Beruflich Dokumente
Kultur Dokumente
L-32958
November 8, 1930
BLOSSOM
AND
COMPANY,
INC., plaintiff-appellant,
vs.
MANILA GAS CORPORATION, defendant-appellee.
Harvey
and
O'Brien
for
appellant.
Ross, Lawrence and Selph and John B. Miller for appellee.
STATEMENT
In its complaint filed March 3, 1927, the plaintiff alleges that
on September 10, 1918, it entered into a contract with the defendant
in which the plaintiff promised and undertook to purchase and
receive from the defendant and the defendant agreed to sell and
deliver to the plaintiff, for a period of four years, three tons of water
gas tar per month from September to January 1, 1919 and twenty
tons per month after January 1, 1919, for the remaining period of the
contract; one-half ton of coal gas tar a month from September to
January 1, 1919, and six tons per month after January 1, 1919, for
the remainder of the contract, delivery to be made at the plant of the
defendant in the City of Manila, without containers and at the price of
P65 per ton for each kind of gas tar, it being agreed that this price
should prevail only so long as the raw materials coal and crude oil
used by the defendant in the manufacture of gas should cost the
defendant the same price as that prevailing at the time of the
contract, and that in the event of an increase or decrease in the cost
of raw material there would be a corresponding increase or decrease
in the price of the tar. That on January 31, 1919, this contract was
amended so that it should continue to remain in force for a period of
ten years from January 1, 1919, and it was agreed that the plaintiff
should not be obliged to take the qualities of the tars required during
the year 1919, but that it might purchase tars in such quantities as it
could use to advantage at the stipulated price. That after the year
1919 the plaintiff would take at least the quantities specified in the
contract of September 10, 1918, to be taken from and after January
1, 1919, and that at its option it would have the right to take any
quantity of water gas tar in excess of the minimum quantity specified
in that contract and up to the total amount of output of that tar of
defendant's plant and also to take any quantity of coal gas tar in
excess of the minimum quantity specified in that contract and up to
50 per cent of defendant's entire output of coal gas tar, and that by
giving the defendant ninety days' notice, it would have the right at its
option to take the entire output of defendant's coal gas tar, except
such as it might need for its own use in and about its plant. That in
consideration of this modification of the contract of September 10,
1918, plaintiff agreed to purchase from the defendant of certain piece
of land lying adjacent to its plant at the price of P5 per square meter,
the proof of which is evidenced by Exhibit C. That pursuant to Exhibit
C, defendant sold and conveyed the land to the plaintiff which in turn
executed a mortgage thereon to the defendant for P17,140.20, to
secure the payment of the balance of the purchase price.
It is then alleged:
VIII. That about the last part of July, 1920 the defendant
herein, the Manila Gas Corporation willfully, and deliberately
breached its said contract, Exhibit C, with the plaintiff by
ceasing to deliver any coal and water gas tar to it thereunder
solely because of the increased price of its tar products and
its desire to secure better prices therefor than plaintiff was
obliged to pay to it, notwithstanding the frequent and urgent
demands made by the plaintiff upon it to comply with its
aforesaid contract by continuing to deliver the coal and water
gas tar to the plaintiff thereunder, but the said defendant
flatly refused to make any deliveries under said contract, and
finally on November 23, 1923, the plaintiff was forced to
commence action against the defendant herein in the Court
of First Instance of Manila, being case No. 25352, of that
court entitled 'Blossom & Co., plaintiff, vs. Manila Gas
Corporation, defendant,' to recover the damages which it
had up to that time suffered by reason of such flagrant
violation of said contract on the part of the defendant herein,
and to obtain the specific performance of the said contract
and after due trial of that action, judgment was entered
therein in favor of the plaintiff herein and against the said
defendant, the Manila Gas Corporation, for the sum of
P26,119.08, as the damages suffered by this plaintiff by the
defendant's breach of said contract from July, 1920, up to
1
failure and refusal to perform the same, and the plaintiff has
so notified the said defendant.
It is then alleged:
XIV. That as shown by the foregoing allegations of this
complaint, it is apparent that notwithstanding the plaintiff in
this case has at all times faithfully performed all the terms
and conditions of said contract, Exhibit C, on its part of be
performed, and has at all times and is now ready, able and
willing to accept and pay for the deliveries of said coal and
water gas tars required by said contract and the notices
given pursuant thereto, the said defendant, the Manila Gas
Corporation, does not intend to comply with its said contract,
Exhibit C, and deliver to the plaintiff at the times and under
the terms and conditions stated therein the quantities of coal
and water gas tars required by said contract, and the several
notices given pursuant thereto, and that it is useless for the
plaintiff to insist further upon its performance of the said
contract, and for that reason he only feasible course for the
plaintiff to pursue is to ask the court for the rescission of said
contract and for the full damages which the plaintiff has
suffered from September, 1923, and will suffer for the
remainder of said contract by reason of the defendant's
After the filing and overruling of its demurrer, the defendant filed an
answer in the nature of a general and specific denial and on April 10,
1928, and upon stipulation of the parties, the court appointed W. W.
Larkin referee, "to take the evidence and, upon completion of the
trial, to report his findings of law and fact to the court."
July 18, 1928, the defendant filed an amended answer in which it
alleged as an affirmative defense, first, that the complaint does not
state facts sufficient to constitute cause of action the reason that a
prior adjudication has been had of all the issues involved in this
action, and, second, "that on or about the 16th day of June, 1925, in
an action brought in the Court of First Instance of the City on Manila,
Philippine Islands, before the Honorable Geo. R. Harvey, Judge, by
Blossom & Company, plaintiff, vs. Manila Gas Corporation,
defendant, being civil case No. 25353, of said court, for the same
cause of action as that set fourth in the complaint herein, said plaintiff
recovered judgment upon the merits thereof, against said defendant
decreeing a breach of the contract sued upon herein, and awarding
damages therefor in the sum of P26,119.08 with legal interest from
November 23, 1923, and costs of suit, which judgment was upon
appeal affirmed by the Supreme Court of the Philippine Islands, in
case G. R. No. 24777 of said court, on the 3d day of March, 1926
and reported in volume 48 Philippines Reports at page 848," and it
prays that plaintiff's complaint be dismissed with costs.
After the evidence was taken the referee made an exhaustive report
of sixty-pages in which he found that the plaintiff was entitled to
P56,901.53 damages, with legal interest from the date of the filing on
the complaint, to which both parties filed numerous exceptions
3
x xx
x xx
and that the letter of June 25, 1926, and the subsequent
demands, with exception of the letter of July 31, 1926, were
not made in pursuance to the terms of the contract, and that
defendant had no liability in refusing to comply therewith,
and in allowing plaintiff damages only for the failure of the
defendant to deliver quantities shown in Exhibits Ref. 21 and
22. (See pages 51, 52, Referee's report.)
IX. The trial court erred in finding and holding that the
demands of plaintiff for additional tars under its contract with
the defendant were extravagant and not made in good faith,
and that when it wrote to defendant that it desired maximum
quantities of coal gas tars and only minimum of water gas
tars, but with the reservation of going back to minimum
quantities of both at any time it chose, it announced its
intention f breaching the contract, and defendant was under
no obligation to deliver maximum quantities of either tars,
and since this was the efficient cause of the failure of
defendant to deliver or plaintiff to accept tars, the blame is
attribute to plaintiff, and it cannot recover for a rescission.
x xx
x xx
x xx
P38,134.60
16,547.33
2,219.60
or a total of
56,901.53
Ref:http://www.lawphil.net/judjuris/juri1930/nov1930/gr_l32958_1930.html
5