Sie sind auf Seite 1von 7

All rights reserved.

Passing on and copying of this


document, use and communication of its contents, not
permitted without written authorization from Alcatel

Network Management System Migration Procedure

Network Management System


Migration Procedure

01

19/05/06

DRAFT

ED

DATE

CHANGE NOTE

Giovanni Marilli
APPRAISAL AUTHORITY

ORIGINATOR

DRAFT

OND

ALCATEL

1/7

INTRODUCTION ................................................................................................................................ 3
1.1 OVERVIEW ............................................................................................................................................ 3

GENERAL INFORMATION ................................................................................................................ 4


2.1 PRECONDITIONS ................................................................................................................................... 4
2.2 RESTRICTIONS ....................................................................................................................................... 4

UPGRADE PROCEDURE .................................................................................................................... 5

TIME FIGURES .................................................................................................................................... 7


4.1 1354RM PLATFORM ............................................................................................................................. 7
4.2 1353NM PLATFORM ............................................................................................................................. 7

01

OND

DRAFT

ALCATEL

2/7

All rights reserved. Passing on and copying of this


document, use and communication of its contents, not
permitted without written authorization from Alcatel

TABLE OF CONTENTS

1AA 00014 0004 (9711) A4

All rights reserved. Passing on and copying of this


document, use and communication of its contents, not
permitted without written authorization from Alcatel

INTRODUCTION

1.1 Overview
This document describes the network migration procedure to be applied to Network Management System in
TIC. Considering the general audience who the document might be directed to, the intended readers should
be:

Alcatel Project Managers

Alcatel Network Management Engineers

TIC Project Managers

TIC Network Management Engineers

TIC Field Engineers

DRAFT

OND

It. 01
3/7

GENERAL INFORMATION

2.1 Preconditions
DCN

DCN must be steady and reliable for the whole upgrade process.

Password Availability

Alcatel NMS engineer will need an operator console and both the administration and
root passwords must be available

2.2 Restrictions

Alarm Surveillance
Customization

1330AS customized sublists will not be migrated: they could be manually

System
Customization

Any customization introduced on the systems will not be migrated; they could be

implemented at the end of the migration process

implemented at the end of migration process, assuming they will have no impact on
the system functionality and stability

01

OND

DRAFT

ALCATEL

4/7

All rights reserved. Passing on and copying of this


document, use and communication of its contents, not
permitted without written authorization from Alcatel

All rights reserved. Passing on and copying of this


document, use and communication of its contents, not
permitted without written authorization from Alcatel

UPGRADE PROCEDURE

Preparation

1354RM Platform
Upgrade

Retrieve Systems Variables and Configurations

Hardware Pre-Checks

Retrieve Network Data

(Optional) System Full Backup

Network Backup (immediate in advance system upgrade)

Software Transfer for 1353NM

1354RM platform migration will be approached considering the high redundancy


environment where is working in. Thus, the following steps will be applied:
1. Data Replication and OS Resilience deactivation
2. New SW release installation on stand by machine
3. Pre Migration Checks
4. Network Data Migration
5. Switch Platform
6. Post Migration Checks
7. Main and presentation machines SW upgrade and integration
8. OS Resilience installation and Replication activation
9. Post Migration Final Checks
After step 5, due to the presence of the original 1354RM still working with the
original SW release, fallback scenario might be implemented

1353NM Platform
Upgrade

1353NM platform upgrade will be approached applying In Service Evolution


procedure, according the following steps:
1. SW Area arrangement
2. New Instance Creation and SW Installation
3. New Instance Off-Line Customization
4. Instance Switch

1AA 00014 0004 (9711) A4

5. 1353NM Integration

DRAFT

OND

It. 01
5/7

6. Old Instance and SW deallocation

After step 7, due to the presence of the original 1353NM instance still working with
the original SW release, fallback scenario might be implemented

01

OND

DRAFT

ALCATEL

6/7

All rights reserved. Passing on and copying of this


document, use and communication of its contents, not
permitted without written authorization from Alcatel

7. Post Upgrade Checks

All rights reserved. Passing on and copying of this


document, use and communication of its contents, not
permitted without written authorization from Alcatel

TIME FIGURES

4.1 1354RM Platform

Task

Supervision

Provisioning

Estimated Time

OS Resilience Deactivation

OK

OK

1 hour

SW Installation stand by machine

OK

OK

3 day

Pre Migration Checks

OK

OK

0,5 day

Network Data Migration

OK

NA

4 hours

Switch Platform

NA

NA

2 hours

Post Migration Checks

OK

OK

1 day

Main and Presentation SW installation

OK

OK

3 days

OS Resilience and Data Replication OK


Activation

OK

0,5 day

Remarks

1. Network management available by 1353NM. 1353NMs will be progressively integrated under


1354RM: time estimated 20 min. per 1353NM

4.2 1353NM Platform

1AA 00014 0004 (9711) A4

Task

Supervision

Provisioning

SW Area Arrangement

OK

OK

1 day

New Instance SW Installation

OK

OK

0,5 day

New Instance SW Customization

OK

OK

2 hours

Instance Switch

NA

NA

2 hours

1353NM Integration

NA

NA

1 hour

Old Instance Deallocation

OK

OK

1 hour

Post Upgrade Checks

OK

OK

0,5 day

DRAFT

OND

Estimated Time

Remarks

It. 01
7/7