Beruflich Dokumente
Kultur Dokumente
Low-cost Options
for Treating
g
Faecal Sludges
(FS) and
Wastewater in
Developing
Countries
(Part D)
Doulaye Kon
EAWAG / SANDEC
www.sandec.eawag.ch
Tel.+41 44 823 55 53
Contents
Design criteria
-
25-30 cm
8 - 12 days (dry weather)
100 - 200 kg TS/m2*a
~ 0.05 m2/cap*
Percolate quantity
-
~ 50-80%
50 80% of FS volume
Design variables
-
Removal efficiencies
(raw sludge percolate)
100
60
[%]
40
20
0
40-60%
80
NH4
COD 70-90%
SS 95%
20-cm stainless
steel ventilation
pipe
7-cm thick
ferro-cement
Outlet
pipe
0.25-cm
plastic sheet
1.2-cm mesh
20-cm concrete
blocks
10-cm reinforced
concrete slab
20-cm PVC
drainage pipe
3 3 effluent
3-m
ffl
t
receiving tank
Root system allows to maintain dewatering capacity of the drying beds during several years
Low desludging requirement since sludge loading cycles may last for several years
Biosolids stabilization and dewatering in one treatment step
Plant growth has to be given particular care (water balance)
Percolate may need further treatment
Appropriate under wet-tropical climatic conditions, less appropriate under dry climatic conditions
Soil filter
- Large gravel (d=5 cm): 45 cm
- Medium gravel (d=2 cm): 15 cm
- Sand (d=0.1 cm): 10 cm
Freeboard
- 1m
Vegetation
- indigenous species (cattails, reeds or bulrushes)
- Start up with plant density 8 shoots/m2
Land requirement
-
~ 0.03 m2/cap
Constructed wetlands
70
80
60
50
60
[m]
40
40
20
30
20
0
SS
CODtot
CODfil
10
TKN
Biosolids accumulation:
90 m of fresh FS loaded
10
-D
Decentralised
t li d approach
h
- Institutional and
financial setup
- Socio-cultural aspects
11
- Influence of temperature
pattern on HE inactivation
- Influence of turning frequency
on HE inactivation
Monitoring parameters
Mixing Ratio
Nitrogen Balance
Maturity parameters
Temperature
Moisture content
Helminth eggs inactivation
12
Temperature pattern
Heap 1, turned when temp > 60
Heap 2 turned each 10 days
75
Temperature (C)
Heap11
Heap21
Heap12
Heap22
60
45
30
0
10
20
30
40
50
60
70
Days
Temperrature (C)
90
60
30
30
0
50
Ascaris Eggs per gTS
0
50
Ascaris Eggs per g TS
60
40
30
20
10
40
30
20
10
0
0
0
20
40
60
80
20
40
60
Days
80
Days
HE removal in heaps
turned each 3 days in the
active composting period
HE removal in heaps
turned each 10 days in the
active composting period
14
Viability test
Helminth Eggs (Ascaris and Trichuris) die off during co-composting :
results from Buobai Co-composting plant/Ghana
40
Ascaris Egg/gTS
Viable Ascaris/g TS
Eggs / g TS
30
20
10
0
0
30
Days
60
90
15
16
Co-composting efficiency
a) Helminth eggs inactivation was not affected by
the turning frequency, less frequent turning
would be sufficient
b) Co-composting process allowed to maintain
temperature > 45C for more than 30 days.
c) Hence, high removal rate (90 to 100%) was
y
achieved after 80 days.
d) The optimal duration of the composting
process (60 + 30 days) is longer enough for
the inactivation of all helminth eggs.
17
Drying ponds
18
Settling/thickening tanks
Settling / thickening
- 2 settling/thickening units operated alternatively (e.g. 4 weeks loading / 4
weeks drying)
- Performance of the tanks strongly depends on the plants state of
maintenance and operation
- Problem when treating fresh public toilet sludges: bad settling behavior
19
Settling/thickening tanks
20
10
Settling/thickening tanks
Treatmentt options
22
11
[
[mg/l]
15000
10000
5000
0
Influent
16000
14000
12000
10000
[mg/l] 8000
6000
4000
2000
0
Eff.
Eff.
Eff.
Eff.
Eff.
sed. tank pond 1 pond 2 pond 3 pond 4
100
90
80
70
[%] 60
50
40
30
20
10
0
60%
20000
86%
COD total
23
Faecal coliforms
[no./1
100 ml]
1.00E+04
1.00E+03
1.00E+02
1.00E+01
1.00E+00
Influent
Eff.
Eff.
Eff.
Eff.
Eff.
sed. tank pond 1 pond 2 pond 3 pond 4
0%
100
90
80
70
60
[%] 50
40
30
20
10
0
1.00E+05
99%
1.00E+06
24
12
Ammonium
1400
[m
mg/l]
1000
800
600
40%
400
200
0
100
90
80
70
[%] 60
50
40
30
20
10
0
Entire plant Sed. tank
Influent
Eff.
Eff.
Eff.
Eff.
Eff.
sed. tank pond 1 pond 2 pond 3 pond 4
0%
1200
Removal efficiency
25
Anaerobic digestion
Anaerobic digestion
- Energy production
26
13
27
Septage
Sewage
C1
C2
L1
L2
Effluent
Design criteria
-
Accumulation
A
l ti off solids
lid
Depth accumulated solids
~
<
0 02 m3/m3
0.02
3/ 3 FS
0.5 m
~ 0.03 m2/cap
28
14
29
30
15
Treatment
process or
option
Design criteria
Drying/dewater
ing beds
Constructed
wetlands
(planted drying
beds)
100-200 kg
TS/m2/year
0.05
m2/cap(Accra)
250 kg
TS/m2/year
SAR: 20 cm/year
(Bangkok)
Solids-liquid
separation
Organic pollutants
in liquid fraction
Parasites
(helminth eggs)
SS : 60-80 %
COD: 70-90 %
NH4+-N : 40-60
%
To be treated for
further improvement
in ponds or
constructed
wetlands
100 % retained
on top of the
filtering media
SS > 80 %
SAR: 20
cm/year
To be treated for
further improvement
in ponds or
constructed
wetlands
100% retained on
top of the filtering
media
31
Treatment
process or
option
Design criteria
Settling /
thickening tank
Facultative
stabilization
ponds
350 kg BOD5/ha/d
Solids-liquid
separation
Organic pollutants
in liquid fraction
Parasites
(helminth eggs)
SS: 60-70 %
COD: 30-50 %
To be treated for
further improvement
in ponds or
constructed
wetlands
Concentrated in
the settled and
floating solids
N t ffor this
Not
thi
purpose
Removed
R
db
by
settlement
32
16
Drying beds
TS
COD
N-NH4
60
40
50
85
97
75
80
70
50
33
Effluent concentration
TS
Settling/Thickening Tank
(septage+public toilet, 1:1)
Constructed wetlands
(septage)
Drying beds
(mg/l)
(mg/l)
COD
N-NH4
(mg/l)
(ms/cm)
EC
9,000-14,000
7,000-12,000
1,000-2,000
20-25
1,000-6,000
300-500
50-150
3.0-3.5
500-1000
4000-600
300-1500
11-20
34
17
SS
NH4 / NH3
Colouration
Management
Pre-treatment
processes
Solids
production
rate and
handling
frequency
Required
labour
management
input
Hygienic
quality
of
bBiosoli
ds
Quality of
effluent for
posttreatment
Post-treatment requirements
Post- treatment
options for solids
Post- treatment
options for liquids
Remarks
Settling /
thickening
tank
High
medium
low
Low to
medium
Storage
Planted / unplanted
drying beds
Co-composting
Planted /
unplanted drying
beds
Co-treatment in
WSP
Settling /
anaerobic
pond
High
Very High
low
Poor to low
Storage
Planted / unplanted
drying beds
Co-composting
Planted /
unplanted drying
beds
Co-treatment in
WSP
Not recommended as
first treatment
Process impaired by
high FS ammonia
content
Drying /
dewatering
beds
(Unplanted)
High
High
Low to
medium
Medium to
good
Storage
Co-composting
Planted drying
beds
Co-treatment in
WSP
Sand quality
Constructed
wetlands
(planted
drying beds)
Low
Medium
Good to
high
High
Extended storage
Constructed
wetlands or WSP
Technology proven
with specific plants
(Typha and Phragmites)
and Availability of
proven macrophytes
Cocomposing
High
High
High to
very high
No effluent
No further
treatment
Anaerobic
digestion
cum biogas
production
medium
high
Medium good
Medium - good
Planted / unplanted
drying beds
Co-composting
Constructed
wetlands or WSP
36
18
19