Beruflich Dokumente
Kultur Dokumente
appendix 1
group, but some could be very substantial budget-wise. The review and
approval of all these takes a lot of time and could well distract the attention
of the project management from the process issues. Therefore, it is important
that the process package should be prepared and approved well in advance.
The detailed description of each of the waste streams (if any), as it leaves
the plant, after any compulsory waste treatment included in the plants
scope, should be an important part of the process package. The temporary
level of objectionable impurities in such streams may possibly jump by
orders of magnitude due to operational errors, and such fluctuations should
be evaluated and taken into account. There should be at least one acceptable
form of disposal of each of the waste streams. If there are several disposal
options, the final choice is a matter to be worked out by the project team
during the detailed engineering phase, in relation to the local conditions and
regulations and to the associated costs.
except for unwanted losses. This is typical, for example, in solvent extraction
processes, in which a relatively large solvent stream circulates in a closed
loop. Other examples are the mercury loop in a chlorine-soda plant and the
mother-liquor loop in a salt purification plant.
A buffering tank volume may be needed for averaging the fluctuations
of certain streams passing from one section to another. In semibatch processes, which, despite their old-fashioned connotations, are still necessary
and useful in specific cases, some of the sections fluctuate on-off and require
buffering before and after, so that the other sections can be operated
continuously, in more or less steady state. In some other processes, the
composition of a raw material may fluctuate and despite all process control
efforts, the output streams from certain sections receiving such raw material
need to be blended and averaged before proceeding.
All these aspects should be discussed explicitly at this stage of the
process package preparation, in connection to the block diagram, to bridge
between the theoretical steady-state ideal and the real-life necessities.
(specific gravity, specific heat, viscosity, vapor pressure) in the specific operating conditions and the kinetics of the reaction as a function of the operating variables.
6.2
6.3
6.4
6.5
A1.7 Services
7.1 These services are essential and major cost factors, although they are
often considered by the R&D scientists as trivial. The options available for each service are not basically different for a new process
Copyright 2002 by CRC Press LLC
than for a conventional one. However, the choices and the options
are much wider before the freezing of the novel process and/or
of the implementation site. Those generally needed in most chemical plants are:
Electricity for drives and sometimes also for heating
Cooling water
Saturated steam at several pressures (live or condensing)
Compressed air
Fuel of different kinds
Occasionally, heating oil, nitrogen and/or oxygen are also needed
Optimization studies to achieve the cheapest, most convenient solution could make a decisive difference for the economic value of the new
process. Often the development team is able to start such studies but
not complete them, as the economic factors have not been clarified
before the process package is presented. If there still are attractive
prospects, these should be described clearly in the process package.
7.2 The nominal consumption rate of each service needed for steady-state
operation can be calculated directly from the material and heat balances presented above, and from the equipment list in the previous
section for the electrical power. Those average consumption rates are
used for the (annual-basis) economic calculations, but higher design
quantities should be provided to cover the instantaneous rates (i.e.,
for starting or stopping, or for emergencies). The process package
can only provide general guidance on these design quantities, and
they may only be finalized after all the detailed information is obtained from the various equipment suppliers. So, one of the first
assumptions (placed on hold) in the detailed process engineering
would relate the maximum delivery rate needed for each service.
These assumptions are generally based on past experience and the
intuition of the leading process engineer, but they should be confirmed as soon of possible so that the services supply can be finalized.
7.3 Fuel could be needed either for direct use in a combustion device
incorporated into the process, or for the dedicated production of
steam or other heating medium in the new plant. Several types and
qualities of fuel can be considered, including coal, liquid petroleum
fractions, or natural methane gas. In addition to the obvious considerations of delivery cost and convenience, a decisive factor in the
choice of fuel will be the impurities in the flue gases discharged from
the stack (SO2/SO3, nitric oxides, metallic dust, and so on) and/or
of fly-ashes. If local ecological restrictions require intensive cleaning
installations, this may cancel the advantages of a cheaper fuel.
7.4 Condensable saturated steam (at different pressures), or another heating medium (oil) is used in heat exchangers. In some cases, it may
be purchased from the sites central services, or from an adjacent
producer. If not, a steam system should be installed with all the
ancillaries, such as the production of boiler-feed water. In many cases,
Copyright 2002 by CRC Press LLC
7.5
7.6
7.7
7.8
7.9
experts recommendations). However, the choice of the least-expensive-butreliable option should be an essential part of the project managers responsibility and this should be indicated clearly in the process package, even in
those cases when it may be considered trivial and well known.
Should there be any doubt on choice of construction material for a
particular stream at the time of reviewing the process package, this reservation should be indicated (hold). Thus, the engineering company will not
make any binding commitment on this item, until it is further clarified and
confirmed with experts or by corrosion tests, and the hold removed by
the process manager.