be held by an entity or person other than the landowner if
the entity or person and the landowner enter into a binding legal agreement that
meets the requirements of this section. The entity or person must agree to comply
with the requirements of these Regulations and with the terms and conditions of
the SWQ Permit, including adherence to the operation and maintenance
requirements specified in Part B, Section 3.
(b)
The third-party agreement shall grant fee simple title to all structural controls to
the entity or person, provide an easement if necessary to allow access by the
entity or person across the landowners property to maintain structural controls or
to implement non-structural controls, and if necessary, to allow storm water from
the landowners property to drain across any adjacent property to a designated
structural control. The legal agreement shall also provide that in the event of its
termination for any reason, including either by choice or by default, the obligation
to comply with the provisions of this section shall revert to the landowner.
22
A SWQ Permit is suspended when the County Engineer, or his inspector, advises the
permittee or some responsible person on the job that the SWQ Permit is suspended
and posts a written suspension notice over the SWQ Permit at the jobsite.
(b)
The following actions by the permittee are grounds for suspension of a SWQ Permit:
1.
2.
Deviating from drawings and specifications filed with the County Engineer
and refusing to make corrections required by the County Engineer; or
3.
(c)
When the suspension notice is posted, the permittee must immediately suspend all
work on the job except that work necessary to abate the suspension. The suspension
will be abated when the corrective work is performed and has passed inspection.
The abatement will be evidenced by the removal of the suspension notice by the
County Engineer or his inspector and the notation on the Permit Notice by the
County Engineer or his inspector that the work has now been re-inspected and
passed. The suspension notice may not be removed by any person other than the
County Engineer or his inspector and removal by any other person will be
ineffective.
Material deviation from the drawings and specifications on file with the County
Engineer, including the SWPPP, or a pattern of consistent deviation from such
23
(c)
(d)
Proceeding with work while a permit is suspended, other than such work necessary
to abate a suspension;
(e)
(f)
(g)
(h)
Consistent violation of the NPDES or TPDES permit for the project during
construction, including failure to correct deficiencies noted during constructionphase inspections.
The County Engineer shall file a complaint stating the reason for SWQ Permit
revocation with the Hearing Examiner.
1.
The Examiner will set a hearing as soon as practicable, but within thirty (30)
days.
2.
The Examiner will deliver the original Complaint and Hearing Notice to the
Clerk of Commissioners Court to be filed, give one copy to the County
Engineer, and designate an appropriate person as Serving Agent and give
two copies to him or her.
3.
The Serving Agent will take the two copies of the Complaint and Hearing
Notice to the site where he will:
a.
24
b.
c.
If no person can be found on the site, the Serving Agent will post the
Complaint and Hearing Notice over the SWQ Permit and/or Notice
of Suspension posted at the job. Upon posting of the Complaint and
Hearing Notice the SWQ Permit shall be suspended.
4.
The Serving Agent will fill in the return on the remaining copy, noting on it
the date, time and manner in which he perfected service, and sign the return
and return the remaining copy to the Hearing Examiner.
5.
At the time set for hearing, if the return copy of the Complaint has been
returned to the Hearing Examiner by the serving agent, and reflects that
service has been perfected, the Examiner may proceed with the hearing.
6.
(b)
The Hearing Examiner will set a time for a hearing, which will be scheduled as soon
as practicable but within thirty (30) days of the receipt of the written complaint or
25
request, and shall prepare a Notice of Public Hearing naming the time and date of
the Hearing. Copies shall be distributed as follows:
1.
The original copy and the Certificate to Commissioners Court will be filed
with the Clerk of Commissioners Court and the Clerk will prepare a file for
the Hearing Notice.
2.
The Examiner will set up his own working or hearing file, in which he will
keep one copy.
3.
4.
The Examiner will deliver one copy to the County Engineer. The Hearing
will be conducted as provided in Part B, Section 6.02.
(c)
Appeal of a suspension will not abate the suspension pending the decision of the
Hearing Examiner.
26
(b)
It has been determined that failure to grant the variance would result in an
exceptional hardship to the applicant; and
(c)
The granting of a variance will not result in a pollutant discharge, additional threats
to public safety, extraordinary public expense, or create nuisances, cause fraud or
victimization of the public.
Economic hardship shall not constitute the sole basis for granting a variance. A hearing before
Commissioners Court regarding variances shall be requested in the manner provided in Part B,
Section 6.04 of these Regulations. If a variance is granted a SWQ Permit shall be issued and the
permittee shall conform to all applicable provisions of these Regulations except the section or
sections for which a variance is granted.
27
Department and may be amended or supplanted from time to time by the County Engineer.
Section 8 Fees
SECTION 8.01 FEES
Fees for SWQ Permits and inspections are to be set by Commissioners Court. Fees shall be paid by
cash, cashiers check, money order, or personal check. Should the check be returned for insufficient
funds the SWQ Permit issued becomes invalid. Fees shall be paid at the time the SWQ Permit is
delivered to the permittee unless the County Auditor has approved other arrangements. The
following fee schedule applies to actions under these Regulations:
INITIAL PERMIT
$300.00
$150.00
INSPECTION/REINSPECTION FEE
$ 50.00
CERTIFICATE OF COMPLIANCE
$ 20.00
CERTIFICATE OF NON-COMPLIANCE
$100.00
$150.00
TRANSFER OF PERMIT
$300.00
28
County through the County Attorneys Office from seeking enforcement of state environmental
laws pursuant to the Texas Water Code.
Section 1 In General
SECTION 1.01 ADMINISTRATION BY COUNTY ENGINEER
The County Engineer or his designee is responsible for the administration of these Regulations
dealing with the Storm Water Discharges Associated with Construction Activity, and the
issuance of SWQ Permits required by these Regulations, and enforcement of these Regulations
and maintaining proper records.
It is a violation of these
Regulations to operate a facility that has Storm Water Discharges Associated with Construction
Activity without an NPDES or TPDES permit for stormwater discharges or in violation of the
NPDES or TPDES permit, the SWQ Permit covering the facility, or the SWPPP.
29
(b)
a certification that the NOI has been submitted to the EPA or the TCEQ as
applicable; and
(c)
The documents required by this section must be submitted to the Storm Water Quality Engineer
at the same time the operator submits the NOI to the EPA or TCEQ as applicable.
Section 2 Inspections
SECTION 2.01 INSPECTION PROCEDURES
Harris County will make periodic unannounced inspections of the site during construction to
insure compliance with the Storm Water Pollution Prevention Plan.
provisions of the SWPPP will be checked on every visit, including the following items:
(a)
(b)
(c)
(d)
(e)
(f)
(g)
30
(h)
Proper storage and end of workday containment of trash, construction debris, and
work materials.
A Notice of Inspection will be issued to the responsible party. If deficiencies are noted, they
must be corrected within 72 hours of receiving a notice. Upon reinspection, if the deficiencies
have not been corrected from the first inspection or additional deficiencies are identified, a
$50.00 reinspection fee will be assessed in accordance with the fee schedule set forth in Part B,
Section 8 of these Regulations. This fee will be assessed on every reinspection conducted where
the previous deficiencies were not addressed or new deficiencies are noted and is in addition to
any civil penalty that may be imposed under Part C, Section 3.01 of these Regulations. An
inspection by Harris County does not insure compliance with any federal or state storm water
requirements.
31
32
If an NOT is submitted because the operator of the facility has changed, a copy of the NOI for
the new operator shall be submitted to the Industrial Manager with the NOT.
The copy of the NOT shall be submitted no later than ten (10) calendar days after either all
Storm Water Discharges Associated with Industrial Activity are eliminated at the facility or the
operator of the facility changes.
Upon designation by Harris County as a Type 1 or Type 2 facility, the Industrial Manager shall
send written notification by certified mail, return receipt requested, to any such facility informing
the facility of the designation. The facility may then appeal the designation in the manner set
forth in Part E, Section 2.01 of these Regulations.
Section 2 Monitoring
SECTION 2.01 MONITORING REQUIRED
Operators of facilities that have storm water discharges shall comply with the following
monitoring requirements:
33
(a)
All Type 1 and Type 2 facilities required to have authorization to discharge storm water
under an NPDES or TPDES permit must undertake all monitoring required by that
permit.
Upon request, the operator of the facility shall submit the results of this
operators must follow EPA standards for monitoring as set forth in 40 CFR Part 136 as
amended, and 30 TAC 319, as amended.
(b)
If a Type 1 facility is not required to have authorization to discharge storm water under
an NPDES or TPDES permit, the facility must on an annual basis analytically monitor
storm water discharges from its facility during a representative storm event on an outfallby-outfall basis for the following parameters:
1.
Any pollutants limited in an existing NPDES or TPDES permit for the facility;
2.
3.
4.
pH;
5.
6.
7.
Total phosphorous;
8.
9.
10.
11.
12.
Temperature;
13.
Any pollutants for which effluent limitations are imposed in the Countys storm
water permit for its MS4; and
14.
Any other pollutant that Harris County has determined the facility is discharging
which contributes a substantial pollutant loading to the MS4 after written
notification by the County sent by certified mail, return receipt requested,
informing the facility that the pollutant must be analyzed.
All sampling conducted by a facility shall occur during a representative storm event and
shall be completed within the first 30 minutes of discharge using a grab sample. If it is
not practicable to complete the sampling within the first 30 minutes, sampling must be
34
subsection, Harris County has established thresholds which are set forth in Appendix B.
(c)
If a Type 2 facility is not required to have authorization to discharge storm water under
an NPDES or TPDES permit, the facility must analytically monitor storm water
discharges from its facility during a representative storm event on an outfall-by-outfall
basis at a frequency to be determined by Harris County for any pollutants Harris County
determines the facility may be contributing to the MS4. Harris County will inform each
facility of the parameter or parameters for which it must analyze and the applicable
threshold for each parameter. Harris County will send written notification of its decision
by certified mail, return receipt requested. All sampling conducted by a facility shall
occur during a representative storm event and shall be completed within the first 30
minutes of discharge using a grab sample.
sampling within the first 30 minutes, sampling must be completed with the first hour of
discharge. Upon request, the operator of the facility shall submit the results of any
monitoring under this section to the Industrial Manager.
A facility with Storm Water Discharges Associated with Industrial Activities that qualifies for a
no exposure certification must obtain a permit to discharge as required in Part D, Section 1.02
before changing operating and management procedures that would result in exposure of storm
water to industrial activities. A Type 1 or 2 facility that qualifies for no exposure certification
35
must notify the Industrial Manager in writing before changing operating or management
procedures that would result in exposure of storm water to industrial activities.
It is a violation of these Regulations for a facility that has submitted the conditional no-exposure
certification to fail to meet the no-exposure certification standards established by the TCEQ or
Industrial Manager, as applicable.
If the results of any monitoring required under Part D, Section 2.01 above, exceed the
thresholds established by Harris County pursuant to Part D, Section 2.01 (b or c), or a
benchmark or effluent limitation in an NPDES or TPDES storm water permit for a
facility, the owner and operator of the facility shall submit the results in writing to Harris
County Pollution Control within thirty (30) days after conducting the monitoring.
(b)
If the results of any monitoring required by this section exceed the thresholds established
by Harris County or a benchmark or effluent limitation in an NPDES or TPDES storm
water permit, the owner or operator of the facility shall investigate the cause of the
exceedance and take appropriate corrective action to eliminate the exceedance as soon as
possible but no later than 30 days from when the exceedance is detected. The operator
shall notify Harris County Pollution Control of the corrective measures that will be taken
and a schedule for implementation.
(c)
36
No person shall discharge or cause to be discharged into the Municipal Separate Storm
Sewer System (MS4) anything that is not composed entirely of storm water except the
following:
37
1.
2.
A discharge or flow resulting from fire fighting by the fire department if that
discharge is not reasonably expected to be a significant source of pollutants to the
MS4;
3.
4.
Water line flushing, provided the water contains less than or equal to 5.0 mg/l
total chlorine when entering the MS4;
5.
Landscape irrigation;
6.
7.
8.
9.
10.
11.
Foundation drains;
12.
Discharges from potable water sources, provided the water contains less than or
equal to 5.0 mg/l total chlorine when entering the MS4;
13.
Irrigation water;
14.
15.
16.
Springs;
17.
Lawn watering provided the water does not contain significant amounts of
fertilizers, pesticides, herbicides, or other undesirable lawn care products;
18.
Footing drains;
19.
20.
Non-commercial car washing (until such time as the TCEQ issues a general
permit for such discharges);
38
21.
Pavement wash waters provided cleaning chemicals are not used or other
significant contaminants are not present (until such time as the TCEQ issues a
general permit for such discharges);
22.
Swimming pool discharges provided the water contains less than or equal to 5.0
mg/l total chlorine when entering the MS4;
23.
Materials resulting from a spill where the discharge is necessary to prevent loss of
life, personal injury or severe property damage provided that the party responsible
for the spill takes all reasonable steps to minimize or prevent any adverse effects
to human health or the environment.
24.
25.
Traffic control device wash water provided cleaning chemicals or detergents are
not used.
(b)
Harris County may determine, on a case-by-case basis, that any of the above listed
discharges in subsection (a) are contributing a substantial pollutant loading to the MS4,
and may prohibit such discharges according to the following:
1.
Harris County will provide written notice that the discharge is prohibited;
2.
The person affected by this may appeal this decision according to Part E, Section
2 and obtain a variance according to Part E, Section 2.05. To appeal, the person
must inform Harris County of its decision to appeal within 30 days after the
receipt of notice from Harris County.
(c)
It is a violation of these Regulations if a person discharges any storm water that contains
a pollutant or any substance which causes, continues to cause, or will cause pollution.
39
(b)
The Hearing Examiner will set a time for a hearing, which will be scheduled as soon
as practicable but within forty-five (45) days of the receipt of the written complaint
or request, and shall prepare a Notice of Public Hearing naming the time and date of
the Hearing. Copies shall be distributed as follows:
1.
The original copy and the Certificate to Commissioners Court will be filed
with the Clerk of Commissioners Court and the Clerk will prepare a file for
the Hearing Notice.
2.
The Examiner will set up his own working or hearing file, in which he will
keep one copy.
3.
4.
The Examiner will deliver one copy to the Industrial Manager. The Hearing
will be conducted as provided in Part E, Section 2.02.
(c)
40
evidence, reserving to himself the power to exclude testimony or exhibits he does not consider
relevant. The Hearing Examiner will maintain an accurate record of the evidence adduced at the
Hearing.
Pollution Control files the objection, notice that the matter is on the agenda will be sent to the
appellant by mail. Commissioners Court will review the matter. The Commissioners Court may
either affirm or reverse the decision of the Hearing Examiner. The determination that the
discharge contributes a substantial pollutant loading to the MS4 will not be abated pending the
review of Commissioners Court.
41
(b)
It has been determined that failure to grant the variance would result in an
exceptional hardship to the applicant; and
(c)
The granting of a variance will not result in a substantial pollutant loading into the
MS4, additional threats to public safety, extraordinary public expense, or create
nuisances, cause fraud or victimization of the public.
Economic hardship shall not constitute the sole basis for granting a variance. A hearing before
Commissioners Court regarding variances shall be requested in the manner provided in Part E,
Section 2.04 of these Regulations. If a variance is granted the applicant may then discharge and
shall conform to all applicable provisions of these Regulations except the section or sections for
which a variance is granted.
Harris County shall have the right to install at a facility that discharges storm water to the
MS4, or to require the installation of, such devices as are necessary to conduct sampling
or metering of the facilitys operations.
(b)
Harris County may require any facility that it determines has discharged or is discharging
a pollutant or any substance which causes, continues to cause, or will cause pollution to
conduct specified sampling, testing, analysis and other monitoring of its storm water
discharges. Harris County may specify the frequency and parameters of any required
monitoring.
(c)
Harris County may require any facility that it determines has discharged or is discharging
a pollutant or any substance that causes, continues to cause, or will cause pollution to
install monitoring equipment as necessary at the facilitys expense. The facility, at its
own expense, shall at all times maintain the sampling and monitoring equipment in a safe
and proper operating condition. Each device used to measure storm water flow and
quality must be calibrated to ensure accuracy.
42
(d)
Any temporary or permanent obstruction to safe and easy access to a facility that is to be
inspected or sampled must be promptly removed by the facility at the written or verbal
request of the Industrial Manager and may not be replaced. The cost of clearing the
access to the facility must be borne by the facility.
43
APPENDIX A
2001 Edition
Table of Contents
Introduction
Background
Purpose
Organization
1
1
1
Grass Swales
Purpose and Definitions
Applications and Limitations
Design Criteria
Sizing Procedures
Maintenance
Sample Calculation for Sizing Grass Swales
2
2
2
3
4
8
10
10
10
11
13
Wet Pond
Purpose and Definitions
Applications and Limitations
Design Criteria
Permanent Pool
Hydraulic Residence Time
Pond Geometry
Permanent Pool Depth
Permanent Pool Surface Area
Sediment Forebay
Basin Configuration
Safety Bench
Vegetative Bench
Sizing Procedure
Maintenance
Sample Calculation for Sizing Wet Ponds
14
14
14
15
15
15
15
16
16
16
16
16
17
18
24
26
26
26
26
27
31
2001 Edition
Page i
32
32
32
33
Bibliography
36
2001 Edition
Page ii
List of Tables
Table 1.1: Sizing Criteria for Grass Swales
11
11
19
28
35
2001 Edition
Page iii
List of Figures
Figure 1: Grass Swale Sample Layout
12
20
21
22
23
29
30
2001 Edition
Page iv
INTRODUCTION
Background
Purpose
Organization
2001 Edition
Grass Swales
Vegetated Filter Strips
Wet Pond
Dry Detention Basins
Constructed Wetlands for Storm Water Treatment
Page 1
Grass Swales
BMP HC01.10
Purpose and
Definition
Application and
Limitations
Design Criteria
Grass Swales
Grass swales are defined as grass-lined, earthen channels, intended to
provide water quality enhancements. Grass swales provide effective
treatment only when they have low longitudinal slopes, with low
velocities and shallow depth of flow in the swale. The main pollutant
removal mechanisms in grass swales are filtration as the storm water
moves through the vegetation and bacterial decomposition. Careful
selections of grass species that allow more contact with
microorganisms living on the vegetation enhance pollutant removal of
grass swales.
Grass swales are applicable best management practices where the peak
flow rates and velocities are low. They are recommended as a standalone best management practices for areas draining 10 acres or less
and where pollutant concentration from the area is low. In
developments draining more than 10-acres, grass swales could be used
in combination with other best management practices.
The primary design factors that determine grass swales' effectiveness
are peak flow rate, depth of flow, and height of vegetation. The design
should promote pollutant removal rather than transporting flow with
greater possible hydraulic efficiency. Therefore, it is critical that
filtration, sedimentation, and other pollutant removal mechanisms are
emphasized.
Grass swales for water quality enhancements should be sized to treat
the flow generated by the design rainfall intensity from the drainage
area. Table 1.1 summarizes the design criteria for grass swales and
Figure 1 depicts a typical layout of a grass swale. Based on the
analysis of the 1-hour precipitation data of rainfall gauges in the Harris
County area, an intensity of 0.27-inch per hour was computed for 90
percent of the storms. Unless amended by additional rainfall data
analysis the design flow shall be calculated using an intensity of 0.27inch per hour. The rational formula (Q=CIA) shall be used to
determine the design flow rate. The flow velocity shall not exceed 1.5
feet per second. The longitudinal slope of the swale shall not exceed 2
percent and the minimum slope shall be 0.1 percent. Because of site
condition, if the desired slope could not be attained, check dams shall
be used as small drop structures to achieve the desired swale slope.
The check dams should be reinforced adequately for erosion
protection. The design of grass swales must encourage sheet flow of
storm water within the swale. If sheet flow conditions cannot be
achieved, a flow spreader (Figure 1-A) must be installed to uniformly
2001 Edition
Page 2
spread the flow across the width of the swale. The width of the swale
shall be sized to achieve a depth of flow, in the grass swale, of 3
inches or half the height of the grass, which ever is less. Table 1.2
summarizes recommended plant list for grass swales. A more
comprehensive plant list is provided in the Guidance Manuals
Appendix E. The design storm shall travel for at least 50 feet on the
grass swale for water quality treatment before its discharge into the
receiving stream or municipal storm sewer system. The length of
swale should be calculated based on a minimum hydraulic retention
time of 5 minutes. Discharges from the grass swale to a receiving
stream or roadside ditch shall not promote erosion, and erosion
prevention devices shall be constructed. The side slope of the swale
shall be 3H:1V or flatter.
Sizing Procedure
Determine the drainage area ( A ) of the site that drains into the
grass swales.
Determine the runoff coefficient ( C ) of the development. Runoff
coefficient values from the City of Houston Design Manual,
Chapter 9 - Storm Water Design Requirements, shall be used.
Based on the design storm, calculate design flow rate ( Qwq ) from
the drainage area using the rational formula.
Qwq = CIA
Where:
Qwq = Water quality design flow rate (ft3/sec)
C = Runoff coefficient (dimensionless)
I = Intensity (in/hr)
A = Area in (acres)
The Manning's roughness coefficient ( n ) for the swale shall be
0.24 for frequently mowed grass with a height of 6 inches.
Determine the longitudinal swale slope ( S ).
Determine the depth of flow ( d ). Depth of flow shall be 3 inches
or half the grass height, whichever is less.
Select a channel shape and a side slope ( z ).
Using Mannings equation, determine the bottom width ( b ) of the
swale by trial and error or use the approximate method given below.
Substitute the value of Qwq calculated above for Q in the
Manning's equation.
1.49
Q=
AR 2 / 3 S 1 / 2
n
Where:
Q = Water quality design flow rate ft3/sec
n = Manning's roughness coefficient (dimensionless)
A = Cross-sectional area (ft2)
R = Hydraulic radius (ft)
S = Longitudinal slope (dimensionless)
2001 Edition
Page 3
P = b + 2d z 2 + 1
T = b + 2 zd
By recognizing that top width (T) is much greater than depth of flow
(d) and the square of the side slope (z2) is much greater than 1 and
certain terms are negligible the approximate solution to determine the
bottom width of a trapezoidal shape is:
Qn
b
zd
1.49 d 1.67 S 0.5
Maintenance
2001 Edition
Page 4
Parking Lot
Commercial Structure
A
Grass Swale
(MS4)
PLAN
Design Water
NTS
SECTION A-A
NTS
LEGEND
Storm water quality treatment area
2001 Edition
Page 5
UNDISTURBED SOIL
SPREADER LIP
6"
MINIMUM
3:1 OR FLATTER
6' MINIMUM
LEVEL SPREADER 1
TYPICAL SECTION
NTS
3" MINIMUM
GRAVEL FLOW
SPREADER
PLACED ON A
STABILIZED
BASE
2' MINIMUM
LEVEL SPREADER 2
TYPICAL SECTION
NTS
2001 Edition
Page 6
Design Parameters
Longitudinal slope2
Maximum velocity
Manning coefficient
0.24
Bottom width
Minimum length
50 feet
3H:1V
If site conditions do not allow a 2% longitudinal slope, check dams must be used as drop
structures to achieve the desired slope. The check dams shall be designed with adequate
erosion protection.
2001 Edition
Page 7
Common Name
Expected Growth
Height
Method of
Planting1
Carex cherokeensis
Cherokee sedge2
4 to 6 inches
Plug
Eleocharis macrostachys
Spikerush
2 to 4 inches
Rhizome/plug
Eleocharis montevidensis
Sand spikerush
2 to 4 inches
Rhizome/plug
Juncus effusus
Soft rush
18 inches to 4 feet
Rhizome/plug
Juncus nodatus
Stout rush
2 to 4 feet
Rhizome/plug
Juncus interior
Inland rush
1 to 3 feet
Plug
Juncus torreyi
Torrey's rush
1 to 3 feet
Plug
Sisyrinchium (sp.)
Blue-eye grass
Up to 4 inches
Seed
Buchloe dactyloides
Buffalograss
2 to 4 inches
Seed
1
2
in
ft 3
* 5 acres = 0.61
hr
sec
Page 8
7. Select the shape of grass swale and side slope. For this
example a trapezoidal channel with a side slope of 4H:1V is
selected.
8. Select the longitudinal slope of the grass swale. For this
example a 1 percent slope is selected.
Basic hydraulic equations and cross sectional formula
A = bd + zd 2
A
R=
P
b
T = b + 2 zd
Qn
zd
1.49d 1.67 S 0.5
c=0.45
i=0.27 in/hr
d=3 inch (0.25 ft)
s=0.01
P = b + 2d z 2 + 1
A=5 acres
Q=0.61 ft3/sec
z=4
n=0.24
2001 Edition
Page 9
Filter Strips
BMP HC01.20
Purpose and
Definition
Application and
Limitations
Design Criteria
2001 Edition
The minimum width of the filter strip shall be 20 feet. For areas
that have a flow path of less than 60 feet, the minimum 20 feet
filter strip shall be provided.
For areas that have a flow path greater than 60 feet, an additional
5 feet of vegetation width shall be added for each additional 20
feet or fraction thereof. The maximum flow path of the paved
surface shall not be more than 150 feet. Table 1.3 summarizes
the required filter strip width for areas that have flow paths from
60 to 150 feet.
Page 10
Maintenance
Design Parameters
Longitudinal slope
Maximum velocity
1 inch maximum
NA
Manning coefficient
NA
Bottom width
Minimum length
NA
20 feet filter strip width for flow path up to 60 feet;
an additional 5 feet of filter strip width shall be
added for each additional 20 feet or fraction thereof
NA
Easement or restricted reserve dedication must contain wording that references the file
number (permit number) and the public entity that holds the plan. The plan must include
the maintenance schedule and frequency.
2001 Edition
Page 11
2001 Edition
Page 13
Wet Pond
BMP HC01.30
Purpose and
Definition
Application and
Limitations
Wet Pond
A wet pond is a constructed storm water treatment facility that retains
a permanent pool of water. The permanent pool area enhances storm
water runoff by gravitational settling, and plants in the fringe areas of
the wet pond remove nutrients. Bacterial action in the water helps in
chemical decomposition of complex substances into simpler forms.
Wet ponds are one of the most effective BMPs to enhance the quality
of storm water runoff. The wet pond permanent pool is designed to
hold and treat the design runoff for water quality enhancements
between storm events through quiescent settling and biological uptake.
In areas where soil permeability is high, water seepage from unlined
ponds could result in a dry pond, particularly in dry seasons. Lining
the bottom and the sides of the ponds with low permeable material
helps to reduce seepage and maintain the design permanent pool
volume. If wet ponds are used in areas with insufficient runoff, a
supplemental water source may be necessary.
Wet ponds may be a single purpose facility to provide water quality
treatment or they may serve multiple functions by providing flood
control storage or recreational facilities. Wet ponds can be designed to
have different storage stages, including the bottom stage permanent
pool, extended detention, and flood protection storage. When
combined with flood control function, the permanent pool is stacked
under the extended detention and flood protection storage with
potentially little loss of developable area.
Design Criteria
2001 Edition
Page 14
2001 Edition
Page 15
Page 16
2001 Edition
Page 17
Maintenance
2001 Edition
Page 18
Wet Pond1
Side slope
Vegetative shelf
Volume of pre-settling basin or forebay 3
Safety bench
Pond configurations (stages)
Distance between inlet and outlet
Outlet
Size to meet extended detention storage
1
Easement or restricted reserve dedication must contain wording that references the file
number (permit number) and the public entity that holds the plan. The plan must include the
maintenance schedule and frequency.
2
For wet ponds, the flowpath length from inlet to outlet should be measured at deepest and
the width at deepest can be found as (average top width + average bottom width)/2.
3
All inlets that convey storm water runoff shall enter first the forebay or pre-treatment basin.
2001 Edition
Page 19
10' Vegetative/Safety
Bench. Side Slope =
10H:1V
54' 55'
B
56'
57'
58'
59'
60'
61'
62'
63'
24" Reverse
Grade Pipe
64'
64'
63'
62'
61'
10' Vegetative/Safety
Bench. Side Slope =
10H:1V
59'
58'
57'
56'
55'
54'
Emergency
Spillway
Outlet Structure
B
PLAN VIEW
NTS
2001 Edition
Page 20
Forebay
Inlet Pipe
Permanent Pool
Water Surface
Elevation = 60'
Submerged
Forebay Inlet
Pipe
Permanent Pool
Water Surface
Elevation = 60'
8' Max
8' Max
Forebay
Forebay
SECTION A-A
NTS
SECTION A-A
(Alternative)
NTS
Top of Basin
Elevation
Varies.
1' Min.
8' Max
2' Min.
Water Quality Outlet
(Perforated PVC)
Forebay
Main Pool
Trash Rack
SECTION B-B
NTS
8' Max
Main Pool
10' Vegetative Safety
Bench. Side Slope =
10H:1V
Width Varies.
Side Slope = 3H:1V
SECTION C-C
NTS
2001 Edition
Page 21
1' MAX
PERMANENT
POOL
ELEVATION
1
3 (MIN)
1
1
10 (MIN)
100 (MAX)
3 (MIN)
VEGETATIVE BENCH
NTS
PERMANENT
POOL
ELEVATION
1
3 (MIN)
1
30 (MIN)
55 (MAX)
1
3 (MIN)
PERMANENT
POOL
ELEVATION
1
3 (MIN)
1
30 (MIN)
55 (MAX)
1' MAX
1
3 (MIN)
6' MIN
VEGETATIVE
BENCH
2001 Edition
Page 22
WATER QUALITY
VOLUME
ELEVATION
HOOD
OPEN PIPE
PERFORATED PIPE
WIRE MESH
TRASH RACK.
PERFORATED RISER
NTS
WIRE MESH TRASH RACK NOTES:
1. WIRE MESH MUST BE FINER THAN
PERFORATION DIAMETER OR SLOT WIDTH.
2. DISTANCE BETWEEN SIDES OF WIRE MESH
RACK MUST BE 3 TIMES THE PERFORATION
DIAMETER OR GREATER.
WATER QUALITY
VOLUME
ELEVATION
HOOD
SLOTTED PIPE
OPEN PIPE
WIRE MESH
TRASH RACK
SLOTTED RISER
NTS
2001 Edition
Page 23
Compute the forebay and the main pool volumes. For this
example the forebay volume is 20 percent of the permanent
pool volume and the remaining 80 percent is the main pool
volume. Forebay volume is 0.17 acre-feet and the main pool
volume is 0.66 acre-feet.
Forebay volume V f = V pp 0.20 0.83 0.20 = 0.17 acrefeet
Main pool Vm = V pp 0.80 0.83 0.80 = 0.66 acre-feet
2001 Edition
Page 24
Ap =
Vwq
120.3 t
Where: Ap = perforation area, square inches
V = volume cubic feet
t = draw down time in hours
H = maximum head in feet
ft 2
0.83 acre feet 43560
acre = 8.10 in 2
Ap =
120.3 24 hr 2.39 feet
The orifice area required is 8.10 in2 and ten one-inch diameter
holes could be used.
7
2001 Edition
Page 25
Application and
Limitations
Design Criteria
2001 Edition
Page 26
Maintenance
2001 Edition
Page 27
Design Parameters
Water quality treatment volume
NA
Side slope
NA
Length to width ratio of 3L:1W or more;
avoid dead storage areas and minimize shortcircuiting
Inlet shall be located 1 foot above the bottom
of the basin
3H:1V or flatter for earthen and no minimum
for concrete
24 to 48 hours3
NA
NA
Placed to maximize flow path and without
causing short-circuiting
Outlet
Design to meet hydraulic resident time
1
Easement or restricted reserve dedication must contain wording that references the file
number (permit number) and the public entity that holds the plan. The plan must include the
maintenance schedule and frequency.
2
All inlets and outlet that convey storm water runoff should be placed to maximize the flow
path inside the basin.
3
An average detention time of 24 hours is desired and may be achieved by using the full
basin drain time of at least 48 hours, with no more than 50 percent of the water quality
volume draining in the first 24 hours
2001 Edition
Page 28
Outlet
Structure
Emergency
Spillway
B
PLAN
NTS
2001 Edition
Page 29
9'
Side Slope
3H:1V
58'
Side Slope as Per
Appropiate Flood
Control
Requirements
SECTION A-A
Top of Basin
Elevation
Varies.
NTS
Inlet Pipe
Extended Detention Storage
Elevation = 62.39'
SECTION B-B
NTS
Page 30
The required orifice area would be 3.6 in2 and eighteen half-inch
diameter holes or equivalent could be used.
2001 Edition
Page 31
Application and
Limitations
Design Criteria
2001 Edition
Wetlands have shallower depths than wet ponds and generally requires
more surface area to treat an equal amount of storm water runoff from
the same size drainage area. Since water depths are shallower than
wet ponds, water loss by evaporation is an important concern. Careful
planning and water budget analysis is needed to be sure sufficient
water will be retained to sustain good wetland plant growth. The most
important pollutant removal processes in wetlands treatment systems
are the purely physical processes of sedimentation via reduced
velocities and filtration by wetland vegetation. Intimately linked with
the sediment biota, the wetland vegetation serves as a major storage
vector for carbon and nutrients, as an energy source for sediment
microbial metabolism, and as a gas exchange vector between
sediments and air. Thus, it is important to design for a substantial
native emergent vegetative component.
Wetlands design is site-specific but general design consideration
includes a sediment forebay, maximized hydraulic retention time,
elimination of dead zone and hydraulic short-circuiting, and selection
and establishment of native wetland vegetation. Table 1.7 summaries
Minimum Design Criteria - Runoff Treatment BMP
Page 32
the design parameter for storm water treatment wetland design. The
sediment forebay should be provided for initial sediment deposition
and reduction of storm water inflow velocities. It is very important to
drop the initial suspended sediment load and lower the inflow water
velocity to maintain system longevity and proper functionality of the
wetland system. Most of the design elements discussed in the wet
pond section are applicable to wetlands. The exceptions are depth and
distribution of aquatic vegetation. These two parameters are discussed
below.
The wetland area should consist of various depths and the following
distribution of depths in the wetland cell could be used as a guide.
Maintenance
2001 Edition
Page 33
2001 Edition
Page 34
Wetlands1
Surface-area-to-pool-depth relationship
Wetland Vegetation
Distance between inlet and outlet
Outlet
Size to meet extended detention storage
1
Easement or restricted reserve dedication must contain wording that references the file
number (permit number) and the public entity that holds the plan. The plan must include the
maintenance schedule and frequency.
2
All inlets that convey storm water runoff should enter first the forebay or pre-treatment
basin.
3
The flowpath length from inlet to outlet should be measured along the deepest section and
the width can be found as (average top width + average bottom width)/2.
2001 Edition
Page 35
Bibliography
City of Austin. 1998. City of Austin Environmental Criteria Manual. City of Austin
Department of Environmental Protection.
Environmental Protection Agency. September 1999. Storm Water Technology Fact Sheet:
Wet Detention Ponds. EPA 832-F-99-048.
Horner, R.R. 1988. Long-Term Effects of Urban Storm Water on Wetlands. In Design of
Urban Runoff Quality Controls. L.A. Roessner, B. Urbonas and M.B. Sonnen, eds.
American Society of Civil Engineers. New York, New York. P 451-465.
Joint Task Force. October 2000. Storm Water Quality Management Guidance Manual. City
of Houston, Harris County, and Harris County Flood Control District.
Maryland Department of the Environment. 1999. Maryland Storm Water Design Manual
Volumes 1 and 2. Maryland Department of the Environment.
Minnesota Pollution Control Agency. 1989. Protecting Water Quality in Urban Areas.
Minnesota Pollution Control Agency Division of Water Quality.
New York State Department of Environmental Conservation. 1992. Reducing the Impacts
of Storm Water Runoff from New Developments. New York State Department of
Environmental Conservation.
Schueler, T.R. 1987. Controlling Urban Runoff: A Practical Manual for Planning and
Designing Urban BMPs. Publication No. 87703. Metropolitan Washington Council of
Governments.
Schueler, T.R. 1992. Design of Storm Water Wetland Systems: Guidelines for Creating
Diverse and Effective Storm Water Wetlands in the Mid-Atlantic Region. Publication No.
92710. Metropolitan Washington Council of Governments. Washington, DC.
State of Florida. 1988. The Florida Development Manual: A Guide to Sound Land and
Water Management. Florida Department of Environmental Regulations, Tallahassee,
Florida.
Fred G. Lee. The Right BMPs? Stormwater. November/December 2000 Issue.
Washington State. August 2000 (Final Draft). Storm Water Management Manual for
Western Washington. Volume V Runoff Treatment BMPs. Washington State Department of
Ecology Water Quality Program.
WEF/ASCE. Urban Runoff Quality Management. 1998. Water and Environmental
Federation Manual of Practice No. 23 and American Society of Civil Engineers Manual and
Report on Engineering Practice No. 87.
2001 Edition
Page 36
Minimum
20
Maximum
Units
101
Acres
45
ft
150
ft
Value
ft/s
Acres
0.1%
10%
Flow Spreader
Sampling Location (Treated)
Type of Vegetation
Height of Vegetation
ft or inches
Collection System
Type of System
Design Frequency
Maximum Flow
Maximum Depth
Maintenance Considerations
Frequency of Owner/Operator Self Inspection
(per half inch rainfall event)
Frequency of Owner/Operator Self Inspection
every
1
weeks
12
months
In developments draining more than 10 acres, filter strips could be used as a supplement with
other best management practices.
The easement or plat dedication must contain wording which references the file number (or
permit number) and the public entity that holds the plan. The plan will include the accepted
maintenance plan.
2001 Edition
Grass Swales
Design Parameter
Minimum
Maximum
Value
101
Acres
50
ft
1.5
Design Depth
ft/s
Type of Grass
Roughness Coefficient
0.24
0.40
Longitudinal Slope
0.1
2%
Side Slope
Units
ft
3H:1V
Bottom Width
ft
Acres
Design Equation
Specify
Discharge Conditions
Specify
Specify
Conveyance of the less frequent storm such as a 2-year must be done in a different location or by a
different method. For properties larger than 10-acres, this system can be used in conjunction with one of
the detention ponds
Overflow Considerations
Overflow Elevation
Specify
Overflow Device
Specify
Design Equation
Specify
ft
Maintenance Considerations
Frequency of Owner/Operator Self Inspection
(per half inch rainfall event)
Frequency of Owner/Operator Self Inspection
Permit Renewal Frequency
every
1
weeks
12
months
In developments draining more than 10 acres, filter strips could be used as a supplement with
other best management practices.
The easement or plat dedication must contain wording which references the file number (or
permit number) and the public entity that holds the plan. The plan will include the accepted
maintenance plan.
2001 Edition
The easement or plat dedication must contain wording which references the file number (or
permit number) and the public entity that holds the plan. The plan will include the accepted
maintenance plan.
2001 Edition
Wet Ponds
Design Parameter
Minimum Maximum Value
Main Pool Depth at deepest point
4
6
Pond Area (includes berms, etc.)
Side Slope
3
Bench Elevation Above Permanent Water Surface
Elevation
Drainage Area Serviced
Easement or Restricted Reserve*
1
Length to Width Ratio
3
Forebay Volume %
20%
Design Volume
0.5
Side Slope
earthen
3
concrete
n/a
Design Water Surface Elevation
Outlet Type
Design Equation
Sampling Location (s) (Pre-treatment and
Treatment)
Vegetation Types
Vegetated Shelf Area
20%
Dual Use Design Considerations (Optional)
Design Storm (2-year, 100-year)
Detention Volume
Water Surface Elevation
Side Slope
Outlet Size and Type
Design Equation
Design Flow Rate
Overflow Considerations
Overflow Elevation
Overflow Path
Overflow Device
Design Equation
Floatable Trapping Mechanism
Maintenance Considerations
Settling Basin Clean Out Criteria (% volume lost
50%
in forebay)
Frequency of Owner/Operator Self Inspection (per every
half inch rainfall event)
Frequency of Owner/Operator Self Inspection
1
2
Permit Renewal Frequency
6
12
Reporting Frequency, Certification Frequency, Permit Renewal, Operation Permit
2001 Edition
Units
ft
ft2 or acres
ft H / ft V
ft
Acres
Acres
acre-ft
ft
ft H/ft V
ft
ft3/s
ft
weeks
months
APPENDIX B
75 mg/l
NH3
15 mg/l
Temp
100 degrees F
APPENDIX C
Submitted by:
Ed Emmett
County Judge
Jack Morman
Commissioner, Precinct 2
Steve Radack
Commissioner, Precinct 3
Jerry Eversole
Commissioner, Precinct 4
TABLE OF CONTENTS
PART I
Background
1 Introduction to Low Impact Development
1.1
1.1.1
1.1.2
1.1.3
PART II
2 Approval Process & LID-based Project Criteria
Acceptable LID Integrated Management Practices
2.2 Pre-Project Meeting Requirements
2.3 Detention and Hydrograph Requirements
2.1
Permeable Pavement
3.7 Tree Box Filter
3.8 Storm Water Planter Box
3.9 Green Roof
3.6
Roadways
Appendix A
Appendix B
Appendix C
Appendix D
Appendix E
Appendix F
Appendix G
PART I
Background
This document is intended to provide a set of interim guidelines for the use of Low Impact Development
(LID) and Green Infrastructure (GI) techniques. Over the last couple of years there has been an increased
public interest in the regulatory adoption of LID and GI techniques, as a potential land development option
to address drainage and storm water quality requirements. The Environmental Protection Agency has also
required the adoption of such region-appropriate practices by November 1, 2011, as a part of the Harris
County Public Infrastructure Department Architecture & Engineering Division (HCPID-AED) and Harris
County Flood Control District (HCFCD) Storm Water Management Programs. This requirement is
specifically located in the Bacteria Reduction Plan found in Section 12 of the Storm Water Management
Program." (HCFCD, 2010 and HCPID-AED, 2010).
It is anticipated that these criteria will be in an interim form for at least 3 years after the date of adoption.
During this interim period, design techniques will be reviewed and monitored for implementation success
to determine how these interim criteria should be modified in the future. If at any time during this interim
period HCPID-AED & HCFCD determine that a modification to the criteria is necessary, updates to this
document will be issued. When such updates are issued they will affect all developments that have not yet
had a pre-project meeting (See Section 2.2).
These criteria do not require a conventional development project to follow these LID requirements, nor
do they intend for every project to be a LID project. However, these requirements shall apply to any new
development or re-development project choosing to incorporate LID practices for the purpose of satisfying
current HCPID-AED and/or HCFCD requirements for detention, infrastructure, stormwater quality, or other
applicable requirements. Furthermore, it is intended that these guidelines should assist in the facilitation
by Texas Commission on Environmental Quality (TCEQ) of Municipal Utility District (MUD)
reimbursements for LID and GI elements.
Illustrations have been included in this document to aid in the understanding of the criteria. These
illustrations are intended to provide visual reference to the concepts addressed in the criteria; however,
they are not construction details and should not be used as such. The Integrated Management Practices
used under this document are to be designed to meet the criteria as applicable to the development
intended.
Final approval of the use of any LID techniques shall not include a maintenance responsibility for HCPIDAED, HCFCD, or any Harris County Precinct, unless specifically agreed to otherwise.
Low Impact Development (LID) is a comprehensive land planning and engineering design approach with
the goal of maintaining, as the minimum, the pre-development hydrologic regime in a watershed without
solely using conventional development and detention basin techniques to satisfy drainage and flood
mitigation requirements.
The term Green Infrastructure (GI) is synonymous with LID. Both terms describe an approach to
infrastructure management that is cost-effective, sustainable, and environmentally friendly. GI, like LID
management approaches and technologies, infiltrate, evapotranspire, capture and/or reuse storm water to
maintain or restore natural hydrology. Integrated Management Practices (IMPs) are LID based practices
that reduce stormwater runoff volume and pollutant loading from developed sites. IMPs function by
slowing runoff, promoting infiltration, and utilizing evapotranspiration through plantings.
Principles of LID
Conserve natural resources that provide valuable natural functions
associated with controlling and filtering storm water.
Minimize & disconnect impervious surfaces.
Direct runoff to natural and landscaped areas conducive to infiltration.
Use distributed small-scale controls or Integrated Management
Practices (IMPs) to mimic the sites pre-project hydrology.
Storm water education leads to pollution prevention.
1.1
Hydrologic goals and objectives should be incorporated into the site planning process as early as possible.
The goal of LID site planning is to allow for full development of the property while maintaining predevelopment hydrologic functions as opposed to solely comparing outfall rates. A few fundamental
concepts that define the essence of low impact development technology must be integrated into the site
planning process to achieve a successful and workable plan. These concepts are so simple that they tend to
be overlooked, but their importance cannot be overemphasized. The steps to achieve LID include first
minimizing the hydrologic impacts created by the site development through site design, and then providing
controls to mitigate or restore the unavoidable disturbances to the hydrologic regime. These fundamental
concepts are defined in the following sections:
Integrating Hydrology
Identify sensitive areas that affect hydrology
Define the Development Envelope
Minimize total impervious area
Disconnect Impervious surfaces
Control and breakup impervious areas with IMPs
LID offers an innovative alternative approach to urban storm water management that uniformly or
strategically integrates storm water controls into multifunctional landscape features where runoff can be
micromanaged and controlled at the sources. LID may allow a variety of urban landscapes or infrastructure
feature (roof, streets, parking, sidewalks, collection/conveyance systems and green space) to be designed
to be multifunctional, incorporating detention, retention, filtration, or runoff use, where feasible.
PART II
2
A LID-based project is one which takes a comprehensive land planning and engineering design approach
with the goal of maintaining, as the minimum, the pre-development hydrologic regime in a watershed
without solely using conventional development and detention basin techniques. These projects will
typically be characterized by the use of distributed IMPs, as described in Appendix A, rather than
centralized pipe and detention basin approaches to meet these goals.
The LID analysis and design approach focuses on the following hydrologic analysis and design components:
Time of Concentration (Tc): Maintaining the pre-development Tc by minimizing the increase of
the peak runoff rate after development by lengthening and flattening flow paths and reducing the
length of the highly efficient conveyance systems.
Retention: The storage of stormwater for an indefinite period of time. A retention feature does not
have an outlet structure, but relies on infiltration, often supplemented by amended soils to improve
the infiltration characteristics.
Detention: The temporary storage of stormwater. A detention feature temporarily detains
stormwater with an outlet that restricts the outflow to a pre-project development rate. For LID
projects, the goal is to drain within 72 hours, unless pre-existing conditions are shown to take
longer.
Change in Impervious Cover: Minimizing changes in impervious areas and preserving more
natural areas to reduce the storage requirements to maintain the predevelopment runoff volume.
Disconnection: Distributing concentrated flow through landscape in a manner intended to
promote slower velocities and infiltration.
2.1
Table 1 below describes which LID IMPs will be acceptable for use in satisfying storm water quality and
detention requirements.
Table 1. Acceptable LID IMPs for Storm Water Management and Mitigation Credit
Storm Water
Quality
Detention
Time of Concentration
Bioretention &
Engineered Soil
Vegetated Swale
Permeable Pavement
X* (1)
IMP
Green Roof
Disconnection
Soil Amendment
Rainwater Harvesting
X* (2)
X* (3)
*(1) Voids within the permeable pavement itself can not be counted for detention, see section 3.6.1.
*(2) Acceptable for Storm Water Quality if re-used for irrigation or other non-potable uses.
*(3) Various LID practices will be considered, so long as sufficient volume reductions and the design approach are
proven. Applies only to commercial sites and non-single family residential structures in limited circumstances, see
section 3.4.1.
2.2
Any person proposing to utilize LID IMPs shall have a pre-project meeting with HCPID-AED & HCFCD. The
Harris County Permit Office is responsible for coordination of the meeting with HCPID-AED and HCFCD personnel.
Table 2. Pre-Project Review Meetings
Subject
Detention
Criteria
Monitoring
Area Eligible for
Low Impact
Development
Peak Flow
Hydrologic
Calculations and
Acceptable
Modeling
Techniques
Location
Relative to
Flood Risk Zone
Eligible LID
Practices
HCFCD Requirements
HCPID-AED Requirements
HCPID-AED and/or HCFCD may be allowed to monitor, test, and/or inspect any LID IMP, and
may choose to coordinate with the owner for the design elements the agencies might need for
future monitoring by the agencies.
The portion of the drainage area within the project limits covered by an agreement for
maintenance, repair, and rehabilitation of the facilities. LID Practices must be pre-approved at
the mandatory pre-project meeting.
The LID design must show that the post-project condition has an equal or lower peak flow than
the pre-project condition peak flow.
TBD at the required pre-project meeting. Techniques will be driven by project size (see section
2.3.1), although multiple methods may be accepted.
Developments in a regulatory floodplain will abide by current floodplain regulations.
Various LID practices will be considered, so long as sufficient volume reductions and the
design approach are proven. In general, LID practices which can be shown to result in the
following benefits will be considered:
Site Acreage
HCFCD Requirements*
Site 10 Acres
HCPID-AED Requirements
Same as HCFCD
Same as HCFCD
* HCFCD Requirements listed in this document are supplemental to the criteria and procedures in the HCFCD 2010
Policy, Criteria, and Procedures Manual, they do not replace them.
LID-based projects of one acre or larger, or those which are part of a larger plan of common development
which exceed one acre, shall have a Storm Water Quality (SWQ) Permit and the accompanying Storm Water
Quality Management Plan (SWQMP). The Maintenance Plan incorporated into the SWQMP must meet or
10
exceed the maintenance requirements indicated in these criteria for the LID practices utilized. Single-family
residential projects of one acre or less in size are exempt from this requirement.
Table 5: Storm Water Quality Treatment Requirements
Site Acreage
Requirements
A vegetated Filter Strip is a band of dense vegetation, usually grass, planted between a pollution source
(e.g., roadway, rooftop downspout, etc.) and a downstream receiving water body or conveyance. The filter
strips function by slowing runoff, trapping sediment and pollutants, and in increasing the ability to
infiltrate a portion of the runoff into the ground. More detailed information can be found in Appendix A.
3.2.1 Requirements
The longest flow path to a filter strip, without the installation of energy dissipaters and/or flow
spreaders, should not exceed 75 feet for impervious ground cover and 150 feet for pervious ground
cover.
11
3.3.1 Requirements
The bottom and sides of the swale must be vegetated. Surface ponding in a vegetated swale must
not exceed 24 hours, however a longer time frame may be considered to match existing conditions
hydrograph.
Public safety and integrity of adjacent structures must be evaluated when considering ponding
depth and duration.
See section 4.1.2 for swales used in Roadways.
3.4.1 Requirements
Acceptable for water quality and detention on the commercial site or non-single family residential
structures.
Development of a water budget shall be conducted to show how volume is made available for
detention.
Storage capacity must be designed to assure capacity is available in multiple rain events.
Not typically accepted for detention purposes.
12
13
3.5.1 Requirements
Table 6. Bioretention System Components
BIORETENTION SYSTEM
COMPONENT
REQUIREMENT
PURPOSE OF COMPONENT
required
required
Vegetation
required
Bridging Aggregate
required
Aggregate
required
Underdrain
required*
Observation/Cleanout Standpipe
required
Positive Overflow
required
not required
Outfall Structure
required
Surface Ponding
required
Maximum surface ponding depth of 2ft for the 2yr event and 4ft for
the 100yr event. Ponding duration not to exceed 24 hours. Ponding
depth & duration shall be discussed at the pre-project meeting.
14
3.5.2
For a Bioretention System with an underdrain, the calculations for Water Quality Volume (Vwq) and
Required Surface Area (Af) are as follows:
Vwq = (P / 12) * A
Where,
Vwq
P
A
Where,
k
i
Where,
Af
Vwq
Df
H
Tf
3.5.3
k = (i * 24) / 24
The infiltration rate of Engineered Soil Media in a bioretention facility must be designed to treat the first 1
of runoff volume from the drainage area it serves. In order to minimize maintenance needs and insure
performance, the Design Infiltration Rate (inches per hour) must account for potential future degradation
and therefore, must provide a minimum safety factor of 2.
For quality control purposes, the supplier of the Engineered Soil Media must provide a certificate which
indicates the infiltration rate of the media on delivery to the project site. An in situ test must be conducted
on site after engineered soil media is placed and settled to insure that the design infiltration rate is met or
exceeded. This test shall be conducted using a field Infiltrometer as outlined in Appendix B.
The separation of the Engineered Soil Media and the aggregate surrounding the underdrain below it must
be handled with care. Historically, geotextile fabrics (typically nonwoven) have been used as a separation
layer; however, these are highly susceptible to clogging which renders the bioretention system inoperable.
Fabric separation layers shall be avoided.
Instead, a thin layer (or two) of appropriately sized aggregates should be utilized as a bridging layer
(sometimes called a choker course or separator lens). A layer of pea gravel will typically provide this
15
bridge. Essentially, this practice relies on the largest 15% of the Engineered Soil Media bridging with the
smallest 15% of the underdrain aggregate particles. Commonly used in United States Golf Association
(USGA) greens construction, this method is simple, highly effective and not susceptible to clogging (USGA,
2004).
3.5.4 Underdrain
Underdrain structures, including subsurface detention or storage structures which are used under
Bioretention systems must have a total opening area which exceeds the expected flow capacity of the
underdrain itself.
Qperforations = C * A 2gh / B
Where,
g
A
h
C
B
This aggregate layer surrounding the underdrain should consist of washed aggregate -1 in diameter.
Holes in underdrain pipe shall consist of the minimum required area calculated above with a minimum
hole diameter of .
16
3.5.5
Observation/Cleanout Standpipe
If the Bioretention facility exceeds 100 feet in length; additional cleanouts must be installed in series every
50 feet. The top of the cleanout must be capped with a screw, or flange type cover to discourage vandalism
and tampering.
17
A domed riser may be installed to ensure positive, controlled overflow from the system. Once water
ponds to a specified depth, it will begin to flow into the riser through a grate, which is typically
domed to prevent clogging by mulch or debris.
An inlet structure with sloped grate may also be installed to ensure positive, controlled overflow from the
system. Once water ponds to a specified depth, it will begin to flow into the inlet. A sloped face will
prevent clogging by mulch or debris.
18
3.6.1 Requirements
19
3.7.1 Requirements
The ponding area in Tree Box Filters shall be designed with a maximum ponding depth of 24 and
to drain ponded water within 24 hours.
Plants can also be selected from those that would be used in traditional bioretention systems (See
Appendix A).
An underdrain pipe is required to drain the feature.
A maximum of 75% of the void space volume may be counted for detention.
Pre-manufactured systems must be installed in accordance with the manufacturers instructions.
3.8.1 Requirements
20
3.9.1 Requirements
Green roofs can provide an acceptable storm water quality treatment on the commercial site or non-single
family residential structures.
4.1
Roadways
Harris County Public Infrastructure Division standards for public roads which implement LID practices
include those detailed in this section.
Requirements
LID Features
Culvert Sizes
Construction Management
Hydrology
Maintenance
Requirements
Water Quality
Detention
Overflow weir or structures are required, and must accommodate the extreme event.
Overflow inlet grates must be designed to minimize blockage.
Overflow bypass should occur at design maximum ponding depth.
Crossovers may be depressed up to 6 to act as 100 year event overflow weirs,
provided crossover is not associated with a major thoroughfare intersection.
Utilize standard minimum curb heights as an option to prevent traffic from entering
the swale.
Acceptable inlet styles are those which do not impinge on safety requirements and
account for the potential for being clogged with debris, such as:
False inlet (preferred)
Curb Cut with recessed flume opening, if top surface bridged.
Horizontally slotted curb at street grade, if sufficiently long.
Inflow inlets to Bioswale should be dropped 3 to assist in capturing sediment before
it reaches the Engineered Soil Media and be sufficiently long so as to prevent flow
restrictions caused by vegetation.
Vegetated Swales may act as a pretreatment system for water quality, but alone will
not meet the water quality requirement to treat the first 1 of runoff.
Maximum side slope at 4:1, unless approved by the County Engineer.
22
Maximum water depth for the 2yr event shall not exceed 2 feet.
In the design, plan for left turn lanes so that this volume is excluded.
Culverts must meet minimum size standard of 18. However, a restrictor on
upstream end may be allowed if needed for hydraulic reasons. Minimum restrictor
size is 6.
Water shall not pond for more than 24 hours (max).
Maintain the requirement for no adverse impact during an extreme event.
If the design includes taking credit for storing storm water within the voids of
engineered soils then appropriate modeling techniques should be used to account
for this.
Utilities
Vegetation
Maximum water depth for the 100yr event shall not exceed 4 feet, and one traffic
lane in each direction shall remain passable.
Shallow depth of typical LID features may offer beneficial design options with
respect to utilities beneath them, but may in some circumstances, limit the use of
Bioswales at the outer edges of the ROW.
Requirements
General
Engineered Soils
23
6:1
2.5
2.2
2.0
4:1
3.7
3.4
3.0
5:1
3.0
2.7
2.5
Note: for the 100-year event, one lane in each direction shall remain passable with a maximum water depth
of 4 feet. For events up to the 10 year, the water shall remain below the gutter line with a maximum water
depth of 3 feet. Deeper bioswales may require evaluation for the appropriate level of vehicle control or
channelization techniques.
4.2
Commercial Development
4.3
The responsible governmental entity, i.e. Municipal Utility District, etc., must make a Maintenance
Declaration as to the intent to construct and maintain the LID IMPs. The declaration shall be filed in the
real property records, and the file number referencing such declarations shall be located on the subject plat
under notes. An example declaration is located in Appendix C.
Any proposed deviations from the approved criteria for pavement width and geometry must be discussed
with HCPID at the Pre-project meeting and approved by HCPID.
24
25
Appendix A
LID IMPs General Reference Material
1 LID Integrated Management Practices (IMP)
Although the LID toolbox is virtually unlimited, the practices described below are believed to be the most
likely to be used in this area, in combination or alone, to achieve the goals of a LID-based project design.
The table below presents the variety of runoff management functions provided by LID IMPs.
Table 11. LID IMP Runoff Management Functions
IMP
Disconnection
Soil Amendment
Vegetated Filter
Strip
Vegetated Swale
Rainwater
Harvesting
Effect or Function
Slow Runoff
X
X
X
Bioretention
Permeable
Pavement
Storm Water
Planter
Green Roof
X
X
X
Filtration
X
Retention
Detention
X
X
X
X
X
X
X
X
Evaporation
X
X
X
X
X
X
Water Quality
X
X
X
X
X
X
X
X
X
1.1 Disconnection
Roofs, roads, and driveways account for a large percentage of post-development imperviousness. These
surfaces influence storm water quality and runoff volume by facilitating the rapid transport of storm water
and collecting pollutants from rainfall, automobiles, and additional sources. Disconnecting storm water can
be achieved through identifying the source of runoff and how it will be managed once disconnection occurs.
Disconnection is ideal for most single-family developments, but can also be applied to many development
sites, including larger office parks and retails centers. This IMP can help reduce total volume and peak rates
of runoff when runoff is directed to other IMPs. Disconnection can help reduce runoff volume and peak
rates; to the extent that it is absorbed via amended soils or captured in rain gardens otherwise it is only
slowed down before reaching the receiving conveyance system.
26
Taking steps to increase the permeability of soils can also play a valuable role in disconnection. Tilling and
amending soils with compost or other amendments can increase permeability and enhance vegetative
growth, both of which can assist in the reduction of volume and peak rates.
Minimize storm water volume by disconnecting roof leaders. In addition to directing runoff to vegetated
areas, runoff may also be discharged to non-vegetated IMPs, such rain barrels, and cisterns for storm water
irrigation and water planning purposes. Disconnection of small runoff flows can be accomplished in a
variety of ways:
Reductions in peak flows may be gained by redirecting and dissipating concentrated flows from impervious
areas onto vegetated surfaces. Strategies for accomplishing this include: directing flows from small swales
to stabilized vegetated areas; breaking up flow directions from large paved surfaces; and encouraging sheet
flow through vegetated areas.
1.2
Vegetated Swale
Vegetated Swales are broad, shallow channels designed to convey and filter storm water runoff while
slowing runoff and removing gross pollutants. They handle runoff from small drainage areas at low
velocities. The bottom and sides of the swale are vegetated, with side vegetation at a height greater than
the maximum design depth.
Storm water runoff is conveyed along the length of the low slope channel, and the vegetation traps
sediments, decreases the velocity of overland flows, and reduces erosion. Vegetated Swales treat runoff by
filtering sediments and associated pollutants through the vegetation, and by infiltration into underlying
soils if in situ soils are conducive to infiltration.
Check dams are typically used in Vegetated Swales to act as flow spreaders, inducing sheet flow along the
swale. They may also be used as a storm water detention mechanism, to encourage sedimentation and to
reduce runoff velocity. Vegetated Swales can be used to convey and treat runoff from parking lots,
buildings, roadways, and residential, commercial, industrial, and municipal land uses. They can also be
used as pretreatment devices for other structural treatment controls.
27
1.3
A vegetated Filter Strip is a band of dense vegetation, usually grass, planted between a pollution source
(e.g., roadway, rooftop downspout, etc.) and a downstream receiving water body or conveyance. They
function by slowing runoff, trapping sediment and pollutants, and in some cases infiltrating a portion of the
runoff into the ground. Filter strips are a sensible and cost- effective storm water management
pretreatment option applicable to a variety of development sites including roads and highways. Given that
vegetation is the key functional component of a vegetated filter strip, due consideration must be given to
the ability of the in-situ soil to support healthy vegetative growth conditions.
The sponge effect of in situ soils in Vegetated Filter Strips may be significantly improved when tilled and
amended with compost to enhance pollutant removal, reduce surface ponding time and slow runoff by
enhancing vegetative cover. Soil amendments may also be selected to adjust pH to levels supportive of
vegetative growth, provide necessary nutrients and minerals, and increase water access and availability
characteristics among other benefits. Check dams are typically used in Vegetated Swales to act as flow
spreaders, inducing sheet flow along the swale. They may also encourage sedimentation and reduce runoff
velocity. Surface ponding in a Vegetated Swale must not exceed 24 hours.
Vegetated Swales can be used to convey and treat runoff from parking lots, buildings, roadways, and
residential, commercial, industrial, and municipal land uses. They can also be used as pretreatment devices
for other structural treatment controls.
Given that vegetation is the key functional component of a vegetated swale, due consideration must be
given to the ability of the in-situ soil to support healthy vegetative growth conditions. A soil profile which
has been cut to create the swale will often expose soils which are not capable of supporting growth
without significant, ongoing use of fertilizers which is unlikely to be carried out over the long term. A
substantial layer of topsoil retained from the site during the grading phase or imported, and placed over
the cut slopes, may alleviate the problem. Vegetation is not restricted to grasses, but regardless of the
plant material selected, native plants are preferred. A soil analysis is highly recommended for any
Vegetated Swale design, to determine what, if any, amendments may be needed to encourage and ensure
proper vegetative growth.
Proper maintenance includes mowing/pruning, weed control, removal of trash and debris, and reseeding of
non-vegetated areas/replacement of plant material. Inspect Vegetated Swales at least twice annually for
damage to vegetation, erosion, and sediment accumulation. Sediments should be removed when depths
exceed 3 inches. If hazardous materials spill and contaminate soils in vegetated swales, the affected soils
should be removed, properly disposed of, and replaced.
28
1.4
Rainwater Harvesting
Cisterns and rain barrels are designed to capture roof runoff for reuse. Cisterns reduce the runoff volume
and may reduce the peak flow rate for small, frequently occurring storms. Cisterns or rainwater catchment
systems can provide a storm water management solution where impervious surfaces are unavoidable and
site constraints limit the use of other LID practices. Such situations may include highly urbanized areas
(such as downtown centers), or dense housing developments without adequate space for storm water
infiltration or detention, or where soil and groundwater conditions do not permit infiltration. In addition to
storm water management benefits, rainwater catchment systems can be utilized as a sustainable building
approach to reduce a developments dependence on municipal water supplies.
There are several management and maintenance factors for the rain water catchment system that should
be considered including the fact that the storage capacity needs to be available to catch the next storm
events flow. For example, if the water in the storage tank is only used for landscape irrigation and the need
for irrigation water during a period of extended rainfall is minimal, the tank may fill after the first few
storms and overflow during subsequent storms. Therefore, rainwater catchment systems that are only
used for landscape irrigation may not be effective for storm water management during the rainy season.
Development of a water budget should be conducted for maximum efficiency and is required to
demonstrate how rainwater harvesting is used to reduce the storm water detention requirement.
1.5
Bioretention is a terrestrial-based (up-land as opposed to wetland), water quality and water quantity
control practice using the chemical, biological and physical properties of plants, microbes and soils for
biofiltration and the removal of pollutants from storm water runoff. Bioretention Cells or Rain Gardens are
vegetated depressions, filled with an engineered soil media which provides biofiltration for removal of
pollutants, increases time of concentration, may provide detention and prevents surface ponding of storm
water. The Bioswale is linear version of a Bioretention Cell and has similar design considerations,
requirements and attributes. Bioswales are typically designed for primary or secondary conveyance as well
as its bioretention and biofiltration benefits.
1.5.1
Design Considerations
A typical bioretention system design includes a depressed ponding area (at a grade below adjacent
impervious surfaces), an engineered soil mix, and an underdrain or underground detention or water
harvesting system.
Bioretention facilities are typically excavated to a minimum depth of 1 to 3 feet, Excavation depth is
typically based on depth to the seasonal high groundwater table, outfall depth considerations and volume
to be captured. Deeper excavation allows for additional storage in the engineered soil, gravel layers,
underdrain or underground detention/storage structures. Unless the system is being constructed without
an underdrain, a layer of geotextile filter fabric or an impermeable liner (if surrounding infrastructure
dictates) should be placed along the sides and bottom of the excavation to separate the engineered soils
from the existing site soils.
29
Engineered soil media occupies the remaining excavated space above the underdrain system, leaving room
for the desired amount of surface ponding. The area is then mulched and planted with shrubs, perennials,
grasses, and small trees. When shrubs and flowers are used as the plant material, a 2 to 3 inch layer of
mulch is used on top of the media. The mulch acts as a pretreatment device to protect the underlying media
and helps to retain some water in the media for the health of the plant.
Generally runoff is ponded to a maximum depth of approximately 12-24 inches and then gradually filters
through the engineered soil media, where it is retained in the porous soils, utilized by plants,
evapotranspired, and either infiltrated into the underlying soils (when applicable), or drained into an
underdrain or underground storage system over a period of hours. The Bioretention system should be
designed so that surface ponding does not exceed 24 hours.
The layout of a Bioretention system should be determined based on site constraints such as location of
utilities, underlying soil conditions, existing vegetation and drainage patters. The plant selection and layout
should consider aesthetics, maintenance, native versus non-native, invasive species, and regional
landscaping practices. It should be noted that ideal plants for a typical Bioretention system are drought and
inundation tolerant.
An important design factor to consider when applying Bioretention to development sites is the scale at
which it will be applied. Typical system scales are:
1.5.2
Bioretention Cells or Rain Gardens are small, distributed practices designed to treat runoff from
small areas. Inflow is typically sheet flow, or can be concentrated flow with energy dissipation.
Bioretention Basins are larger systems treating parking lots and/or commercial rooftops, or other
large areas, usually in commercial or institutional areas. Inflow can be either sheet flow or
concentrated flow. Bioretention basins may also be distributed throughout a residential subdivision
for instance, but in this case they should be located in common area or within drainage easements,
to treat a combination of roadway and lot runoff.
Urban Bioretention structures include systems such as Tree Filters, Curb Extensions, and Planter
Box Filters.
The infiltration rate of Engineered Soil Media in a bioretention facility must be designed to treat the first 1
of runoff volume from the drainage area it serves. In order to minimize maintenance needs and insure
performance, the Design Infiltration Rate (inches per hour) must account for potential future degradation
and therefore, must provide a minimum safety factor of 2.
The Engineered Soil Media shall be placed and graded using low ground-contact pressure equipment or by
excavators and/or backhoes operating on the ground adjacent to the bioretention facility. No heavy
equipment shall be used within the perimeter of the bioretention facility before, during, or after placement
of the media. The Engineered Soil Media shall be placed in horizontal layers not to exceed 12 inches for the
entire area of the bioretention facility. It shall be compacted by saturating the entire area of the
bioretention facility after each lift is placed until water flows from the underdrain. Water for saturation
shall be applied by spraying or sprinkling. An appropriate sediment control device shall be used to treat
any sediment-laden water discharged from the underdrain. Final grading of the Engineered Soil Media shall
be performed after a 24-hour settling period.
30
For quality control purposes, the supplier of the Engineered Soil Media must provide a certificate which
indicates the infiltration rate of the media on delivery to the project site. An in situ test must be conducted
on site after engineered soil media is placed and settled, to insure that it meets the design infiltration rate.
This test shall be conducted using a field Infiltrometer, as outlined in Appendix B.
The Engineered Soil Media depth should be determined based on the mature root depth of the selected
vegetation, (typically between 18 and 24 inches). Trees and larger shrubs may require a greater soil depth.
1.5.3 Mulching
Once the plants are in place, the entire bioretention facility shall be mulched to a uniform thickness of 3
inches. Well aged (minimum age of 6 months) shredded hardwood bark mulch is the only acceptable
mulch.
The flow entrance of the Bioretention facility is an important component of the bioretention. The best
method of capturing and treating runoff is to allow the water to sheet flow into the facility over grassed
areas. This is not always possible, especially where site constraints or space limitations impede such an
approach. A remedy to this problem is to provide flow inlets that can reduce the velocity of the water. In
the case of parking lot landscape islands, curb cuts protected with energy dissipaters such as landscape
stone can be used. It is important to note that entrances of this type will tend to become obstructed with
sediment and trash that settles out at lower velocities. This is not a problem as long as routine parking lot
maintenance is performed. The trapped sediment along the curbline provides a convenient location for
parking lot sweeping. On occasion, accumulated sediment and debris should be removed from the flow
entrance area if the accumulation is obstructing flow into the facility itself.
Erosion control and energy dissipation features should always be provided where concentrated runoff
enters bioretention systems (e.g. cobbles or riprap beneath a curb-cut opening or a splash block beneath a
roof drain downspout). In addition:
Vegetated swales or filter strips can be added to the design to provide pretreatment (e.g. for
sediment reduction).
Trench drains can accept runoff from impervious surfaces and convey it to a bioretention facility.
The trench drain may discharge to the surface of the system or may connect directly to an aggregate
infiltration bed beneath.
Curbs can be used to direct runoff from an impervious surface along a gutter to a low point where it
flows into the bioretention system through a curb cut. Curb cuts may be depressed curbs, full height
curbs with openings cast or cut into them or may be false inlets, designed to look like a traditional
curb inlet.
1.5.5 Underdrain
The role of an underdrain in the bioretention facility is to ensure proper drainage for the plants and to
ensure proper infiltration rates occur so as to avoid standing water for extended periods. Underdrains are
configured in many different ways and typically include a washed gravel/stone "blanket" encompassing a
horizontal, perforated discharge pipe or other perforated drainage system. A pea gravel separation layer as
31
described above can be used between the under drains aggregate blanket and the Engineered Soil Media to
protect the underdrain from blocking. Underdrains keep the soil at an adequate aerobic state, allowing
plants to flourish.
Underdrain structures, including subsurface detention or storage structures which are used under
Bioretention systems must have a total opening area which exceeds the expected flow capacity of the
underdrain itself.
To estimate the capacity of flows through the perforations, orifice flow conditions are assumed and a
sharp-edged orifice equation can be used. First, the number and size of perforations needs to be
determined (typically from the manufacturers specifications) and used to estimate the flow rate into the
pipes using the head of the Engineered Soil Media depth plus the ponding depth. Second, it is conservative
but reasonable to use a blockage factor to account for partial blockage of the perforations by the drainage
layer media. A safety factor of two is required.
This aggregate layer surround the underdrain should consist of washed aggregate -1 in diameter.
Placement of the gravel over the underdrain must be done with care. Avoid dropping the gravel high levels
from a backhoe or front-end loader bucket. Spill directly over underdrain and spread manually.
Underdrains must discharge into an adequate conveyance system. The underdrain system should be sized
to support the flow rate of the engineered soils and the volume of water entering. Discharge from the
underdrain can be routed to a down gradient storm drain pipe or channel or another IMP device. The
underdrain system should have a vertical solid section that extends above the surface of the ponding area
in the basin to provide a monitoring well and clean out access port.
In some cases, a liner may be necessary to avoid infiltration into surrounding soils and/or
groundwater. Examples include facilities located in Brownfields, or in close proximity to structures or
roadbeds, or in areas where there is outdoor storage or use of chemicals or materials within the drainage
area that could threaten groundwater quality if a spill were to occur.
A positive overflow, via the surface or subsurface, is required to safely convey excessive runoff from
extreme storm events. Bioretention systems should include design features that allow flows from relatively
large storm events to either bypass the system or overflow to a conventional storm drain structure such as
a channel, a curb and gutter system, or a storm drain overflow inlet. Off-line designs are an option and are
best accomplished when only one inlet is present in the bioretention system. Once the bioretention facility
is full, the high flows would bypass the inlet. Bypass flows or overflows can also be routed to another
downstream storm water treatment system such as a vegetated swale or an extended detention basin.
1.5.7
Required Maintenance
One of the major advantages of a bioretention system over any underground BMP is that inspection is easy
since the system is in full view to inspect the health of the plants and amount of debris or sedimentation
that has accumulated. Once plants are established, only minimal plant maintenance and occasional removal
of sediment and debris is necessary. Mulch should be replaced on an annual basis. Other considerations
include:
32
1.6
Upon installation and during the first year, Bioretention systems should be inspected monthly for
potential erosion and/or extended ponding.
Key inspection/maintenance areas include inlet and overflow areas for potential erosion, the
ponding area for trash and debris, and the Observation/Cleanout Standpipe for potential early signs
of stagnant water in the system if an underdrain system is included.
Inspections can be reduced to a semi-annual schedule once the system has proven to work properly
and vegetation is well established.
An evaluation of the health of the plants, trees and shrubs should be conducted biannually.
Pruning, weeding and trash removal should be conducted as necessary.
Mulch replacement is generally required every year.
If ponding is observed to exceed 24 hours, particularly during the primary mosquito breeding
season (June through October), the reason for the extended ponding should de determined and
mitigated.
If a spill occurs and hazardous materials contaminate soils in landscape detention areas, the
affected materials should be removed immediately and the appropriate engineered soil media and
materials replaced as soon as possible.
Permeable pavement includes a wide range of paved or load-bearing surfaces that allow water to pass
rapidly through the surface and into the sub-grade that serves as a reservoir, a filter bed, and a loadbearing layer. Permeable pavement decreases the runoff volume and peak flow rate and captures
pollutants. These systems allow for infiltration of storm water while providing a stable load-bearing
surface for walking and driving. Porous pavement detention can be used as a substitute for conventional
pavement, but should be limited to parking areas and low traffic volume roadways where little to no truck
traffic is anticipated.
Example applications include residential street parking lanes, parking stalls in commercial or retail parking
lots, overflow parking areas, maintenance walkways/trails, emergency vehicle and fire access lanes,
stopping lanes on divided highways, equipment storage areas, and patios. Permeable pavements may not
currently be used on residential driveways or major thoroughfares.
Permeable pavement treats rainfall that falls directly on the surface, as well as runoff from adjacent
impervious areas. These systems contain void spaces to provide infiltration of runoff into their underlying
engineered porous materials and then into existing site soils. Generally, underlying engineered materials
consist of clean sands or gravels separated from existing site soils by a synthetic filter fabric. Underlying
engineered materials detain and filter pollutants prior to infiltration into underlying soils or discharge to a
conventional storm drain system through an underdrain system. With these systems, it is important to note
that the load-bearing sub-grade must be sufficiently thick to support the design load from the intended use
and provide storage for volume or detention control. Porous paving systems can preserve natural drainage
patterns, enhance groundwater recharge and soil moisture, and can help establish and maintain roadside
vegetation. Although a good substitute for conventional concrete and asphalt in certain applications such as
parking lots or long private driveways, porous paving systems are not suitable in high-traffic areas.
All installations of permeable pavement systems should be carried out according to manufacturers
specifications. There are several types of Permeable Pavement systems, including:
33
1.6.1 Underdrain
The overall maintenance goal is to avoid clogging of the void spaces. Remove accumulated debris and litter
as needed. Inspect Permeable Pavement systems several times during the first few storms to insure proper
infiltration and drainage. After the first year, inspect at least once a year.
Permeable pavements and materials should be cleaned with a vacuum-type street cleaner at least twice a
year to prevent clogging of the pervious surface. Hand held pressure washers can be effective for cleaning
the void spaces of small areas with some pavement systems and should follow vacuum cleaning.
Maintenance personnel must be instructed not to seal or pave with non-porous materials.
Vegetated paving systems require careful vegetative maintenance to insure the health and viability of the
vegetation.
1.7
Tree box filters are bioretention systems enclosed in concrete boxes or other sub-surface structures that
drain runoff from paved areas via a standard storm drain inlet structure. They consist of a precast concrete
(or other) container, a mulch layer, bioretention media mix, observation and cleanout pipes, under-drain
pipes, a street tree or large shrub, and a grate cover. The filters are installed below grade at the curb line.
For low to moderate flows, storm water enters the tree box inlet, percolates through the media, and exits
through an underdrain into the storm drain. For high flows, storm water bypasses the tree box filter once it
becomes full and flows directly to the downstream curb inlet. As an engineered media-based filter, tree box
filters remove pollutants through the same physical, chemical, and biological processes as traditional
bioretention systems. Under normal conditions, pretreatment is not necessary. Most of the general design
standards noted previously for bioretention systems also apply to tree box filters. Tree box filters should
generally be designed per the bioretention system design criteria and engineered media testing
requirements.
34
1.8
Storm Water Planters, also known as flow through planters, are also bioretention systems in enclosed in
concrete structures. They can be designed to drain runoff from paved areas via curb inlet structures or
pipes, or they can be located under roof drain downspouts for treatment of roof runoff. They should be
designed with an underdrain pipe. Waterproofing should be incorporated into the designs of Storm Water
Planters sited near buildings and other structures.
Most of the general design standards noted above for bioretention systems also apply to storm water
planters. For example, the ponding area in Storm Water Planters should be designed with a maximum
ponding depth of no more than 12-24 and to drain ponded water within 24 hours. Plants can also be
selected from those that would be used in traditional bioretention systems.
1.9
Green Roof
A green roof is a vegetated roofing system. Green roofs typically consist of a number of layers: a
waterproofing membrane, a drainage system, root protection, growing media (soil) and vegetation. Green
roofs provide numerous environmental benefits and offer a valuable tool for integrated storm water
management.
Green roofs may cover all or part of a buildings roof. Green roofs retain rainfall from small, frequently
occurring storms through storage in the soil. In turn, this water is lost to evaporation or transpiration by
plants. For larger storms, the runoff volume and peak flow rate is reduced because of percolation and
temporary storage in the soil. Green roofs improve water quality through a variety of physical, biological
and chemical processes in the soil.
Structurally, there are two types of green roofs: extensive and intensive. Extensive green roofs are
lightweight vegetated roofs typically consisting of 4-8 inches of growth media (or soil), planted with hardy,
drought-tolerant species to minimize additional irrigation, maintenance, cost and weight. They typically
require supplemental irrigation to support growth during initial establishment of vegetation and during
extended dry periods. Modular green roof systems are available that can come pre-planted in ready-toinstall blocks. Alternatively, intensive green roofs can be designed to support lawns, trees, and create a
useable outdoor garden space; often referred to as roof gardens. While these amenities do not preclude
environmental benefits of green roofs, they do require extra structural support, cost, and have functional
goals in addition to storm water management objectives. They also typically require supplemental
irrigation systems.
Upon installation, the green roof system should be inspected monthly for the first year and after each large
storm event for erosion, plant survival, proper drainage, and waterproofing. Inspections can be reduced to
a quarterly schedule once the green roof system has proven to work properly and vegetation is established.
If necessary, irrigate in short bursts only (3-5 minutes) to prevent runoff. Irrigation frequencies should be
established by the designer using an automated system. Clean out drain inlets as needed. Weeding and
mulching may be necessary during the establishment period, depending on the planting design. Replace or
fill in vegetation as needed. Inspect soil levels semi-annually to ensure plant survival and rainfall
absorption.
35
Landscaping is a critical component of bioretention because of the natural ability for plant material to treat
pollutants in urban storm water. The integration of landscaping also sets bioretention apart from other
integrated management practices by allowing the storm water practice to be distributed throughout the
site - closer to the pollution sources - while improving the site aesthetics. With the proper landscaping
application of bioretention, most people interacting with the built environment will tend to admire the
sites aesthetics and not even be aware that storm water management exists on the site.
Key factors in the design of bioretention facilities are careful selection of plant materials that can tolerate
highly variable hydrologic changes and an overall planting plan that ecologically and aesthetically blends
the facility into the landscape. Designing for ease of maintenance is also a critical element of any landscape
plan.
Consider interactions with adjacent plant communities including the potential to provide links to wildlife
corridors. Adjacent plant communities should be evaluated for compatibility with any proposed
bioretention area species. Nearby existing vegetated areas dominated by non-native invasive species pose a
threat to adjacent bioretention areas. Invasive species typically develop into monocultures by outcompeting other species. Mechanisms to avoid encroachment of undesirable species include providing a
soil breach between the invasive communities for those species that spread through rhizomes and
providing annual removal of seedlings from wind borne seed dispersal. It is equally important to determine
if there is existing disease or insect infestations associated with existing species on site or in the general
area that may affect the bioretention plantings.
Soil Amendment
2.1
The sponge effect of in situ soils may be significantly improved when tilled to depth of at least 6 and
incorporating at minimum of 2 of compost within the root zone to improve soil quality, plant viability and
soil hydraulic conductivity, which enhances time of concentration, provides enhanced pollutant removal
and reduces surface ponding time. This practice is typically utilized for Vegetated Swales and Vegetated
Filter Strips, but should be strongly considered for general landscape and turf areas.
Prior to soil amendment, existing soils must be sampled and evaluated to determine amendment quantities
and plan the amending process. In addition to compost, soil analysis may reveal the need for other soil
amendments, such as lime, gypsum and specific nutrients.
Compost shall be mature, stable, weed free, and produced by aerobic decomposition of organic matter. The
product must not contain any visible refuse or other physical contaminants, substances toxic to plants, or
over 5% sand, silt, clay or rock material by dry weight. The moisture level shall be such that no visible
water or dust is produced when handling the material.
The results of compost analysis shall be provided by the compost supplier. Before delivery of the compost,
the supplier must provide the following documentation:
a copy of the lab analysis, less than four months old, performed by a Seal of Testing Assurance
Certified Laboratory verifying that the compost meets the physical requirements as described.
Compost shall uniformly be applied over the entire area to a depth of two (2) inches, and incorporated into
the soil to a minimum depth of six (6) inches. Where tree roots or other natural features limit the maximum
depth of incorporation, compost quantities should be adjusted. Required volume of compost may be
estimated using the following approximation: one (1) inch compost spread over 1000 square feet = three
(3) cubic yards. The Designer may specify different compost application rates depending upon soil
conditions.
2.2
Mulching
Once the plants are in place, the entire bioretention facility shall be mulched to a uniform thickness of three
(3) inches. Well aged (minimum age of six [6] months) shredded hardwood bark mulch is the only
acceptable mulch.
2.3
The role of plant species in the bioretention concept is to bind nutrients and other pollutants by plant
uptake; to remove water through evapotranspiration; and to create pathways for infiltration through root
development and plant growth. Root growth provides a media that fosters bacteriologic growth, which in
turn develops a healthy soil structure. A variable plant community structure is preferred to avoid
monoculture susceptibility to insect and disease infestation and to create a microclimate, which
ameliorates urban environmental stresses including heat and drying winds. Parking lot island bioretention
is particularly susceptible to extended dry conditions. A layered planting scheme will help discourage
weeds as well as creating suitable microclimates. There are many potential side benefits to the use of
planting systems other than water quality and quantity treatment. Planting systems, if designed properly,
can improve the value of the site; provide shade and wind breaks; improve aesthetics; support wildlife; and
absorb noise.
Landscape Maintenance
All landscape treatments require maintenance. Landscapes designed to perform storm water management
functions are not necessarily more maintenance intensive than highly manicured conventional landscapes.
A concave lawn requires the same mowing, fertilizing and weeding as a convex one and less irrigation after
rain is filtered into the underlying soil. Sometimes infiltration basins may require a different kind of
maintenance than conventionally practiced.
Typical maintenance activities include periodic inspection of surface drainage systems to ensure clear flow
lines, repair of eroded surfaces, adjustment or repair of drainage structures, soil cultivation or aeration,
care of plant materials, replacement of dead plants, replenishment of mulch cover, irrigation, fertilizing,
pruning and mowing. Landscape maintenance can have a significant impact on soil permeability and its
ability to support plant growth. Most plants concentrate the majority of their small absorbing roots in the
upper 6 inches of the soil surface if the surface is protected by a mulch or forest litter. If the soil is exposed
or bare, it can become so hot that surface roots will not grow in the upper 8 to 10 inches. The common
practice of removing all leaf litter and detritus with leaf blowers creates a hard crusted soil surface of low
37
permeability and high heat conduction. Proper mulching of the soil surface improves water retention and
infiltration, while protecting the surface root zone from temperature extremes.
In addition to impacting permeability, landscape maintenance practices can have adverse effects on water
quality. Because commonly used fertilizers and herbicides are a source of organic compounds, it is
important to keep these practices to a minimum, and prevent over watering. Over watering can be a
significant contributor to run off and dry weather flows. Watering should only occur to accommodate plant
health when necessary. When well-maintained and designed, landscaped concave surfaces, bioretention
systems, vegetated swales and other LID IMPs can add aesthetic value while providing the framework for
environmentally sound, comprehensive storm water management systems.
This Guide, and the collaborative permitting process which it informs, seeks to insure a process in which all
parties benefit from the opportunities to learn as we determine the best adaptations, applications and
implementations of Low Impact Development and Green Infrastructure practices in our community.
4.2
Construction
The effectiveness of LID systems is a function of the design and the construction techniques employed. Of
these two parameters, construction is perhaps more critical at achieving quality results. Poor construction
techniques will cause the best designed IMP to fail prematurely, usually from sedimentation and/or
clogging.
4.2.1 Training
It is very important that contractors, vendors, and inspectors be properly trained in the design
specification and construction requirements for all LID practices employed. The success of many LID
techniques depends on accurately following the grading plan; the use of proper materials and the
appropriate location of practices. Due to the complexities of the practice, it may be necessary for vendors,
contractors, and permit personnel to participate in training classes. For example, the design and
construction of bioretention cells requires the knowledge of several disciplines including engineering,
landscape architecture, and soil science to ensure the proper design and construction of the project.
4.2.2 Communication
LID uses innovative techniques, unique strategies and various combinations of practices. Consequently,
each development results in a unique design with its own set of issues and challenges. It is vital that
everyone involved in the LID project (contractors, vendors, design engineers, and inspectors) understands
38
the unique details of the LID project. A pre-construction meeting is the most useful approach to ensure that
the project goals and issues are effectively communicated. Ideally the contractor, vendor, design engineer,
and inspector should hold a meeting to go over the plans and discuss all aspects of the project. During the
pre-construction meeting, the inspector may evaluate the proposed sequence of construction, sediment
control requirements, and indicate when inspection points during construction of the LID practices are
required as identified in the design manual.
Throughout the construction process, there must be effective communication. No construction project takes
place without unforeseen problems and the need to make some field adjustments. Proper lines of
communication must be in place throughout the construction phase between the general contractor, site
engineer, inspector, and permit staff to address required changes. Designers must also make it a priority to
make construction sequencing and details conspicuous on plans.
Proper erosion and sediment control during construction is vital for LID practices. If existing vegetation is
to be used for treatment (bioretention, swales or buffers), then these areas must be protected from
sedimentation. Areas that may be used for biofiltration must be protected to prevent sediment from
clogging soils with silts and clays. Preventing damage from sedimentation is less expensive than cleaning or
rehabilitating an area.
4.2.3.1 Storm Water Pollution Prevention (SWPPP) During Construction
The clearing, grubbing and scalping (mass clearing or grading) of excessively large areas of land at one time
promotes erosion and sedimentation problems. On the areas where disturbance takes place the site
designer should consider staging construction, temporary seeding and /or temporary mulching as a
technique to reduce erosion. Staging construction involves stabilizing one part of the site before disturbing
another. In this way the entire site is not disturbed at once and the duration of soil exposure is minimized.
Temporary seeding and mulching involves seeding or mulching areas that would otherwise lie open for
long periods of time. The time of exposure is limited and therefore the erosion hazard is reduced. Two
methods of sediment control are typically applied to bioretention facilities as follows.
The first method (most typical) is to direct all drainage away from the locations of IMPs to avoid excessive
sedimentation. Flow can be directed away from the bioretention IMP by utilizing silt fencing materials,
wattles and temporary diversion swales
The second method of erosion and sediment control design allows the area proposed for the bioretention
IMP to be used as a temporary sediment control structure. If a sediment control structure is to become a
bioretention IMP, the sediment materials shall be removed prior to constructing the bioretention IMP and
placing the Engineered Soil Media.
Care must be taken to protect tree conservation areas during construction. Tree conservation areas are
ineffective if the trees die shortly after the project is completed.
In order to effectively protect trees, it is important to consider the following during any construction
process:
39
All types of construction equipment can cause mechanical injury to roots, trunks, or branches. This
can weaken a trees resistance to a number of diseases and insect infestation. Trees should be
clearly marked and given wide clearance. Excavation around trees should not be within the drip
line of the tree.
Soil compaction squeezes the air and water out of the soil making it difficult for a tree to absorb
oxygen and water. No construction equipment should be allowed to run over the roots within the
drip line of the tree.
Grading practices that deposit soil over the roots of trees eventually suffocates those roots. More
than an inch or two of soil over the roots is enough to potentially suffocate the roots of trees and
compromise the health of the tree. Measures can be taken to improve soil aeration around tree
roots if it is necessary to add fill within the critical root zone (see Figure 6-1).
Grading practices that divert too much runoff to a mature stand of trees can result in damage. As a
tree matures its ability to adapt to changes decreases. Additionally, if a stand of trees is located in a
normally dry area that suddenly becomes very wet, the additional water may kill the trees. An
arborist should be consulted these situations to determine the trees tolerance to a change in
hydrology.
A tree protection plan with written recommendations for the health and long-term welfare of the
trees during the pre-construction, demolition, construction, and post-construction development
phases, should be developed. The tree protection plan should include specifics about avoiding
injury, information about treatment for damage and specifics about required inspections of
protected trees. The tree protection plan should also provide information about caring for damaged
trees.
Construction sequencing is important to avoid problems while constructing LID projects. Proper
sequencing decreases the likelihood of damage to the BMP during construction and helps to ensure optimal
performance of each IMP. Each LID practice is somewhat different, therefore information should be
provided to the contractor on the proper sequencing. The construction drawings should clearly state the
designer's intentions and an appropriate sequence of construction should be shown on the plans. This
sequence should then be the topic of a detailed discussion at the pre-construction meeting (that must
include the on-site responsible construction personnel) and then enforced by an appropriate inspection
program throughout the construction period.
Conservation areas must be identified and protected before any major site grading takes place. Most of the
engineered LID practices (bioretention, infiltration trenches, and infiltration swales) should be constructed
at the end of the site development process, and preferably when most of the site is stabilized. Any LID
practice that relies on filtration or infiltration must be protected throughout the construction phase from
sedimentation and should not be activated until the contributing drainage area is stabilized. For example,
bioretention systems should be constructed at the time of final grading and landscaping, and/or these
areas should be protected from sedimentation until the drainage routes to the facility are stabilized.
4.2.6 Maintenance
As with any stormwater management technique, maintenance is essential with LID BMPs to ensure that the
designed stormwater benefits continue. Post-construction inspections and maintenance are important to
40
ensure that each technique is functioning effectively. Annual inspections are recommended, with more
frequent inspections during the first year to ensure that vegetation is thriving.
Inspection and maintenance of structural LID practices such as cisterns, vegetated roofs, permeable
pavements, infiltration structures, and manufactured proprietary devices should follow state or local
stormwater minimum standards, as well as manufacturers recommendations for maintenance or repair.
Any under-drains or outfall structures should be inspected on a regular basis and cleaned out or repaired
as necessary. The primary maintenance requirement for vegetative LID structural and non-structural
practices is inspection and periodic repair or replacement of the treatment areas components. This often
includes the maintenance of the vegetative cover (pruning), replacing mulch, removing weeds, and possibly
removing sediment to preserve the practices hydraulic properties. For many LID practices, this generally
involves little more than the routine periodic landscape type maintenance. Maintenance requirements are
further discussed above in sections associated with specific LID technique.
To ensure continued long-term maintenance, all affected landowners should be made aware of their
individual or collective maintenance responsibilities through legal instruments such as maintenance
agreements and maintenance easements that convey with the property. Outreach materials, such as LID
brochures or facts sheets that explain the function of practices and the anticipated maintenance
responsibilities for homeowners, should be included in settlement or homeowner association documents.
The developer should prepare a maintenance plan that provides clear guidance and instructions to the
property owner property manager or property owners association about the annual maintenance needs of
each LID technique.
41
Appendix B
Harris County Standard Operating Procedure for Determining In Situ
Hydraulic Performance of High Flow Rate Bioretention Media
Objective
Provide as-built confirmation of proper installation and hydraulic performance, to meet Harris County
minimum 30/hour Infiltration rate requirements, of bioretention media on newly-placed bioretention
systems. This procedure measures the entire media profile under saturated conditions to insure a reliable
and accurate result.
Example Site Test Layout and Design Schematic
For bioretention systems with a surface area less than 50 m2 (538 ft2), in situ hydraulic testing should be
conducted at three points that are spatially distributed. For systems with a surface area greater than 50 m2,
an extra monitoring point should be added for every additional 100 m2 (1076 ft2). (Values are based on
recommendations from the Facility for Advancing Water Biofiltration.)
Testing should be performed on the perimeter since this is the area most likely to be impacted by sediment
in the runoff.
X
10 ft
X
43.5 ft
Figure 1. Site Layout
42
Equipment Description
The components of this test apparatus are readily accessible, inexpensive and lightweight.
Infiltrometer Components:
X inches long x 6 inch ID schedule 40 white PVC pipe with 2 inch beveled ending and 2 opposite holes
drilled one inch from top sized for rebar
(X = media depth + 2 inch pipe into UD + 3 inch pipe above media; ex: for a 12 inch media depth you
would need 17 inch pipe)
24 inch piece of rebar for insertion through 2 drilled holes for removal of pipe from media after test
5 ft long x 6 inch ID schedule 40 clear PVC cylinder
6 inch gate valve with pull handle designed to fit schedule 40 PVC
Tube of silicone caulking
Hammering Components:
4 inch thick by 8 inch wide by 24 inch long pressure treated wood board
5# to 10# sledge hammer
Other Materials
Water
Manhole lifter or crow bar for use on rebar to remove pipe from media after test completion
Light weight oil or petroleum jelly with dry wipes for application
Level
Stopwatch
Rake/shovel
Measuring tape
Large stones (~2 inch; see Figure 6)
Flashlight
Clipboard with pencil and Table 1 from this document
Assembly:
Insert 5 ft long x 6 inch clear PVC cylinder into topside opening of gate valve. Apply silicone caulking to
outside area where cylinder and gate valve meet. Smooth out caulking to create leak proof seal. Let dry
according to directions on tube.
Test Methodology
1. Carefully scrape away any surface covering (e.g. mulch, gravel, leaves) without disturbing the soil
filter media surface.
43
2. In an area near the test location, confirm media profile depth by using a shovel to dig to under drain
stone and place measuring tape in hole to determine depth from top of under drain stone to top of
media bed. A flash light may be needed to ensure the under drain stone has been reached before a
depth measurement is taken.
3. At the test location which has been cleared of mulch, locate the six (6) inch wide white PVC pipe
(beveled end down) on the surface of the media. Ensure testing is not too close to vegetation. Place
the wooden board over the pipe and then gently pound with the sledge hammer on top of the board
(Figure 3). Hammer the PVC pipe into the entire media profile based on the depth previously
determined until it is approximately 3 inches above the media (Figure 4). Check with level to insure
that the pipe is plumb. Note: It is important that the pipe is driven in slowly and carefully to
minimize disturbance of the filter media profile. The media may slightly move downward in the
pipe during hammering, but not more than 1 inch, and will not significantly affect hydraulic
performance.
4. If top of pipe is less than 3 inches from media surface, remove media around outside of pipe so that
the pipe is 3 inches from the media bed. This will allow the gate valve coupling to properly slide
onto the pipe.
5. Remove board and rub lightweight oil/petroleum jelly on outside of PVC pipe above media (Figure
5).
6. Place 2 inch dissipater stones into pipe (Figure 6).
8. Measure from the original surface of the media within the column to the 1ft, 2 ft, 3 ft, 4 ft and 5 ft
gradations, and mark them on the clear PVC cylinder (Figure 8). The 1 ft and 5 ft marks are the
critical marks, since the timed fall of the water level between these two intervals represent the
pass/fail criteria for the test. (The time at other intervals between 1ft and 5 ft may be recorded for
additional information, but will not be used in the pass/fail criteria).
9. Fill a 5 gallon bucket with 3 gallons from the filled 55 gallon drum. Leave cap off of drum at test site
to prevent airlock. Alternative water supply sources are acceptable.
10. Ensure the gate valve to the infiltrometer is closed. Fill with the 3 gallons of water (Figure 9). To
create a saturated condition, an initial wetting of the media using the infiltrometer is conducted by
opening up the gate valve completely. The gate valve should be slowly opened by tapping gently on
the handle to prevent, a sudden high flow of water which might disturbance of the media surface
by. Pulling open by hand tends to force the valve open too quickly.
45
11. After the water level disappears from the clear column, a drain down time of 25 minutes is allowed
to ensure free water has drained from the system. The media is now at field capacity (fully
saturated).
12. After 25 minutes, ensure the gate valve is closed. Fill the 5 gallon bucket with water and continue to
fill the column until water level reaches the very top of the clear pipe. Water is then re-introduced
by opening the gate valve slowly by tapping the handle gently. The stopwatch should be started
when the falling water level reaches the 5 ft gradation, and recorded subsequently at every 1 ft
gradation. The stopwatch time must be stopped when the water level reaches the 1 ft mark.
13. Pass/fail criteria is based on maximum drawdown times (Table 1), relative to media depth. For
example, a media profile depth of 18 inches should not exceed a drawdown time of 27 minutes and
0 seconds between the 5 ft and 1 ft gradations.
Table 1. Maximum Time Criteria Based on Media Depth
Media Depth
(inches)
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
44:06
44:54
45:36
46:18
47:00
47:42
48:24
49:00
49:36
50:12
50:48
51:24
52:00
52:30
47
Appendix C
Maintenance Declaration
MAINTENANCE DECLARATION
Low Impact Development & Green Infrastructure Design Criteria for Storm Water Management
This Maintenance Declaration (this Declaration) is made as of the ___ day of ___________, 20__, by
_____________[INSERT NAME OF OWNER OF PROPERTY COVERED BY APPLICABLE PLAT]_______ (Owner).
RECITALS
A. Owner is a _______[INSERT TYPE OF ENTITY]___ and has the legal authority to construct {water,
sewer, and drainage facilities, road facilities and related road improvements, and recreational and
landscaping improvements} (Specify those that apply) within the Property (hereinafter defined). .
B. Owner owns that certain real property described on Exhibit A attached to this Declaration and
incorporated herein for all purposes (the Property).
C. In accordance with the Low Impact Development & Green Infrastructure Design Criteria for Storm
Water Management (the LID Criteria), certain enhancements to public improvements are
required. Owner intends to submit to Harris County, Texas (the County) for approval a plat
covering the Property (the Plat), which, among other things, includes enhancements to certain
public improvements to be constructed within the Plat boundaries pursuant to the LID Criteria as
are identified below (collectively, the Enhancements).
D. Owner desires to declare its obligation to construct and maintain the Enhancements.
NOW, THEREFORE, Owner hereby declares that, upon acceptance of the Plat by the County and
construction of the Enhancements, Owner will be responsible for all maintenance for the following
Enhancements [check as applicable]:
Storm water quality and drainage features, including green infrastructure and low impact
development practices
Water and sanitary sewer lines
Conduit
Recreational improvements
48
Enhanced landscaping
Other ____________________________________________________________
__________________________________________________________________
Other ____________________________________________________________
__________________________________________________________________
Other ____________________________________________________________
__________________________________________________________________
This Declaration shall be governed by, construed and interpreted in accordance with, and
enforceable under, the laws of the State of Texas.
IN WITNESS WHEREOF, Owner has caused this Declaration to be executed as of the date and year
first set forth above.
[INSERT NAME OF OWNER]
ATTEST:
__________________________________________
(name and title of Owners representative)
(add in if appropriate)
Attachment:
Exhibit A Description of Property
After recording, return to: [insert Owners address]
49
Appendix D
References
USGA Recommendations for a Method of Putting Green Construction, 2004 USGA
WSUD Engineering Procedures: Stormwater, 2005, Melbourne Water
Stormwater Management Guidance Manual Version 2.0, City of Philadelphia
Low Impact Development Guidance Manual, City of Wilmington, North Carolina
Town of Huntersville Water Quality Design Manual, 2008, Mecklenburg County Water Quality
Program
Low Impact Development Technical Guidance Manual for Puget Sound, 2005, Puget Sound Action
Team & Washington State University Pierce County Extension
Seattle Right of Way Improvements Manual, City of Seattle
Bioretention.com website
Low Impact Development Handbook, 2007, County of San Diego
Low Impact Development Center, Inc. website
San Mateo County Sustainable Green Streets and Parking Lots Design Guidebook, 2009 San Mateo
County
HCFCD, 2010. HCFCD Storm Water Management Program (SWMP). TPDES Permit No.
WQ0004685000. Revised October 31, 2010.
HCFCD, 2010. HCFCD Policy, Criteria, & Procedure Manual. Revised December 2010.
HCPID, 2010. HCPID Storm Water Management Program (SWMP).
TPDES Permit No.
WQ0004685000. Revised October 31, 2010.
50
Appendix E
Resources
San Mateo County Sustainable Green Streets and Parking Lots Design Guidebook, First Edition, January
2009 (http://www.flowstobay.org/ms_sustainable_guidebook.php)
Town of Huntersville Water Quality Design Manual, 2008, Mecklenburg County Water Quality Program
(http://www.huntersville.org/Planning%20Info/Huntersville%20Design%20Manual%20January%201,%
202008%20Version.pdf)
Low Impact Development Technical Guidance Manual for Puget Sound, 2005, Puget Sound
(http://www.psparchives.com/publications/our_work/stormwater/lid/LID_manual2005.pdf)
51
Appendix F
Acknowledgments
This Guide represents a commitment by Harris County to enhance, enable and integrate sustainable use of
land and water for our areas continued growth and economic vitality. This is in fact the mission statement
of the Houston Land/Water Sustainability Forum, in which both Harris County Public Infrastructure
Division and Harris County Flood Control have played a significant role since the its inception.
The direct impetus for the LID & Green Infrastructure Design Guide was the success of a Forum-sponsored
Low Impact Development Design Competition, in which a broad range of participants from the local design
community were asked to create a project design using these practices, in one of three categories: Green
Roadway, Suburban Residential and Urban Redevelopment. The projects were real, in fact one was an
existing Harris County road slated for expansion, and the data on which the designs were based was the
same information any owner would have provided to a design team.
The results of the competition were twofold. First, there was a profound recognition by the participants of
the value, validity and benefits for all parties in widespread adaptation and adoption of these practices.
Second, was a groundswell of interest in getting new projects which utilize them permitted smoothly and
without the delays which might otherwise accrue to permitting a new style of development which take
such fundamentally different approach than the traditional development for which current rules and
regulations were designed.
Rewriting regulations can be a time consuming process. Recognizing that taking advantage of the
enthusiasm for adopting these practices, which have proven so beneficial elsewhere, and moving forward
with LID-based projects meant removing the obstacles to permitting them. During the summer of 2010,
under the auspices of the Houston Land/Water Sustainability Forum, a series of three day-long
collaborative workshops were held specifically to examine the obstacles to permitting LID-based projects,
exploring how LID practices could be adapted to meet the intent of current rules and developing guidelines
for the permitting process. This process examined the primary development categories of Suburban
Residential, Green Roads, Commercial and General Site Design, as well as Urban Infill and Redevelopment.
Participants in this process included key permitting, storm water, and development regulatory staffers, and
leadership, from Harris County Public Infrastructure Division, Harris County Flood Control and the City of
Houston. The design community was represented by the firms whose teams placed in the finals of the
design competition and included civil and transportation engineers, planners, landscape architects and
architects. Representatives from the Houston Council of Engineering Companies, the American Society of
Landscape Architects and American Association of Civil Engineers and developers associated with the
Greater Houston Builders Association also contributed.
52
Appendix G
Acronyms
BMP
EPA
GI
HCFCD
HCPID-AED
HOA
IMP
LID
MTFP ROW
MUD
PCPM
Q
Qallocated
Qexist
Qprop
ROW
SWPPP
SWQ
SWQMP
Tc
TC&R
TCEQ
USGA
WQv
53