Beruflich Dokumente
Kultur Dokumente
: 26513265
e- mail: nrpcprotection@gmail.com
Fax : 26865206
Website : www.nrpc.gov.in
18-, , 110016
Government of India
Northern Regional Power Committee
18-A, Shaheed Jeet Singh Marg, Katwaria Sarai, New Delhi-110016
No. NRPC/OPR/107/01/
Dated: 09.07.2012
FAX MESSAGE
From : Superintending Engineer (O), NRPC.
To
: Members of Protection Sub-Committee
1. Director (P&C)/BBMB, Chandigarh, Fax-0172-2652054
2. SE (Elect. Op), UT of Chandigarh, Chandigarh - 160 009, Fax-0172-2740505
3. General Manager (O&M) DTL, New Delhi, Fax-23221059
4. GM (SLDC), Delhi Transco Limited, New Delhi, Fax-23221059
5. GM (T), Common Services IPGCL, New Delhi,, Fax-23370247
6. Chief Engineer (TS), HVPNL, Panchkula, Fax-0172-2591244
7. SE (M&P), HVPNL, Dhulkote , Haryana, Fax-0172-2540014
8. SE (PPM), Haryana Power Generation Co. Ltd., Panchkula , Fax-0172-2586836
9. Director (Technical-II), UHBVN, Panchkula, Fax-0172-3019112
10. Chief Engineer (Transmission), HPSEB, Hamirpur, Fax-01972-223435
11. Chief Engineer (Comml. & Survey Wing) PDD, Jammu, Fax-0191-2474233
12. Chief Engineer (P&M),PSEB, Ludhiana , Fax-0161-2741280, 2451491
13. SE (Protection), RRVPNL,Jaipur, Fax-0141-2296755
14. SE (Protection), RRVUNL,Suratgarh, (Rajasthan), Fax-0141-2740920
15. Managing Director, JVVNL, Jodhpur, Fax-0291-2741870
16. Superintending Engineer (T&C), UPPCL, Meerut (U.P.), Fax-0121-2666062
17. Chief Engineer, (L-2), UPRVUNL Lucknow, Fax-0522-2287822, 2287880
18. MD, Dakshinanchal Vidyut Vitran Nigam Ltd.,Agra, Fax-0562-2605465
19. DGM (T&C), PTCUL, Dehradun, Fax-0135-2760331
20. DGM (In-charge), Yamuna Valley, UJVNL,Dehradun, Fax-0135-2763507
21. Chief Engineer (O&M), NHPC ,Faridabad, Fax-0129-2272413
22. Chief Engineer (O&M), NPCIL, Mumbai, Fax-022-25563350
23. GM (O&M) NR I, PGCIL, New Delhi , Fax-011-26601079
24. GM (O&M), NR-II, PGCIL, Jammu, Fax-01951-237186
25. Chief Manager (TS), N.R.L.D.C, New Delhi, Fax- 011-26852747
26. GM (OS) NTPC Ltd.,Noida, Fax-0120-2410082, 2410068
27. DGM (Maintenance), SJVNL, New Shimla, Fax- 0177-2673283
28. Director (GM division), CEA,New Delhi, Fax-011-26109750
...................................................................................................................................
th
Sub:-Minutes of the 17 Protection sub Committee Meeting held on 24th April, 2012.
th
The 17 Protection sub Committee Meeting was held on 24th April, 2012 at NRPC, New
Delhi. The minutes of this meeting can be downloaded from NRPC website at
http://www.nrpc.gov.in.
Sd/(Ajay Talegaonkar)
Superintending Engineer (O)
The 17 Protection sub Committee Meeting was held on 24th April, 2012 at
NRPC, New Delhi. The list of participants is enclosed at Annex-I.
A.1 CONFIRMATION OF MINUTES OF 16th MEETING OF PROTECTION SUB
COMMITTEE.
The sub-committee confirmed the minutes of 16th meeting of PSC, held on 22nd
December, 2011, which were issued vide letter No. NRPC/SE (O)/OPR/107/01
dated 13.03.2012.
B.
This end
Other end
Status of carrier
protection
Jamalpur-Dhandari-I&II
BBMB
PSTCL
Not Available
Jalandhar-Butari
BBMB
PSTCL
-do-
Jalandhar-Jamsher-I&II
BBMB
PSTCL
-do-
BarnalaLehraMohabbat
BBMB
PSPCL
-do-
Samaypur-Badshahpur
BBMB
HVPNL
Not Available
Samaypur-Palwal-I&II
BBMB
HVPNL
-do-
Samaypur-Palli-I&II
BBMB
HVPNL
-do-
Bhiwani-Bapora-I&II
BBMB
HVPNL
-do-
SE(O), NRPC requested PSTCL and HVPNL to brief the sub-committee about
latest status.
Representative of PSTCL informed that PLCC of 220 kV transmission lines
Jalandhar-Butari, Jalandhar-Jamsher-I&II and Jamalpur-Dhandari-I are now
functional and PLCC of transmission line Jamalpur-Dhandari-II would be functional
by first week of May, 2012. He further informed that issue of non-functionality of
220 kV BarnalaLehra-Mohabbat line was taken up with PSPCL but their reply is
awaited.
Representative of HVPNL informed that the case for procurement of necessary
equipments for transmission lines at Sr. No. 5, 6, 7 is under process and it would
take another six months to complete the work. Further he informed that BhiwaniBapora-I&II is radial line and does not require single phase auto reclosure scheme.
B.1.2.2 With regard to tele-protection scheme, DTL informed that communication
channel for the same would be fibre optic cables being laid by POWERGRID under
ULDC phase-II.
B.1.2.3 With reference to implementing Single Phase Auto Reclosure Scheme on
lines emanating from RAPP-B, representative of POWERGRID informed that same
has been made operational by NPCIL on RAPP-B - Chittorgarh line.
B.2 commissioning of carrier scheme on Transmission Lines
B.2.1 SE(O), NRPC stated that in 15th PSC meeting held on 18.08.2011, PSTCL
had stated that during commissioning of carrier schemes on transmission lines
connected with POWEREGRID, it had been observed that in some cases the
Direct Trip signal was through TNC handle while in some cases it was through
distance relay with command being issued on operation of Distance Protection
Relay (DPR) in zone-II or zone III or on directional earth fault or Switch On To
Fault (SOTF). He had requested for a clear directive on this issue. In the same
meeting POWERGRID had stated that they would consider the issue raised by
PSTCL and would respond in the next PSC meeting.
As no consensus could be reached in 16th PSC meeting held on 22.12.2012, a
sub-group was constituted with following members:
1. Sh. Kuleshwar Sahu, CM, POWERGRID
2. Sh. Rajbir Singh, EE, PSTCL
3. Sh. Kavinder Singh, SE, UPPTCL
4. Sh. M. K. Singhal, SE, RVPNL
5. Sh. T. Muthu Kumar, Sr. Engg. , NRLDC
A meeting of the sub-group constituted by PSC to discuss the issue of Direct Trip
signal through TNC handle and through distance relay was held on 24.04.2012 at
15:00 hrs after 17th PSC meeting. The sub-group recommended that for 220 kV
lines Direct Trip (DT) signal would be sent to other side breaker only in case of
operation of Bus-Bar protection and LBB protection and no DT signal would be
sent through TNC handle or on operation of Distance Protection Relay (DPR) in
zone-II or zone III or on directional earth fault or Switch On To Fault (SOTF).
C . N E W
I T E M S
F O R
D I S C U S S I O N
and further as these equipment are in critical and important 400 kV links, it is
suggested that 60 % of these shall be shifted and relocated for important 220 kV
links, and 40% can be retained as spares. The 400 kV links shall be provided with
new ABB make ETL carriers and NSD 50 protection couplers, which are found to
be very reliable and stable.
c) It is recommended that a 4 member team in Protection and communication
shall be trained on testing and maintenance of Power line carriers and protection
couplers. This team shall further train Engineers at respective stations for routine
testing and fault detection.
PSC Deliberation: PSC agreed that a dedicated team of expert with all necessary
testing and other equipments is required. Almost all utilities have such a team of
expert to look after the healthiness of PLCC. Recommendation no 13.3(b) is DTL
specific and is not valid for other utilities.
Recommendation No. 13.7- Disturbance Recorder and Event Logger
healthiness and suitability
Where ever static relays are present, the details of which are presented in section
6.3, they are to be replaced by Numerical relays with suitable IRIG-b and SNTP
cards. Existing numerical relays are to be upgraded with IRIG-B and SNTP cards
as all of the existing numerical relays do not have the time stamping features.
PSC Deliberation: Disturbance Recorder and Event Logger is a primary
requirement for all utilities. The availability and healthiness of DR/EL is being
regularly monitored at OCC and PSC level regularly.
Recommendation No. 13.8- Time synchronizing unit:
SNTP & IRIG-B protocol facility shall be enabled in the TSU in all 220 & 400 kV
substations.
PSC Deliberation: Numerical relays are having Time synchronizing facility.
Recommendation No. 13.9- Field test procedure for Relays
It is recommended that periodic maintenance testing shall be carried out once in a
year for Electro mechanical relays and once in 2 years for numerical relay.
Trending of performance data shall be carried out which will provide an
understanding of relay performance deviation over time required for judging the
status and predicting possible mal functioning. The detailed test procedures
formats (format 1- format 18) for different relays used in DTL system in the section
Date
29-May11
Detais of tripping
Multiple tripping at
400/220kV
Muradnagar
& Moradabad
(UPPTCL)
1-Sep-11
Multiple tripping at
220kV Mainpuri, (U.P)
Sub-station
Station/
Utility
UPPTCL
UPPTCL
Remarks
Report
awaited.
Report
awaited.
Remark/Analysis
in
PSC
Breakers at both end for
400 kV MuradnagarDadri line were already
opened and were being
closed. Earth link of 400
kV bus-B was wrongly
closed due to which
remote
end
breaker
tripped.
Bus
Bar
protection not working
A transient fault on 220
kV
bus
tripped
all
connected feeders. No
abnormality observed on
the bus.
13-Sep11
Tripping of lines in
220kV U.P grid &
tripping of ICTs at
400/220kV
Mainpuri Substation
UPPTCL
20-Sep11
Loss of generation of
240 MW at Parichha
TPS
UPPTCL
31-Aug11
Multiple tripping,
generation loss & load
loss in western U.P
UPPTCL
Uncleared
fault in
220kV
line in
U.P
system
lead to
tripping
of
Mainpuri(
PG)
ICT#1 &
2 on
backup
protectio
n. Report
from
UPPTCL
awaited.
Report
awaited.
Report
awaited.
Report awaited.
14-Nov11
Multiple tripping at
400kV Mau (UPPTCL)
Substation
UPPTCL
Report
awaited.
400 kV Mau-Azamgarh
line
tripped
from
Azamgarh end on Rphase fault but line did
not trip from Mau end
resulting in tripping of
400 kV Mau-I and Mau-II
lines
from
400
kV
Ballia(PGCIL) substation
in Zone-II. Later on
investigation
revealed
that Main-I protection
(RAZFE) at Mau end
failed to issue final trip
command and the Main-II
protection (SIPROTEC)
failed to operate on
account of D.C. failure.
Patrolling of the MauAamgarh line was carried
out and R-phase disc
insulator string found
damaged at one of the
tower
which
was
attended and this line
was finally charged on
the same day. Later on
distance protection at
Mau end were tested and
found in order.
Mau line had tripped during the incident. 400kV Anpara-Sarnath ckt-2 was out of
service.
In 71st and 72nd OCC meetings, UP SLDC was asked to analyze the
incident, and submit a detailed report. UPPTCL had submitted their report dated
26.03.2012. As per report transient fault had occurred in 400kV Anpara-Mau line.
The fault was close to Mau end. Zone-1 had operated at Mau end and Zone-2
picked up at Anpara end. Instantaneous tripping through Carrier aided tripping
could not be achieved at Anpara end due to unhealthy PLCC link and Anpara end
tripped in Zone-2. Generator neutral over-current had picked up for all the three
210 MW units which led to their tripping. UPPTCL has referred the matter
regarding the setting for Generator Neutral Over current relay to the Protection
Sub-Committee.
SE(O), NRPC requested UPPTCL to appraise PSC about the healthiness of
PLCC link & testing of distance protection relays of 400kV Anpara-Mau line
Representative of UPPTCL informed that PLCC end-to-end CIT tests were
conducted in the first week of April 2012 during shutdown of the above line. Defect
identified in CIT Protection coupler scheme at Anpara end has since been
attended and scheme was made operational. He further informed that existing
PLCC system ETI-21 has become old and obsolete and UPPTCL has initiated
action for its replacement. Further checking of Main-I distance protection RAZFE
at 400 kV Azamgarh substation for 400 kV Mau feeder has been carried out on
13th April, 2012. Slight re-adjustment in relay setting has been carried out and the
behavior of distance protection is under observation. The Main-II distance
protection SIPROTEC has also been tested and relay behavior has been found to
be in order.
Further SE(O), NRPC informed that Chief Engineer, Anpara Thermal Power
Station in his letter dated March 15th, 2012 to SE(O), NRPC has requested for
consent to replace the present IDMT electromechanical relay to a definite type
digital or solid state O/C relay with time delay of 1.0 sec. and current setting of 0.4
Amps.
After detailed deliberations, PSC was of the view that IDMT type
characteristic would be more suitable for the purpose. The setting of relay should
be such that its operating time is more than the operating time of
a. Line distance protection relays Zone-3 time for a fault in the line
b. Line Back Up E/F relays highest operating time for a fault in the line
c. Highest operating time of IDMT E/F protection of ICTs at the local as
well as remote bus
reported that Bus-bar protection had operated at Salal HEP. Similar incident of
complete outage had occurred at Salal HEP on 8th and 11th May 2011.
Representative of NHPC had informed in 72nd OCC meeting that all outgoing lines
from Salal had tripped on over-voltage. He requested NHPC to appraise PSC
about the status of healthiness of EL & DR at Salal HEP.
Representative of NHPC informed that due to over-voltage, the distance
protection relay MiCOM had operated. The settings of over-voltage relay for stageI is 110% with 05 sec. delay and stage-2 is at 150% with 100 msec. delay.
PSC was of the view that NHPC should either disable the over-voltage relay
at 220 kV level or if it is be to used then setting of different circuits of same line
should be based on voltage grading.
Regarding EL, representative of NHPC informed that they had awarded the
work of repair of EL and same would be repaired soon.
C.3.5 Complete outage of 400/220kV Allahabad (P.G) Substation at 5:39 hrs.
on 14th January 2012.
400kV Allahabad-Sarnath, 400kV Singrauli-Allahabad ckt-1&2, Rihand-Allahabad
ckt-1&2, Allahabad-Mainpuri ckt-1&2, 400kV Allahabad-Sasaram, 400kV
Allahabad-Kanpur ckt-2, 400kV Allahabad- Fatehpur ckt-3 had tripped during the
incident. As reported the breaker of 400kV Allahabad-Sarnath line was under
lockout at 400kV Allahabad (P.G) end. The triggering incident of fault was
flashover in isolator connecting 400 kV Allahabad-Sarnath line with BUS-1 at
Allahabad. This flashover occurred while opening isolator in charged condition
(Main circuit breaker of this line was under lockout). This resulted into a fault which
led to tripping of all feeders from 400/220kV Allahabad(P.G) substation.
Representative of POWERGRID had stated in 72nd OCC meeting that LBB
could not operate due to peculiar behavior of the relay. Distance protection relay
for Allahabad end lines gave continuous command for 154 m-sec but LBB
operations requires 200 m-sec for it operation. Again distance relay gave
command to LBB for operation but timing of command was less than 200 m-sec
because of which LBB could not operate. All lines connected to Allahabad tripped
in Zone-2 i.e. around 500 msec. Third time relay had picked up for 217 m-sec and
this time LBB operated. Due to non-operation of main-1 protection for more than
200 m-sec, Bus-Bar protection could not be operated. The matter of peculiar
behavior of relay was referred to ABB by POWERGRID and it was stated that
response from ABB was awaited.
It was decided in 72nd OCC meeting that the matter would be discussed
Protection sub-Committee. SE(O), NRPC requested POWERGRID to appraise
PSC about their findings. Further, he stated that 400kV Singrauli-Allahabad Ckt-
1& 2 tripped from Singrauli STPS end within 100ms of occurrence of fault. This
Protection operation at Singrauli end needs investigation. He requested NTPC to
appraise PSC about the findings
Representative of POWERGRID stated that ABB had informed that the ratio
of voltage and current during the fault condition was well within the reach of relay
that is why it operated. But the issue as to why fuse failure indication appeared on
the panel although no fuse failed is still awaited from ABB.
Representative of NTPC indicated that due to non receiving of carrier signal
at Singrauli end within 100 msec. relay did not block the breaker from tripping.
C.4 Additional tripping
The following additional tripping were discussed:
C.4.1 Tripping of ICT's at 400/220kV Muradnagar Substation (UPPTCL) on
12th February 2012 at 10:20hrs
SE(O), NRPC stated that fire in 220kV side CT of 400/220kV ICT-1 led to
tripping of ICT-2 & ICT-3 at 400/220kV Muradnagar Substation. The concerned
agency (UPPTCL) may appraise the PSC and forward the detailed analysis report
to NRPC/ NRLDC along with the printouts of DR/EL.
Representative of UPPTCL informed that Y phase CT of the Transfer Bus
Coupler caught fine resulting into tripping. The CT was 32 year old and same was
replaced.
C.4.2 Generation loss at Dadri TPS at 17:40 hrs on 13th March 2012
All running units of Dadri generation complex (except GT#4 of Dadri GPS)
tripped causing generation loss of 2650 MW. HVDC Rihand Dadri Bipole also
tripped during the event. The SPS of HVDC Rihand-Dadri had operated causing
generation reduction in Singrauli/Rihand STPS and load shedding in Western part
of NR.
As per Fax message received from NTPC on 14th March 2012
i.
Earth switch remained closed while restoring back 400kV Bus-2 after
shutdown.
ii.
Bus-Bar protection of 400kV Dadri 400kV bus-1 operated due to zero time
delay in LBB relay. This caused outage of entire station
iii.
Fault current recorded was 53 KA
NTPC representative stated that 400 kV Dadri Bus-II was under shutdown work
was carried with local earthing. After the work was over bus fault occurred while
charging the bus as local earth connection was not removed. Thereafter Bus Bar
protection of Bus-1 also operated due to operation of LBB relay as no time delay is
there in LBB protection. This resulted in complete outage of Dadri station. He
further informed that no equipment was damaged and fault current was within the
limit of equipment. EL was not working.
PSC was of the view that such human error should be avoided and communication
should be clear and proper. If required , manpower could be trained for the same.
C.4.3 Generation loss, load loss and tripping of 220kV lines in Delhi system
on at 19:08hrs on 3rd April 2012
Tripping of Pragati Gas units 2&3, Rajghat TPS units 1&2, tripping of 220kV
mandola-wazirabad ckt-1, 2,3&4 had occurred during the incident. Generation loss
of 300 MW and load loss of 700MW occurred during the incident.
DTL had sent a report. However no D.R/E.L print was enclosed with the report.
According to report, conductor snapping had occurred in 220kV Madola-Wazirabad
ckt-4 & 220kV Mandola-Wazirabad ckt-3 also tripped as the snapped conductor
had fallen on this line which led to their tripping. 220kV Mandola-Wazirabad ckt1&2 had tripped from Mandola end on distance protection. This led to islanding of
Pragati and RPH units and later their tripping.
SE(O), NRPC requested DTL to clarify following points:
a. Distance protection had not operated at Wazirabad end for 220kV
Mandola-Wazirabad ckt-3.
b. Tripping of 220kV Mandola-Wazirabad ckt-1&2 from Mandola end as
the fault was in 220kV Mandola-Wazirabad-ckt-3&4.
Representative of DTL informed that line tripped from Mandola end due to
mis-match of setting of Distance protection at Mandola and Wazirabad. The same
is being discussed with POWERGRID and outcome would be conveyed to NRPC
Secretariat and NRLDC.
C.4.4 Tripping of 400kV lines and ICT's at 400/220kV Azamgarh (UPPTCL)
substation on at 00:43hrs on 4th April 2012
SE(O), NRPC stated that 400kV Azamgarh-Sultanpur, 400kV AzamgarGorakhpur(UPPTCL), 2 No. ICT's at Azamgarh Substation had tripped during the
incident. Reportedly the triggering cause was failure of CT at Azamgarh
Substation. He requested UPPTCL to appraise the PSC and forward the detailed
analysis report to NRPC Secretariat/ NRLDC along with the printouts of DR/EL.
Representative of UPPTCL stated that on 04.04.2012 at 00:42 hrs, 315
MVA, 400/220/ kV and 240 MVA, 400/220 kV ICTs at 400 kV Azamgarh substation
tripped due to damaging of B-phase 220 kV side CT of 315 MVA ICT. The 315
MVA ICT tripped on Differential Protection while 240 MVA ICT tripped on Back up
Earth Fault protection. Both ICTs were charged after replacing and testing the
damaged CT.
C.4.5 Tripping of 400kV lines and load loss in U.P Load loss 01:27 hrs on
02nd April 2012
SE(O), NRPC stated that 400kV Dadri-G.Noida, Ballabgarh-G.Noida,
3x315MVA 400/220kV ICT's at G.Noida tripped during the incident. Load loss in
U.P was approximately 400MW.
NTPC,Dadri had sent a preliminary report in which it was stated that failure
of R-Phase L.A of 400kV Dadri-G.Noida line occurred at Dadri end. Line autoreclosed but tripped due to sustained fault.
UPPTCL was requested brief the PSC about following:
a.
Tripping of ICTs at Greater Noida
b.
Tripping of 400kV Ballabgarh-G.Noida line
Representative of UPPTCL informed that at 400 kV Greater Noida
substation 400 kV Dadri CB was sluggish due to manufacturing defect in its
tripping plunger which has been set right. He further informed that HS element of
Direction Earth Fault relay of 400 kV Dadri line operated due to low time setting
which has been increased from 200 msec. to 800 msec.
C.4.6 Tripping of 400kV lines & Generation loss RGTPP, Khedar at 10:12 hrs
on 5th April 2012
SE (O), NRPC stated that tripping of 400kV Khedar-Kirori ckt-1&2, 400kV
Khedar-Fatehabad ckt-1&2, running units at RGTPP (Khedar)had occurred during
the incident. Generation loss of 1130MW had occurred at RGTPP, Khedar. As
reported, triggering cause was operation of Busbar protection at 400kV Khedar
(HVPNL). He requested HVPNL to appraise the PSC and forward the detailed
analysis report to NRPC Secretariat / NRLDC along with the printouts of DR/EL.
Representative of HPGCL informed that on 05.04.2012 at 10:12 hrs.
both units at RGTPP station were running at 600 MW each. Generator
Transformer Unit-II bay was feeding to Bus-II at 400 KV Switchyard. Suddenly it
was found that R-phase bus isolator of GT-2 bay was sparking severely. Load of
GT-2 was tried to shift on Bus-I. During change over, due to unbalance current,
bus bar protection operated and consequently both units tripped.
D.1.1 SPS at 400 kV Bamnauli Sustation
Representative of DTL informed that in view of the loading pattern and
system conditions at 400 kV Bamnauli Sub-station, there is an urgency of
implementing SPS already approved in 16th TCC and 17th NRPC meeting. He
proposed that the PLC, transducers and RTU meant for SPS at Maharani Bagh
which have already been procured by POWERGRID could be diverted to
Bamnauli. DTL would arrange these equipment for SPS at Maharani Bagh in due
course. He informed that the matter has already been discussed with
POWERGRID. PSC recommended that in view of the system conditions PLC,
transducers and RTU can be diverted from Maharani Bagh to Bamnauli. PSC also
requested DTL to initiate the early procurement action so that SPS at Bawana substation (DTL) and at Maharani Bagh sub-station (POWERGRID) also get
implemented in accordance with the decision taken by NRPC.
D.1.2 Non availability of Auto Recloser scheme on 220 kV POWERGRID lines
terminating at UPPCL end (Agenda by POWERGRID)
Representative of POWERGRID informed that certain lines emanating from
POWERGRID end and terminating at UPPTCL end don not have Auto Recloser
facility at UPPTCL end. List of such transmission lines is enclosed as Annex-III.
Representative of UPPTCL informed that Auto Recloser on lines at Sr. No
8, 9, and 10 would be made operational by June, 2012 and on 220 kV MerrutModipuram line by the first week of May, 2012
Designation
DGM (NCR-OS)
DGM (OS)
AGM (OS)
Organization
NTPC
NTPC
NTPC
Mobile
9650993073
9415005883
9650990308
E-mail ID
anmol.sandhi@yahoo.com
Arun Kumar
Narender Sharma
P. K. Paliwal
XEN/M&P
XEN/M&P
SE M&P
HVPNL
HVPNL
HVPNL
9315315617
9354194827
9354112531
xencchrr@yahoo.co.in
mpccrtk@yahoo.co.in
T. Muthu Kumar
Dy. Mgr.
NRLDC
9650446415
V. V. Sharma
Rajiv Porwal
Ajay Kumar Gola
Kuleshwar Sahu
N.K. Bhardwaj
GM
CM
Sr. Mgr. (O&M)
Chief Mgr (OS)
Sr. Manager (E)
NRLDC
NRLDC
POWERGRID
POWERGRID
NHPC
9873549064
9871581133
9899555175
9419217140
09560033939
Pintu Das
Rakesh Sharma
Sr. Engr./NJHPS
Dy. C.E.
SJVNL
PSTCL
9418475284
09646118204
Sr. XEN
PSTCL
09646118223
C N Banerji
E. K. Kapoor
SE (T&C)
SE, T&C, Agra
UPPTCL
UPPTCL
09415311083
8874204464
Deepak Kumar
SE (Elec.) Anpara
TPS
UPRVUNL
09415900248 dkbgp@rediffmail.com
AE (E)
GM(SLDC)
DGM
HPSEBL
DTL
DTL
01972-221150
9999533629
9540040640
B. L. Gujar
Manager(T) Prot.
DTL
9999533985
se.ptch11@gmai.com
roopkumar2008@gmail.com
dgmprotection@gmail.com
bharatlalgujar@gmail.com
Prem Prakash
GM(O&M)
DTL
9999533630
premnimbekar@yahoo.com
Raghuvendra
Singh
Sukhvinder Kumar
CE(MP&S)
RRVPNL,
Jaipur
BBMB
09414061411
ce_m&p@rvpn.co.in
9810239848
sk_badhan@yahoo.com
HPGCL
9315164619
vinitmishra@hpgcl.gov.in
HPGCL
9315154765
skataria.engg@gmail.com
Vinit Mishra
Addl. SE/Dy.
Director
XEN (Switchyard),
RGTPP
Sumit Kataria
AE(Switchyard)RG
TPP
P. K. Pahwa
MS
Ajay Talegaonkar SE(O)
NRPC
NRPC
mohdzia@ntpc.co.in
ppfrancis@ntpc.co.in
semphse@yahoo.co.in
t_muthukumar80@yahoo.co.in
vvsharma@powergrid.india.com
rajivporwal@gmail.com
ajay514@yahoo.co.in
kuleshwars@gmail.com
nkbhardwajnhpc@rediffmail.com
pinturanjan@yahoo.co.in
sepmldh@pstcl.org
xenprotectionludhiana@yahoo.in
setcald@gmail.com
setncagra@upptcl.org
Annexure-I
Details of Relay and Setting
S.
No
Description of
line (example)
400KV DadriMandola-I
Mandola end:
Name of
protection
relay(Mod
el/Ma ke)
Zone Settings
Zone 1
e.g.
Main-I:
REL670
(ABB
make)
FFR
Power Swing
Blocking
Operation
Operation
ON/OFF
Reach(%)
ON/OFF
Carrier
Scheme
PUR/POR/
PBR
Op. Mode
Time sett.
Zone 2
B/U Over
Current
Function
B/U Earth
Fault Function
SOTF
Broken
Conductor
A/R
Stub
Protection
Over- Votage
Protection
Operatio
n
Operation
Operation
Operation
Operation
Operation
Operation
ON/OFF
ON/OFF
ON/OFF
ON/OFF
ON/OFF
Mode:
ON/OFF
ON/OFF
First
Stage
In case of
Blocking
Scheme;
Relay
coordination
time.... ms
Zero seq
3U0>%Ubas e
Reach (%)
Dir. Mode:
OFF/ NonDirect./FW
D/REV
First Stage
Dir. Mode: OFF/
NonDirect./FWD/REV
Blocking zones:Z1,
Z2, Z3
IDMT
IDMT
I1 (PMS)...%In
t1 (TMS)...
In1 (PMS)....%In
Zone 3
Second
Stage
Second
Stage
Reach (%)
Dir. Mode:
OFF/ NonDirect./FW
D/REV
Definite
time
Definite time
Zone 3
Reach (%)
t1 (TMS)-
Time sett.
400KV DadriMandola-I
Mandola end:
Time sett.
e.g.
Main-II:
MICOM
(AREVA
make)
U< % Ubase
I>%Ibase
3I0< %Ibase
Time sett.
I2- ....Amps
In2-.... Amps
t2(definite
time delay)....sec
t2(definite time
delay)....sec
I> %Ibase
1PH/3-PH/
Dead time:....
sec
Reclaim Time:
.... sec
Stage-1
U1>% volts
Stage-1
time delay:
....sec
Stage-2
U2>%volts
Stage-2
time delay:
...sec