Method Statement for


Asphalt Paving Works
Civil Engineering
bySamMalhotra
Advertisements:

OnlineConstructionClass
Blueprints,Estimating,Materials:EarnYourSDSUCertificateNow!

MethodStatementforAsphaltPavingWorksaregivenbelow:

1.Scope:
Thescopeofworkofthismethodstatementistodescribethe
responsibilitiesofpersonnelinvolved,executionprocedure,safety
factorsanddocumentstoberecordedforAsphaltPavingWorks.

2.RelevantProcess/Specifications:
TenderSpecifications

3.Responsibility:
TheConstructionManager/ProjectEngineerisresponsibleforthe
asphaltpavingworks.
TheCivilConstructionContractorsSafetyOfficershallensurethat
necessaryworkpermitsareavailedbeforetheworkcommencesand
thattheworkiscarryingoutinsafemanner.
Theresponsibilityofthesurveyactivitieslieswithasphaltpavingwork
subcontractor.Thesurveyteamofcivilconstructioncontractorshall
verifythedatafrequently.
InspectionandtestingactivitiesshallbecontrolledbytheQCEngineer
ofCivilConstructionContractorthroughthesitelaboratoryof
http://www.shareyouressays.com/117121/methodstatementforasphaltpavingworkscivilengineering

1/7

6/16/2015

MethodStatementforAsphaltPavingWorksCivilEngineering

Company.

4.PlantsandEquipment:
Bitumenspraytankers,asphaltpaver,Tandemsteelroller,handrollers,
asphaltbatchingplant,etc.

5.ExecutionProcedure:
PriortoCommencement:
Safety:
Primeimportanceshallbegivenforpersonnelsafetyandprotectionof
utilitylines/services.Itshallbeensuredthatthepersonnelinvolvedare
awareabouttheCompanySafetyregulationandconfirmthatthe
machineriesareregularlymaintained.Furthertoabove,thefollowing
keypointsshallbeconsideredimportant.
a.Copiesofdrivers/operatorslicensevehiclesregistrationandsecurity
passestobesubmittedtoCompanysafetydepartmentbefore
commencingthework.
b.Allmovingvehicle/equipmentshallhavereversehorn.
c.Transportingofpersonspervehicleisrestrictedtothenumberof
seatbeltsavailableinthepickup.
d.Deepexcavationsshallbeadequatelyshored,barricadedand
warningsigns&lightsshallbeposted.
e.Roadsafetysigns/roaddiversionsignsshallbeinstalledwherever
applicableforthesafemovementofvehiclesandequipment.
f.AllmajorequipmentshallbetestedandcertifiedbyThirdPartyprior
tomobilizationtosite.
ExistingServicesandFacilities:
a)Beforecommencementofthework,ascertainthenatureandlocation
ofallexistingaboveandundergroundservicesatsitebyvisualsurvey
andreviewingtheservicelayoutdrawing(ifavailable)
Ifanyprotection,rerouting,terminationorremovalsofservicesare
requiredforthesmoothprogressingofwork,itshallbediscussedand
http://www.shareyouressays.com/117121/methodstatementforasphaltpavingworkscivilengineering

2/7

6/16/2015

MethodStatementforAsphaltPavingWorksCivilEngineering

writtenapprovalshallbeobtainedfromemployer/companyas
appropriate.Forserviceprotection,approvedmethodofprotectionshall
beadopted.
b)Awarningtapeshallbetiedatadistanceof2metersawayfromthe
services/aswarningsign,torestrictthemovementoftheequipment.
Survey:
a)Establishandprotectsufficientnumberofstationstoreestablishthe
stationsiftheyaredisturbedduringwork.
b)Postwoodenstackforlineandgradientoftheroad.
c)Theexistingsandtracksshallbeblocked,reroutedandtraffic
diversionsignsshallbepostedpriortothecommencementofthework.
InProcessProcedure:
Theexecutionproceduresshallbedividedintofollowingsections,
whichare:
a)PrimeCoat.
b)Bindercourse.
c)Tackcoat.
d)Wearingcourse.
a)PrimeCoat:
QualityofPrimershouldbeasperBS1707or1S:217,IS:454andIS:
8887.
Immediatelybeforeapplyingtheprimecoat(whichshallbepreliminarily
approved),thefullwidthofthesurfaceshallbecleanedwith
compressedair.
i)Thebituminousmaterialfortheprimecoatshallbeappliedbymeans
ofbitumenspraytankers.
ii)Thisshallbeappliedinasinglelayerattherateof0.71.5liters
/sq.mandatatemperaturenotexceeding70C.Thissurfaceshallbe
curedfor24hours.
http://www.shareyouressays.com/117121/methodstatementforasphaltpavingworkscivilengineering

3/7

6/16/2015

MethodStatementforAsphaltPavingWorksCivilEngineering

iii)Theoverspreadareashallbecuredmorethan24hours/until
excessprimecoatisevaporated.
b)BinderCourse:
QualityofBindershouldbeasperAASHOT182orIS:73,IS:
217,1S:454andIS:8887.
i)Immediatelybeforepavingthebindercoursematerial,thesurfaceof
theprimecoatshallbecleanedwithcompressedairandshallbe
ensuredthatthesurfaceisdry.
ii)Thehotasphaltmixshallbebroughtfromthemixingplantby6
wheeltrucksortrailers.Uponarrivalatsite,theasphaltmixshallbe
dumpedintotheasphaltpaver.
iii)Theasphaltpavershalllaythematerialtotherequiredthickness
andlevel.
iv)Themixshallbecompactedassoonaspossibleafterspreadingthe
material.Tandemrollersshallfollowthelayingoperationtocarryout
breakdownrollinguptotemperatureof110120C.Pneumatictired
rollersandtandemrollersshallfollowthebreakdownrollingand
sufficientpassesshallbemadetoachievetherequiredcompaction.
Rollingshallstartfromthesidesandproceedtowardthecenter.Each
tripoftherollershalloverlapthepervioustripbyatleast30cm.Roller
wheelshallbekeptmoistened.Therollershallbecapableofreversing
withoutbacklashandshallbefreefromwornparts.
Heavyrollersshallbeusedtocompleteallrollingincludingelimination
ofwavescausedbythelighterrollers.Fullcompactionshallbe
obtainedbeforetheasphalttemperaturereaches100C.Compaction
shallbeinaccordancewithspecificationofrelevantstandard.
v)Theconstructionjointsshallbepreparedbycuttingthelayer
verticallydownbymeansofasphaltsawcuttingmachineorwithjack
hammer.Thejointshallbecleanedwellbycompressedairandtack
coatmaterialshallbeappliedontheverticalandhorizontalsurfacefor
betterbonding.Extremelygoodcareshallbetakenwhenasphaltislaid
atconstructionjoints.
vi)Theareasinaccessibleforheavyrollersshallbecompactedwith
http://www.shareyouressays.com/117121/methodstatementforasphaltpavingworkscivilengineering

4/7

6/16/2015

MethodStatementforAsphaltPavingWorksCivilEngineering

platecompactorsorhandtampers.Afterreachingthebasecoursetop
level,suitablefillmaterial(dunesand)shallbedumpedtothetoplevel
ofbasecourseonthesidesofroadshoulders.Itshallbeleveled,
shaped(1:6ratios)andcompactedto90%maximumdrydensity.
c)TackCoat:
i)Thematerial(whichshallbeprimarilyapproved)shallbeappliedat
therateof0.3to0.6lit/sq.matthetemperaturenotexceeding54C
abovethebinderandatwherethereisajointwithexistingasphalt
surface.
ii)Thesurfaceshallbecuredfortheperiodaspermanufacturers
recommendationsuntilatackysurfaceisvisible.
d)WearingCourse:
i)Thehotasphaltmixshallbespreadoverthecuredsurfaceoftack
coatbyautomaticasphaltpavertotherequiredprofileandthickness.
ii)Themixshallbecompactedassoonaspossibleafterspreadingthe
material.Tandemrollershallfollowthelayingoperationtocarryout
breakdownrollinguptoatemperatureof110120C.
SelfpropelledrollersandTandemrollersshallfollowthebreakdown
rollingandsufficientpassesshallbemadetoachievetherequired
compaction.
Rollingshallstartfromthesidesandproceedtowardthecenter.Each
tripoftherollershalloverlaptheprevioustripbyatleast30cm.
Rollerwheelsshallbekeptmoistened.Therollershallbecapableof
reversingwithoutbacklashandshallbefreefromwornparts.Heavy
tandemroller(CC41)shallbeusedtocompleteallrollingincluding
eliminationofwavescausedbythelighterrollersFullcompactionshall
beobtainedbeforetheasphalttemperaturereaches80C.Compaction
shallbeinaccordancewithspecificationofrelevantstandard.
iii)Trafficshallnotbeallowedonthislayeruntilitisproperlycooled,a
minimumperiodof12hoursshallbeconsideredafterthecompletionof
therolling.
iv)Thetestholesshallmemadegoodwithhotasphaltmixand
http://www.shareyouressays.com/117121/methodstatementforasphaltpavingworkscivilengineering

5/7

6/16/2015

MethodStatementforAsphaltPavingWorksCivilEngineering

compactedusingMarshalHammer.
InspectionandTesting:
TestingshallbeconductedbyCompanysthirdpartysitelaboratory.
RelevantQCrecordsshallberaisedbyCivilConstructionContractors
QCEngineer.AlsotestsshallbecarriedoutaspertheFieldQuality
ControlPlanofAsphaltWork.
Advertisements:

EcoBenefitColorAsphalt
Premixed,pavingat1cmthickvarietyofcolors,favourableprice

RelatedEssays:
1. EssayonCivilSociety:astherealmoforganizedsociallife(553
Words)
2. EssayontheConceptofCivilReligioninIndia(521Words)
3. EssayonElementsOpposingCommonCivilCourtinHindi
4. PracticeofCivilReligioninAncientGreek,RomanCitiesand
America(1624Words)

http://www.shareyouressays.com/117121/methodstatementforasphaltpavingworkscivilengineering

6/7

6/16/2015

MethodStatementforAsphaltPavingWorksCivilEngineering

WelcometoShareyouressays.com!Ourmissionistoprovideanonlineplatformtohelpstudentstodiscussanythingand
everythingaboutEssay.Thiswebsiteincludesstudynotes,researchpapers,essays,articlesandotheralliedinformation
submittedbyvisitorslikeYOU.
BeforepublishingyourEssayonthissite,pleasereadthefollowingpages:
1.ContentGuidelines
2.PrivacyPolicy
3.TOS
4.DisclaimerCopyright

PublishYourEssay

POPULAR

Money Is More Important Than Love Essay


OCTOBER24,2012

380 Words Essay on Corruption in India (free to read)


AUGUST7,2011

1309 Words Essay on Global Warming: Causes, Effects and Remedies


AUGUST7,2011

Advertisements:

2015WorldsLargestCollectionofEssays!PublishedbyExperts.AllRightsReserved.

http://www.shareyouressays.com/117121/methodstatementforasphaltpavingworkscivilengineering

7/7

Das könnte Ihnen auch gefallen