Beruflich Dokumente
Kultur Dokumente
ON WESM POLICY
DEVELOPMENT
Report to the DOE
(PHRD Project TF055609)
10 March 2008
Final Report: Extension of WESM
to Visayas
TO VISAYAS
Disclaimer
The professional analysis and advice in this report has been prepared by
Intelligent Energy Systems Pty Ltd (IES) for the use of the party or parties to
whom it is addressed, the Recipient(s), and for the purposes specified in the
report.
This report is supplied in good faith and reflects the knowledge, expertise and
experience of the consultants involved. In conducting the analysis for this report
IES has endeavoured to use what it considers is the best information available at
the date of publication, including any information supplied by the Recipient. IES
makes no representations or warranties as to the accuracy of the assumptions or
estimates on which the forecasts and calculations are based.
Although IES exercises reasonable care when making forecasts or predictions,
factors in the process, such as future market behaviour, are inherently uncertain
and cannot be reliably forecast or predicted. All projections, forecasts and
calculations in this report are for illustrative purposes only, using assumptions
and estimates described herein. The calculations are based on certain
assumptions that may not be realised or estimates that may prove to be
inaccurate. In addition, the projections involve a number of risks and
uncertainties. Actual results may be materially affected by changes in economic
and other circumstances. Factors that could cause actual results to differ
materially from the projections contained in the report, include, but are not limited
to, changes in interest rates, changes in general economic conditions, changes in
applicable legislation or government policy and changes in supply and demand
for energy.
IES makes no representation or warranty that any calculation, projection,
assumption or estimate contained in this report should or will be achieved or is or
will prove to be accurate. The reliance that the Recipient places upon the
calculations and projections in this report is a matter for the Recipients own
commercial judgement. In addition, IES shall not be liable in respect of any claim
arising out of the failure of the Recipients investment to perform to the
advantage of the Recipient or to the advantage of the Recipient to the degree
suggested or assumed in any advice or forecast given by IES.
IESREF: 4952
ii
TO VISAYAS
Executive Summary
Introduction
Mr Stephen Wallace of Intelligent Energy Systems (IES) was contracted to
provide technical assistance to the Philippines Department of Energy (DOE) on
Wholesale Electricity Market (WESM) Policy Development in the areas of:
This report comprises the second tranche of work for the technical assistance
and is largely focussed on the proposed extension of the WESM to Visayas.
Consultation
IES and DOE had one or more specific meetings with stakeholders to discuss the
extension of the WESM to the Visayas grid. We had separate meetings with:
Market Operator;
Visayas Generators:
Distribution utilities:
These meetings were in addition to the earlier consultations IES and DOE had
with all of the key stakeholders currently involved in the WESM regarding issues
in the WESM and the proposed reserves market.
Key Findings
There are a number of problems concerning extending the WESM to Visayas; the
main ones being:
A. Participants Readiness.
IESREF: 4952
iii
TO VISAYAS
B. Supply and Demand Situation.
The tight demand and supply balance situation in Cebu, Negros and Panay
will make it difficult to start the WESM in the immediate future. However,
unless this situation can be readily rectified by transmission upgrades alone
then new generation plant will be required but private investors are unlikely
to build new plant unless there is an operating market, the WESM, or there
are government guarantees or long term power purchase agreements.
However, avoiding the latter two options is one of the reasons for creating
the WESM. Consequently introducing the WESM to Visayas is going to be
difficult.
Extending the WESM to Visayas is probably essential to ensuring that there
is adequate generation to meet the demands there. This is likely to result in
high WESM prices in Cebu, Negros and Panay which should encourage
generation in the medium to long term and consequently reduce the
frequency of power interruptions. However there is a danger that high
WESM prices in Visayas could cause lots of political problems for the
market.
One solution to this apparent conundrum could be to start the market with a
number of market power and risk mitigation measures in place such as:
a.
b.
c.
d.
e.
f.
g.
other market power and risk management measures that the DOE and
ERC can develop.
The contracting could be financial (derivatives) contracts or bilateral contracts which are effectively
derivatives (swap) contracts settled through the WESM.
IESREF: 4952
iv
TO VISAYAS
Finding and implementing an adequate set of market power and risk
mitigation measures will not be an easy task.
C. Transparency Issue.
There still are some dysfunctional aspect of the WESM market rules and the
WESM implementation that could adversely affect the market in Visayas;
these should be rectified.
There is a need (a) for FTRs in the longer term and (b) for making some
minor adjustments to the proposed reserve market to better cater for the
particular requirements of the Visayas region.
The most dysfunctional aspects of the WESM are fixed up, in particular
those aspects of the WESM that will contribute to ensuring that all available
capacity is offered into the WESM at a price and plant limitations such as
energy constraints are effectively managed by the traders via the prices and
quantities offered;
IESREF: 4952
TO VISAYAS
b.
measures are in place to ensure that the risks of high WESM spot prices
due to a tight demand and supply balance and local market power of
generators are effectively mitigated so that the revenue and cost
streams of generators, DUs, ECs and wholesale customers are
reasonably predictable and the impacts of any high spot prices dont
adversely affect customers too much.
IESREF: 4952
vi
TO VISAYAS
Table of Contents
Executive Summary
iii
iii
iii
v
Introduction
1.1
1.2
1.3
1.4
3
4
5
6
7
8
9
10
11
iii
Introduction
Consultation
Key Findings
Criteria for Extending the WESM to Visayas
Objective
Background
Scope of Work
Consultation
9
9
11
12
14
2.1
2.2
2.3
2.4
2.5
2.6
2.7
14
14
16
19
21
24
25
Introduction
Market Participants
Network and Connections
Loads
Generation
Demand and Supply Balance
Involuntary Load Shedding
26
28
29
30
31
32
33
34
35
11.1 Introduction
11.2 Market Price Incentives
11.3 Starting the WESM with Tight Demand and Supply
11.4 Contracting and Retailing/Supply Arrangements
11.5 Market Power Mitigating Measures
11.6 Pricing to Ensure Proper Signalling of Supply Shortages
11.7 Provision of Information
35
35
35
36
37
37
37
13 Readiness of Systems
14 Conclusion
40
40
41
43
45
45
46
48
49
40
IESREF: 4952
49
50
vii
TO VISAYAS
List of Figures
Figure 1
Figure 2
Figure 3
Figure 4
Grid Map)
Visayas Loads for 5th to 11th February 2008
DOE Process for Determining Participant Readiness
18
20
41
List of Tables
Table 1
Table 2
Table 3
Table
Table
Table
Table
20
22
24
25
Leyte A Components
32
4
5
6
7
Table 8
IESREF: 4952
viii
TO VISAYAS
Introduction
Mr Stephen Wallace of Intelligent Energy Systems (IES) was contracted to
provide technical assistance to the Philippines Department of Energy (DOE) on
Wholesale Electricity Market (WESM) Policy Development. This report
comprises the second tranche of work for the technical assistance and is largely
focussed on the proposed extension of the WESM to Visayas. This report is
based considerably on the earlier report which looked proposed WESM reserve
market as many of the issues for the reserve market really need to be resolved
before the WESM is extended to Visayas.
1.1
Objective
The background to the DOEs interest in the reserve market and other aspects of
the WESMs development is outlined in the next section.
1.2
Background
IESREF: 4952
TO VISAYAS
sector that has reasonable and efficient spot prices and can attract timely
investment and private sector participation.
The DOE wants to monitor the development of competition in the WESM. On the
WESMs third month of operation, an investigation was conducted by the Market
Surveillance Committee (MSC) on the strategic bidding of the government entity
trading pre-existing PPAs with IPPs (PSALM). The MSC concluded that there
was evidence that the PSALM traders had acted in a co-ordinated way and
PSALM had misused its market power. ERC then took over the jurisdiction of the
matter and eventually concluded that there was not prima facie evidence that
PSALM had abused its market power even though there was circumstantial
evidence that three of the four PSAL traders had acted in a co-ordinated manner
rather than as three independent traders.
Given the potential impact of WESM in the development of the power sector, the
DOE needs to assess the efficiency of spot prices. Based on the current WESM
operation reports, there are a significant numbers of hours with spot prices at or
below zero, which is deemed unusual for that type of market and that can
potentially create distortions or inefficiencies in the pricing signals for investors
and participants. Moreover, traders or generators may tend to bid higher prices
to compensate the hour were spot sales are priced at zero. This in turn makes
the WESM prices more volatile.
This zero price scenario may be attributed to the market procedures on the
management of generation minimum load or Pmin. Another area of concern is
the increase in number of constraint violations in the WESM, which result in a rerun to calculate spot prices and seem to show an increase in violation of
constraints related to demand and supply balances and transmission congestion.
In summary, there is a need for a review and assessment of WESM results and
its rules, as well as to the relevant provisions of EPIRA and its IRRs, given
current conditions and expected development in the power industry.
There are other anticipated developments in the WESM. These are the proposed
commercial operation of the WESM reserve markets and the extension of WESM
to Visayas on the 3rd Quarter of 2007 (now thought to be later than this quarter,
probably in 2008). In the case of WESM Reserve Markets, it is expected that the
Regulatory decision on the filing of Pricing and Cost Recovery Mechanisms for
Reserves will be forthcoming on the 2nd Quarter of 2007(now thought to be the
4th quarter 2007).
Given the DOEs overall mandate on policy making in the power sector and
WESM development, it is proactively responding to the current development of
the scope of WESM to ensure its efficiency. Consequently, prior to the DOE
declaration of the WESM launch in Visayas and its extension to a reserves
market, criteria on the prerequisites for such extensions shall be established. The
timing and the adequacy of conditions are the critical issue that needs to be
assessed for DOE to declare a go or no go decision.
IESREF: 4952
10
TO VISAYAS
1.3
Scope of Work
The specific scope of work outlined by the DOE is listed below but also as part of
providing technical assistance, the DOE is expecting that the consultant will
share practical experience on electricity markets in order for the DOE to develop
a pro-active strategy in establishing the prerequisites and conditions necessary
for expanding the scope of the WESM and other policy decisions on the WESM.
1.3.1
Review and provide advice on the regulatory filing for Pricing and Cost
Recovery Mechanisms for Reserves;
Analyze the adequacy of the WESM Rules relative to the Reserves Market
(i.e., impact of Pmin; possible changes to MDOM);
Deliverables:
Study on the expected results of the WESM Reserve Markets including the
benefits vis a vis the existing WESM Energy Market
1.3.2
IESREF: 4952
11
TO VISAYAS
Deliverables:
1.3.3
Deliverables:
1.4
Consultation
IES and DOE had specific meetings with stakeholders to discuss the extension of
the WESM to the Visayas grid. We had separate meetings with:
Market Operator;
Visayas Generators:
Toledo
Distribution utilities:
CEBECO 1
IESREF: 4952
12
TO VISAYAS
CEBECO 2
CEBECO 3
VECO
These meetings were in addition to the earlier consultations IES and DOE had
with all of the key stakeholders currently involved in the WESM regarding issues
in the WESM and the proposed reserves market. During these earlier
consultations, IES and DOE met with each of the following stakeholders at least
once:
First Gas;
Meralco; and
IESREF: 4952
13
TO VISAYAS
Introduction
Leyte/Samar,
Cebu,
Bohol,
Negros, and
Panay.
Because the Visayas region is not as strongly meshed as the Luzon region
issues regarding generation competition and local market power, local reserve
and system security requirements, divergence of nodal prices and hedging price
differences need to be considered when considering the extension of WESM to
Vsayas. A number of complications also arise in terms of expanding the
transmission system which requires under sea inter-island transmission
connections which are costly and difficult to implement. This combined with the
geography of the location has implications for the optimal citing of generation
assets.
2.2
Market Participants
The market participants for the Visayas grid, as of November 2007, are
presented in Table 1. Some of them only have observer status.
Table 1
Organisation
Abbreviation
Role
Status
Full
GBPC
Generator
NPC
Generator
PSALM
Generator
Participant
Full
Participant
Full
Participant
Full
Generator
Participant
Full
GBPC
Generator
Participant
Electric
Antique Electric Cooperative, Inc.
Intelligent Energy Systems
ANTECO
IESREF: 4952
Cooperative
Not registered
14
TO VISAYAS
Organisation
Abbreviation
BOHECO
Role
Status
Electric
Cooperative
Not registered
Distribution
Bohol Light Company Inc.
BLCI
Utility
Not registered
Electric
Capiz Electric Cooperative, Inc.
CAPELCO
CEBECO I
CEBECO II
CEBECO III
CENECO
Cooperative
Not registered
Electric
Full
Cooperative
Participant
Electric
Full
Cooperative
Participant
Electric
Full
Cooperative
Participant
Electric
Full
Cooperative
Participant
Electric
ESAMELCO
ILECO I
ILECO III
LEYECO I
Cooperative
Not registered
Electric
Full
Cooperative
Participant
Electric
Cooperative
Not registered
Electric
Cooperative
Not registered
Electric
Leyte II Electric Cooperative, Inc.
LEYECO II
Cooperative
Not registered
Electric
Leyte III Electric Cooperative, Inc.
LEYECO III
LEYECO IV
Cooperative
Not registered
Electric
LEYECO V
NOCECO
PECO
PECO
Cooperative
Not registered
Electric
Full
Cooperative
Participant
Electric
Full
Cooperative
Participant
Distribution
Utility
Not registered
Electric
Cooperative
Not registered
Electric
Samar Electric Cooperative, Inc.
SAMELCO
Cooperative
Not registered
Electric
Samar II Electric Cooperative, Inc.
SAMELCO II
Cooperative
Not registered
Electric
SOLECO
VECO
IESREF: 4952
Cooperative
Not registered
Distribution
Full
Utility
Participant
15
TO VISAYAS
Organisation
Abbreviation
Role
Status
PHILPHOS
Customer
Participant
Customer
Observer
Customer
Observer
Other Utilities
Observer
Full
Strategic Corporate Investment
Partners Ltd.
International Institute for Energy
Conservation
PNOC - Energy Development
Corporation
What is noticeable in the table above is that many of the electricity co-operatives
(ECs) have not registered as participants in the WESM. If they dont register as
participants then National Power Corporation (NPC) will assume the role of
wholesale supplier of last resort and hence will be effectively participating in the
spot market as both a generator and retail supplier. However, NPC is not
registered for the role of wholesale supplier of last resort / retailer in the WESM.
Many electricity co-operatives are unlikely to ever be retail participants in the
WESM as they are unlikely to be able to satisfy the prudential requirements.
Consequently, the role of NPC as a wholesale supplier of last resort (retailer in
the WESM) is not fully appreciated and has important implications with respect to
the sale of NPCs assets, the PPA trader arrangements and NPCs own financial
risk management and exposure to the WESMs prices. If NPC sells off most of
its generation assets yet is still the wholesale supplier to a number of electricity
co-operatives then it will have a considerable exposure to WESM prices unless it
hedges this exposure with contracts with generators. Given this potential
exposure to WESM prices then in this case it should be registered as a supplier
and be required to meet the prudential requirements of the market even if it was
only by government guarantee.
2.3
The network in Visayas is largely a radial network starting at Samar and ending
at Panay. Figure 2 shows the islands that make up Visayas and the main
transmission system that supplies them. Figure 2 is an extract from Transcos
2006 Power Grid Map. Some of the key points to note are:
Not all elements in the Luzon grid are managed on an N-1 security basis. In
fact all of the interconnections between the islands in Visayas and between
Visayas and Luzon are not managed on an N-1 basis. The power flows can
be dispatched up to the interconnector continuous ratings. Consequently
should one interconnector line trip, for whatever reason, to avoid either
overloading the remaining line where there are two lines or frequency
problems where there was one line and the system has been islanded then
there is a need for automatic load shedding and generator tripping schemes
to maintain system security.
IESREF: 4952
16
TO VISAYAS
Figure 1
+440 MW
-150 MW
Leyte
400 MW
360 MW 1
+-100 MW2
Cebu
100 MW
80 MW 1
Negros
100 MW
Panay
60 MW 1
100 MW
Luzon
80 MW 1
Bohol
IESREF: 4952
17
TO VISAYAS
Figure 2
IESREF: 4952
18
TO VISAYAS
2.4
Loads
IES was provided with hourly load data for each of the islands comprising the
Visayas grid. This data was for the year 2005. We were also supplied with
Visayas data for July 2006 to June 2007 but this data was not decomposed into
loads for each island. From both sets of data we estimated that the recent load
growth in Visayas was around 7% per annum. Thus we were able to create
estimates for the load characteristics for each of the islands in the Visayas grid
for 2008. For Bohol there is an estimated 0MW for the minimum demand which
is due to there being several hours in 2005 when the demand was zero
presumably due to forced outages which prevented any Bohol demand being
met. The statistics for 2005 are presented in Table 2 and estimated statistics for
2008 are presented Table 3. The figures for Panay and Visayas do not include
the loads for PECO. According to the SO, the system peak demand for Visayas
occurs around November to December in contrast to the Luzon which has its
peak demands around May to June.
Table 2
Demand
statistics
Minimum
Average
Maximum
Standard
Deviation
Bohol
0
27
47
Cebu
166
312
445
LeyteSamar
49
124
190
Negros
70
135
198
Panay
4
69
132
133
70
20
28
20
967
46
438
168
195
120
PECO
22
65
108
Coincident
maximum
demand
Table 3
Minimum
Average
Maximum
Standard
Deviation
98
Estimated demand statistics for 2008 for Visayas grid (in MW)
Visayas
506
825
1197
Bohol
0
33
59
Cebu
205
386
551
LeyteSamar
60
154
235
Negros
86
167
245
Panay5
5
86
163
165
10
87
25
35
25
1197
57
542
208
241
148
PECO6
27
80
134
Coincident
maximum
demand
122
The figures for Panay do not include the loads for PECO
The PECO figures are rough estimates based on some monthly data. They are larger than other figures
but finding a definitive source is difficult.
5
The figures for Panay do not include the loads for PECO
6
The PECO figures are rough estimates based on some monthly data
4
IESREF: 4952
19
TO VISAYAS
th
th
Figure 3 presents one week of Visayas loads from 5 to 11 February 2008. The
peak demands for this week are all below the peak demands in Table 3 as would
be expected as this is not the time of peak demands. However, what is
noticeable is that the Panay forecasts for peak demands are similarly high as for
the other islands. They dont stand out as being excessively high.
Visayas Loads for 5th to 11th February 2008
Figure 3
500
450
400
350
MW
300
250
200
150
100
50
0
Feb 5
Feb 6
Feb 7
Leyte/Samar
Feb 8
Cebu
Negros
Feb 9
Feb 10
Bohol
Feb 11
Panay
Table 4
Proportion
of average
demand
Customers
Abreviation
Island
ANTECO
Panay
0.9%
BOHECO
Bohol
20
2.5%
BLCI
Bohol
16
2.0%
CAPELCO
Panay
32
3.9%
CEBECO I
Cebu
26
3.2%
CEBECO II
Cebu
33
4.1%
CEBECO III
Cebu
0.0%
CENECO
Negros
102
12.6%
ESAMELCO
Samar
1.0%
IESREF: 4952
20
TO VISAYAS
Abreviation
Island
Average
Demand
(MW)
ILECO I
Panay
30
3.7%
ILECO III
Panay
0.9%
LEYECO I
Leyte
LEYECO II
Leyte
LEYECO III
Leyte
LEYECO IV
Leyte
1.1%
Customers
Proportion
of average
demand
Cooperative, Inc.
0.0%
30
3.7%
0.0%
LEYECO V
Leyte
24
3.0%
NOCECO
36
4.4%
PECO
73
9.0%
PECO
SAMELCO
Negros
Panay
Panay
Samar
SAMELCO II
Samar
11
1.4%
SOLECO
1.5%
VECO
300
37.0%
PHILPHOS
Leyte
Cebu
Leyte
12
35
4.3%
811
100.0%
TOTAL
2.5
0.0%
0.0%
Generation
The generating units in Visayas are listed in Table 5. Many of these units are
operating below their registered capacities (Pmaxs). For instance:
the three power barges are operating at maximum output levels in the
20MW-24MW range rather than their rated capacities of 32MW each;
Leyte A can not operate at the maximum of 590MW due to a lack of steam.
These three examples highlight a general issue in Visayas that the actual
dependable capacity of a number of units is materially below the rated capacity.
Consequently Visayas has a lot less dependable generation than might appear
based on the rated capacities. Table 5 attempts to document the WESM
generators and their registered capacities and their dependable capacities. This
is not an easy task as there are several sources of inconsistent or erroneous
information. In addition to the WESM registered generators there are a number
of embedded generators. The larger ones are in Table 6.
Intelligent Energy Systems
IESREF: 4952
21
TO VISAYAS
The other interesting aspect of the supply side of Visayas is that the power
barges are movable and there are a number of connection points in the
Philippines that the barges could be moved to. In Visayas they can be located in
Panay, Cebu and Bohol.
Table 5
Resource
Name
7BDPP_G01
7BDPP_G02
Plant
Bohol Diesel Power
Plant
Bohol Diesel Power
Plant
Org
Island
Fuel
Type
Pmin
(MW)
NPC
BOHOL
Diesel
NPC
Pmax
(MW)
Regist
Depen
ered
dable
11
BOHOL
Diesel
11
LHEP
BOHOL
Hydro
1.2
JANOPOL
BOHOL
Hydro
NPC
CEBU
Diesel
7.3
NPC
CEBU
Diesel
7.3
NPC
CEBU
Diesel
7.3
NPC
CEBU
Diesel
7.3
NPC
CEBU
Diesel
7.3
NPC
CEBU
7.3
NPC
CEBU
27.5
25
NPC
CEBU
27.5
25
NPC
CEBU
10
50
48
NPC
CEBU
Diesel
Gas
Turbine
Gas
Turbine
Thermal
(Coal)
Thermal
(Coal)
11
55
52
GLOBAL
CEBU
Diesel
12
37
GLOBAL
CPPC
CEBU
CEBU
Thermal
(Coal)
Diesel
EAUC
CEBU
Diesel
NPC
PSALM
ETD3
CEBU
32
20
LEYTE
Diesel
Geother
mal
174.3
590.6
578
NPC
LEYTE
Geother
mal
37.5
30
NPC
LEYTE
Geother
mal
37.5
30
5CDPPI_G01
5CDPPI_G02
5CDPPI_G03
5CDPPI_G04
5CDPPI_G05
5CDPPI_G06
5LBGT_G01
5LBGT_G02
5NAGATH_G01
5NAGATH_G02
5TPC_G01
5TPC_G02
5CPPC_G01
5EAUC_G01
4LEYTE_A
4LGPP_G01
4LGPP_G02
IESREF: 4952
10
64
70
55
62
49.6
42
22
TO VISAYAS
Pmax
(MW)
Resource
Name
4LGPP_G03
6NNGPP_G01
6PAL1A_G01
6PAL1B_G01
6PAL1C_G01
6PAL2A_G01
6PAL2B_G01
6PAL2C_G01
6PAL2C_G02
8PDPP_G01
8PDPP_G02
8PDPP_G03
8PDPP_G04
8PDPP_G05
8PDPP3_G01
8PDPP3_G02
8AVON_G01
8PPC_G01
(MW)
Regist
Depen
ered
dable
Org
Island
Fuel
Type
NPC
LEYTE
Geother
mal
37.5
30
PNOCEDC
NEGRO
S
Geother
mal
14
49
12
NPC
NEGRO
S
Geother
mal
7.5
37.5
31
NPC
NEGRO
S
Geother
mal
7.5
37.5
31
NPC
NEGRO
S
Geother
mal
7.5
37.5
31
NPC
NEGRO
S
Geother
mal
20
20
NPC
NEGRO
S
Geother
mal
20
20
NPC
NEGRO
S
Geother
mal
20
20
NPC
NEGRO
S
Geother
mal
20
20
NPC
PANAY
Diesel
7.3
NPC
PANAY
Diesel
7.3
NPC
PANAY
Diesel
7.3
NPC
PANAY
Diesel
7.3
NPC
PANAY
Diesel
7.3
NPC
PANAY
Diesel
60
19
NPC
PANAY
Diesel
60
19
GLOBAL
PANAY
Diesel
20.00
20
GLOBAL
PANAY
Diesel
72
69
NPC
PANAY
Diesel
32
24
NPC
PANAY
Diesel
32
24
267.8
1716
1473
Plant
Tongonan
Geothermal Power
Plant (Leyte)
Northern Negros
Geothermal Power
Plant
Negros Geothermal
Power Plant (1&2)
Palinpinon
Negros Geothermal
Power Plant (1&2)
Palinpinon
Negros Geothermal
Power Plant (1&2)
Palinpinon
Negros Geothermal
Power Plant (1&2)
Palinpinon
Negros Geothermal
Power Plant (1&2)
Palinpinon
Negros Geothermal
Power Plant (1&2)
Palinpinon
Negros Geothermal
Power Plant (1&2)
Palinpinon
Panay Diesel Power
Plant I
Panay Diesel Power
Plant I
Panay Diesel Power
Plant I
Panay Diesel Power
Plant I
Panay Diesel Power
Plant I
Panay Diesel Power
Plant 3
Panay Diesel Power
Plant 3
Panay Power
Corporation
Panay Power
Corporation
Total
IESREF: 4952
Pmin
(MW)
Pmax
23
TO VISAYAS
Table 6
Plant
PECO
15 MW Bunker
Fuel (GBPC)
5 MW Bunker
Fuel (GBPC)
Guimaras Power
Project
2.6
Org
Panay Electric
Corp.
PPC/Global
Business Power
Corp.
PPC/Global
Business Power
Corp.
Trans-Asia
Pmax (MW)
Pmax (MW)
Location
Fuel
Type
Registered
Dependable
Panay
Diesel
19.85
0.00
Panay
Diesel
12.60
7.60
Panay
Diesel
5.00
5.00
Panay
Diesel
3.40
3.40
IESREF: 4952
24
TO VISAYAS
Table 7
Island
Leyte
Bohol
Cebu
Negros
Panay
Total
Total for Cebu
Negros and
Panay
Generation
668
21
399
185
201
1473
Demand
208
57
542
241
270
1318
Excess /
deficit
460
-36
-143
-56
-70
155
785
1053
-268
Reserves7
79
2
47
22
24
156
Excess /
deficit after
reserves
381
-39
-190
-78
-93
-19
93
-361
From Table 7 it is quite clear the Cebu, Negros and Panay combined have a
deficit of generation, -268MW. This deficit can be met with the 360MW of power
available from the interconnection with Leyte but if generation reserves are
considered then the situation is much tighter. In the case of Panay alone the
situation is worse with a deficit of -70MW, which can be less than capability of the
interconnection to Negros (60MW to 100MW depending on stability limits). Thus
when the possibility of generator outages and any reserve requirements for
frequency control are considered, it can be seen that the Visayas grid is very
susceptible to supply shortages.
2.7
Involuntary load shedding is a regular feature of the Visayas grid. The load
shedding is occurring due to shortages of supply. The loads in Panay are the
most often shed. This is because the power flows are from Leyte to Cebu then
Negros and then Panay and consequently shedding load in Panay means less
load needs to be shed due the marginal losses in providing power to Panay.
However even though this is an efficient solution it is not very equitable.
The total reserves were allocated on the basis of MW of generation in each island.
IESREF: 4952
25
TO VISAYAS
ensuring that there is adequate competition in both the energy and reserve
markets;
or
if ensuring that there is adequate competition is not possible without the
WESM to facilitate increased availability and dependable capacity of existing
plant and new generation entry, then market power mitigation measures8 are
in place including adequate measures to prevent the pass through of high
spot prices to captive and other customers, given the tight demand and
supply balance situation in Visayas;
Other than ensuring high levels of contracting in the market, effective market power mitigation strategies
are not at all obvious and may be difficult to develop. Consequently, there would need to be a coordinated
effort between DOE and ERC to develop coherent strategies for avoiding creating market power as much as
possible by looking at the sales process and PSALM IPPA portfolio structures and for mitigating the effects
of market power when it is present.
IESREF: 4952
26
TO VISAYAS
Participant Readiness
The conditions and other related issues are discussed in subsequent sections.
IESREF: 4952
27
TO VISAYAS
ex ante market re-run prices using ex post re-run prices and the lack of
transparency and speed with which re-run prices are calculated;
The use of ex post prices as replacements for ex ante rerun prices has
reduced the incentives for some plant to offer all their capacity into the
market. This is because the ex post prices are almost always lower than
what would have been the case had the ex ante re-run prices been
based on just relaxing the violated constraints in the ex ante dispatch.
This is due to the ex post prices including must run plant in the market
dispatch when this plant may not have been offered into the market ex
ante.
energy prices being set well below the bid cap even when there is
involuntary load shedding used to balance supply and demand; and
The IES report also outlined possible ways of remedying these problems.
IESREF: 4952
28
TO VISAYAS
Reserve Market
It is probably not necessary to have the full reserves spot market operating
before extending the WESM to Visayas. However, given the tight demand and
supply balance in Visayas it is probably necessary to have contracted reserves
co-optimised with the energy market dispatch to ensure the optimal use of all
available plant.
As well, before starting the full reserves spot market it will be necessary for the
reserve service definitions to be extended to include lower services to cater for
(a) times in which the HVDC connection to Luzon trips and (b) times when one of
the AC connections from Leyte to Cebu trips. During such events some of Leyte
As generation is tripped by venting the steam directly rather than passing it
through the generation units to avoid overloading the remaining interconnections
or pushing up frequency. This is a frequency control ancillary service and should
be priced and dispatched in the market. A more detailed discussion of the
proposed reserve market is outlined in IESs earlier report, Technical Assistance
on WESM Policy Development: Final Report Task 1.
Even though having the full reserve spot market operating in Luzon should not
necessarily be a precondition to starting the WESM in Visayas, dispatching
contracted reserves via the MDOM co-optimisation of energy and reserves
should be.
Currently Visayas is regularly short of plant capacity and consequently reserve
requirements are not always met. Consequently if the WESM were extended to
Visayas without the co-optimisation of reserves, the SO would constrain off
individual units to provide reserves and then on occasions would have to interrupt
loads to achieve a demand and supply balance. There could be regular
occurrences of under generation. On the other hand if the dispatch of energy
and reserves is co-optimised then the constraint violation costs for the
contingency reserves could always be set to lower values than the nodal energy
balance constraints and thus ensuring demands are met before meeting the
contingency reserve requirements. Under this arrangement, involuntary load
shedding would essentially be acting as a non market contingency reserve.
IESREF: 4952
29
TO VISAYAS
IESREF: 4952
30
TO VISAYAS
IESREF: 4952
31
TO VISAYAS
Generation Competition
There will not be adequate competition in both the energy and reserve markets in
Visayas in the immediate future because there is a very tight demand and supply
balance and there is regular involuntary load shedding. Under these
circumstances generators in Panay, Negros and Cebu will regularly have
substantial market power and be able to set prices to very high levels. Over time
this can change if there is sufficient new entry and the dependable capacities of
some of the existing plants are returned to levels closer to their rated capacities.
In addition to the tight demand and supply balance in Panay, Negros and Cebu,
the problem of market power is likely to be further exacerbated by PSALMs
packaging of power stations in the proposed asset sales. PSALM intends selling
the Negros Geothermal Power Plant (Palinpinon) combined with the Panay
Diesel Power Plant and the Tonganan Geothermal Plant (Leyte) combined with
Bohol Diesel Power Plant. The sale of the combined generation portfolio of
Palinpinon and Panay Diesel creates a situation of local market power for the
purchaser in Panay and Negros.
In addition if Leyte A is packaged as just one IPP Administrator (IPPA) then the
IPPA will have some degree of market power as well though this will be mitigated
to some extent by the fact that loads in Leyte are much smaller than generation
capacity. None the less, if possible, it would probably be better to create two
IPPAs to trade the Leyte A power stations. This looks as though this could be
done with a little care as Leyte A is composed of four power stations: Malitbog
(231MW), Mahanagdong A (120MW), Mahanagdong B (60MW), Upper Mahiao
(112.5MW) and the Optimization Plant for each power station (49MW). Careful
attention would have to be paid to the steam arrangements. A flexible
arrangement could possibly be created via an internal market for unders and
overs for steam requirements.
Table 8
Name of Plant
Mahanagdong A
Mahanagdong B
Upper Mahiao
Malitbog
Total
Leyte A Components
No.
Optimization
Units
2
1
3
1
7
Output
(MW net)
12.45
6.25
16.95
13.35
49 MW
Operation
Plant Type
Topping
Topping
Topping
Bottoming
IESREF: 4952
Main Plant
120
60
112.5
231
Total Plant
132.45
66.25
129.45
244.35
572 MW
32
TO VISAYAS
IESREF: 4952
33
TO VISAYAS
IESREF: 4952
34
TO VISAYAS
IESREF: 4952
35
TO VISAYAS
process to be one of setting benchmark rates rather than rates based on a cost
pass through and to eliminate from EPIRA the requirement that retailers
purchase at least 10% of their supply from the WESM.
As well, DOE would need to facilitate a process to ensure that before starting the
WESM in Visayas that all customers, DUs, ECs and generators (including IPPAs
and NPC generators for sale) were contracted with longer term contracts that
were designed to minimise adverse affects of volatile spot prices during the initial
years of the market. A great deal of thought would have to go into these
arrangements to ensure that spot market risks were managed to acceptable
levels. FTR arrangements may be necessary to achieve this.
IESREF: 4952
36
TO VISAYAS
particular the possibility of setting up contracts for a transitional period which do
not allow the counter parties to opt in or out at any stage. The arrangements to
date have effectively had such flexibility. Some generators which had been sold
have returned their contracts. This was probably due to the contracts not being
a good match to their generation capabilities and cost structures. None the less,
embedding such optionality into the contracting arrangements increases the risks
for some participants, in particular NPC.
Other measures which aim to cap the market price or directly control the offers
generators make should be avoided if at all possible as they are essentially
attempts to re-regulate the market.
IESREF: 4952
37
TO VISAYAS
lastly, allows all affected parties to identify when some participants are
misusing their market power rather than have to wait until a market
surveillance group or regulator identifies the problem.
downloadable results from WAP, DAP processes (even though graphs are
provided);
underlying data for market indices (while market indices are viewable as
graphs, it would be useful to DOE and the public if the underlying data could
be downloaded directly thus saving the need for computing the indices from
scratch using raw data);
the detailed network model which is used in dispatch for each hour (this
doesnt appear to be available, despite there being a clause in the market
rules requiring the market operator to provide this information, as per clause
3.2.1.1 of the market rules the data could be in the form of changes from
the normal values of the market network model); and
IESREF: 4952
38
TO VISAYAS
the five minute SCADA snapshots of the system and the translation table for
moving between SCADA tags and market elements or the snapshots
converted into the values corresponding to the market network model.
One of the main problems with the data is that it is provided only over rolling
periods and the full history is difficult to obtain. For example, typically at most 2
months is provided. While we understand the difficulty in making full historical
data sets available, a suitable benchmark might be a year of historical data and
the option to purchase or obtain a full history from the Market Operator.
IESREF: 4952
39
TO VISAYAS
Market Operator;
Visayas Generators:
Distribution utilities:
although the generators had submitted market offers etc and tested the
market systems they were not really ready to operate in the market; and
the distribution utilities and electricity co-operatives were not ready. Many
had not even registered and participated in the trial operations and nearly all
of them were not ready to operate in a market context.
IESREF: 4952
40
TO VISAYAS
th
view to having them ready by the 26 of July 2008. The DOEs diagram of this
process is presented in Figure 4.
Figure 4
V i s a ya s W E S M C o m m e r c i a l O p e r a t i o n
Novem ber 2007
G overnance Issues
Visayas R epresentative to R CC
E R C C om petition R ules
January 2008
January 2008
February 2008
2008
2008
D eclaration of V isayas
W E SM C om m ercial
O peration
12.3
IESREF: 4952
41
TO VISAYAS
Pricing and contracting with retailers (DUs and ECs) and contestable
customers;
Bilateral contracting;
Derivatives contracting;
Database systems that can collect and store all relevant market data;
Systems to record and store history of generators own offers and any
changes;
IESREF: 4952
42
TO VISAYAS
Systems and procedures to ensure that generators meet the dispatch target
for energy and reserve.
Settlements;
Regulation (WESM Rules, ERC Hearings, OATS and other related regulatory
issues);
Pricing; and
Regulated retail rates for captive customers with pass through/without pass
through of energy cost;
Regulation including WESM Rules, ERC decisions, OATS and other regulatory
issues.
IESREF: 4952
43
TO VISAYAS
12.4.2 Risk Management
Do you have a documented risk management policies and procedures and
corresponding systems for managing risk which addresses the following?
Bilateral contracting ;
Derivatives contracting;
Regulated retail rates for captive customers without pass through of energy
cost;
Database systems that can collect and store all relevant market data;
Settlements;
IESREF: 4952
44
TO VISAYAS
Regulation (WESM Rules, ERC Hearings, OATS and other related regulatory
issues;
Strategies;
Pricing; and
Have all of the providers of reserves been tested for their technical
capabilities to deliver the reserves?
Has the SO documented all of the key security limits and formulated them
appropriately for MDOM? In particular:
Thermal limits,
Voltage limits,
Has the SO documented all the material deviations of all line capacities from
the Visayas market network model (MNM)?
IESREF: 4952
45
TO VISAYAS
12.6.2 Operations
Does the SO have the capacity to manage the dispatch of all the generators
under market operations where generator dispatch targets for energy and
reserve could change materially from hour to hour? In particular is the SO
ready and capable of the following?
Updating security limits for MDOM in real time with changes in system
conditions
Have the documents regarding security limits, etc been published to the
market? In particular:
Regulation (WESM Rules, ERC Hearings, OATS and other related regulatory
issues);
IESREF: 4952
46
TO VISAYAS
generators can lodge bids but are probably not fully prepared for commercial
operation in a market. The ECs and DUs still are not really prepared.
IESREF: 4952
47
TO VISAYAS
13 Readiness of Systems
There were issues regarding the communications systems between the SO in
Visayas and the MO in Luzon. The ideal situation would be to establish a
number of completely independent communication paths such that the collective
system is highly reliable. At a meeting in 27th February 2008 the MO informed
the DOE the communication redundancy issues were satisfactorily solved. This
will be validated by the certification that will be issued and submitted by the MO
and SO to the DOE.
IESREF: 4952
48
TO VISAYAS
14 Conclusion
14.1 Key Findings
There are a number of problems concerning extending the WESM to Visayas; the
main ones being:
A. Participants Readiness.
The tight demand and supply balance situation in Cebu, Negros and Panay
will make it difficult to start the WESM in the immediate future. However,
unless this situation can be readily rectified by transmission upgrades alone
then new generation plant will be required but private investors are unlikely
to build new plant unless there is an operating market, the WESM, or there
are government guarantees or long term power purchase agreements.
However, avoiding the latter two options is one of the reasons for creating
the WESM. Consequently introducing the WESM to Visayas is going to be
difficult.
Extending the WESM to Visayas is probably essential to ensuring that there
is adequate generation to meet the demands there. This is likely to result in
high WESM prices in Cebu, Negros and Panay which should encourage
generation in the medium to long term and consequently reduce the
frequency of power interruptions. However there is a danger that high
WESM prices in Visayas could cause lots of political problems for the
market.
One solution to this apparent conundrum could be to start the market with a
number of market power and risk mitigation measures in place such as:
a.
b.
c.
10
IESREF: 4952
49
TO VISAYAS
need some revisions to the Visayas SOs ancillary service procurement
program ASPP);
d.
e.
f.
g.
other market power and risk management measures that the DOE and
ERC can develop.
There still are some dysfunctional aspect of the WESM market rules and the
WESM implementation that could adversely affect the market in Visayas;
these should be rectified.
There is a need (a) for FTRs in the longer term and (b) for making some
minor adjustments to the proposed reserve market to better cater for the
particular requirements of the Visayas region.
The most dysfunctional aspects of the WESM are fixed up, in particular
those aspects of the WESM that will contribute to ensuring that all available
capacity is offered into the WESM at a price and plant limitations such as
IESREF: 4952
50
TO VISAYAS
energy constraints are effectively managed by the traders via the prices and
quantities offered;
b.
measures are in place to ensure that the risks of high WESM spot prices
due to a tight demand and supply balance and local market power of
generators are effectively mitigated so that the revenue and cost
streams of generators, DUs, ECs and wholesale customers are
reasonably predictable and the impacts of any high spot prices dont
adversely affect customers too much.
IESREF: 4952
51