Beruflich Dokumente
Kultur Dokumente
V.P.R. ARIYADASA
REPORT
ON
CEB EXPERIENCE
V.P.R. ARIYADASA
ELECTRICAL ENGINEER
LAXAPANA POWER STATION
CEYLON ELECTRICITY BOARD
3RD SEPTEMBER 2013
TABLE OF CONTENTS
1
PERSONAL DATA
0
Experience Report
V.P.R. ARIYADASA
INTRODUCTION
RESPONSIBLE EXPERIENCE
5.1. SITE ENGINEER AT UTHURU WASANTHAYA
5.1.2. ACHIEVEMENTS
5
4.1.3.1. SPILLING OF MAUSSAKELLE RESERVOIR
TH
10
APRIL 2013
10
11
Experience Report
V.P.R. ARIYADASA
..
1.
Personal data
Name
V.P.R. Ariyadasa
E.P.F No
37982
Date of birth
Nationality
Sir Lankan
Education
Membership of
Professional societies
Work Experience
July 2009
:
to date
2.
Bank of Ceylon,
Electrical Engineer
Temporary Instructor,
University of Moratuwa
Introduction
I am pleased to submit this CEB experience report for the consideration of K3 interview
Experience Report
V.P.R. ARIYADASA
Experience Report
V.P.R. ARIYADASA
commissioned in 1983 and 1989 having two vertical fransis turbines with total of 60MW. The
total capacity of the Laxapana complex is 345 MW now.
Laxapana complex has two reservoirs called Catlereigh and Maussakelle and three ponds
called Norton, Canyon and Laxapana.
generation of one power station depends on the annual rainfall, machine outages and running
period of the other power stations. Therefore the operations of all the power stations are
interrelated and are carried out according to the system demand by communicating with system
control centre.
After the general training in the Hydro Power Station I trained in the Laxapana Power
Station as the Operation Engineer for about two months. The important areas that I covered in
this training period are:
Machine & transformer capacities of old Laxapana and new Laxapana power
stations
Water discharge rates, reservoir/pond capacities and spill & operation levels
Auxiliary services cooling water system, service water system, auxiliary power
supply, bearing oil circulation & cooling system, substation lighting.
Protection schemes for machines, transformers and lines alarm and tripping
settings
Documentations log sheets, water level and rainfall book, daily machine and line
outage, monthly statically data, weekly spill data, duty assignment to junior staff.
5.
Responsible experience
Experience Report
5.1
V.P.R. ARIYADASA
Experience Report
V.P.R. ARIYADASA
Experience Report
V.P.R. ARIYADASA
Other than normal construction works, we could achieve plenty of experiences on other
relates subjects as well.
5.1.3.1 Testing of Concrete Poles
The main cost component of the project was the cost for concrete poles.
All the poles were purchased locally and prior to that a CEB official should test the materials
whether those are according to the standards and approve. The testings were mainly done for
8.5m/100kg, 11m/300kg, and 11m/500kg poles.
Other than that, some testings on Galvanised cross arms, Stay assemblies,
etc. were done on request.
5.1.3.2 Way leaves clearing
Before energising a scheme, way leaves must be cleared according to the
standards. Due to the community participation is a must we get together with the villagers and
arrange a campaign to cut way leaves with a guidance of the CEB official.
When the community participation was not available, quotations were
called and arrange contractors to cut the way leaves ensuring the standards.
5.2
plants and equipment in the power station up to the switch yard line isolator and to ensure
personally that the power station contributes its share of the system load as required and
planned up to the maximum at all times.
Experience Report
V.P.R. ARIYADASA
Personally responsible for all operations in the power station and the switchyard when on
shift duty.
To report immediately to the chief engineer or engineer in charge of the power station any
serious defect or breakdown of plant or equipment and to furnish a complete report of the
breakdown.
To restore supply in the shortest possible time in the event of partial or total failure due to
plant of feeder failures.
To isolate and make safe any plant, equipment, switchgear or feeder back into commission
after the maintenance or repair work is over.
To operate an agreed scheme whereby all operating personnel not up to the required
standard could be trained effectively and efficiently to acquire the required competence in
the shortest possible time.
To ensure that the CEB and the factory safety rules and regulations are strictly adhered to.
To maintain records of attendance of operating staff and all statical data (loading of sets,
feeders, water levels etc).
Experience Report
V.P.R. ARIYADASA
essential materials using waybills. Also wayleave clearing also initiated in parallel. The work was
carried out such a way that the line can be reenergized in every night peaks.
After the hard works, the line was completed within 10 days of period. Since we took the
right decision on the right time we were able to accomplish our goal.
5.3.2 Emergency power supply to the Periyamadu Camp
This was happened on in October, 2011. Four day emergency function was arranged in the
Periyamadu camp (in Mannar) requesting immediate power supply from CEB. That time no LT
power line was available only the transformer was installed 2.5km away from the function
location. We had only two days of time period to provide supply.
So we didnt have enough time to construct LT power line for that purpose. So we
discuss with the army and started to draw the LT power line on bare land. Since we used Arial
Bundle Cables (ABC) we had enough insulation without getting earthed. Also arrange some army
people for the protection of the power line, safeguarding power line from the people.
The function was very successful and we were able to provide power supply throughout
the event.
Experience Report
V.P.R. ARIYADASA
Experience Report
V.P.R. ARIYADASA
opening time was not enough in that time. ( normal setting was 60s for 600s) We asked the
ALSTOM officer to increase the opening time for some more time. ( now the setting is 100s for
600s period) The problem solved.
5.3.6 Old Laxapana Stage II machines trip
The O/L Stage II machines no. 04 and no. 05 suddenly tripped at 5.00 a.m. indicating
inverter supply fault. It was very important to restart the machines due to the spilling of Norton
pond because of the heavy rainy situation.
The machine AC pumps were fed by three main supply paths. Default is the feeding AC
supply from the DC battery supply inverted using AC inverters and feed the pumps. Second is
getting AC supply from auxiliary transformer supply and perform AC-AC conversion and feed.
The third and last option is the bypass mode which directly supplies the AC from auxiliary
transformer supply.
In this situation, the initial two options were not supported since the fault remains and
preventing restarting of generators. Only bypass mode was supporting and hence restarted the
machines using that mode and load immediately to reduce the water wastage.
Due to the change of auxiliary transformer lead to trip the machine again instruct
operation staff to be on alert.
11