Beruflich Dokumente
Kultur Dokumente
FINAL REPORT
Environment Consultant:
Project Proponent:
(Approved Consultant)
March, 2015
Table of Contents
Chapter
Title
Page
Executive Summary
1.0
Introduction
1.1
1.2
1.3
1.4
1.5
2.0
Introduction
Type of the Project
Need of the Project
Project Location and Layout
Size and Magnitude of Operations
Project Schedule for Approval and Implementation
Process Technology
Process Description
Captive Power Plant
Cement Plant
Raw Material Requirement and Sources
Raw Material Handling
Utility Systems and Auxiliary Facilities
Environmental Effects
Pollution and Control Measures
C2-1
C2-1
C2-2
C2-2
C2-3
C2-15
C2-16
C2-17
C2-36
C2-40
C2-40
C2-48
C2-49
C2-53
C2-54
4.0
C1-1
C1-1
C1-2
C1-10
C1-10
Project Description
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
3.0
Introduction
Geology, Hydrogeology and Drainage
Landuse Studies
Soil Characteristics
Meteorology
Ambient Air Quality
Water Quality
Noise Level Survey
Ecology and Biodiversity
Demography and Socio-economics
Traffic Density Survey
C3-1
C3-1
C3-16
C3-25
C3-29
C3-39
C3-46
C3-52
C3-56
C3-74
C3-77
C4-1
C4-1
C4-8
C4-85
TC-I
C5-1
C5-6
C5-10
General
Monitoring Schedule
Process Monitoring and Reporting Arrangements
Implementation Schedule of Mitigation Measures
Infrastructure for Environmental Protection
Cost Provision for Environmental Measures
Greenbelt Development
Rainwater Harvesting Facilities
C6-1
C6-4
C6-8
C6-9
C6-9
C6-11
C6-11
C6-14
Additional Studies
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11
7.12
7.13
7.14
7.15
7.16
7.17
7.18
8.0
Selection of Process
Selection of Alternative Sites
Carbon Credit Project / Reduction of Greenhouse
Gas Emission Projects
7.0
Page
6.0
Title
Project Benefits
8.1
8.2
8.3
8.4
8.5
8.6
C8-1
C8-1
C8-1
C8-2
C8-3
C8-5
TC-II
Title
Administrative Aspects
9.1
9.2
9.3
10.0
Organization Policy
Corporate Environmental Policy
Institutional Arrangements for Environment Protection
And Conservation
C9-1
C9-2
C9-2
11.0
Page
Introduction
Major Plant Facilities
Baseline Environment
Summary of Anticipated Environmental Impacts
and Mitigation Measures
Risk Assessment and Disaster Management Plan
Budget Requirement for Environment Protection
Conclusions
C10-1
C10-1
C10-2
C10-3
C10-8
C10-9
C10-10
Disclosure of Consultants
11.1
11.2
Introduction
Vimta Lab Limited Environment Consultant
Table of Contents
List of Figures
List of Tables
C11-1
C11-1
TC-I
TC-IV
TC-VI
TC-III
List of Figures
Figure
Title
1.1
1.2
1.3
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
3.2.1
3.2.2
3.2.3
3.2.4
3.2.5
3.2.6
3.2.7
3.2.8
3.3.1
3.3.2
3.3.3
3.3.4
3.4.1
3.5.1
3.5.2
3.5.3
3.5.4
3.5.5
3.6.1
3.7.1
3.8.1
3.9.1
3.9.2
3.9.3
4.1
4.2
4.3
4.4
4.5
Index Map
Study Area Map
Google Map
Photographs showing Site Features of the Project Area
Layout of the Proposed Plant Area
Project Site Layout Super imposed on Toposheet
Steel Plant Process Flow Diagram
Process and Material Flow Diagram
Process Flow Chart Pellet Plant
Recovery Type Coke Oven Plant
Process Flow Diagram of Sintering Plant
Process Flow Diagram of Hot Metal Production using BF
Process Flow Diagram of Steel Making
Process Flow Diagram of Lime and Dolo Calcination Plant
Typical Flow Diagram of Proposed CPP
Map showing the Plant Layout, Township and Railway siding
Flow Chart Linking Pollutants and Principle Operations in the
Integrated Steel Plant
Geology of the Study Area
Lithological Section of a Borewell
Drainage Map of the Study Area
Hydrogeological Map of the Study Area
Water Levels during Premonsoon 2014
Water Levels during Post Monsoon 2013
Pumping Test Data Plot
Pumping Test Data Analysis
Thematic Map of the Study Area
Landuse Pattern based on Satellite Data
Satellite Image and Landuse Pattern of the Project Site
Digital Elevation Model of Study Area
Soil Sampling Locations
Average Mixing Height
Windrose Diagram of Pre Monsoon & Monsoon IMD Ranchi
Windrose Diagram of Post Monsoon & Winter IMD Ranchi
Annual Windrose Diagram IMD Ranchi
Site Specific Windrose
Ambient Air Quality Sampling Locations
Water Sampling Locations
Noise Monitoring Locations
Ecological Sampling Locations
Regenerating Vegetation on Hill Slopes
Plantation of SAL and Eucalyptus
Short Term 24 hourly Incremental Concentration of PM
Short Term 24 hourly Incremental Concentration of SO2
Short Term 24 hourly Incremental Concentration of NOx
Isopleths showing Incremental Concentrations for CO
Isopleths showing Incremental Concentrations for NOx
Page
C1-4
C1-5
C1-6
C2-4
C2-6
C2-7
C2-18
C2-19
C2-22
C2-24
C2-27
C2-30
C2-33
C2-35
C2-37
C2-41
C2-56
C3-3
C3-4
C3-6
C3-7
C3-10
C3-11
C3-15
C3-15
C3-21
C3-22
C3-23
C3-24
C3-26
C3-34
C3-35
C3-36
C3-37
C3-38
C3-41
C3-49
C3-53
C3-58
C3-68
C3-69
C4-18
C4-19
C4-20
C4-36
C4-37
TC-IV
Title
4.6
4.7
4.8
Page
C4-39
C4-40
4.13b
4.13c
4.13d
4.14
5.1
6.1
6.2
7.1
7.2
7.3a
7.3b
7.4a
C4-57
C4-58
C4-58
C4-63
C5-9
C6-16
C6-17
C7-5
C7-7
C7-25
C7-25
7.4a
7.5a
7.5a
7.6a
7.6b
7.7
7.8
9.1
9.2
C4-46
C4-50
C4-51
C4-52
C4-56
C4-57
C7-27
C7-27
C7-29
C7-29
C7-30
C7-30
C7-36
C7-46
C9-3
C9-4
TC-V
List of Tables
Tables
1.1
1.2
1.3
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10a
2.10b
2.11
2.12
2.13
2.14
2.15
2.16
2.17
2.18
2.19
2.20
3.2.1
3.2.2
3.2.3
3.2.4
3.3.1
3.3.2
3.3.3a
3.3.3b
3.4.1
3.4.2
3.4.3
3.5.1
3.5.2
3.6.1
3.6.2
3.6.3
3.7.1
3.7.2
3.7.3
3.8.1
3.8.2
3.9.1
Title
Environmental Setting of the Site
Demand Availability and Resultant GAPS /Surpluses
Environmental Attributes and Frequency of Monitoring
Product Details
Major Plant Facilities
Landuse Breakup
Land Breakup of the Project Area
Present Landuse
Energy & Gas Balance
Power Requirement
Main Water Re-circulation Systems
Technology Facility at various Processing Levels
Typical Technical Features for each 3 MTPA CO Plant
Technical Features for each CDQ unit
Operating Parameters of each Sinter Plant
Annual Raw Materials (Wet & Dry Basis) Requirement
Typical Chemical Properties of Iron Ore
Typical Chemical Properties of Coking Coal
Typical Chemical Properties of PCI Coal
Desirable Chemical Analysis of Limestone
Typical Chemical Properties of Quartzite
Major Elements and Trace Elements in Raw Material
Quantities and Storage Capacities of Major Raw Materials
Source and Nature of Pollution
Well Inventory in Study Area
Pumping Test Data in Large dia Dug Well
Recovery data in Large dia Dug Well
Pumping Test Data Analysis
Landuse Pattern in the 10 km Study Area
Landuse / Land Cover Classification System
Landuse Breakup of the Study Area
Landuse Breakup of the Project Area
Details of Soil Sampling Locations
Soil Analysis Results
Standard Soil Classification
Climatological Data Station Ranchi
Summary of the Meteorological Data Generated at Site
Details of Ambient Air Quality Monitoring Locations
Summary of Ambient Air Quality Results
Summary of Chemical Characterization of RSPM
Details of Water Sampling Locations
Surface Water Quality
Ground Water Quality
Details of Noise Monitoring Locations
Ambient Noise Levels in the Study Area
Details of Ecological Sampling Locations
Page
C1-3
C1-9
C1-12
C2-1
C2-8
C2-9
C2-10
C2-10
C2-12
C2-13
C2-14
C2-16
C2-23
C2-23
C2-26
C2-42
C2-43
C2-44
C2-44
C2-45
C2-45
C2-46
C2-49
C2-53
C3-9
C3-13
C3-14
C3-14
C3-16
C3-17
C3-19
C3-20
C3-25
C3-27
C3-28
C3-31
C3-32
C3-40
C3-44
C3-45
C3-47
C3-50
C3-51
C3-54
C3-55
C3-59
TC-VI
Title
Page
TC-VII
Title
Page
6.3
6.4
6.5
6.6
6.7
6.8
6.9
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.10
7.11a
7.11b
7.11c
7.11d
7.12
7.13a
7.13b
Implementation Schedule
C6-9
Environment Monitoring and Frequency
C6-9
Cost Provision for Environmental Measures
C6-11
Recommended Plant Species for Greenbelt
C6-13
Greenbelt Development Plan
C6-14
Pre Development Annual & Monsoon Run-off from the CatchmentC6-14
Pre Development Annual & Monsoon Run-off from the WatershedC6-15
Compliance of Queries Raised by Technical Committee
C7-1
Public Hearing Issues and Action Plan
C7-9
Category Wise Schedule of Storage Tanks
C7-13
Hazardous Materials stored, Transported and Handled
C7-13
Properties of Fuels used in the Plant
C7-14
Applicability of GOI Rules to Fuel/Chemical Storage
C7-16
Preliminary Hazard Analysis for Storage Areas
C7-16
Preliminary Hazard Analysis for the Whole Plant in General
C7-17
Fire Explosion and Toxicity Index
C7-17
Fire Explosion and Toxicity Index
C7-18
Damage due to Incident Radiation Intensities
C7-19
Exposure Time Necessary to Reach the Pain Threshold
C7-19
Physical Impact of Explosion Over Pressure
C7-19
Physical Impact of Toxic Concentration
C7-20
Pasquill-Gifford Atmospheric Stability Classes
C7-21
Toxicological Levels Considered for Consequence Analysis
C7-22
Flammable and Explosive Levels Considered for Consequence
Analysis
C7-22
7.14 Maximum Impact distance for Toxic/Flammable Vapour Cloud
Of Carbon Monoxide Gas from BF/CO Gas Holders
C7-24
7.15 Various Scenarios of Hydrogen
C7-26
7.16a Thermal Radiation Levels due to Failure of LPG Bullet
C7-28
7.16b Explosive Over Pressure Levels due to Failure of LPG Bullet
C7-28
7.17 Thermal Radiation due to failure of HFO/LDO Tanks
C7-28
7.18 Hazard Analysis for Process in the Plant
C7-32
7.19 Hazardous Events contributing to On-site Facility Risk
C7-32
8.1
Budget for Proposed CSR Programs
C8-6
8.2
Detailed CSR Action
C8-6
10.1 Major Plant Facilities
C10-1
10.2 Solid Waste Generation and Disposal
C10-6
10.3 Hazardous Waste Generation and Disposal
C10-7
10.4 Budget for Proposed CSR Scheme
C10-9
10.5 Cost Provision for Environmental Measures
C10-10
TC-VIII
EXECUTIVE SUMMARY
Project Proponent:
Environment Consultant:
March 2015
1.0
PROJECT DESCRIPTION
1.1
Introduction
M/s. JSW Jharkhand Steel Limited propose to install 10.0 million tonnes per
annum (MTPA) integrated steel plant along with 900 MW captive power plant
(CPP) and township near Barenda village, Sonahatu block in Ranchi district of
Jharkhand state.
The proposed project has been envisaged keeping in view the growing demand of
steel in domestic as well as international market. The project has been envisaged
in Jharkhand state, based on the availability of raw materials and resources and
availability of good connectivity to the markets. The proposed plant will have
positive impact on socio-economic development of local people. Total project cost
is estimated to be about Rs. 35,000 crores and EMP cost is about 1750 crores.
The proposed project can be classified as 3(a) type activity under the category A
as per EIA notification dated 14th September 2006.
1.2
Environmental Setting
The study area map of 10 km radius around the proposed site is given in Figure1. The environmental setting of the proposed project is as follows:
The proposed plant falls at the intersection of latitude 2308'45.2"N2311'2.3"N and longitude 854730.2"E - 8550'9.2"E and at an elevation of
about 220-240 m above mean sea level (MSL);
11 protected forests and one reserve forest block exists within 10 km radius;
Nearest major town from the plant is Muri and city is Ranchi;
Nearest village from the plant is Barenda and is located at about 0.5 km in north
direction;
Nearest railway station from the plant is Suisa at about 7.7 km in east direction;
and
Proposed plant site does not fall in any critically polluted areas as per the
CPCB/MoEF circular dated January 2010.
FIGURE-1
STUDY AREA MAP (10 KM RADIUS)
VIMTA Labs Limited, Hyderabad
2.0
PROCESS DESCRIPTION
The integrated steel plant consists of a number of unit processes. It is proposed
to adopt the BF-BOF route for the proposed integrated steel plant. The ore burden
of the blast furnace will comprise a high proportion of sinter, pellet along with
some sized ore. This charge mix will also enable to achieve low levels of coke
consumption in the blast furnace.
It is proposed to install a pellet plant. This pellet plant will produce BF grade
pellets to be used in blast furnace.
Hot metal production using blast furnace process has been envisaged for the
proposed project, as the process is most established and competitive iron making
technology till date. A number of technological improvements have taken place in
blast furnace, which have resulted in higher production, less coke consumption,
most energy efficient, long campaign life, etc. The hot metal produced from the
blast furnace will be transported to the steel melting shop using hot metal ladles.
Basic Oxygen Furnace (BOF) technology for production of liquid steel has been
envisaged for the proposed project. This process till date dominates the steel
production scenario of high capacity integrated steel plant worldwide mainly due
to its energy efficiency. As such, external energy in terms of either electrical
power or solid/liquid/gaseous fuel is not required for process. However,
requirement of electricity and gaseous fuel are mainly for driving of electrical
equipment, ladle heating, etc. Most of the other steel making process except BOF
like electric arc furnace/ induction furnace process consumes high amount of
electrical energy. However, oxygen with high purity is required for conversion of
hot metal to liquid steel and scrap/iron ore/DRI is required as coolant in BOF
process. A significant amount of medium calorific value (2000 kCal/Nm3) gas is
generated during carbon refining reaction period of steel making which will be
cleaned in the gas cleaning plant. Hot metal will be pre-treated before charging
into the converter.
With a view to achieve improved homogeneity and productivity of the primary
unit and serving as a buffer between the primary unit and the caster, ladle
furnace is the ideal secondary refining unit. The correction and homogenization of
steel composition and temperature, desulphurization and decarburization, etc.
can be efficiently carried out in a ladle furnace.
The liquid steel from the BOF converters will be continuously cast into
slabs/billets/blooms through conventional casters, which will subsequently
produce HR/CR Coils, sections, wire rods, bars etc.
2.1
Raw Material
3
4
5
8
9
Coking coal
Coking coal
Non-coking coal for PCI
gross
Thermal coal
Bentonite
Ferro alloy
Limestone (cement
grade)
10
11
12
13
14
Source
Captive mine (Ankua) /
other mines in
Jharkhand
Captive mine(s) (Ankua)
/ other mines in
Jharkhand
Madhya Pradesh
Madhya Pradesh
Jharkhand
Satna Maihar
/Imported
Madhya Pradesh
/Imported
Captive mines (Rohne)
Imported
Quantity
in TPA
Mode of
Transportation
to Site
Rail
29,000,000
Rail
900,000
1,300,000
1,100,000
140,000
1,600,000
700,000
5,520,000
4,800,000
2,300,000
Captive mines
Jharkhand
Jharkhand
3,000,000
400,000
200,000
Jharkhand
6,000,000
Rail
Rail
Road
Rail /Road
Rail /Road
Rail
Rail
Rail
Rail
Rail /Road
Road
Rail /Road
Water Requirement
The total water requirement for the proposed plant will be about 80 Million
Gallons per day (MGD), i.e. about 15150 m3/hr including water requirement for
the proposed CPP. About 46.7 MGD of the required water will be sourced from
Subarnrekha river, which flows at a distance of about 2.4 km from the plant site
in north direction and remaining 33.3 MGD of required water will be drawn from
Chandil dam (downstream).
Manpower
Considering a labour productivity of 1,000 tonnes of finished steel per man-year,
which is at par with international standard, the requirement of total manpower
works out to about 5,000 in phase-I and about 10,000 in final phase at 10.0
MTPA production level.
However, the proposed 10.0 MTPA integrated steel plant will additionally generate
more than 20,000 to 30,000 indirect secondary and tertiary employment. It is
expected that a number of ancillary industries will develop near the proposed site,
which will be mutually beneficial.
The manpower required for the proposed project will be about 20,000 persons
during construction and 10,000 during operation phase including skilled and
unskilled workers.
Township
A full-fledged township developed for proposed plant will be utilized for
accommodating the staff. Other amenities such as school, community center,
hospital, shopping complex, post office, bank etc will be established as required in
the township.
3.0
Soil Environment
A total of 10 samples within the study area were collected and analyzed. It has
been observed that the texture of soil is mostly sandy clay in the study area. It
has been observed that the pH of the soil quality ranged from 7.5 to 8.1 indicating
that the soil is slightly alkaline in nature. The electrical conductivity was observed
to be in the range of 268 to 480 S/cm. Available potassium was observed to be
in the range of 341.0 to 457.3 kg/ha. The nitrogen values range between as
162.8 to 230.2 kg/ha and the phosphorus values observed in sampling locations
varies between 42.0 to 66.6 kg/ha.
Meteorology
The meteorological parameters were recorded on hourly basis during the study
period near proposed plant site and comprises of parameters like wind speed,
wind direction (from 0 to 360 degrees), temperature, relative humidity,
atmospheric pressure and rainfall. The summary of meteorological data generated
at site is presented in Table-2. The predominant wind directions during study
period are from northwest.
TABLE-2
METEOROLOGICAL DATA GENERATED AT SITE
Month
March 2014
April 2014
May 2014
Range
Temperature (0C)
Max
Min
40.5
16.6
42.5
20.5
43.4
21.0
16.6-43.4
Rainfall
(mm)
16
Nil
Nil
16
5
Air Quality
The study area represents mostly rural/residential environment. Ten ambient air
quality monitoring stations were selected in and around project site and studies
were carried out as per CPCB guidelines. The summary of ambient air quality data
generated during monitoring period is given in Table-3. Ambient air quality
analysis reveals that these results are well within limits in all locations as per
national ambient air quality standards 2009.
TABLE-3
SUMMARY OF AMBIENT AIR QUALITY RESULTS
Sr. No
1
2
3
4
5
Parameters
Particulate Matter (PM10)
Particulate Matter (PM2.5)
Sulphur Dioxide (SO2)
Nitrogen Dioxide (NOx)
Carbon Monoxide (CO)
Range, g/m3
37.0-52.7
19.1-25.9
9.3-12.2
11.5-16.0
200-371
Water Quality
Eight ground water samples and eight surface water samples were collected. These
samples were taken as grab samples and were analyzed for various parameters to
compare with the standards.
The analysis results indicate that the pH ranges in between 7.2 to 7.6, which is well
within the specified standard of 6.5 to 8.5. Total hardness was observed to be
ranging from 46.0 to 233.0 mg/l. The hardness was found to be well within the
limit of 600 mg/l at all locations.
Chlorides at all the locations were within the permissible limit, ranging in between
10.5 to 62.5 mg/l. Fluorides were observed to be ranging in between 0.2 to 0.6
mg/l and are found to be within the permissible limit. Nitrates are found to be in
range of 2.0 13.0 mg/l. Bacteriological studies reveal that no coliform bacteria
are present in the samples. The heavy metal contents were observed to be in well
within the limits.
The analysis results indicate that pH is found to be in the range of 7.3-7.8, which is
well within the specified standard 6.5-8.5. The TDS was observed to be in the
range of 92.0-660.0 mg/l. Dissolved Oxygen was observed to be in the range of
5.3-6.2 mg/l. The chlorides and sulphates were found to be in the range of 11.5121.5 mg/l and 3.2-16.3 mg/l respectively. It is observed that chlorides and
sulphates are well within the permissible limits. It is evident from the above values
that all the parameters are well within the permissible limits. Bacteriological studies
VIMTA Labs Limited, Hyderabad
reveal the absence of E. coli forms. The analysis results indicate that there is no
evidence of any industrial contamination.
The noise monitoring has been conducted for determination of noise levels at ten
locations in the study area. Noise monitoring results reveal ambient noise levels in
all locations are well within the limits as per ambient noise standards.
From the field observations, it can be concluded that the forests in the study area
are under high anthropogenic pressure and show signs of degradation in the form of
tree cutting, lopping, poaching, grazing, collection of NTFPs and habitat
fragmentation.
As per MOEF and forest department, Jharkhand reveals that there are no wildlife
sanctuaries, national parks/biospheres in 10 km radius from the proposed site
boundary. As per the records of the botanical survey of India there are no plants of
conservation importance in the study area.
On comparison of the check list given in the Schedule-I of the Wildlife (Protection)
Act 1972 and the list of wildlife recorded in the study area, it can be concluded that
no species of schedule-I animals exist in the study area and rest of the species
belong to Schedule-II, III, IV and V of Wildlife (Protection) Act, 1972.
4.0
IMPACT ASSESSMENT
4.1
Fugitive Emissions
Fugitive dust emissions from the proposed plant would be significant as there will
be air pollution due to activities like transport of iron ore, limestone, coal
handling, crushing unit, cement plant and CPP generally due to the movement of
vehicles on the roads.
Impact on Water Resources
In the proposed steel plant, the major water requirement will be for the power
plant, slag granulation, DM and softener plant, gas cleaning plant, domestic and
general purposes. There will not be any discharge of wastewater into the surface
water resources from the plant under normal circumstances of dry weather
conditions. Hence, the impact on the surface water quality is not envisaged.
Impact on Noise Levels
The main noise generating sources will be from sinter plant, pellet plant, blast
furnace, DR plant and captive power plant. There will be associated road or rail
traffic, including truck movement and loading equipment. Consequently steel
manufacturing is likely to generate noise and vibration. Noise and vibration is
greater from heavy truck traffic associated with operations and transport of raw
materials and finished product.
Impact on Ecology
The impact of air pollutants on vegetation due to the proposed project is
identified and quantified by using air dispersion modeling. The simulations have
been done to evaluate PM10, SO2 and NOx likely to be contributed by the proposed
project activities, the resultant concentrations for study period are within the
limits as per National ambient air quality standards.
No wildlife sanctuaries are found within 10 km radius of the project site. Hence,
no impact is envisaged on the wildlife due to proposed plant. Similarly, as per the
forest department, no endangered or rare species of flora and fauna are reported
or observed in the study area.
5.0
5.1
Water sprinkling;
The felling of trees will be kept at minimum;
The greenbelt will be developed; and
To maintain condition of construction equipment and prevention maintenance so
that minimum disturbance to the surrounding environment.
5.2
The raw material handling section would be provided with dust suppression
(DS)/dust extraction (DE) systems complete with bag filters/ESPs;
The principal air pollution control system for sinter plant would consist of dedusting and waste gas cleaning systems separately;
The coke oven gas generated in the coke ovens after by-product recovery
would be utilized as supplementary fuel for proposed steel plant complex;
The top gas coming out from the blast furnace would be cleaned by taking the
gas through BF gas cleaning device for separation of particulate before the
clean gas is recovered for meeting in-plant energy demand. The stock house
and cast house areas would be provided with proper DE/FE systems complete
.with ESPs and stacks;
The LD gas generated in the SMS shop would be subjected to wet cleaning
before it is used as plant supplementary fuel. There would be proper fume
extraction systems to capture any secondary fumes generated during hot
metal and liquid steel transfer points. Dust emission from calcining plant
would be controlled by bag filters. WHRB will be installed with ESP for control
of air emissions;
Captive power plant will be provided with ESP and adequate stack height of
275 m.
Fugitive Emissions
Technologies/Current Practices
Coke Ovens
In coke ovens, the volatile materials
released during cooking flows from
the oven to the by-product plants
where ammonia, benzol, xylene,
toluene, tar, pitch and tar acids are
recovered.
The
operations
are
associated with fugitive and stack
emissions. The PAH compounds
released during cooking operation as
Requirements
Automation
operations;
for
process
10
Sr. No
Technologies/Current Practices
fugitive emissions are carcinogenic
in nature.
The technologies available to control
the pollution are:
HPLA system;
Hydraulic door and door frame
cleaner;
Doors with double knife edge
and rope sealing;
Water sealed AP caps; and
Screw feeder.
Sintering Plant
Requirements
Proposed coke dry quenching;
3
4
6
7
Proper
operation
and
maintenance of ESP / bag filter /
wet scrubber for air emissions;
BF slag utilization.
Effective operation and maintenance
of ESP / bag filter / multiclones for
process
and
work
zone
dust
emissions.
Improvements in the systems for
controlling fugitive emissions.
Noise level can be reduced by stopping leakages from various steam lines,
compressed air lines and other high pressure equipment;
11
Providing noise proof cabins to operators where remote control for operating
noise generating equipment is feasible;
The air compressor, process air blower, pneumatic valves should be provided
with acoustic enclosure;
The noise control system will be designed to form an integral part of the
plant;
All the openings like covers, partitions will be designed properly; and
Inlet and outlet mufflers will be provided which are easy to design and
construct.
Pollutants
Oil
Rolling oil
Lubricants
Source
Hot and cold rolling mills
Various
electrical
and
mechanical equipment and
machine
halls.
Spills
segregated
Treatment/Disposal/Use
Settling tanks fitted with oil and
grease traps; Used oil collected for
incineration
Floor
spills
soaked
up
on
adsorption compound; cutting oil
and other emulsion segregated for
incineration; oily water skimmed
at source and free oil collected for
12
Sr. No.
Pollutants
Fuel oil
Solvents
Tar
Quench oil
Hydraulic
Pumps, winches and
oil
presses
Suspended Solids
Scale
Casters
Burden
fines
Fly ash
Coal
and
coke fines
Chemicals
Acid
sludge
Caustic
wash
Lime
Brine
Cleaners
Source
Toxic
chemicals
Heat
Cooling
water
Boiler blow
down
Treatment/Disposal/Use
incineration
Spills segregated by dykes and
incinerated
Collected for incineration
Collected for sale
Soldom replaces, can be
incinerated
Spills segregated and incinerated
By product plant
Regenerated or burnt
By product plant
Incinerated
Mould or steel
Coating
water
softner
sludge
Ion
exchange
resin
regenerations
Surface treatment,
degreasing
Coke oven gas, lime drips
and metal treatment
Recovery
for
pickle
liquor
treatment, control release to
wastewater
Reclaimed or regulated release to
wastewater
Segregated for oil recovery or
incinerated
Chemical or biological destruction,
incineration
13
Non-Hazardous Waste
The main solid waste generated in the proposed steel plant will be BF slag, BOF
slag which is non-hazardous waste. Other solid waste includes gas cleaning plant
sludge, dust from ESP, bag filter and dust extraction system and refractory debris
etc., this solid waste except refractory will be completely reused in sinter plant
and coal fines will be used in the power plant. Further, Oil soaked cotton waste,
organic wastes from steel plant, paper, plastics and waste bag filters will be
generated. The non-hazardous waste and hazardous waste generation and its
disposal are given in Table-4 and Table-5 respectively.
TABLE-4
SOLID WASTE GENERATION AND DISPOSAL
Sr. No
1
Solid waste
Generation TPA
Proposed disposal
98 % granulated and sold to
Cement plants, 2% treated in
dry pits and used for land fill
BOF slag is granulated ,
metalics separated and used
in construction
Slag
30,00,000
14,80,000
Sludge
1,29,000
1,51,000
Slimes from
Beneficiation plant
Mill scales
58,00,000
38,000
1,49,000
1,06,572
3,43,428
38,000
4
A
B
5
A
B
Rolling mills
Dusts
Flue dust from Blast
furnace
Dust from bag filter
Ash
7,50,000
16,00,000
50,000 -1,00,000
14
TABLE-5
HAZARDOUS WASTE GENERATION AND ITS DISPOSAL
Sr. No
Category
Quantity KL or
T/Yr @ 10 MTPA
1
2
2750 KL / Year
450 t
8.7 t/y
59 t/y
3
4
5
73216000 KL
315 t
8172 t
Proposed disposal
Sold to authorised parties
Regenerated in ARP
Regenerated in ARP
Used back in Coke oven
Sent to hazardous waste land
fill
Incinerated
Greenbelt Development
The greenbelt will be developed along the periphery of the plant and all open
spaces within the plant area covering an area of 465 ha and vegetation density of
about 2500 trees/ha. Accordingly, about 11,62,500 saplings will be planted.
Due care will be taken to ensure that a greenbelt is developed around the plant
and colony. All areas devoid of vegetation and having low density will be
systematically and scientifically afforested. JSW-JSL has proposed to develop
greenbelt in 30 % of area.
The anticipated capital expenditure for the environment management is about Rs.
1750 crores.
6.0
7.0
PROJECT BENEFITS
Proposed plant will result in considerable growth of stimulating the industrial and
commercial activities in the state. Small and medium scale industries may be
further developed as a consequence.
15
Air quality;
Water and wastewater quality;
Noise levels;
Soil quality; and
Greenbelt development.
CONCLUSION
The proposed integrated steel plant has certain level of adverse impacts on the
local environment. However, with the judicious implementation of the proposed
pollution control and environment management measures, even the adverse
impacts anticipated due to construction and operation of the proposed steel plant
will be mitigated. Further, development of this project has certain major
beneficial impact/effects in terms of bridging the steel demand and supply gap
and providing employment opportunities that will be created during the course of
its setting up and as well as during the operational phase of the project.
Thus, in view of considerable benefits from the project with containable adverse
environmental impacts, the proposed project will be most advantageous to the
region as well as to the nation.
****
16
1.0
INTRODUCTION
M/s. JSW Jharkhand Steel Limited proposes to establish 10.0 Million Tonnes Per
Annum (MTPA) capacity Integrated Steel Plant (ISP) along with 900 MW Captive
Power Plant (CPP) and township near Barenda village, Sonahatu block in Ranchi
district of Jharkhand state.
This chapter describes the purpose of the present Environmental Impact Assessment
(EIA) report, identification of the project and project proponent, brief description,
nature, size, location of the project and importance to the country, region. The
chapter also includes the details of regulatory scoping carried out as per Terms of
Reference (ToR) issued by the Ministry of Environment Forests and Climate Change
(MoEF & CC), Government of India (GoI), New Delhi.
1.1
1.2
1.2.1
1.2.2
C1-1
in its individual companies, with each one committed to consolidate its core strength
and excelling in its field of specialization.
JSW Steel Limited operates a 10 MTPA steel plant at Vijayanagar, Bellary district of
Karnataka based on COREX & BF-BOF-CC-HSM process route and one of the largest
private steel producer in single location in India. JSW also has cold rolling,
galvanizing, galvalume and colour coating plants at Tarapur and Vasind in
Maharashtra.
The JSW group owns and operates JSW Salem Works, which is the only integrated
steel plant in Tamil Nadu. The plant has a capacity of 1.0 MTPA and there are plans to
further expand to 2.0 MTPA. JSW operates Dolvi works near Mumbai, with a capacity
of 3.0 MTPA and is in process of expanding to 5.0 MTPA.
JSW Vijayanagar works has been declared the winner of Prime Ministers Trophy for
excellence in performance for the year 2012-13. A copy of letter received from MoS,
Government of India is enclosed as Annexure-III.
1.2.3
1.3
1.3.1
1.3.2
C1-2
site is well drained. These lands are basically rainfed single crop oriented lands. The
site is generally a plain land with mild slopes.
The index map, study area map covering 10 km radius from the proposed plant site
on topo sheet and google map are shown in Figure-1.11, Figure-1.2 and Figure1.3 respectively. The environment settings surrounding the project site are given in
Table-1.12.
TABLE-1.1
ENVIRONMENT SETTING IN 10 KM RADIUS
Sr. No.
1
Particulars
Project area
Climatic conditions
(Based on IMD Ranchi
50 km, SE)
Site specific
data
7
8
9
10
11
12
Nearest highway
Nearest railway station
Nearest airport
Nearby villages
Nearest own
Reserve forest/ protected
forest
climatological
Details
Near Barenda village, Sonahatu block, Ranchi
district, Jharkhand state
Coordinates- Latitude & longitude
A : 23 11 1.6 N, 85 47 30.2 E
B : 23 11 2.3 N, 85 49 43.4 E
C : 23 11 2.3 N, 85 50 09.2 E
D : 23 09 12.6 N, 85 50 5.4 E
E : 23 08 45.2 N, 85 49 5.6 E
F : 23 10 16.9 N, 85 47 49.1 E
220 m-240 m aMSL
Annual mean max temp: 38.20C (summer)
Annual mean min temp: 9.70C (winter)
Annual total rainfall: 1454.9 mm
Predominant wind direction :NW,SW and W
Monitored at Barenda : (summer-2014)
Maximum temperature: 42.30C
Minimum temperature: 17.3 0C
Predominant wind direction: NW,SW and W
Present land is partially flat and undulating. Plant
site consists of mostly rain fed cropland and
barren land.
National Highway-33 (15.5 km, SW)
Suisa (7.7 km, E)
Ranchi (50 km, SE)
Barenda (0.5 km, N)
Muri Town (20 km, N)
i. PF near Barenda village (0.5 km, NW)
ii. PF near Mahil village (0.6 km, ESE)
iii. PF near Tetuldih village (1.7 km, NNE)
iv. PF near Pepride village (2.9 km, S)
v. PF near Rohardih village (4.0 km, ESE)
vi. PF near Garadih village (4.1 km, ESE)
vii. PF near Bhusudih (4.6 km, SSW)
viii. PF near Chatam village (4.7 km, SE)
ix. PF near Mukrub village (5.8 km, NE)
x. PF near Saparum village (6.9 km, ESE)
xi. PF near Barukande village (7.9 km, SSW)
xii. Kalimati RF (8.2 km, NE)
C1-3
Plant Site
Ref:-Maps of India
FIGURE-1.1
INDEX MAP
VIMTA Labs Limited, Hyderabad
C1-4
FIGURE-1.2
STUDY AREA MAP (10 KM RADIUS)
VIMTA Labs Limited, Hyderabad
C1-5
10KM
F
D
E
LEGEND
Plant Area
Township
Railway Siding
FIGURE-1.3
GOOGLE MAP
VIMTA Labs Limited, Hyderabad
C1-6
Sr. No.
13
14
15
16
17
18
19
Particulars
Ecologically sensitive zones
like wild life sanctuaries,
national parks, elephant and
tiger reserves, migratory
routes
and
biospheres
(existing or proposed)
Archaeological monuments
Water bodies
Defence Installations
Nearest Port
Seismicity Zone
Name of the industries 3with
in 25 km radius
Details
None within 10 km radius.
Certified map (SOI topo sheet) received from
Chief wild life warden (CWLW), Jharkhand
certifying the same. The certified copy is enclosed
in Annexure-IV
None within 10 km radius
Domra nadi (adjacent in south)
Kanchi river (2.0 km, NW)
Subarnarekha river (2.4 km, NNE)
Raru nadi (5.0 km, N)
None within 10 km radius
Haldia port (250 km, SSE)
Zone-II as per IS:1893 (Part-1) 2002
No operating industries within 25 km radius
There are 2 proposed greenfield industries within
25 km
- Tata Power Ltd (Energy-10 km) and
- Hindalco Industries Ltd Sonahatu,
Alumina Smelter & Power - 5 km).
Few operating brick kilns are observed.
1.3.3
C1-7
Production
The finished steel production in India has grown from a mere 1 Mt in 1951 to 13.2 MT
in 1990-91 and further increased to 71.3 MT in 2011-12. During the first two decades
of the planned economic development, i.e. 1950 to 1960-61 and 1960-61 to 1970-71,
the average annual growth rate of steel production has been about 8%. However,
this growth rate could not be maintained in the following two decades. During 197071 to 1980-81, the average annual growth rate in finished steel production came
down to 5.2% and picked up marginally to 5.6% during 1980-81 to 1990-91.
However, average annual growth during 1990-91 to 2000-01 has been encouraging
to the level of 8%. The production of finished steel grew by 16.52 %, from 44.54 MT
in 2005-06 to 49.39 MT in 2006-07. The finished steel production for the 2008-09
registered a growth of 0.6% over 2007-08. Based on the assessment of the current
ongoing projects, both in greenfield and brownfield, the working group on steel for the
12th Plan has projected that the crude steel capacity in the country is likely to be 120
MT by 2020.
Demand
Domestic Demand
Generally, a developing economy undertakes large number of infrastructure projects,
which are necessary for building of the nation and ensuring economic growth. China
is a leading example of the economic growth through phenomenal development of
infrastructure.
The Indian economy grew at 6.5% in 2011-12, down from 8.4% in 2010-11. The GDP
growth in 2011-12 was the lowest in the past nine years.
Global crisis, geopolitical disturbances and weather extremities contributed to the
domestic economic slowdown. The industrial sector growth slowed to 3.4% in 201112 against 7.2% in 2010-11 and was primarily responsible for the slowdown of Indias
economic progression. Present low per capita consumption in India is expected to
drive demand for steel, which is likely to grow @ 7.5% per annum as per Ministry of
Steel, Government of India projections, as detailed in the National Steel Policy 2005.
Export Demand
Though India started steel production in 1911, steel exports from India began only in
1964. Exports in the first five years were mainly due to recession in the domestic iron
and steel market. Once domestic demand revived, exports declined. India again
started exporting steel only in 1975 touching a figure of 1 MT of pig iron and 1.4 MT
VIMTA Labs Limited, Hyderabad
C1-8
Resultant Gaps/Surpluses
Based on the demand and availability, future gaps and surpluses have been projected
in Table-1.2.
TABLE-1.2
DEMAND, AVAILABILITY AND RESULTANT GAPS/SURPLUSES
Sr. No.
Products
Steel Products
Non Flat Products
Wire Rods
Demand
Availability
- Gaps/Surpluses*
Light Merchant Products
Demand
Availability
- Gaps/Surpluses*
Medium Merchant Products
Demand
Availability
- Gaps/Surpluses*
Heavy Sections
Demand
Availability
- Gaps/Surpluses*
Flat Products
HR Plates
Demand
Availability
2006-07
2011-12
2016-17
6040
4940
- 1100
8840
4940
- 3900
12970
4940
- 8030
9790
10150
(+) 360
14060
11900
(-) 2160
20220
11900
(-) 8320
2440
2115
(-) 325
3465
2115
(-) 1350
4910
2115
(-) 2795
560
720
(+) 160
750
820
(+) 70
1000
820
(-) 180
3680
1350
5175
2700
6900
2700
C1-9
Sr. No.
6
Products
- Gaps/Surpluses*
HR Coils /Sheets
Demand
Availability
- Gaps/Surpluses*
2006-07
(-) 2330
2011-12
(-) 2475
2016-17
(-) 4200
14400
12040
(-) 2360
23160
16180
(-) 6980
42525
16180
(-) 26345
1.4
To conduct literature review and to collect data relevant to the study area;
To predict incremental levels of pollutants in the study area due to the proposed
project activities;
C1-10
Existing topography, location of surface water bodies like ponds, canals and
rivers;
Field studies have been conducted for a period of three months (March 2014 to May
2014) representing pre-monsoon season to determine existing conditions of various
environmental attributes as outlined in Table-1.3. The applicable environmental
standards for the project are given in Annexure-V and the methodology of
monitoring and analysis is given in Annexure-VI.
C1-11
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township
near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-1
Introduction
TABLE-1.3
ENVIRONMENTAL ATTRIBUTES AND FREQUENCY OF MONITORING
Sr.
No.
1
Environmental
Component
Surface
meteorology
Ambient
Quality
Water Quality
Air
Sampling
Locations
Sampling
Parameters
One
central
location
Temperature, wind
speed,
wind
direction
10 locations
16 locations
Total
Sampling
Period
3 months
Hourly
Rainfall
3 months
Daily
Rainfall: 0.2 mm
Relative humidity,
cloud cover
As
per
NAAQS
2009
3 months
Hourly
RH: +/- 3%
24 hourly
PM10: 5 g/m3
PM2.5: 2 g/m3
SO2: 4 g/m3
NOx: 9 g/m3
CO: 12.5 g/m3
O3 : 2 g/m3
Pb : 12.5 g/m3
As per IS:10500
Grab sampling
Once in
period
study
Grab sampling
Once in
period
study
(8-surface
water
8-ground
water)
Sampling
Frequency
Detection Limit
EC:+/-0.1 us/cm
TSS/TDS: 0.5 mg/l
O&G:0.1mg/l
DO: 0.5 mg/l
BOD:2 mg/l
COD: 0.5 mg/l
Ca, Mg, Na, K: 0.1
mg/l Alkalinity, PO4,
SO4, Cl, NO3: 0.1 mg/l
Coliform: 1 MPN
0.001 mg/l
Methodology
The
meteorology
parameters
were
recorded
using
automatic
micrometeorological equipment consisting of
anemometer, wind wane and thermometer.
Review of secondary data collected from
IMD station at Ranchi.
Rainfall was recorded every morning at
0830 hours
Automatic Humidity was recorded.
Gravimetric method for PM10 and PM2.5.
Modified West & Gaeke method for SO2
(IS-5182 part-II 1969) using tetrachloro
mercurate 0.01 N absorbing solution.
Jacob-Hochheiser method (IS-5182 part-IV
1975) for NOX using sodium arsenate
absorbing solution of 0.01 N absorbing
solution. CO was measured by GC method.
As per APHA methods. The conductivity,
temperature
were
analyzed
at
site
laboratory and rest of the parameters were
analyzed at VIMTA's central laboratory at
Hyderabad.
C1-12
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and Township
near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-1
Introduction
Sr.
No.
Environmental
Component
Sampling
Locations
Sampling
Parameters
Noise
10 locations
Leq
Soil
10 locations
Terrestrial
Ecology
Total
area
study
Soil
profile,
chemical
constituents,
suitability
for
agricultural growth
Flora and fauna
Total
area
study
Demography and
Socio-economic
aspects
Land Use
Total
area
Geology
Hydrogeology
(Surface
and
ground)
10
Total
Sampling
Period
Hourly
readings
for
24 hours
Composite
sample up to
1.0 m depth
Sampling
Frequency
Once in
period
study
Detection Limit
Methodology
Once
during
study period
Field
observations
Once in
period
Demographic
profile
study
Total
area
study
Geological history
Total
area
study
Drainage pattern,
nature of streams,
aquifer
characteristics,
recharge
and
discharge areas
study
per
Secondary
information
sources
like
(Geological survey of India and Central
Ground Water Board)
****
soil
C1-13
2.0
PROJECT DESCRIPTION
2.1
Introduction
This chapter presents the major resources required for proposed project, project
schedule, process description, technological facilities and plant configuration, raw
material requirement and handling and likely environmental effects due to the
proposed project.
2.2
Type of Project
The proposed green field project of JSW Jharkhand Steel Limited comprises of an
integrated steel plant, CPP and a cement plant within a single plant complex. The
proposed 10.0 MTPA integrated steel plant has been proposed in Jharkhand state
on the basis of the growing domestic as well as international demand in steel
sector and availability of raw material and infrastructure.
A coal/gas based CPP of 900 MW capacity is proposed to meet the power
requirement for the proposed steel plant within the plant complex. A 6.0 MTPA
cement plant will also be installed to utilize the blast furnace (BF) slag and fly ash
generated from steel plant and CPP to the extent possible.
Products
Steel Products
HR Coils
Bars
Wire Rods
Medium Sections
Heavy Sections
Cold Rolled Coils
Plates
Galvanised Steel
Tin Plates
Electrical Steel
Colour Coating
Pellets
Cement
Quantity (MTPA)
4.5
1.0
1.0
1.2
2.2
2.3
1.5
1.0
1.0
1.0
1.0
3.0
6.0
Capacity of the plant is 10 MTPA, apart from the above mentioned, there will be
power generation of 900 MW for captive usage.
C2-1
2.3
2006-07
(million tonnes)
39.5-40.7
2012-13
(million tonnes)
77.8 78.0
2019-20
(million tonnes)
140
JSW Jharkhand Steel Limited (JSWJSL) has drawn up a growth plan with the
objective of increasing its market share, including market penetration and
maintaining its leading position in Indian steel industry. One of the key objectives
of JSWJSL is to be of a world-class company and leader in Indian steel business
horizon by leveraging its key competencies. This core competency will enable
JSWJSL to manufacture products at a lower cost and more speedily than its
competitors and enhance bottom-line.
2.4
C2-2
available in the detailed engineering stage. The view of the project site is
depicted through photographs and shown in Figure-2.12.
2.4.3 Drainage Pattern and Water Bodies
The project site is well drained, sloping towards S as well as SE directions. The
project area drains into seasonal Domra river flowing along the plant boundary in
the south, which ultimately joins Subarnarekha river flowing in north-south
direction. Though the site will be leveled for construction of plant facilities, the
run-off from the site will be re-routed through efficiently designed drainage
network.
2.4.4 Layout Plan
The total area of the project is 3800 acres (1538 ha). The overall plant layout and
plant layout superimposed on the topo sheet along with coordinates are shown in
Figure-2.23 and Figure-2.34. The township in 300 acres will be constructed
outside the plant complex, taking due consideration of the prevailing wind
directions. The proposed township will be located in the northeast direction to
the plant and falls in the cross-wind direction.
2.5
C2-3
FIGURE-2.1(A)
PHOTOGRAPHS SHOWING SITE FEATURES AT PROJECT AREA
Vimta Labs Limited, Hyderabad
C2-4
FIGURE-2.1(B)
PHOTOGRAPHS SHOWING SITE FEATURES AT PROJECT AREA
Vimta Labs Limited, Hyderabad
C2-5
FIGURE-2.2
LAYOUT OF THE PROPOSED PLANT AREA
Vimta Labs Limited, Hyderabad
C2-6
LEGEND
Plant Area
Township
Railway Siding
FIGURE-2.3
PROJECT SITE LAYOUT SUPERIMPOSED ON THE TOPO SHEET
Vimta Labs Limited, Hyderabad
C2-7
TABLE-2.2
MAJOR PLANT FACILITIES
Sr. No.
1
2
3
Plant Facilities
Beneficiation Plant
Pellet Plant
Coke Oven plant
Capacity
29.0 MTPA
2 x 4.0 MTPA
2 x 3.0 MTPA-Recovery type ovens
with CDQ having stamp-charging
facilities and by-products
2 x 7.8 MTPA
2 x 4.9 MTPA
1.2 MTPA
3 x 180 t + 2 x 280/300 t
3 x 180 t + 2 x 280/300 t
1 x 180 t + 1 x 280/300 t
2 x 6 strand
1 x 6 strand
2 x 3 starnd
2 x 2 starnd
1.0 MTPA
1.0 MTPA
1.2 MTPA
2 x 1.1 MTPA
4.5 MTPA
1.5 MTPA
2.3 MTPA
1.0 MTPA
1.0 MTPA
1.0 MTPA
1.0 MTPA
3 x 2500 TPD
5 x 600 TPD
2 x 600 TPD
3 x 300 MW
6.0 MTPA
5.52 MTPA
2.30 MTPA
4
Sinter Plant
5
Blast Furnace
6
Direct Reduction Plant
7
BOF Converter
8
Ladle Furnace (LF)
9
RH-TOP
10
Billet Caster
11
Bloom Caster
12
Shaped Bloom Caster
13
Slab Caster
14
Wire Rod Mill
15
Bar Mill
16
Medium Section Mill
17
Heavy section Mill
18
Hot Strip Mill
19
Plate Mill
20
Cold Rolling Mill
21
Galvanizing Line
22
Tin Plate Mill
23
Electrical Steel
24
Colour Coating line
25
Oxygen Plant
26
Lime Calcination Plant
27
Dolo Calcination Plant
28
Captive Power Plant
29
Cement Plant
30
Coking coal washery
31
Non- coking coal washery
Other Facilities
32
Township
300 acres
33
Water supply pipelines/channels & intake wells/weirs
34
External infrastructure
35
Railway sidings, railway bridge over Subarnarekha river and rail connection
to existing railway lines
Source-Project Report-JSW
C2-8
2.3. A copy of Mutual agreement for land acquisition signed with land oustees is
enclosed in Annexure-VII5
TABLE-2.3
LAND USE BREAK-UP
Sr. No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
A
B
C
D
E
Plant Facilities
Raw material Handling and storage facilities
Bas mix yard 1
Bas mix yard 2
Beneficiation plant
Coal washery
Coal washery
Coke oven 1
Coke oven 2
Sinter Plant 1
Sinter plant 2
Pellet plant 1
Pellet plant 2
DR plant
Blast furnace 1 & 2
SMS 1
SMS 2
Rolling mills 1
Rolling mills 2
Rolling mills 3
Plate mill
Lime & dolo calcination plant
Cement plant units
MSDS 1
MSDS 2
MSDS 3
Water treatment plant
Oxygen plant
Central repair shop
Stores
Tailing pond
Miscellaneous (road, railway siding, pipe & conveyor corridor, etc.)
Total steel plant
Captive power plant
Raw water reservoir
Greenbelt development
Township
Grand Total
Source: Project Report-JSW
Area (acres)
163.4
22.1
22.1
51.7
11.2
11.2
68.7
68.7
25.5
25.5
39.8
39.8
10.0
185.3
77.9
77.9
75.9
75.9
75.9
45.2
38.0
49.3
25.5
5.8
6.0
8.0
21.0
15.5
3.2
66.6
687.6
2100
150
200
1050
300
3800
C2-9
1
2
Item
Plant and
Rail line
and Siding
Township
Total
Note: *
#
DC
No. of
Village(s)
involved in
the Project
Seven
One
300.00#
0.00
3800.00
1065.72
: Chotta Nagpur Tenancy Act, 1908 (CNT)
: Land schedule verification is under progress.
: Dy. Commissioner.
0.00
1982.28
0.00
452.00
TABLE-2.5
PRESENT STATUS OF LAND (3500 acres)
Sr. No
1
Progress
(in %)
% wrt
Grand Total
Area
(Registry +
U/P for
Registry +
U/P for DCs
Permission)
1893.24
54.09%
Raiyati Land
(Direct
Registry
executed in
favor of JSW)
Govt.
Land
(Transfer
on lease)
368.40
34.57%
3500.00
1065.72
1982.28
452.00
173.345
38.35%
NOC received from all concerned 7 gram sabhas for transfer of GM land & for
the Project also.
C2-10
ovens. Out of 900 MW, it is envisaged that about 300 MW will be generated from
waste heat recovery boilers and about 600 MW will be generated from
conventional coal fired boilers. The main receiving and step down station of the
plant, power will be stepped down to 33 kv to feed the various plant load centers.
These load centers will have provision to step down further to 11 kv/6.6 kv and
415 V for distribution of power at required voltages.
Necessary power compensation equipment and harmonic filters will be provided
to take care of the fluctuating load of converter shop and continuous casters. For
all 220 kv, 33 kv, 11 kv and 6.6 kv supplies, centralized supervision, monitoring
and emergency control system will be adopted. Energy and gas balance of the
proposed project is given in Table-2.67.
Construction power of about 5 MW is proposed to be arranged through Jharkhand
State Electricity Board from the nearest substation. The power requirement for all
the components of steel plant is given in Table-2.7.
C2-11
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-2
Project Description
TABLE-2.6
ENERGY AND GAS BALANCE
Generation of Fuel Gas
COG
BFG
SMS
Product
MTPA
6.0
9.8
10.422
Annual
Hrs/Yr
8,760
8,400
8,400
Products
MTPA
6.0
15.60
8.0
9.8
1.2
10.422
2.3
2.3
4.5
1.5
1
1
1
1
1
1.2
2.2
6
Operating Hrs
Hrs/Yr
8,760
7,920
7,920
8,400
8,400
7,920
7,920
8,400
7,920
7,920
7,920
7,920
7,920
7,920
7,920
7,920
7,920
8,400
Calorific Value
KCal/Nm3
4350
850
2000
Unit Production
Mcal/Tonne
Nm3/Tonne
1479
340
1445
1700
180
90
Nm3/Hr
Nm3/Yr
337,671
1,983,333
111,664
2,958,000,000
16,660,000,000
937,980,000
20,555,980,000
14.4%
81.0%
4.6%
100%
Coke oven
Sinter
Pellet plant
BF
DRI
SMS
CRM
LCP
Hot strip mill
Plate mill
Tin plate mill
Galvanising line
Electrical steel
Wire rod mill
Bar mill
Medium section mill
Heavy section mill
Cement plant
Unit Heat
Consumption
Gcal/Ton
0.680
0.020
0.175
0.509
2.500
0.039
0.617
0.750
0.270
0.250
0.250
0.380
0.300
0.300
0.300
0.290
0.290
0.087
CV
Kcal/Nm3
1050
900
2000
1100
4300
3000
1850
1850
1850
1850
1850
1850
1850
1850
1850
1850
1850
1850
Flow
Nm3/hr
443,575
43,771
88,384
540,273
83,056
16,975
96,854
111,004
82,924
25,594
17,063
25,935
20,475
20,475
20,475
23,751
43,544
33,591
Balance Gas
Total available gas to power plant (Nm3/hr)
Total available gas to power plant (Kcal/hr)
Heat rate of gas based power plant (Kcal/kwh)
Total power generation from gas based power plant
C2-12
TABLE-2.7
POWER REQUIREMENT
Sr. No.
1
2
3
Plant Facilities
RMHS
Beneficiation plant
Pellet plant
5
6
7
8
Sinter plant
Blast furnace with PCM
Direct reduction plant
SMS
Continuous casting
machine (CCM)
(Billet/bloom/shaped
bloom caster)
Slab caster
Wire rod mill
Medium section mill
Heavy section mill
Hot strip mill
Plate mill
Bar mill
Cold rolling mill complex
Oxygen plant
Lime & dolo calcination
plant
Cement plant
Coking & non-coking
coal washery
Miscellaneous
(services & utilities)
Power generation from
TRT & CDQ
Total
power
Requirement
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Capacity
29.0 MTPA
2 x 4.0 MTPA
2 x 3.0 MTPA - Recovery type
ovens with CDQ having stampcharging
facilities
&
byproducts
2 x 7.8 MTPA
2 x 5500 m3 (2 x 4.9 MTPA)
1.2 MTPA
3 x 180 t + 2 x 280/300 t
2 x 6 strand
1 x 6 strand
2 x 3 strand
2 x 2 strand
1.0 MTPA
1.2 MTPA
2 x 1.1 MTPA
4.5 MTPA
1.5 MTPA
1.0 MTPA
2.3 MTPA
3 x 2500 tpd
5 x 600 tpd
2 x 600 tpd
6.0 MTPA
5.52 MTPA
2.30 MTPA
MW
36
50
66
36
95
138
39
80
25
25
23
17
32
52
25
32
52
125
10
50
4
38
150
900 MW
C2-13
Sanction for 80 MGD water (for construction and operation) from Subarnarekha
River received from WRD, Government of Jharkhand on 09.04.08 given in
Annexure-IX(A).
Further, water supply agreement has been executed between Government of
Jharkhand through Executive Engineer, Water Ways Division Ranchi, Water
Resources Department (WRD) and JSW Jharkhand Steel Limited on 29.07.2013
for Phase-I Integrated Steel Plant at Sonahatu Block, Ranchi District
(Subernarekha River 40 MCM) given in Annexure-IX8(B).
The treated raw water will be collected in a partly on-ground reservoir in the
plant. The reservoir will have two compartments and will be pumped to different
plant units and for individual plant units re-circulating water systems will be
provided. The different categories of water to be used in the re-circulating system
are:
De-mineralized (DM) water for closed re-circulating cooling systems;
Soft water for closed re-circulating cooling systems;
Indirect cooling water (ICW) for secondary cooling of the water-to-water heat
exchangers of the closed cooling circuits;
Direct cooling water (DCW) for gas cleaning circuits, slag granulation, open
machinery cooling and scale flushing; and
Make-up water & service water for captive power plant.
Make-up water for different process units will be made available from main plant
make-up water ring main and will be conveyed to respective cold wells of various
re-circulating systems and storage reservoirs. Suitable isolating and control
valves will be provided in the make-up water pipelines conveying water to cold
wells and storage units.
Wastewater generated from different areas of plant will be treated to the desired
extent and recycled in the re-circulating system as far as possible, facilitating
adequate reuse of water. Backwash water generated from different pressure
filters will be treated in a treatment plant having sludge disposal facilities. The
treated water will be reused in the direct cooling circuit. The main water
recirculation systems are given in Table-2.8.
TABLE 2.8
MAIN WATER RECIRCULATION SYSTEMS
Sr. No.
1
Re-circulation Circuit
Closed soft water (primary
circuit)
Process Covered
Coke Oven BF stove coolers, tuyeres
and stoves Lintel cooling in Pellet Plant
Lance cooling LF cooling Top lance
cooling Vessel pre-heater cooling
Vessel cooling Mould cooling for slab
casters Machine cooling for casters For
removing scales in mills
Permission for drawl of water from the state irrigation department as per ToR-46
C2-14
Sr. No.
2
Re-circulation Circuit
Open
industrial water
(clean water cycle)
Open
industrial
water
(contaminated water cycle)
Process Covered
Secondary side cooling of plate heat
exchangers. Compressed air station
degasser cooling LF transformer BF
cooling pellet plant Indirect cooling
of plate mill Sinter Plant cooling
Power plant cooling
Uncontaminated circuit of by-product
plant -Indirect cooling of re-heating
furnace
Spray and machine cooling (direct
cooling) in conventional slab caster.
Effluent treatment plant of BF GCP.
Contaminated circuit of by-product plant.
Direct cooling of plate mill.
Blast Furnace LF, VD/VOD, mould,
machine and spray cooling of conventional
slab caster. Reheating furnace cooling
Coke Oven.
Source-Project Report-JSW
C2-15
2.7
Process Technology
Processing Step
Beneficiation
Coal washery
Coke making
Pelletization
Sintering
Iron making
7
8
Steel making
Secondary refining
Continuous casting
10
Hot rolling
11
12
Cold Rolling
Finished Steel
13
14
15
16
Calcining
Oxygen Making
Power
Cement
Technological Facility
Beneficiation plant
Coal quality up-gradation
Recovery coke oven
Pellet plant
Sinter plant
Blast furnace
& direct reduction plant
Basic oxygen furnace
Ladle furnace
RH degassing
Slab caster
Billet caster
Bloom caster/shaped bloom caster
Wire rod mill
Bar mill
Section mills
Hot strip mill
Plate mills
Cold roll mill
Galvanising line
Colour coating line
Tin plate mill
Electrical steel
Lime & dolo calcination plant
Oxygen plant
Captive power plant
Cement plant
Source-JSW
external
C2-16
2.8
Process Description9
The integrated steel plant consists of a number of unit processes. The typical
process flow diagram is shown in Figure-2.410. Process and material flow sheet
for the proposed 10.0 MTPA steel plant is given in Figure-2.511.
10
C2-17
FIGURE-2.4
STEEL PLANT PROCESS FLOW
Vimta Labs Limited, Hyderabad
C2-18
Environmental Impact Assessment for the proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-2
Project Description
FIGURE-2.5
PROCESS & MATERIAL FLOW SHEET
Vimta Labs Limited, Hyderabad
C2-19
The oversize material (+3 mm) from the screen will be conveyed to a crusher &
the crushed material will be fed back to the screen feed conveyor. The fine ore
through the screen-feeding conveyor is fed on to the vibrating screen through a
slurry box. The oversize material from the screen will be transferred to a crusher
through a crusher-feeding conveyor. The crusher will be located outside the main
plant building and nearer to the surge bins protected by structural sheds. The
crushed material will further transfer on to the screen-feeding conveyor. The
screen undersize material (in slurry form) will be fed to the primary classifier. The
coarse material (underflow) from primary classifier will be fed to scrubber. The
scrubbed material will be fed to secondary classifier. The fines (overflow) from
both the classifiers will be collected in a sump by gravity through open launder.
Density transmitters has been envisaged in the overflow lines of the both the
classifiers, which is used to control the speed of the spiral.
The coarse material (underflow) from secondary classifier will be fed to
dewatering screen for removal of moisture. The final discharge from the
dewatering screens (which is the feed to sinter plant) will be collected on a
conveyor. The material will be further transferred to base blending yard of sinter
plant through conveyor.
The fines (overflow) from both the classifiers & dewatering screen (-100 mesh / 0.15 mm) will be collected in a sump by gravity through open launder. The slurry
will then be pumped to a battery of cyclones. The overflow from the cyclones (-10
micron) will be transferred to tailings thickener. The cyclone underflow will be fed
to Wet Low Intensity Magnetic Separator (WLIMS) by gravity through launder to
recover magnetite ore. From WLIMS, the feebly magnetic fraction will be collected
in a sump located at ground level. The slurry will be pumped to High Gradient
Magnetic Separator (HGMS) for recovering hematite ore. The magnetic fraction
from HGMS and WLIMS will be transferred to belt filter via dewatering cyclone for
removal of moisture. The discharge from belt filters will be collected on a
conveyor to further transfer the same to the pellet plant storage yard. The
product of the belt filter will have moisture content of about 8-10%. The cyclone
overflow and the tailings fraction from HGMS is transferred to tailings thickener.
The tailings pumps will pump the underflow solids from the thickeners to the
tailings pond. The overflow from the thickeners is circulated back to the process
water reservoir.
2.8.3 Pellet Plant
The pelletization process involves reduction of moisture in the iron ore to less
than 1%, grinding to 45 micron size, feed preparation by adding binders and
moisture, green pelletization and induration (heat hardening).
For full and proper utilization of the iron ore resources available, it is proposed to
install 2 (two) Nos. of 4.0 MTPA pellet plant. This pellet plant will utilize the
beneficiation plant product to produce BF grade pellets to be used in the blast
furnace and DR grade pellets to be used in direct reduction plant. Iron ore
concentrate, limestone and coke breeze from local ground storage will be
conveyed to the silos of iron ore concentrate and additive storage unit within the
pellet plant. From these silos limestone and coke breeze are collected in preset
Vimta Labs Limited, Hyderabad
C2-20
quantities and dried to reduce the moisture content to below 1% before feeding it
to the ball mills for co-grinding to get the requisite fineness. Grinding of coarse
bentonite will be done separately in a Raymond mill.
Then the iron ore concentrate, ground additives and bentonite are transported to
the respective silos in ground material storage unit. Further, mixing in paddle
mixer, green pellet formation in pelletising discs and heat hardening of green
pellets in indurating machine will be carried out.
One travelling grate indurating machine of 464 m2 grate area will be installed with
all other associated service facilities for each pellet plant. Mixed gas will be used
for drying before grinding and finally during induration of green pellets. The
process flow diagram of pellet plant is shown in Figure-2.6.
The operating parameters of each pellet plant are given below:
Capacity
No. of annual working days
Indurating machine area
Pellet width
Useful strand length
Fuel for induration
L/S & coke breeze additive
Grinding
Bentonite grinding
Mixing
Balling
Feeding green balls on
Machine
Induration
Separation of hearth layer
:
:
:
:
:
:
4.0 MTPA
330 days
464 m2
4.0 m
116 m
Mixed gas (CV = 2000 kcal/Nm3)
:
:
:
:
C2-21
FIGURE-2.6
PROCESS FLOW CHART OF PELLET PLANT
Vimta Labs Limited, Hyderabad
C2-22
3
4
5
6
III
Name
Production capability (rating ability) - gross
coke (dry)
Product output
Gross coke (dry)
8010 mm
< 10 mm
Coke gas (dry)
For coke oven & by-product plant
Balance gas
BF Gas
Tar
Sulfur paste
Crude benzol/benzene/toluene/xylene
Annual operation days
Unit
TPA
Quantity
3,000,000
TPA
TPA
TPA
Nm3/annum
Nm3/annum
Nm3/annum
Nm3/annum
TPA
TPA
TPA
day
3,000,000
2,550,000
4,50,000
147x106
111X106
1386X106
1832X106
148,000
10,000
45,000
365
TABLE-2.10(B)
TECHNICAL FEATURES FOR EACH COKE DRY QUENCHING UNIT
Sr.
No.
1
2
3
4
5
6
Items
C2-23
Coking Coal
Crushing
Blending
Coke Oven
Gas
Coke Ovens
Coke Oven
Gas
Recovery
Power
Crude tar,
Sulphur,
Benzol / BTX
Coke
Quenching
Screening
BF
Coke
Coke
Breeze
FIGURE-2.7
RECOVERY TYPE COKE OVEN PLANT
Vimta Labs Limited, Hyderabad
C2-24
Along with the above, the following additional units are also proposed:
C2-25
Apart from the above advantages, the iron ore fines generated in the mines
during production of iron ore lumps are used in the sinter plant, which avoids the
problems related to disposal of fines in the iron ore mines. Moreover,
metallurgical waste materials generated in different process steps including part
of converter slag can also be recycled in the sinter plant, which minimizes the
dust pollution inside the plant boundary. The sinter plant will be equipped with
the following major facilities:
Capacity of the sinter plant has been estimated based on use of about 70-75%
sinter in the burden of blast furnaces and 2 (two) number of sinter plant of
capacity 7.8 MTPA each has been envisaged for the proposed project. The
operating parameters of each sinter plant are given in Table-2.11.
TABLE-2.11
OPERATING PARAMETERS OF EACH SINTER PLANT
Sr. No.
1
2
3
4
5
6
Unit
MTPA
t/m2/h
mm
d/y
h/d
Kcal/t
Value
7.8
1.37
6-50
330
24
20,000
7
8
9
10
Item Description
Capacity
Productivity (Rated)
Size of finished sinter
Annual working regime
No. of working hours/day
Gaseous energy consumption for ignition / ton of BF
sinter
Coke breeze consumption / ton of BF sinter
Under-grate suction
Sinter m/c bed height (including 30-50 mm hearth layer)
Cooler type / bed height
kg/t
mm WC
mm
-------
11
12
deg. C
mg/Nm3
~ 86
1,500
600-650
Circular
cooler
< 100
< 50
C2-26
FIGURE-2.8
PROCESS FLOW DIAGRAM OF SINTERING PLANT
Vimta Labs Limited, Hyderabad
C2-27
Hot metal produced from the blast furnace will be transported to the steel melting
shop using torpedos/ladles. Pig casting machines or nodulising machine of
adequate capacity will also be provided as a balancing device. The process flow
diagram of hot metal production using blast furnace is shown in Figure-2.9.
The blast furnace is a large steel stack lined with refractory bricks, where iron
ore, coke and limestone are dumped into the top, and preheated air is blown into
the bottom. The raw materials require 6 to 8 hours to descend to the bottom of
the furnace where they become the final product of liquid slag and liquid iron.
These liquid products are drained from the furnace at regular intervals. The hot
air that was blown into the bottom of the furnace ascends to the top in 6 to 8
seconds after going through numerous chemical reactions. Once a blast furnace is
started it will continuously run for four to ten years with only short stops to
perform planned maintenance.
The purpose of a blast furnace is to chemically reduce and physically convert iron
oxides into liquid iron called "hot metal". The blast furnace is a counter-current
reactor where solids descend and gases ascend. In this reactor there are
numerous chemical and physical reactions that produce the desired final product,
which is hot metal.
Hot metal produced from the blast furnace will be transported to the steel melting
shop using torpedos/ladles. Pig casting machines or nodulising machines of
adequate capacity will also be provided as a balancing device.
Considering the daily requirement of hot metal in the steel melting shop for
production of liquid steel, which is sufficient to produce about 10.0 MTPA finished
Vimta Labs Limited, Hyderabad
C2-28
steel, 2 (two) blast furnace of capacity 4.9 MTPA each and volume 5500 m3 each
have been envisaged for the proposed project. Slag generated from the blast
furnaces will be granulated in the cast house slag granulation plant. The
granulated slag will be utilized for cement manufacturing.
2.8.7 Pig Casting Machine/Noduliser Unit
A pig casting facility of an adequate capacity has been proposed to cast surplus
hot metal. Alternatively, a nodulizer unit may also be considered.
With a view to converting the blast furnace slag into value-added product, which
is otherwise wasted and also to eliminate the slag disposal problem, a cast house
slag granulation unit has been envisaged.
2.8.8 Slag Crushing Unit
The blast furnace slag has been widely used in cement making. It is also used as
admixture along with the OPC clinker. A slag crushing unit has been planned in
the expansion phases for crushing the slag for use in the construction industry.
The hot metal will be transported to BOF shop/hot metal pretreatment station by
torpedo ladles.
2.8.9 Direct Reduction Plant
One Direct Reduction (DR) plant with average gross production capacity of 1.2
MTPA has been envisaged to meet the DRI requirement of steel plant.
DRI is produced from direct reduction of iron ore (in the form of lumps, pellets or
fines) by a reducing gas produced from coke oven gas/LD gas/Mixed gas. The
reducing gas is a mixture of mainly hydrogen (H2) and carbon monoxide (CO)
which acts as a reducing agent. This process of directly reducing the iron ore in
solid form by reducing gases is called direct reduction.
2.8.10 Steel Making
The production of quality steel through BOF has become predominant in order to
meet the bulk demands of various grades of steel. This process is now preferred
over other process as it uses Oxygen as source of energy. The major thrust in
BOF operations are in the areas of lowering inclusions and accompanying
elements in crude steel automation of converter operations and process control,
improved product quality environmental protection aspects of converter
operations; improved converter lining, adoption of preventive maintenance
techniques and recycling of scrap. Substantial improvement in refractory life has
been achieved by employing slag-splashing technique (using top-blown nitrogen
to blow slag, modified with dolomite over the refractory) after tapping the steel.
C2-29
Environmental Impact Assessment for the proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
DOLOMITE
QUARTZITE
LUMP ORE
SINTER
PELLET
COKE
FERROUS
BURDEN MATERIALS
LIME STONE
Chapter-2
Project Description
VENTURI SCRUBBER
CYCLONE
SEPTUM VALVE
TO FUEL GAS NETWORK
HOT STOVES
TUYERES
OUTLET
SHUT-OFF
VALVE
INLET
SHUT-OFF
VALVE
RECYCLE TO
SINTER
PLANT
DUST
EMERGENCY
TRIP VALVE
GENERATOR
BLAST FURNACE
HOT BLAST
COLD BLAST
BLOWER
FIGURE-2.9
PROCESS FLOW DIAGRAM OF HOT METAL PRODUCTION USING BLAST FURNACE
C2-30
C2-31
One (1) RHOB unit of matching size (180 T) and one (1) 280/300 T RH degassing
unit as secondary refining have been envisaged for production of value-added
steels. The VD unit will be used for production of various steel grades and for
special applications.
2.8.13 Slab Caster
The product-mix envisages processing of approximately 4.6 MTPA of liquid steel
through conventional slab caster. Considering the capacity of the plant,
conventional slab casting machine has been envisaged for the proposed plant.
The slab caster will be equipped with the state-of-the-art facilities like electromagnetic stirring, mould oscillation, shrouding of liquid metal with inert gas,
online width control, etc. Considering market requirements, two (2) double strand
slab caster capable of producing slabs of 950-1850/2200 mm width and 220/250
mm thickness have been envisaged for the proposed project. However this could
be revised to cater to the future market requirements.
2.8.14 Hot Strip Mill
It is envisaged to process slabs through hot strip mill finishing train for the
production of hot rolled coils / strips. This will have the ability to produce coils of
thickness 1.6 mm to 12.7 mm and with 900 mm to 2000 mm width with a
capacity of 4.5 MTPA.
Continuous cast slabs identified by cast number and individual slab number
marked on them are received in the slab yard. The slabs are stocked in piles in
the slab yard. From the stock, the slabs are charged into the reheating furnaces
according to the mill rolling programme.
The slabs are heated to a temperature of about 1250 C in walking beam type
reheating furnaces. The heated slabs are extracted one by one by extractors
located at the discharge side of each of the furnaces. The scales on the heated
slabs is first removed by a hydraulic scale breaker, where high pressure water at
250 bar is sprayed on slab top and bottom surfaces simultaneously. The slab is
then rolled in the universal roughing mill down to 25 mm to 40 mm thick breakdown bars. Vertical edgers attached to the mill, edge the slabs on the odd passes
to edge about 100 mm width and to hold desired finished width. Before feeding
to the first finishing stand, a crop shear crops the head and tail ends of the bar.
The cropped breakdown bar passes through the scale washer where high pressure
water at 250 bar is sprayed on top and bottom surfaces simultaneously, which
removes the secondary scale. The cleaned breakdown bar is then rolled in the 6stand finishing mill train to the desired thickness. The rolled strip is cooled to the
desired coiling temperature on the run-out table provided with water sprays. The
strip is then coiled in the down coiler.
The coiled strip is transported by a system of conveyors to the coil yard for
storage. The coil is strapped, weighed and identified on the conveyor system.
The hot coils delivered by the conveyor system to the coil yard are removed by
EOT cranes. Coils are loaded into the trailers/ railway wagon by EOT cranes and
dispatched from the coil yard.
Vimta Labs Limited, Hyderabad
C2-32
Environmental Impact Assessment for the proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-2
Project Description
FIGURE-2.10
PROCESS FLOW DIAGRAM OF STEEL MAKING
Vimta Labs Limited, Hyderabad
C2-33
C2-34
FIGURE-2.11
PROCESS FLOW CHART OF LIME AND DOLO CALCINATION PLANT
Vimta Labs Limited, Hyderabad
C2-35
2.9
C2-36
Generator
Water
Treatment
Raw Water
Turbine
D.M Makeup
Deaerator
LP Heater
Boiler
Reservoir
C.W
Pump
Neut Pit
BFP
H P Heater
Mill
CEP
Intake Pump
RIVER
Economisar
Condenser
Coal
Bunker
Makeup
Cooling
Tower
Ash Water
Pump House
Central
Monitoring Basin
Air
Preheater
FD
Fan
To Ash Handling
System
Dust Supression/
Sanitation/
Green Belt Dev.
PA
Fan
ID
Fan
Electrostatic
Precipitator
Bottom Ash
Chimney
FIGURE-2.12
TYPICAL FLOW DIAGRAM OF PROPOSED CPP
Vimta Labs Limited, Hyderabad
C2-37
The auxiliary steam for the power station is drawn from main steam line and after
pressure reduction and de-superheating is used for de-aeration, turbine gland
sealing, etc. Provision for steam supply to auxiliary steam system from cold
reheat piping through adequately sized pressure reducing and desuperheating
station will also be there.
The unit is also provided with HP and LP bypass system for quick hot start and
boiler stability with large load rejections.
Description of major plant and equipment of a typical 3 x 300 MW power plant
unit is given hereunder.
The steam generator, which would be designed for firing coal/fuel gas would be
radiant, reheat, natural circulation, single drum, balanced draft. Semi-outdoor
type of unit rated to deliver 980 TPH of superheated steam at 175 bar, 540OC
when supplied with feed water at a temperature of 253.7C at economiser inlet.
The steam generator would be provided with six mill type coal pulverisers along
with individual raw coal feeders and coal bunkers. The boiler would be designed
to handle and burn HFO/LSHS oil as secondary fuel up to 22.5% MCR capacity for
startup and low-load operation.
The boiler would also be provided with light diesel oil (LDO) firing system having
a capacity corresponding to about 7.5% MCR for warm-up during start-up. The
required fuel oil and light fuel oil pressurizing units and fuel oil heating equipment
will be provided. High energy arc (HEA) ignitors would be provided to ignite LDO
as well as fuel oil.
The steam generator would consist of a corner fired water cooled furnace, radiant
and convection super heaters, reheaters, economiser, regenerative air heaters,
steam coil air heaters etc. The draft plant comprises axial forced draft fans, radial
induced draft fans and radial type primary air fans.
Electrostatic precipitators and fly ash hoppers with associated ducting/piping
would be provided for the collection of ash. Soot blowers would be provided at
strategic locations and would be designed for sequential automatic operation from
the unit control room.
The steam turbine would be rated for 300 MW maximum continuous output, at
the generator terminals, with throttle steam conditions of 175 bar pressure and
540OC superheat, 540OC reheat temperature, 0.1033 kg/cm2 back pressure and
all feed water "heaters in service. The steam turbine would be a reheat,
condensing unit tandem compound with a double exhaust LP turbine.
The generator stator would be water cooled. The rotor would be suitable for
conventional hydrogen cooling, with the windings cooled with hydrogen circulated
by fans mounted on the rotor.
Vimta Labs Limited, Hyderabad
C2-38
To prevent a boiler trip in the event of a full export load throw-off and
maintain the unit in operation at house load;
To prevent a boiler trip following a turbine trip and enable quick restart of
the turbo set;
To minimise warm restart deviations of the unit after a trip;
To conserve condensate during start-up; and
To facilitate quick load changes in both directions without affecting the
steam generator operation during start-up.
C2-39
Cement Plant
It is proposed to setup a cement plant of 6.0 MTPA capacity within the integrated
steel plant complex for utilizing the BF slag and the fly ash to the maximum
extent.
It is proposed to use BF slag in the cement plant after granulation of the same.
The annual quantity of PSC generation will be 3.0 MTPA. The remaining quantity
of BF slag will be used for making railway ballast and used as aggregate for road
building.
As a major initiative to utilize fly ash for cement making, it is also proposed to
utilize part of the total fly ash generated for cement making. The annual quantity
of PPC generation will be 3.0 MTPA. The rest of the fly ash will be sold to other
cement manufacturers or group companies for cement making and also for
manufacturing brick and building plant.
The major units in cement manufacturing are mentioned as under:
1
2
3
4
5
6
7
8
9
10
11
2.11
C2-40
FIGURE-2.13
MAP SHOWING THE PLANT LAYOUT TOWNSHIP AND RAILWAY SIDING
Vimta Labs Limited, Hyderabad
C2-41
3
4
5
6
7
8
9
10
11
12
13
14
Raw Material
Coking coal
Non-coking coal for
PCI - gross
Thermal coal
Bentonite
Ferro alloy
Limestone (cement
grade)
Source
Quantity
in TPA
29,000,000
Mode of
Transportation
to Site
Rail
900,000
Rail
1,300,000
1,100,000
140,000
1,600,000
Rail
Rail
Road
Rail /Road
700,000
Rail /Road
5,520,000
Rail
4,800,000
2,300,000
Rail
Rail
3,000,000
400,000
200,000
6,000,000
Rail
Rail /Road
Road
Rail /Road
Captive mines
Jharkhand
Jharkhand
Jharkhand
Iron Ore
The estimated requirement of total iron ore lumps and fines is 29.0 MTPA. Iron
ore fines generated in the mines will be used in the sinter plants and pellet plants
which will be installed inside the plant boundary for production of sinter and pellet
and charging the same in the proposed blast furnaces.
JSW Steel Limited has been alloted Ankua iron ore mine (2201344.34 N to
2201720.50N 8501435.08E to 8501716.66 N) in Jharkhand which has a
12
C2-42
mineable reserve of about 211 MT of iron ore. The expert appraisal committee
(EAC) has recommended Environmental clearance of Ankua iron ore mine. A copy
of the minutes of meeting of expert appraisal committee for Ankua iron ore mine
is given in Annexure-X13.
The requirement of iron ore of the plant will be served mostly from Ankua mine.
The iron ore lump is proposed to be met from captive mine / other mines in this
region. Hence, keeping in view the availability of iron ore deposits in this region,
the following tentative analysis of iron ore have been considered, as given in
Table-2.13. These characteristics will be achieved with ore beneficiation.
TABLE-2.13
TYPICAL CHEMICAL PROPERTIES OF IRON ORE
Parameters
Fe
SiO2
Al2O3
LOI
Percentage (%)
64.0
2.50
2.60
3.0
Coal
Generally for coke making, metallurgical coal of different grades is used in blend.
Availability of low ash coking coal of desired quality in this country is limited.
Hence, it has been envisaged that major requirement of metallurgical blast
furnace coal for the proposed steel plant will be met through imports. The
possible sources of supply of metallurgical coal are Australia and China, while
South Africa and Indonesia are the possible sources for BF injection coal. The
indigenous coal blocks of semi coking coal, which may be available, will be
developed for blending with the imported coking coal.
Coking Coal
The requirement of coking coal is about 8.7 MTPA, out of which 4.8 MTPA shall be
imported for blending with coal from Rohne coal block. JSW has been allocated
the Rohne coal block (2304430N to 2304745N 8501600E to 8501945E) and
the copy of the allocation letter is given in Annexure-X14. The Indian coking coal
is proposed to be sourced from Rohne coal block in Jharkhand and other linkages.
JSW has a share of about 69.07% in the Rohne coal block. The entire coal from
Rohne block is proposed to be washed in coal washery for coal upgradation. The
tentative analysis of imported and indigenous coking coal is mentioned in Table2.14.
In the latest development, the Honble Supreme Court Order dated 24.09.2014,
in addition to other coal blocks, Rohne Coal block allocated to Rohne Coal
Company Pvt Ltd (JV Company) has been de-allocated. However, JSW is in the
process of bidding through e-auction to meet our coal requirement for end use
plant.
13
14
Iron ore from captive mine (JSW Ankua Iron ore mine) linkage documents as per ToR-4
Coal from captive coal mine (Rohne coal mine) linkage documents as per ToR-4
C2-43
TABLE-2.14
TYPICAL CHEMICAL PROPERTIES OF COKING COAL
Parameters
Moisture
Ash
Volatile matter %
Sulphur content %
Percentage (%)
Indigenous Coking Coal
Imported Coking Coal
~ 5.0-7.0
6.0-8.0 (max)
21-30
7-9 (max)
21-27
24-26
0.65-0.75
0.55-0.60
It is proposed to blend imported and indigenous coal in the ratio of about 55:45.
The entire coal quantity is proposed to be transported through rail.
The non-coking or PCI coal requirement for the blast furnace is about 1.6 MTPA
and it is about 2.3 MTPA allowing for washing and handling losses. The PCI coal
required for the blast furnace for pulverized coal injection through the tuyres. The
ash content of the injected coal is normally lower than that of the coke for the
most efficient coal dust injection operation. The tentative analysis of PCI coal is
mentioned in Table-2.15.
TABLE-2.15
TYPICAL CHEMICAL PROPERTIES OF PCI COAL
Parameters
Fixed carbon (dry, ash free basis)
Volatile matter
Ash (dry basis)
Total moisture
CV of coal
Size of coal
Percentage (%)
59-68
20-30
10-12
15% maximum
7000 kcal/kg (approx.)
<100 mm
Limestone
Limestone will be required as flux material both for iron making and for steel
making. In case of steel making, limestone will be calcined in a captive calcination
plant and the calcined product, namely burnt lime, will be used in steel melt shop
for production of liquid steel.
For iron making, it has been proposed to use high-grade low alumina limestone
through sinter route. Hence, for a better burden preparation, the requirement of
limestone for sinter making has been planned to be met from captive sources /
Satna or Niwer- Jukehi area of central India.
Low silica, dense and hard SMS grade limestone is available in Jaisalmer area of
Rajasthan, but the cost of transportation of this limestone to eastern India is very
Vimta Labs Limited, Hyderabad
C2-44
high and exploitation is limited due to environmental problem. Hence, for quality
reasons, sustained supply and cost effectiveness, the entire requirement of SMS
grade limestone may be met through import. This shall be considered during
detailed engineering stage of the plant. High-grade low silica limestone is
produced and traded by several countries namely Japan, Vietnam, Thailand,
Middle-East etc.
The desirable chemical analysis of BF grade limestone and typical analysis of
imported limestone is given in Table-2.16.
TABLE-2.16
DESIRABLE CHEMICAL ANALYSIS OF LIMESTONE
Parameters
Percentage (%)
BF Grade Limestone
SMS Grade Limestone
3.61
0.43
0.60
0.20
50.74
54.54
1.91
0.91
SiO2
Al2O3
CaO
MgO
Quartzite
It has been proposed to use quartzite in the blast furnace. Known occurrences of
quartzite of high grade are reported from almost all over Jharkhand. Hence, it has
been proposed to procure quartzite from Jharkhand State. A typical analysis of
quartzite from this area is given in Table-2.17.
TABLE-2.17
TYPICAL CHEMICAL PROPERTIES OF QUARTZITE
Parameters
SiO2
Al2O3
Percentage (%)
96.5
0.60
Steel Scrap
Steel scrap / DRI shall be used as coolant in the BOF converter. It is proposed to
utilize DRI from DR Plant and in-plant generation of scrap for this purpose. Some
DRI would also be charged into the blast furnaces.
2.11.2 Petrological and Chemical Analysis of the Raw Materials
The analysis of raw materials with respect to major elements and trace elements
are given in Table-2.1815.
Results of petrological and chemical analysis of major raw materials as per ToR-18, ToR-19, ToR-20 and
ToR-21
15
C2-45
TABLE-2.18(A)
MAJOR ELEMENTS & TRACE ELEMENTS IN RAW MATERIALS
Sr. No.
A
1
2
3
4
5
6
7
8
B
1
2
3
4
5
6
7
8
9
10
Parameters
Composition
Loss on ignition, %
Silica (as SiO2), %
Aluminium (as Al2O3), %
Iron (as Fe2O3), %
Calcium (as CaO), %
Magnesium (as MgO), %
Sodium (as Na2O), %
Phosphorous P, %
Trace Elements / Metals
Arsenic (As), g/g
Cadmium (Cd), g/g
Chromium (Cr), g/g
Copper (Cu), g/g
Iron (Fe), g/g
Lead (Pb), g/g
Mercury (Hg), g/g
Manganese (Mn), g/g
Nickel (Ni), g/g
Zinc (Zn), g/g
Iron Ore
2.87
8.89
4.52
58.17
0.056
0.002
0.005
0.03
2.02
28.60
1.52
BDL
0.079
0.024
0.319
TABLE-2.18(B)
MAJOR ELEMENTS & TRACE ELEMENTS IN RAW MATERIALS
Sr. No.
A
1
2
3
4
5
6
7
8
B
1
2
3
4
5
6
7
8
9
10
Parameters
Composition
Loss on ignition, %
Silica (as SiO2), %
Aluminium (as Al2O3), %
Iron (as Fe2O3), %
Calcium (as CaO), %
Magnesium (as MgO), %
Sodium (as Na2O), %
Phosphorous P, %
Trace Elements / Metals
Arsenic (As), g/g
Cadmium (Cd), g/g
Chromium (Cr), g/g
Copper (Cu), g/g
Iron (Fe), g/g
Lead (Pb), g/g
Mercury (Hg), g/g
Manganese (Mn), g/g
Nickel (Ni), g/g
Zinc (Zn), g/g
Lime Stone
39.80
7.30
1.48
1.14
47.20
2.70
0.017
0.019
BDL
0.017
0.055
0.062
0.45
0.008
BDL
BDL
0.011
0.07
C2-46
TABLE-2.18(C)
MAJOR ELEMENTS & TRACE ELEMENTS IN RAW MATERIALS
Sr. No.
A
1
2
3
4
5
6
7
8
B
1
2
3
4
5
6
7
8
9
10
Parameters
Composition
Loss on ignition, %
Silica (as SiO2), %
Aluminium (as Al2O3), %
Iron (as Fe2O3), %
Calcium (as CaO), %
Magnesium (as MgO), %
Sodium (as Na2O), %
Phosphorous P, %
Trace Elements / Metals
Arsenic (As), g/g
Cadmium (Cd), g/g
Chromium (Cr), g/g
Copper (Cu), g/g
Iron (Fe), g/g
Lead (Pb), g/g
Mercury (Hg), g/g
Manganese (Mn), g/g
Nickel (Ni), g/g
Zinc (Zn), g/g
TABLE-2.18(D)
MAJOR ELEMENTS & TRACE ELEMENTS IN RAW MATERIALS
Sr. No.
A
1
2
3
4
5
6
7
8
B
1
2
3
4
5
6
7
8
9
10
Parameters
Composition
Loss on ignition, %
Silica (as SiO2), %
Aluminium (as Al2O3), %
Iron (as Fe2O3), %
Calcium (as CaO), %
Magnesium (as MgO), %
Sodium (as Na2O), %
Phosphorous P, %
Trace Elements / Metals
Arsenic (As), g/g
Cadmium (Cd), g/g
Chromium (Cr), g/g
Copper (Cu), g/g
Iron (Fe), g/g
Lead (Pb), g/g
Mercury (Hg), g/g
Manganese (Mn), g/g
Nickel (Ni), g/g
Zinc (Zn), g/g
C2-47
TABLE-2.18(E)
MAJOR ELEMENTS & TRACE ELEMENTS IN RAW MATERIALS
Sr. No.
A
1
2
3
B
1
2
3
4
5
6
C
1
2
3
4
5
D
1
2
3
4
5
6
7
8
9
10
11
E
1
2
3
4
5
6
7
8
9
10
2.12
Parameters
Coal
(Australia)
Total moisture, %
CSN
HGI
Proximate Analysis (Air dry basis)
Inherent moisture, %
Ash, %
Volatile matter, %
Fixed carbon, %
Sulphur, %
Calorific value, kcal/kg
Petrographic Analysis
Vitrinite %
Semi vitrinite %
Inertinite %
Exinite %
Mineral matter %
Ash Analysis (Air dry basis)
SiO2 %
Al2O3 %
Fe2O3 %
CaO %
MgO %
Mn3O4 %
TiO2 %
P2O5 %
SO3 %
Na2O %
K2 O %
Trace Elements / Metals
Arsenic (As), g/g
Cadmium (Cd), g/g
Chromium (Cr), g/g
Copper (Cu), g/g
Iron (Fe), g/g
Lead (Pb), g/g
Mercury (Hg), g/g
Manganese (Mn), g/g
Nickel (Ni), g/g
Zinc (Zn), g/g
Non-Coking Coal
(Indian)
9.1
1.5
70
10.7
1
58
1.5
12.3
26
53
0.35
7563
3.2
9.5
27.2
60.1
0.57
6887
41
2
46
4
7
39
2
49
3
7
53.26
23.68
12.65
3.72
0.04
0.70
1.14
1.05
0.32
0.12
1.04
50.4
32.8
7.7
2.8
0.9
0.5
1.4
1.4
1.2
0.4
0.6
0.008
0.007
0.152
0.026
2
0.016
BDL
0.03
0.042
0.037
0.005
0.065
0.145
0.032
1.5
BDL
BDL
0.065
0.034
0.029
C2-48
ore and flux and the other for coal will be constructed at the railway-unloading
yard. The incoming gross quantity of major raw materials and the number of days
of storage in the plant are given in Table-2.19.
TABLE-2.19
QUANTITIES AND STORAGE CAPACITIES OF MAJOR RAW MATERIALS
Sr. No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Net Quantity
(TPA)
29,000,000
900,000
1,300,000
1,100,000
140,000
1,600,000
700,000
5,520,000
4,800,000
2,300,000
3,000,000
400,000
200,000
6,000,000
Storage Capacity
(days)
7
7
7
20
20
7
15
15
15
15
20
15
15
15
All raw materials unloaded in loading stations will be transported to ore and flux
storage yard by belt conveyors. Non-uniformity and bunching factors have been
considered for indigenous and imported raw materials respectively. As per this,
the total number of rakes works out to be about 50 per day at 10.0 MTPA
capacity.
2.13
Oxygen
High purity oxygen (99.5%) will be required mainly for converter blowing and
heating, cutting operation in the continuous casters and other general purpose
usage. Low purity oxygen (95%) will be required for enrichment of cold blast to
the blast furnace stoves. The hourly requirement of oxygen for the steel plant is
1,95,900 Nm3/hr.
Oxygen plant of required capacity will be installed by third party on build, own
and operate (BOO) basis and purchased by JSW steel at predetermined price.
Such an agreement is already under place at JSWs existing plant at Vijaynagar
Karnataka, the same will be followed.
Nitrogen
Nitrogen will be mainly required for converter gas cleaning, cooling of the blast
furnace bell-less top, gas line purging and general purpose applications. The
hourly requirement of nitrogen is 1,22,800 Nm3/hr.
C2-49
Compressed air will be required for pneumatic devices, instrumentation & control,
general purpose usage, pneumatic conveying, bag filter pulsing etc.
Requirement of compressed air has been estimated as 2,58,070 Nm3/hr. This will
be provided by central compressed air station with piped compressed air to the
different consumption points.
Chilled water is required for air conditioning of control rooms, etc in various areas
of the steel plant. Two vapour compression type chilled water plants will be
provided. Water inlet and outlet temperatures of chiller plant will be maintained
at 16oC and 7C respectively.
Fuel System
The by-product gases (i.e. blast furnace gas, coke oven gas and converter gas)
will be utilized for heating and burning applications (BF stove heating, coke oven
under firing, sinter plant, rolling mill furnaces, etc.) of the steel plant. Available
gases after meeting the above applications will be utilized for steam and power
generation.
Blast furnace (BF) gas will be used mainly as fuel in stoves, sinter plant and
power plant. In addition to the above consumers, BF gas will also be used in
CDI, cast house runner drying and LRS. Semi-clean BF gas will be used for
pressure equalization BF top. BF gas will be distributed to the consumers through a
system of piping network, operating at a pressure of 800 mm WC (Approx). BF gas
will be stored in gas holders of 50,000 m3 each capacity and from there it will be
sent to different consumers in the plant. Coke oven gas will be stored in
50,000 m3 each gas holder, while LD gas shall be stored in a gas holders
having capacity of 50,000 m3 each. Mixed gas will be used mainly as fuel for
sinter plant, pellet plant, ladle pre-heating in SMS and plate mill. For sinter plant,
BF gas & CO gas will be mixed in proper ratio to get CV of 900 Kcal/Nm3 and for
ladle preheating BF gas & CO gas will be mixed in proper ratio to get CV of 2000
kcal/Nm3. Thus the by-product fuel gases viz. CO gas and BF gas will be used
judiciously as gaseous fuel in various units of plant. The surplus gases from BF &
coke oven will be used in the CPP for generation of power.
Plant Automation
It has been envisaged that Level-1 and Level-2 automation systems that will
come along with the various equipment/facilities, to provide process and
equipment level control including supervisory automation functions. In addition,
higher level computer system will be provided to cater to the needs for production
planning & control (PPC) as well as management information system (MIS) for
the whole plant.
C2-50
The centralized production planning and control system will provide overall and
area/shop wise production planning. This system will be interfaced to the
automation systems of various plant units through suitable gateways, to enable
downloading of production targets and uploading of production and consumption
figures. The management information system will provide necessary information
about the plant and other administrative functions.
Communication System
Warehouse
Laboratory
To meet the analytical and testing needs of the proposed plant, laboratories as
mentioned below will be provided at different locations in the plant:
Ancillary Facilities
C2-51
During plant construction phase of the project, work force of about workers needs to
be deployed, which consists of skilled and un-skilled workers. All the workers will be
housed in labour colony, which will be located near the project site.
The colony which will be temporary in nature will have the following amenities:
1
2
3
4
5
Open type drain has been envisaged for the plant storm water drainage. The
drains will be laid generally by the side of the roads. Storm water run-off,
collected through arterial and trunk drain, will be discharged suitably for
minimum pollution.
Sanitary faecal sewage will be collected from the ablution blocks through pipeline
and the same will be connected to a sewage treatment plant. The effluent from
sewage treatment plant will be utilized for the development and maintenance of
greenery.
Roads
Adequate plant road system will be provided considering the types of vehicles and
the traffic volume. The road system will be designed to minimize cross movement
of vehicles. Adequate vehicle parking facilities and road weighbridges will be
provided.
Township17
The new township will be constructed to take care of the accommodation facilities
of the employees. Area for the township has been identified near Barenda.
The township is to serve a large steel plant of 10 MTPA capacity and CPP of 900
MW capacity and may have up to 9620 dwellings of various categories in about
300 acres of land. Adequate green belt/green cover will be developed in the
township.
The township will be located in the northeast direction to the plant and falls in the
cross-wind direction to the proposed plant site.
16
17
C2-52
2.14
Environmental Effects
The proposed integrated steel plant would comprise various production
facilities/departments, such as raw materials handling, coke ovens, pellet plant,
sinter plant, lime calcining plant, blast furnace, DRI, BOF shop and rolling mills.
The inputs to the above facilities will comprise raw materials in process material,
along with water, fuel and power.
The major type of pollution from the power plant is gaseous emissions. In
addition, wastewater and solid waste will also be generated. In the proposed
cement plant, the main sources of air pollution will be the emissions from stacks
attached to raw meal grinding units, clinker burning, coal grinding and cement
grinding.
The sources and nature of pollution from the proposed plant and the types of
environmental pollution likely to occur are presented in Table-2.20.
TABLE-2.20
SOURCES AND NATURE OF POLLUTION
Facility/Department
Raw material yard
Beneficiation plant
Sinter plant & pellet
plant
Pollutants
Fugitive dusts
Dust
SO2, NOx, dust, heat and noise
Heat in cooling water
Coke oven
Type of Pollution
Air pollution
Air, water pollution
Air pollution
and noise pollution
Thermal pollution of water
bodies at the outfall
Air pollution
Blast furnace/DRI
Calcining plant
Air,
noise
pollution
Cement plant
Fugitive dust
and
water
The quantities and the composition of the gaseous, liquid and solid waste that are
likely to be generated in the plant will be managed and treated such that their
final disposal into the environment meets all the statutory requirements and thus
the environmental impacts are minimized.
C2-53
2.15
The raw material handling section would be provided with dust suppression
(DS)/dust extraction (DE) systems complete with bag filters/ESPs and
adequate stack height will be provided;
The principal air pollution control system for sinter & pellet plant would consist
of de-dusting and waste gas cleaning systems separately;
The coke oven gas generated in the coke ovens after by-product recovery
would be utilized as supplementary fuel for proposed steel plant complex;
The top gas coming out from the blast furnace would be cleaned by taking the
gas through BF gas cleaning device for separation of particulate before the
clean gas is recovered for meeting in-plant energy demand;
The stock house and cast house areas would be provided with proper DE/FE
systems complete with ESPs and stacks;
The LD gas generated in the SMS shop would be subjected to wet cleaning
before it is used as plant supplementary fuel;
For the control of fugitive dust emission within and around the coal handling
units, dust extraction and suppression system will be provided. Dust
suppression system shall be installed at all the transfer points in coal handling
plant and coal stockyard;
All rotary equipment like fans, blowers, pumps & compressors, rolling mills
would be of low noise design. The grouting of this equipment will be made
free from vibrations. The work zone noise exposure of the operating personnel
would be avoided by remote operation from the control rooms;
C2-54
The fly ash will be conditioned with water spray to reduce fugitive dust during
loading and unloading operations;
The ash in the open trucks will be covered with tarpaulin to prevent flying of
the fine ash during transportation; and
Water sprinkling system will be provided in the ash disposal area to restrict
flying of fine ash due to wind.
The wastewater generated from the indirect cooling circuit would be routed
through the cooling tower and pressure filter for recycling purpose;
The wastewater generated from the coke ovens will be treated in a biooxidation plant to reduce the level of phenolic compounds, oil & grease and
cyanide. The treated wastewater will be reused in the system;
The wastewater from gas cleaning plants of blast furnace and steel melt shop
containing suspended solids will get clarified in the wastewater treatment
plant. The clarified water will be recycled to the waste gas cleaning units.
Similarly, the wastewater coming out from the continuous casting machine
will be treated to remove scales and oil and the treated water will be recycled
after cooling;
The ash disposal area will be lined with impervious lining to prevent seepage
of rain water from the disposal area in the ground and pollute ground water;
and
The sanitary wastewater will be treated in sewage treatment plant and the
treated water will be used for dust suppression and maintenance of greenbelt
development.
C2-55
LIME
STONE
Particulates
Nox, SO2
H 2 S Steam
SS, BOD
LIME BURINING
TRANSPORT
AND
STORAGE
Fugitive Dust
CRUSHING
Particulates, Noise
COAL
SS, BOD
NH 3 CN
Phenol
COOLING OR
GRANULATION
COOLING
CRUSHING
Slag
Hydrocarbons
Steam
Particulates
CO, NH 3 ,SO 2 ,
Nox, H2 S
SINTERING &
PELLETIZING
Particulates
IRON MAKING
PRETREATMENT
SCRAP
Particulates
PREPARATION
CRUSHING
Sludge
STEEL MAKING
Noise
LIQUID
STEEL
Sludge
Legend
Particulates
SO , NOx, HF
2
CO
Hydrocarbons
Noise
SINTERING &
PELLETIZING
ORE
LADLE
TREATMENT
CONTINUOUS
CASTING
Particulates, Noise
SS, Oils
Steam
Air Pollutant
Water Pollutant
Solid Waste
STEEL
PRODUCTION
FIGURE-2.14
FLOW CHART LINKING POLLUTANTS AND PRINCIPAL
OPERATIONS IN AN INTEGRATED STEEL PLANT
Vimta Labs Limited, Hyderabad
C2-56
C2-57
3.0
3.1
3.2
C3-1
The precambrian shield was faulted by later earth movements to form roughly EW trough where the fresh water gondwana sediments were accumulated. These
include sandstone, shale and coal seams, which occur in chain of outliers in
gneissic terrain within the drainage area of the river Damodar and span from
Upper carboniferous (Talchir formation) to lower middle jurassic (Mahadeva
Formation). These are absent in the present study area. Regional stratigraphic
succession and geology based on quadrangle sheet 73E of Geological Survey of
India are presented in Figure-3.2.1.
Geology of the study area is dominated by granite gneiss of Chotanagpur group of
rocks with thin alluviual cover in the central and eastern part and mica schist in
the southern part. Bore wells drilled for drinking water supply by PHED in Barenda
village indicate that fractured granite gneiss extends up to a depth of 165.00 m.
Lithological section of a bore well drilled in Barenda is presented in Figure3.2.21.
3.2.2 Physiography2
The study area is the part of Chotanagpur plateau. Physiographically, the area is
characterized by varied landforms like high hill ranges, eroded valleys and
undulating land. Dumra pahar in the northeast and Bariburu pahar in the
northwest of the study area and hills and rides in the central part towards north
of proposed site and in the southern part of the study area are main hill ranges
partially covered mainly dense/scrub forest. The lower area lies covers major part
of the study area mainly created by river Subarnarekha and its tributaries. The
maximum elevation observed for hills areas is 538 m amsl and is at the
northwestern part of the study area namely Bariburu pahar. The lowest elevation
is 183 m amsl and is at the southeastern part of the study area. The general
slope of the land is towards southeast.
3.2.3 Drainage Pattern
The Subarnarekha is one of the longest east flowing inter-state river. It covers
large areas of Bihar and some parts of West Bengal and Odisha. The
Subarnarekha river originates near Nagri village in Ranchi district of Jharkhand at
an elevation of 600 m. The total length of the river is about 395 km. The principal
tributaries of the river are Kanchi, Kharkai, Karkari and Dulang.
Subarnarekha river is about 2.4 km from proposed project site towards northeast.
Raru nadi running northwest- southeast in the north and Kanchi nadi running
southwest-northeast from western part of the study area join Subarnarekha
towards north of proposed project site. Domra nadi flowing west-east along the
southern boundary of the proposed project site joins Subarnarekha towards
southeast of the project site. Major part of the study area has dendritic pattern
with a drainage density of 1.37 km/sq.km. The drainage in the area is controlled
by several small streamlets joining Raru nadi, Kanchi nadi, Domra nadi, Karru
nadi and Subarnarekha river. Distributories of right bank canal of Kanchi runs
southwest-northeast in the central part of the study area passing just outside the
proposed project site. Drainage map of the study area is presented in Figure3.2.3.
1
2
C3-2
FIGURE-3.2.1
GEOLOGY OF THE STUDY AREA
VIMTA Labs Limited, Hyderabad
C3-3
FIGURE-3.2.2
LITHOLOGICAL SECTION OF A BORE WELL
VIMTA Labs Limited, Hyderabad
C3-4
The estimated water requirement for the project is about 80 million gallons per
day (MGD) (132.7 MCM per annum), out of which 46.7 MGD (77.4 MCM per
annum) of water will be drawn from Subarnarekha river in the upstream and 33.3
MGD (55.3 MCM per annum) of water will be drawn from Chandil dam in the
downstream at about 45 km south from the proposed plant site.
The flow monitoring data indicates that the surface flow during 2000-2001 and
2005-2006 non-monsoon periods was below the requirement. Suitable
impounding arrangements in the form of a pickup weir or intake well at the river
source will have to be considered to meet the plant water requirement, along with
dedicated pipeline or open channel.
Chandil dam across Subarnarekha river is a composite dam which is 720.10 m
long and 56.5 m high with a gross storage of 1963 hm (1963 MCM) and live
storage of 1611 hm (1611 MCM) at Maximum Water Level (MWL)/Full Reservoir
Level (FRL) 192 m.
3.2.4 Hydrogeology
The hydrogeological studies have been carried out in the area to understand the
local geology, geomorphic features, drainage network, aquifer characteristics and
yield of water. Accordingly various components controlling the hydrogeological
regime of the study area have been studied. Detailed hydrogeological
investigations were carried out in the month of May 2014 for the study area is
presented in Figure-3.2.4. Detailed hydrogeology study report is enclosed in
Annexure-XI. The salient features are discussed below:
C3-5
FIGURE -3.2.3
DRAINAGE MAP OF THE STUDY AREA
VIMTA Labs Limited, Hyderabad
C3-6
FIGURE 3.2.4
HYDROGEOLOGICAL MAP OF STUDY AREA
VIMTA Labs Limited, Hyderabad
C3-7
The shallow aquifers are being tapped through dug wells, dug-cum bore wells and
hand pumps. Many dug wells dry up during summer months. Hand pumps
generally tap first fracture zones and its depth is 30-40 m bgl. In granite gneiss
terrain, first fracture occurs between 50-70 m and second fracture is found
between 100-120 m depth. Discharge of bore wells varies between 10 to 30
m/hr in these areas. Third set of fracture can be found between 15-200 m bgl.
Discharge varies between 15 to 25 m/hr and drawdown varies between 20-25 m
bgl. Shallow and deep bore wells drilled in the study area are mainly for drinking
water purpose fitted with hand pumps and submersible pumps. The irrigated
agriculture is mainly rain, canal dependent with support irrigation from dug and
dug-cum bore wells.
Well inventory of 34 wells in 34 settlements was conducted in the study area
during the field visit. Mostly the groundwater is developed by way of dug wells
whose depth varies from 5.50 m to 16.90 m with diameter varying from 1.20 m
to 6.14 m. The depth to water level during pre-monsoon range from 3.30 m to
10.90 m bgl and the average water level is 7.00 m bgl. The depth to water during
post-monsoon range from 0.23 m to 6.93 m bgl and the average water level is
2.78 m bgl. The average fluctuation between pre and post-monsoon seasons is
4.23 m. Well inventory data is furnished in Table-3.2.1 and water level contours
are presented in Figure-3.2.5 and Figure-3.2.6.
C3-8
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-3
Baseline Environmental Status
TABLE-3.2.1
WELL INVENTORY IN STUDY AREA
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
Well No
GW1
GW2
GW3
GW4
GW5
GW6
GW7
GW8
GW9
GW10
GW11
GW12
GW13
GW14
GW15
GW16
GW17
GW18
GW19
GW20
GW21
GW22
GW23
GW24
GW25
GW26
GW27
GW28
GW29
GW30
GW31
GW32
GW33
GW34
Village
Mango
Marangkiri
Dudni
Mankidih
Dangdung
Tunturi
Simali
Atna
Tilaipiri
Pilid
Pohardih
Jargordih
Adardih
Hartaidih
Kudm
Chumudih
Salukdih
Pandudih
Chukahatu
Hasardih
Jojopudi
Barudih
Dimbudih
Jamdih
Jhabri
Brididth
Baredih
Donadih
Sareyd
Jamudag
Jahedih
Baluwodih
Rangamati
Kurdhum
Lat
2311'56.2"N
2312'34.9"N
2311'25.2"N
2310'20.2"N
2312'07.8"N
2312'09.8"N
2310'44.9"N
2309'40.1"N
2308'48.1"N
2307'15.1"N
2308'33.5"N
2307'17.5"N
2307'18.5"N
2305'37.5"N
2305'21.4"N
2304'10.7"N
2306'56.5"N
2310'14.4"N
2310'15.1"N
2307'44.8"N
2306'36.7"N
2306'06.0"N
2308'16.3"N
2309'22.7"N
2316'40.0"N
2314'30.3"N
2310'44.8"N
2310'40.0"N
2312'30.3"N
2313'28.3"N
313'02.0"N
314'59.3"N
313'47.8"N
315'47.2"N
Long
8548'49.0"E
8550'58.9"E
8550'52.0"E
8551'39.0"E
8553'25.7"E
8553'10.3"E
8554'41.3"E
8555'05.8"E
8550'19.8"E
8551'35.2"E
8552'26.5"E
8553'35.5"E
8553'20.3"E
551'22.3"E
8549'44.0"E
8549'15.5"E
8549'53.8"E
8549'37.1"E
8547'58.8"E
8547'47.5"E
8547'00.7"E
8545'14.7"E
8543'44.0"E
8544'02.6"E
8548'29.1"E
8548'41.1"E
8546'27.8"E
8541'38.0"E
8543'26.2"E
8544'36.1"E
8545'23.8"E
8547'09.8"E
8552'33.7"E
8551'24.0"E
Well
Type
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Dug
Purpose
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Domestic
Total
Depth (m)
Dia
(m)
Lining
(Dug Well) (m)
8.70
12.02
10.12
9.93
12.96
9.61
9.11
10.60
12.00
16.90
11.20
10.80
11.60
12.80
10.70
8.12
5.50
11.90
10.15
9.40
8.60
5.80
6.10
10.00
9.30
6.95
7.80
8.79
9.20
9.90
12.05
9.80
11.50
10.00
3.00
1.60
1.58
3.60
1.70
2.40
2.10
2.98
2.20
1.60
4.00
2.90
3.50
1.40
3.55
3.00
1.25
2.10
1.90
1.20
1.80
2.45
1.40
3.10
3.50
6.08
6.14
2.10
3.20
2.80
1.70
2.70
2.60
3.30
8.70
12.02
10.12
9.93
12.96
9.61
9.83
10.60
12.00
16.90
11.20
10.80
11.60
12.80
10.70
8.12
5.50
11.90
10.15
9.40
8.60
5.80
6.10
10.00
9.30
6.95
7.80
8.79
9.20
9.90
12.05
9.80
10.50
10.50
Fluctuation
(m)
3.80
4.12
3.62
2.92
3.92
2.89
3.69
3.80
3.40
4.67
4.60
4.70
4.00
4.20
3.40
2.92
2.30
4.15
4.40
4.50
2.95
1.95
2.59
4.78
3.94
3.85
3.30
4.39
6.67
5.80
6.95
6.40
8.00
6.08
C3-9
FIGURE -3.2.5
WATER LEVELS DURING PRE-MONSOON 2014
VIMTA Labs Limited, Hyderabad
C3-10
FIGURE3.2.6
WATER LEVELS DURING POST-MONSOON 2013
VIMTA Labs Limited, Hyderabad
C3-11
C3-12
Papadopulos devised a method that accounts for well bore storage for a large
diameter well that fully penetrates a confined aquifer (Kruseman and de Ridder,
1990). Using the Jacob correction factor, this method can also be applied to
unconfined aquifers. The aquifer test data was analyzed using Large Diameter
Well Papadopulos and Cooper, 1967, which provided good fits. Type curves
were generated by the software and were both automatically and manually
matched to the observed drawdown data. Type curves were generated for
numerous combinations of parameters in order to assess and obtain the
combination of parameters which provided the best match with the observed
data. Pumping test data, analysis and aquifer parameters derived are presented
in Table-3.2.24 & Table-3.2.3, Figure-3.2.7 & Figure-3.2.8 and Table-3.2.4
respectively. The Transmissivity was found as 56.51 m/day while storage
coefficient was found as 0.00026 and hydraulic conductivity was found as 0.083
m/day.
TABLE-3.2.2
PUMPING TEST DATA IN LARGE DIA DUG WELL
Date: 05.05.2014
Time of Test Start: 09.16 AM
Measuring Elevation: 0.30 m agl
Lat: 2311'52.5"
Time Since Pump Started
(Min)
1
2
3
4
5
6
7
8
9
10
15
20
25
30
40
50
60
80
100
120
140
160
180
200
220
WL Below MP
in m
2.63
2.65
2.72
2.80
2.86
2.92
3.00
3.03
3.06
3.10
3.21
3.28
3.42
3.50
3.65
3.85
3.87
3.95
4.00
4.09
4.15
4.25
4.45
4.53
4.60
Draw Down
(s) in m
0.01
0.02
0.07
0.08
0.06
0.06
0.08
0.03
0.03
0.04
0.11
0.07
0.14
0.08
0.15
0.20
0.02
0.08
0.05
0.09
0.06
0.10
0.20
0.08
0.07
Discharge
(Q) in Lps
3.33 lps
3.5 lps
3.5 lps
3.5 lps
C3-13
TABLE-3.2.3
RECOVERY DATA IN LARGE DIA DUG WELL
Time Since
Pump Started
(min)
221
222
223
224
225
226
227
228
229
230
235
240
245
250
260
270
280
300
320
370
420
T/T'
WI Below
Mp In M
Residual
Drawdown (S)
1
2
3
4
5
6
7
8
9
10
15
20
25
30
40
50
60
80
100
150
200
221.00
111.00
74.33
56.00
45.00
37.67
32.43
28.50
25.44
23.00
15.67
12.00
9.80
8.33
6.50
5.40
4.67
3.75
3.20
2.47
2.10
4.59
4.57
4.53
4.50
4.49
4.45
4.43
4.40
4.42
4.40
4.39
4.38
4.36
4.35
4.35
4.35
4.32
4.55
4.52
4.57
4.54
1.97
1.95
1.91
1.88
1.87
1.83
1.81
1.78
1.80
1.78
1.77
1.76
1.74
1.73
1.73
1.73
1.70
1.93
1.90
1.95
1.92
TABLE-3.2.4
PUMPING TEST DATA ANALYSIS
Sr.No.
1
2
3
Aquifer Parameter
Transmissivity - m/day
Storage coefficient
Hydraulic conductivity - m/day
Value
56.51
0.00026
0.083
C3-14
FIGURE-3.2.7
PUMPING TEST DATA PLOT
FIGURE-3.2.8
PUMPING TEST DATA ANALYSIS
VIMTA Labs Limited, Hyderabad
C3-15
3.3
3.3.1 Objectives
The objectives of land use studies are:
To analyze the impacts on land use due to plant activities in the study area;
and
To give recommendations for optimizing the future land use pattern vis-a-vis
growth of plant activities in the study area and its associated impacts.
3.3.2 Methodology
For the study of land use, literature review of various secondary sources such as
district census handbooks, regional maps regarding topography, zoning
settlement, industry, forest etc., were taken. The data was collected from various
sources like district census handbook, revenue records, state and central
government offices and Survey of India (SOI) topo sheets and also through
primary field surveys.
3.3.3 Land use Based on Secondary Data
Based on the census report, 10 km radial distance around this plant boundary
has been considered in the study. These areas were studied in detail to get the
idea of land use pattern in the study area. The land use census data 2011 is yet
to be published and the land use pattern of the study area as per 2001 census is
presented in Table-3.3.1. The village wise land use data is presented in
Annexure-XII.
TABLE-3.3.1
LAND USE PATTERN IN THE STUDY AREA
Sr.No
1
2
3
4
0-3 km
467
3-7 km
809
7-10 km
1276
0-10 km
2552
Area %
4.89
1668
7905
1184
1293
10129
1908
1513
14336
2535
4474
32369
5627
8.57
62.02
10.78
1211
12435
2384
16523
3579
23239
7173
52195
13.74
100.00
C3-16
Forest
The revenue forest land under the study area consists 2552 ha (4.89%) of the
total geographic area.
Cultivable Waste
This land includes that land, which was cultivated sometime back and left vacant
during the past 5 years in succession. Such lands may either be fallows or
covered with shrubs, which are not put to any use. Lands under thatching grass,
bamboo bushes, other grooves useful for fuel etc., and all grazing lands and
village common lands are also included in this category. The study area comprises
about 10.78% cultivable wastelands.
The land not available for cultivation is 13.74% of the total study area, which
includes area of land with shrub, land without shrub, quarry, mining area, rocky/
stony and barren area.
3.3.4 Land Use Based on Satellite Imagery
Present land use based on remote sensing satellite imageries were collected and
interpreted for the 10 km radius study area for analyzing the land use pattern of
the study area. Based on the satellite data, land use/ land cover maps have been
prepared.
The present land use / land cover maps were prepared based on the classification
system of National standards. For explanation for each of the land use category
the details as given in Table-3.3.2 are considered.
TABLE-3.3.2
LAND USE/LAND COVER CLASSIFICATION SYSTEM
Sr. No.
1
Level-1
Built-up Land
Agriculture Land
Forest
Level-2
Town/cities
Villages
Institution/industry/godown etc
Plotted area/layout
Crop land
Plantations
Fallow
Evergreen/semi evergreen
C3-17
Level-1
Wastelands
Water Bodies
Others
Level-2
Deciduous
Forest plantation
Rocky/stony waste
Land with /without shrubs
Saline/sandy & marshy/swampy
River/stream
Lake/reservoir/tanks
Orchard/Other plantation
Shifting cultivation
Salt pans, snow covered/glacial
Barren/vacant land
Data Requirements
Methodology
The methodology adopted for preparation of land use/ land cover thematic map is
monoscopic visual interpretation of geocoded scenes of IRS-P6 Resourcesat-II
L4FMX and field observations are taken. The various steps involved in the study
are preparatory field work, field survey and post field work.
The False Colour Composite (FCC) of IRS-P6 Resourcesat-II L4FMX satellite data
are used for pre-field interpretation work. Taking the help of topo sheets, geology,
geo-morphology and by using the image elements the features are identified and
delineated the boundaries roughly. Each feature is identified on image by their
image elements like tone, texture, colour, shape, size, pattern and association. A
tentative legend in terms of land cover and land use, physiography and erosion
was formulated. The sample areas for field check are selected covering all the
physiography, land use / land cover feature cum image characteristics.
a)
b)
c)
Softwares used
ERDAS Imagine for image processing/rectification/geocoding;
AutoCAD for data preparation after visual interpretation of the image; and
Arc View for image/landuse presentation.
Ground Truth Collection
Both toposheets and imagery were taken for field verification and a transverse
plan using existing road network was made to cover as many representative
sample areas as possible to observe the broad land use features and to adjust the
sample areas according to field conditions. Detailed field observations and
investigations were carried out and noted the landuse features on the imagery.
VIMTA Labs Limited, Hyderabad
C3-18
The base maps of the study area were prepared, with the help of survey of india
toposheet. Preliminary interpreted land use and the land cover features
boundaries from IRS-P6 false colour composite were modified in light of field
information and the final thematic details were transferred onto the base maps.
The final interpreted and classified thematic map was catrographed. The
cartographic map was coloured with standard colour coding and detailed
description of feature with standard symbols. All the classes noted and marked by
the standard legend on the map.
Final Output
The final output would be the landuse/land cover map and numerals were given
different colour code for each category as shown in map. Area estimation of all
features of land use/land cover categories was noted. The thematic map and land
use pattern is shown in Figure-3.3.15 and Figure-3.3.26. The details of the land
use in 10 km radial study area are given in Table-3.3.3. Satellite image and land
use pattern of the project site is shown in Figure-3.3.3. Digital elevation model
of the study area (10 km radius) is shown in Figure-3.3.47.
TABLE-3.3.3(A)
LAND USE BREAK UP OF THE STUDY AREA
Sr.No.
Land Use
Area
(ha)
Percentage
(%)
2788
20
5.63
0.04
1340
948
220
2.70
1.91
0.44
15
1702
29966
2483
0.03
3.43
60.47
5.01
3787
2990
678
29
7.64
6.03
1.38
0.06
1591
996
49555
3.21
2.01
100.00
C3-19
Observations
The land use pattern of the study area indicates forest land of 5.06 % in the study
area and the land under agriculture is about 68.95%.
TABLE-3.3.3(B)
LAND USE BREAK UP OF THE PROJECT AREA
S.No.
Land Use
Area
(ha)
Percentage
(%)
0
0
0.00
0.00
0
0
0
0.00
0.00
0.00
0
16
1327
111
0.00
1.04
86.28
7.22
0
44
5
0
0.00
2.86
0.33
0.00
16
19
1538
1.04
1.24
100
C3-20
FIGURE-3.3.1
THEMATIC MAP OF STUDY AREA
VIMTA Labs Limited, Hyderabad
C3-21
FIGURE-3.3.2
LAND USE PATTERN BASED ON SATELLITE DATA
VIMTA Labs Limited, Hyderabad
C3-22
FIGURE-3.3.3
SATELLITE IMAGE AND LAND USE PATTERN OF THE PROJECT SITE
VIMTA Labs Limited, Hyderabad
C3-23
FIGURE-3.3.4
DIGITAL ELEVATION MODEL
VIMTA Labs Limited, Hyderabad
C3-24
3.4
Soil Characteristics
It is essential to determine the potentiality of soil in the area and to identify the
impacts of urbanization on soil quality. Accordingly, the soil quality assessment
has been carried out.
Location
Project Site
Sayatanr village
Garadih village
Sonahatu village
Jaherdih village
Barenda village
Marangkiri village
Mahuldih village
Tilaipiri village
Hesadih village
Distance
from Plant Boundary
(km)
4.2
6.5
8.5
4.8
0.5
2.5
2.9
1.0
3.0
Direction w.r.t
Proposed Plant
Boundary
WSW
W
WNW
NW
N
NE
E
SE
SSW
C3-25
FIGURE-3.4.1
SOIL QUALITY SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-26
TABLE-3.4.2 (A)
SOIL ANALYSIS RESULTS
Sr. No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Parameters
pH
Conductivity
Texture
UOM
-s/cm
--
Sand
Silt
Clay
Bulk Density
Exchangeable Calcium as Ca
Exchangeable Magnesium as Mg
Exchangeable Sodium as Na
Available Potassium as K
Available Phosphorous as P
Available Nitrogen as N
Organic Matter
Organic Carbon
Water soluble Chloride as Cl
Water soluble Sulphate as SO4
Sodium Absorption Ratio
Aluminium
Total Iron
Manganese
Boron
Zinc
%
%
%
g/cc
mg/kg
mg/kg
mg/kg
Kg/ha
Kg/ha
Kg/ha
%
mg/kg
mg/kg
%
-%
%
mg/kg
mg/kg
mg/kg
S1
7.8
295.0
Sandy
Clay
38.0
20.0
42.0
1.0
2810
1280
320
457.3
46.4
162.8
0.72
0.42
251.4
78.9
0.56
0.62
1.21
183.0
43.2
62.4
S2
8.0
367.0
Sandy
Clay
35.0
33.0
32.0
1.1
2400
1160
280
392.2
49.5
188.7
0.52
0.30
285.0
71.6
0.53
0.89
1.78
192.0
50.2
72.6
S3
7.5
425.0
Sandy
Clay
42.0
19.0
39.0
1.0
2475
1240
275
372.0
52.8
204.6
0.93
0.54
231.0
96.4
0.50
0.32
1.15
210.9
38.6
84.8
S4
7.6
382.0
Sandy
Clay
34.0
26.0
40.0
1.0
3260
1820
430
387.5
42.3
176.7
0.83
0.48
245.7
87.3
0.67
0.60
1.32
243.0
50.2
74.2
S5
7.8
298.0
Sandy
Clay
42.0
13.0
45.0
1.2
3050
1625
325
427.8
42.0
189.7
0.69
0.40
319.9
88.5
0.53
0.48
1.24
380.2
70.4
105.6
TABLE-3.4.2(B)
SOIL ANALYSIS RESULTS
Sr. No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
Parameters
pH
Conductivity
Texture
UOM
-s/cm
--
Sand
Silt
Clay
Bulk Density
Exchangeable Calcium as Ca
Exchangeable Magnesium as Mg
Exchangeable Sodium as Na
Available Potassium as K
Available Phosphorous
Available Nitrogen as N
Organic Matter
Organic Carbon
Water soluble chloride as Cl
Water soluble sulphate as SO4
Sodium Absorption Ratio
Aluminium
Total iron
Manganese
Boron
Zinc
%
%
%
g/cc
mg/kg
mg/kg
mg/kg
Kg/ha
Kg/ha
Kg/ha
%
mg/kg
mg/kg
%
-%
%
mg/kg
mg/kg
mg/kg
S6
7.7
424.0
Sandy
Clay
36.0
24.0
40.0
1.2
2430
1200
290
418.5
50.1
202.0
0.61
0.35
211.6
73.2
0.54
0.52
1.04
264.0
72.4
68.9
S7
7.6
392.0
Sandy
Clay
32.0
30.0
38.0
1.1
3260
1820
340
409.2
66.6
191.0
0.41
0.24
320.5
97.6
0.54
0.75
1.50
328.9
45.2
83.2
S8
7.8
378.0
Sandy
Clay
35.0
23.0
42.0
1.0
3290
1800
375
379.8
61.9
164.3
0.56
0.32
202.3
88.1
0.58
0.68
1.36
482.6
50.6
68.9
S9
7.7
268.0
Sandy
Clay
38.0
22.0
40.0
1.1
2945
1375
315
341.0
58.4
230.2
0.82
0.48
230.4
68.5
0.54
0.83
1.66
372.4
52.4
84.3
S10
8.1
480.0
Sandy
Clay
32.0
20.0
48.0
1.0
4280
2125
475
379.8
59.5
193.8
0.93
0.54
363.7
87.5
0.66
0.90
1.80
689.8
78.3
110.0
C3-27
Soil Test
pH
Organic Carbon
Nitrogen (kg/ha)
Classification
<4.5 Extremely acidic
4.51- 5.50 Very strongly acidic
5.51-6.0 moderately acidic
6.01-6.50 slightly acidic
6.51-7.30 Neutral
7.31-7.80 slightly alkaline
7.81-8.50 moderately alkaline
8.51-9.0 strongly alkaline
9.01 very strongly alkaline
Upto 1.00 Average
1.01-2.00 harmful to germination
2.01-3.00 harmful to crops (sensitive
to salts)
Upto 0.2: very less
0.21-0.4: less
0.41-0.5 medium,
0.51-0.8: on an average sufficient
0.81-1.00: sufficient
>1.0 more than sufficient
Upto 50 very less
51-100 less
101-150 good
151-300 Better
>300 sufficient
C3-28
Sr. No.
5
Soil Test
Phosphorus (kg/ha)
Classification
Upto 15 very less
16-30 less
31-50 medium,
51-65 on an average sufficient
66-80 sufficient
>80 more than sufficient
0 -120 very less
120-180 less
181-240 medium
241-300 average
301-360 better
>360 more than sufficient
Potash (kg/ha)
3.5
Meteorology
The meteorological data recorded during the study period is very useful for proper
interpretation of the baseline information regarding plant site area and
surrounding area for air quality dispersion. Historical data on meteorological
parameters will also play an important role in identifying the general
meteorological regime of the region.
The year may broadly be divided into four seasons:
3.5.1
Winter season
Pre-monsoon season
Monsoon season
Post-monsoon season
:
:
:
:
December to February
March to May
June to September
October to November
Methodology
The methodology adopted for monitoring surface observations is as per the
standard norms laid down by Bureau of Indian Standards (IS : 8829) and India
Meteorological Department (IMD). On-site monitoring was undertaken for various
meteorological variables in order to generate the site-specific data. Data was
collected every hour continuously from 1st March 2014 to 31st May 2014.
C3-29
IMD data from Ranchi has been collected for pressure, temperature, relative
humidity, rainfall, evaporation, wind speed and direction. The data at IMD is
usually measured twice a day viz., at 0830 and 1730 hr.
3.5.2
Presentation of Data
C3-30
seasons was observed to be dry. The monthly variations in the relative humidity
are presented in Table-3.5.1.
3] Atmospheric Pressure
The average pressure level was found to be in the range of 928.1 to 942.3 mb at
0830 hr and 924.8 mb to 939.8 mb at 1730 hr. It can be seen from the data that
not much variations are observed in the average atmospheric pressure levels. The
pressure levels are found to be fairly consistent over the region. The monthly
variations in the pressure levels are presented in Table-3.5.1.
TABLE-3.5.1
CLIMATOLOGICAL DATA
STATION: IMD, RANCHI
Month
January
February
March
April
May
June
July
August
September
October
November
December
Atmospheric
Pressure (mb)
0830
1730
942.3
941.0
938.7
935.9
932.5
928.6
928.1
929.4
933.5
937.9
941.1
941.9
939.8
937.8
934.9
931.1
928.6
924.8
925.1
928.9
930.1
935.7
939.3
938.6
Temperature
(0C)
Mean
Mean
Max
Min
23.8
9.8
26.2
12.1
31.3
16.9
36.3
21.3
38.2
24.3
34.4
24.2
29.4
22.5
29.1
22.2
29.5
21.7
28.8
18.3
26.0
12.6
23.5
9.7
Relative
Humidity (%)
0830
1730
63
56
42
37
46
68
87
87
84
73
56
60
52
42
32
27
34
63
83
84
83
69
54
50
Total Rainfall
Rainfall
(mm)
24.5
38.5
27.9
21.9
48.9
200.6
358.4
351.6
251.9
108.9
17.6
4.2
1454.9
4] Rainfall
The average annual rainfall based on the 10 year IMD data, was observed to be
1454.9 mm. The monsoon sets in the month of June and continues till September
and sometime extends upto mid October. The maximum amount of rainfall (358.4
mm) occurs in the month of July. The maximum number of rainy days was also
observed in the month of July. Monthly variations in the rainfall are given in
Table-3.5.1.
5] Cloud Cover
During the winter and the pre-monsoon seasons, it was observed that the skies
were generally very clear. In the post-monsoon season, generally light clouds
were observed in the evenings, with clear mornings. During the monsoon season,
both in the mornings and evenings, the skies were found to be generally clouded.
C3-31
6] Wind Speed/Direction
Generally, light to moderate winds prevail throughout the year. Winds were light
and moderate particularly during the morning hours, while during the afternoon
hours the winds were stronger. The seasonal and annual windrose patterns are
shown in Figure-3.5.2 to 3.5.4.
3.5.3.2 Observations on Primary Data
The site specific data is presented in Table-3.5.28 and discussed below:
TABLE-3.5.2
SUMMARY OF THE METEOROLOGICAL DATA GENERATED AT SITE
Month
March 2014
April 2014
May 2014
Range
Temperature (0C)
Max
Min
40.5
16.6
42.5
20.5
43.4
21.0
16.6-43.4
Rainfall
(mm)
16
Nil
Nil
16
1] Temperature
Maximum temperature of 43.4oC and minimum temperature of 16.60C was
recorded during the study period. Maximum temperature was observed during
May and the minimum temperature was observed during March in the study
period.
2] Relative Humidity
During the period of observation the relative humidity recorded ranged from
29.5% to 38.4%. Maximum humidity was observed during the month of March.
3] Rainfall
Rainfall was observed to be 16 mm during March and no rainfall during April and
May.
4] Cloud Cover
The clear skies were observed mostly during the study period.
5] Wind Speed/Direction
The wind roses for the study period representing pre-monsoon season is shown in
Figure-3.5.5. A review of the wind rose diagram shows that predominant winds
are mostly from NW followed by SW and WNW direction. Calm condition prevailed
for 7.8% of the total time.
Site-specific micro meterological data for the study period as per ToR-27 and ToR-29
C3-32
3.5.3.3 Comments
The India Meteorological Department (IMD) records the data at two times a day viz.
0830 hr and 1730 hr while the site specific data has been recorded at an hourly
interval. On comparison of site specific data generated for study period vis--vis the
IMD data, slight variations were found. The following observations are brought out:
The temperature recorded on site when compared vis--vis the IMD data, slight
variations were found. The maximum and minimum temperatures recorded at site
during study period were 43.40C and 16.6oC, whereas the maximum and minimum
temperature recorded at IMD, Ranchi for the same pre-monsoon season are 38.2oC
and 16.9oC respectively.
The relative humidity was observed to range from 29.5% to 38.4% during the
study period whereas according to IMD, Ranchi data the relative humidity was
observed to range from 27% to 46%. The variation could be because of the fact
that the RH values considered for the site are actual values while the range of IMD,
Ranchi data represents the average values over 10 years.
The data generated at continuous monitoring station near project site when
compared with the data recorded at IMD, it can be observed that the data
generated at the site is broadly compatible with regional meteorology, except
minor variations as described above.
The variations can be attributed to distance between two stations, different
altitudes of monitoring stations, monitoring frequency and the topographical
features between the two stations.
3.5.4 Site Specific Upper Air Data9
SODAR was operated continuously from 1st May to 30th May 2014. This is a final
report prepared based on one month data. Data generation remained almost
continuous throughout this period using power backup system.
The hourly echograms obtained for a total of about 688 hours in 30 days have
been analyzed to obtain mixing heights. Graphical representation of mixing height
has been shown in Figure-3.5.1. A detailed sodar study report is enclosed in
Annexure-XIII.
C3-33
FIGURE-3.5.1
AVERAGE MIXING HEIGHT
Mixing Height
The mixing height during day time has been observed more than 1000 m
throughout the period of observation. Peak mixing Height for the study period 1st
May to 30th May month is 3065 m.
i) Nocturnal Inversion Period
The period of nocturnal inversion is from 20:00 hrs in the evening to 06:00 hrs in
the morning. The mixing height during nocturnal inversion period in month of May
125 to 357 m.
ii) Early Morning Rising Inversion Layer
The nocturnal inversion layer starts rising at 0800 hrs with the rising of the sun.
It continues to rise till 1000 hrs. The fumigation hours are from 08:00 hrs to
10:00 hrs.
iii) Day Time Convective Mixing Layer
Day time connective structures start forming noon after sunrise under the rising
layer. After 0900 hrs they come in full bloom and rise to height a more than 1000
m. The convective structures start decreasing in the afternoon and disappear
around 19:00 hrs.
iv) Evening Transition Period
The evening transition period is between 18:00 hrs to 19:00 hrs. During this
period the connective structure drop off and the inversion starts forming.
VIMTA Labs Limited, Hyderabad
C3-34
N 3.2%
NN
E1
.2%
10.7% S
N 5.0%
NN
E2
.2%
15.5% S
N 5.7%
NN
E0
.6%
SS
W
3.7
%
SS
W
11.3% S
3.6
%
SS
W
3.3
%
6.0% S
17-30 HRS
MONSOON
17-30 HRS
PRE MONSOON
5%
SCALE
5%
SCALE
ES
E3
.8%
%
.5
11
SS
W
SW
6%
4.
2.3
%
W
WS
E 11.5%
SE
%
.2
11
7%
7.
C-4.1%
6.5% W
%
2.2
E
N
.7%
E1
EN
.2%
E1
SS
SE
.6%
E0
SS
ES
E2
.4%
E 7.2%
ES
E1
.8%
7%
5.
W
NN
W
NN
.0%
E1
EN
WN
W
E 7.3%
W
WS
SW
%
2.3
W
N
%
2.6
3%
6.
3%
5.
.2%
E2
EN
08-30 HRS
MONSOON
%
.2
10
W
N
%
1.0
SW
4.0
%
E
N
0%
7.
SE
%
.8
20
C-1.5%
6.4% W
W
WS
E
N
.8%
E1
SS
%
.0
30
WN
W
%
5.0
6%
5.
SW
08-30 HRS
PRE MONSOON
16.
4%
C-5.0%
10.9% W
SE
.3%
E0
SS
%
5.0
WN
W
E 2.7%
ES
E1
.4%
W
WS
W
NN
C-10.1%
%
1.5
W
NN
.3%
E0
EN
9.6% W
%
.4
17
E
N
5.5
%
3%
3.
W
N
%
2.3
W
N
WN
W
8%
6.
%
.3
12
6.6
%
N 3.6%
NN
E0
.7%
Chapter-3
Baseline Environmental Status
SPEED CALM
SPEED CALM
1
11
19
>19 Km/hr
11
19
>19 Km/hr
FIGURE-3.5.2
WIND ROSE - PRE-MONSOON AND MONSOON (IMD- RANCHI)
VIMTA Labs Limited, Hyderabad
C3-35
N 8.9%
SS
W
17-30 HRS
POST MONSOON
SW
NN
E2
.0%
N 12.5%
ES
E2
.3%
17-30 HRS
WINTER
5%
SCALE
W
WS
7%
2.
2.0% S
1.0% S
SS
W
5%
5.
1.0
2%
7.
.6%
E0
EN
C-7.2%
E 5.1%
2.3% W
SE
1.0
WN
W
2%
4.
SE
.3%
E0
SS
ES
E2
.5%
%
E0
SS
1.
.5%
E1
EN
E 7.5%
C-10.0%
W
WS
SW
5%
0%
8.2
SS
W
2.0% W
NN
E3
.5%
WN
W
%
.0
14
W
NN
W
NN
08-30 HRS
WINTER
%
7.7
7.5
N 17.0%
%
.5
21
4.0
1.3
%
08-30 HRS
POST MONSOON
0.7
0%
2.5% S
%
.0
34
5.
3%
1.
SE
.3%
E0
SS
SW
WN
W
6%
3.
.7%
E0
EN
6.4% W
C-32.9%
E 3.0%
ES
W
E0
S
W
.3%
%
1.4
W
S
7%
.
3
0%
1.
SE
.5%
E0
SS
SS
W
.5%
E0
EN
E 4.5%
5.0% W
C-18.5%
ES
W
E
1.0
WS
%
%
1.0
NN
E2
.0%
6.7
3.3% S
NN
E8
.0%
W
NN
WN
W
5%
%
6.8
%
.5
11
W
N
W
NN
3.5
%
.4
17
W
N
7.5
%
.5
16
N 13.0%
Chapter-3
Baseline Environmental Status
5%
SCALE
SPEED CALM
SPEED CALM
1
11
19
>19 Km/hr
11
19
>19 Km/hr
FIGURE-3.5.3
WIND ROSE POST-MONSOON AND WINTER (IMD- RANCHI)
VIMTA Labs Limited, Hyderabad
C3-36
WN
W
%
11
.9
%
6.
3%
E
8.0% S
2.0
7%
3.
.7%
SS
W
W
WS
E0
SS
.0%
E1
EN
C-17.0%
E 4.3%
ESE
1.2
%
8.0% W
%
3.4
NN
E3
W
NN
5.6
.0%
4.5
%
.4
12
N 7.1%
Chapter-3
Baseline Environmental Status
WN
W
5.0% S
SS
W
%
4%
6.
1.8
4%
2.8
%
5.
ESE
.6%
S
W
W
WS
E0
SS
%
1.0
.2%
E1
EN
E 7.9%
C-6.0%
4.4% W
8.
5%
W
NN
%
5.0
8.1
N 10.0%
NN
E2
.0%
%
.9
23
08-30 HRS
ANNUAL
17-30 HRS
ANNUAL
5%
SCALE
SPEED CALM
1
11
19
>19 Km/hr
FIGURE-3.5.4
WIND ROSE-ANNUAL (IMD- RANCHI)
VIMTA Labs Limited, Hyderabad
C3-37
N
W
1.0
%
NN
E1
.5%
.7%
W2
NN
N 4.7%
%
.1
19
WN
W1
NE
3%
4.
E1
EN
C-7.8%
W 6.2%
ES
E2
.6%
.1%
SS
W3
9%
4.
.3%
5%
SCALE
SPEED
SE
E1
%
.8
11
S 9.7%
SW
E 4.3%
SS
.4
W3
WS
.6%
CALM
1.0
11
19
>19
Km/hr
FIGURE-3.5.5
SITE SPECIFIC WIND ROSE- (PRE-MONSOON 2014)
VIMTA Labs Limited, Hyderabad
C3-38
3.6
3.6.1
3.6.2
10
C3-39
Arsenic (As);
Lead (Pb);
Benzo Pyrene (BAP); and
Poly-aromatic hydrocarbons (PAH).
Name of the
Station
AAQ1
AAQ2
Project site
Sayatanr village
Distance from
the Boundary of
Plant Site (km)
4.2
AAQ3
Sonahatu village
8.9
AAQ4
Sigid village
3.6
NW
AAQ5
Barenda village
0.5
AAQ6
Marangkiri village
2.5
NE
AAQ7
Mankidih village
2.9
AAQ8
Tilapiri village
1.1
SE
AAQ9
Adardih village
8.0
SE
AAQ10
Hesadih village
3.0
SSW
Direction w.r.t.
the Boundary of
Plant Site
WSW
Environmental
Setting
Rural
Cross wind
(Rural/Residential)
Up wind
(Rural/Residential)
Cross wind
(Rural/Residential)
Cross wind
(Rural/Residential)
Cross wind
(Rural/Residential)
Down wind
(Rural/Residential)
Cross wind
(Rural/Residential)
Down wind
(Rural/Residential)
Cross wind
(Rural/Residential)
C3-40
E
N
.7%
4.
3%
.5%
W2
NN
WN
W1
1.0
%
N 4.7%
19
.1
%
NN
E1
NW
.6%
E1
EN
C-7.8%
W 6.2%
E 4.3%
ESE
SE
E1
4.
S 9.7%
11
.8
%
SS
W3
2.6
%
9%
.3%
.1%
3.4
SS
W
WS
5%
SCALE
SPEED
CALM
FIGURE-3.6.1
AIR QUALITY SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
1.0
11
19
>19
Km/hr
C3-41
3.6.3
Summary of Observations
The results of the monitored data indicate that the ambient air quality of the region
in general is in conformity with respect to rural/residential norms of the National
Ambient Air Quality Standards of CPCB, with present level of activities.
11
12
1]
PM10: The maximum value for PM10 is observed at Hesadih village (AAQ10),
as 52.7 g/m3 with the minimum value observed at Barenda village (AAQ5),
as 37.0 g/m3 during the study period.
2]
3]
SO2: The maximum value for SO2 is observed to be 12.2 g/m3 at Hesadih
village (AAQ10) station with the minimum value observed at Sayatanr
village (AAQ2) station as 9.3 g/m3 respectively during the study period.
4]
NOx: The maximum value for NOx is observed at Project site (AAQ1)
station, as 16.0 g/m3 with the minimum value observed at Project site
(AAQ1) station as 11.5 g/m3 during the study period.
5]
CO: The maximum value for CO is observed at Project site (AAQ1) and
Mankidih village (AAQ7), as 371 g/m3 with the minimum value observed at
Plant site (AAQ1) station as 200 g/m3 during the study period.
6]
O3: The maximum value for O3 is observed at Sigid village (AAQ4), as 7.1
g/m3 with the minimum value observed at Sonahatu village (AAQ3) station
as 2.3 g/m3 during the study period.
7]
Lead (Pb): Lead concentrations were observed <0.05 ng/m3 in all the
sampling locations.
8]
Arsenic (As): Arsenic values in all the locations are observed to be less
than 0.2 ng/m3.
C3-42
9]
Nickel (Ni): Nickel values in all the locations are observed to be less
than0.1 ng/m3.
10]
11]
12]
Benzo(a) Pyrene (BaP): BaP values observed in all the locations are
<1.0 ng/m3.
13]
Conclusion
From the above analysis of the data, it infers that the air quality levels in the
study area are of fairly good quality. The observed concentrations can be
attributed to rural and residential activities and rural and semi urban activties.
These are no operating industries in the region. The observed concentrations are
within permissible limits specified by CPCB.
C3-43
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-3
Baseline Environmental Status
TABLE-3.6.2
SUMMARY OF AMBIENT AIR QUALITY RESULTS (PRE-MONSOON SEASON, 2014)
Station
Code
AAQ1
AAQ2
AAQ3
AAQ4
AAQ5
AAQ6
AAQ7
AAQ8
AAQ9
AAQ10
Station
Code
AAQ1
AAQ2
AAQ3
AAQ4
AAQ5
AAQ6
AAQ7
AAQ8
AAQ9
AAQ10
Locations
Min
Project Site
Sayatanr village
Sonahatu village
Sigid village
Barenda village
Marangkiri village
Mankidih village
Tilapiri village
Adardih village
Hesadih village
Range
42.1
38.2
38.7
41.2
37.0
38.2
39.2
38.2
39.7
41.0
Locations
Min
Project Site
Sayatanr village
Sonahatu village
Sigid village
Barenda village
Marangkiri village
Mankidih village
Tilapiri village
Adardih village
Hesadih village
Range
200
293
220
268
216
231
263
268
287
284
PM10 (g/m3)
Max
Avg
52.1
51.2
50.2
51.0
51.4
51.2
50.5
50.2
49.5
52.7
37.0 -
CO (g/m3)
Max
Avg
371
368
351
349
367
354
371
365
366
366
200 -
270
341
304
307
304
279
313
326
330
332
371
45.7
43.3
44.6
46.0
45.7
47.3
47.2
45.3
45.4
47.1
52.7
98th
%le
349
366
351
345
360
338
367
365
363
366
98th
%le
51.1
50.7
49.7
50.7
51.3
51.0
50.5
49.4
49.3
52.1
Min
4.5
3.0
2.3
4.1
3.1
2.7
3.1
2.4
2.4
2.4
Min
19.2
19.1
19.3
20.6
19.3
21.4
20.1
19.6
20.9
19.5
PM2.5 (g/m3)
Max
Avg
23.8
25.8
25.6
25.5
25.7
25.9
25.9
25.7
25.6
25.1
19.1
O3 (g/m3)
Max
Avg
6.8
6.9
6.8
7.1
6.9
6.8
5.9
6.1
6.1
6.1
2.3
5.7
4.9
4.3
5.4
5.4
4.8
4.4
4.6
4.6
4.6
7.1
20.8
21.9
22.8
23.0
22.8
24.3
24.2
23.5
23.3
22.4
25.9
98th
%le
6.7
6.8
6.5
6.9
6.8
6.7
5.8
5.9
5.9
5.9
98th
%le
23.3
25.8
25.5
25.3
25.7
25.9
25.9
25.5
25.5
24.8
Min
9.4
9.3
9.4
9.5
9.5
9.4
9.8
9.5
9.4
9.8
SO2 (g/m3)
Max
Avg
11.8
11.7
10.7
11.6
11.8
11.8
11.8
11.4
11.8
12.2
9.3
10.4
10.1
10.0
10.4
10.2
10.3
10.5
10.2
10.8
11.6
12.2
98th
%le
11.7
11.7
10.7
11.5
11.7
11.6
11.5
11.4
11.7
12.2
Min
NOx (g/m3)
Max
Avg
11.5
11.7
12.2
12.1
12.2
11.6
12.1
11.8
11.7
11.8
16.0
15.8
15.8
15.2
15.8
15.9
15.1
15.6
15.6
15.9
11.5
13.9
13.5
13.3
13.8
13.8
13.5
13.9
13.4
14.4
13.6
16.0
98th
%le
15.6
15.8
15.3
15.0
15.3
15.4
15.0
15.0
15.6
15.7
NH3
(g/m3)
C6H6
(ng/m3)
BaP
(ng/m3)
As
(ng/m3)
Ni
(ng/m3)
Pb
(ng/m3)
PAH
(ng/m3)
<20.0
<20.0
<20.0
<20.0
<20.0
<20.0
<20.0
<20.0
<20.0
<20.0
<20.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<1.0
<0.2
<0.2
<0.2
<0.2
<0.2
<0.2
<0.2
<0.2
<0.2
<0.2
<0.2
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
<0.1
<0.05
<0.05
<0.05
<0.05
<0.05
<0.05
<0.05
<0.05
<0.05
<0.05
<0.05
<0.0022
<0.0022
<0.0022
<0.0022
<0.0022
<0.0022
<0.0022
<0.0022
<0.0022
<0.0022
<0.0022
C3-44
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-3
Baseline Environmental Status
TABLE-3.6.3
SUMMARY OF CHEMICAL CHARACTERIZATION OF RSPM PRE-MONSOON SEASON 2014
Sr.
No
Components
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Free Silica
Aluminium
Calcium
Sodium
Potassium
Magnesium
Lead
Zinc
Vanadium
Iron
Manganese
Boran
Cadmium
Copper
Nickel
Cobalt
Mercury
Arsenic
Sulphur
Phosphorus
Chlorides
Chromium
AAQ1
Min
0.2
0.7
2.5
1.6
1
0.23
0.06
1.2
<0.001
0.23
1.2
2
<0.001
0.06
0.01
<0.001
<0.001
<0.001
0.3
2.8
2.5
0.01
Max
0.58
1.6
5
3.5
2.3
1.5
0.2
4.6
0.03
0.5
2.4
4.8
0.02
0.2
0.03
<0.001
<0.001
0.003
1
4.5
4.2
0.03
AAQ2
Min
0.18
1
2.3
1.2
0.5
0.1
0.08
0.68
<0.001
0.7
1.5
1.2
<0.001
0.03
0.02
<0.001
<0.001
<0.001
0.5
3
2.5
0.01
Max
0.62
2.2
4
2.5
1.8
1.2
0.3
1.5
0.06
1.8
3.8
4.5
0.1
0.05
0.06
<0.001
<0.001
0.005
1.5
4.8
4.5
0.06
AAQ3
Min
0.19
1.2
3.4
1.5
1.8
0.2
0.05
1.68
<0.001
0.2
0.6
1.6
0.01
0.06
0.005
<0.001
<0.001
<0.001
0.023
2.2
1
0.009
Max
0.68
2.5
5.1
3.4
3.5
0.8
0.15
4.2
0.02
0.5
1.6
4.52
0.02
0.025
0.029
<0.001
<0.001
0.003
0.5
4.9
2.2
0.06
AAQ4
Min
0.09
1.6
2.9
2.2
1.6
0.15
0.08
1.95
<0.001
0.2
1.02
3
<0.001
0.05
0.02
<0.001
<0.001
0.003
0.3
1.5
1.6
0.02
Max
0.54
2.9
3.5
4.2
3.2
1.5
0.26
5.2
0.02
1
2.8
4.5
0.06
0.35
0.04
<0.001
<0.001
0.02
1.2
4
4.2
0.08
AAQ5
Min
0.19
0.6
2.3
1.3
0.8
0.2
0.03
0.9
<0.001
0.19
1.2
1.8
<0.001
0.03
0.02
<0.001
<0.001
0.005
0.5
3.8
2.5
0.01
Max
0.48
1.2
4.3
4.2
2.3
1.5
0.25
3.4
0.02
1.32
2.5
4.3
0.02
0.35
0.06
<0.001
<0.001
0.08
1.5
4.8
3.87
0.05
AAQ6
Min
0.2
0.8
2.56
1.67
1.02
0.22
0.05
1
<0.001
0.2
1.5
1.9
<0.001
0.07
0.02
<0.001
<0.001
<0.001
0.4
2.5
2.8
0.02
Max
0.5
1.3
3.8
3
1.5
1.9
0.5
1
0.06
1.3
3.4
4.3
0.03
0.35
0.12
<0.001
<0.001
0.008
1.6
5.1
4.5
0.05
AAQ7
Min
0.32
1.2
2.01
1.9
0.5
0.32
0.15
0.5
<0.001
0.8
1.6
2.5
<0.001
0.02
0.01
<0.001
<0.001
<0.001
0.256
3.4
3.2
0.005
Max
0.73
2.8
5.1
3.3
1.69
1.458
0.34
1.35
0.02
1.23
3
5
0.05
0.6
0.08
<0.001
<0.001
0.005
1.1
5
5
0.06
AAQ8
Min
0.2
1.5
1.326
1.6
1.3
0.9
0.08
2
<0.001
0.34
1.5
1.895
<0.001
0.09
0.02
<0.001
<0.001
0.01
0.62
1.21
1.3
0.01
Max
0.75
2.6
3.55
4.2
3.2
2
0.32
4.5
0.02
1
3
4.2
0.05
0.42
0.05
<0.001
<0.001
0.03
1.3
3.5
4.1
0.08
C3-45
3.7
Water Quality
Selected water quality parameters of surface and ground water resources within 10
km radius of the study area has been studied for assessing the water environment
and evaluate anticipated impact of the project. Understanding the water quality is
essential in preparation of environmental impact assessment and to identify critical
issues with a view to suggest appropriate mitigation measures for implementation.
The purpose of this study is to:
The information required has been collected through primary surveys and
secondary sources.
3.7.1
Surface Hydrology
The drainage in the study area is governed by Subarnarekha river flowing from
north to south direction. Many small rivers, viz., Raru nadi, Kanchi nadi, Ghosru
nadi and several seasonal nallas meet the river during its course in the study area.
3.7.2
Methodology
Reconnaissance survey was undertaken and monitoring locations were finalized
based on:
The ground water and surface water sources covering 10 km radial distance were
examined for physico-chemical, heavy metals and bacteriological parameters in
order to assess the effect of industrial and other activities on surface and ground
water. The samples were analyzed as per the procedures specified in 'Standard
Methods for the Examination of Water and Wastewater' published by American
Public Health Association (APHA).
Samples for chemical analysis were collected in polyethylene carboys. Samples
collected for metal content were acidified with 1 ml HNO3. Samples for
bacteriological analysis were collected in sterilized glass bottles. Selected physicochemical and bacteriological parameters have been analyzed for projecting the
existing water quality status in the study area.
C3-46
3.7.3
Location
Surface Water
SW1
Subernarekha upstream (North of Marangkiri
village)
SW2
Subernaredkha downstream (Near Sari kuli
village)
SW3
Kanchi nadi upstream (near Garadih village)
SW4
Kanchi nadi downstream (between Jeherdih and
Barenda)
SW5
Raru nadi
SW6
Subarnarekha river (near Marangkiri village)
SW7
Domra nadi (river was dry)
SW8
Pond near Kodadih village (river was dry)
Ground Water
GW1
Project site
GW2
Sayatanr village
GW3
Jaherdih village
GW4
Barenda village
GW5
Marangkiri village
GW6
Mahuldih village
GW7
Tilaipiri village
GW8
Hesadih village
3.7.4
Distance
from Plant
Boundary
(km)
Direction
w.r.t. Plant
Boundary
5.5
NNE
6.1
ESE
6.2
2.7
W
N
7.0
2.4
3.4
4.3
N
NE
SE
SW
4.2
4.8
0.5
2.5
2.9
1.0
3.0
WSW
NW
N
NE
E
SE
SSW
Presentation of Results
The results of the water quality monitored during the study period representing premonsoon season are given in Table 3.7.2 and Table-3.7.3.
13
C3-47
parameters are well within the permissible limits. Bacteriological studies reveal the
absence of E. coli forms. (Table-3.7.2)
3.7.4.2 Ground Water Quality
The analysis results indicate that the pH ranges in between 7.2 to 7.6, which is well
within the specified standard of 6.5 to 8.5. Total hardness was observed to be
ranging from 46.0 to 233.0 mg/l. The hardness was found to be well within the limit
of 600 mg/l at all locations.
Chlorides at all the locations were within the permissible limit, ranging in between
10.5 to 62.5 mg/l. Fluorides were observed to be ranging in between 0.2 to 0.6
mg/l and are found to be within the permissible limit. Nitrates are found to be in
range of 2.0 13.0 mg/l. Bacteriological studies reveal that no coliform bacteria are
present in the samples. The heavy metal contents were observed to be in well
within the limits (Table-3.7.3).
C3-48
FIGURE-3.7.1
WATER SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-49
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-3
Baseline Environmental Status
TABLE-3.7.2
SURFACE WATER QUALITY
Sr. No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
Parameter
PH
Colour
Conductivity
Total Dissolved Solids
Dissolved Oxygen
BOD ( 3 days at 27oC)
COD
Total Hardness as CaCo3
Total Alkalinity as CaCo3
Calcium as Ca
Magnesium as Mg
Chloride as Cl
Residual free chlorine
Phosphate as PO4
Sulphate as SO4-Fluorides as FNitrates as NO3
Sodium as Na
Potassium as K
Total Boron as B
Cyanides as CN
Phenolic compound
Oil and grease
Cadmium as Cd
Arsenic as As
Copper as Cu
Lead as Pb
Iron as Fe
Chromium as Cr
Selenium as Se
Zinc as Zn
Aluminium as Al
Mercury as Hg
SAR
Insecticides
Anionic detergents as MBAS
Total Coliforms
Units
Hazen units
S/cm
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
MPN/ 100 ml
SW1
7.4
2
286.0
185.0
5.8
<3
<5
103.0
112.6
27.3
8.5
16.8
<0.2
<0.1
7.8
0.4
6.4
18.5
6.2
0.03
<0.02
<0.001
<0.1
<0.01
<0.01
<0.01
<0.01
0.03
<0.05
<0.01
0.02
<0.01
<0.001
0.79
Absent
<0.1
Absent
SW2
7.5
3
413.0
265.0
5.6
<3
<5
148.0
158.3
35.2
14.5
23.5
<0.2
0.1
11.5
0.5
12.6
26.5
8.0
0.05
<0.02
<0.001
<0.1
<0.01
<0.01
<0.01
<0.01
0.05
<0.05
<0.01
0.04
<0.01
<0.001
0.95
Absent
<0.1
Absent
SW3
7.3
2
147.0
92.0
6.0
<3
<5
49.0
58.7
11.5
5.0
11.5
<0.2
<0.1
6.8
0.2
2.8
14.8
2.8
0.01
<0.02
<0.001
<0.1
<0.01
<0.01
<0.01
<0.01
0.02
<0.05
<0.01
0.01
<0.01
<0.001
0.92
Absent
<0.1
Absent
SW4
7.8
3
1025.0
660.0
6.2
<3
<5
444.0
210.5
121.5
34.2
121.5
<0.2
0.2
16.3
0.7
14.3
30.2
11.2
0.08
<0.02
<0.001
<0.1
<0.01
<0.01
<0.01
<0.01
0.12
<0.05
<0.01
0.08
<0.01
<0.001
0.62
Absent
<0.1
Absent
SW5
7.5
2
484.0
310.0
5.4
<3
<5
160.0
182.0
40.0
14.6
34.0
<0.2
0.1
8.2
0.3
5.6
30.0
15.6
0.12
<0.02
<0.001
<0.1
<0.01
<0.01
<0.01
<0.01
0.04
<0.05
<0.01
0.06
<0.01
<0.001
1.03
Absent
<0.1
Absent
SW6
7.6
3
235.0
152.0
5.3
<3
<5
64.0
79.0
16.0
5.8
28.4
<0.2
0.1
3.2
0.1
4.8
23.0
10.0
0.08
<0.02
<0.001
<0.1
<0.01
<0.01
<0.01
<0.01
0.02
<0.05
<0.01
0.02
<0.01
<0.001
1.25
Absent
<0.1
Absent
$ Limits not specified as per IS code, Note:- SW-7 and SW-8 were dry at the time of sampling.
C3-50
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-3
Baseline Environmental Status
TABLE-3.7.3
GROUND WATER QUALITY
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
$ Limits not
Parameter
pH
Colour (Hazen units)
Taste
Odour
Conductivity
Turbidity (NTU)
Total Dissolve solids
Total Hardness as CaCO3
Total Alkalinity
Calcium as Ca
Magnesium as Mg
Residual Chlorine
Boron
Chloride as Cl
Sulphate as SO4
Fluorides as FNitrates as NO3
Sodium as Na
Potassium as K
Phenolic Compounds
Cyanides
Anionic Detergents
Mineral Oil
Cadmium as Cd
Arsenic as As
Copper as Cu
Lead as Pb
Manganese as Mn
Iron as Fe
Chromium as Cr6+
Selenium as Se
Zinc as Zn
Aluminium as Al
Mercury as Hg
Pesticides
E-coli(Nos/100 ml)
Coliform Organisms
specified as per IS code: 10500
IS:10500
Limits
6.5 8.5
5 (25)
Agreeable
Unobjec-tionable
$
5 (10)
500 (2000)
300 (600)
200 (600)
75 (200)
30 (100)
0.2 min
1
250 (1000)
200 (400)
1.0 (1.5)
45 (NR)
$
$
0.001 (0.002)
0.05 (NR)
0.2 (1.0)
0.01 (0.03)
0.01 (NR)
0.01 (NR)
0.05 (1.5)
0.05 (NR)
0.1 (0.3)
0.3 (1.0)
0.05 (NR)
0.01(NR)
5 (15)
0.03 (0.2)
0.001 (NR)
Absent
Absent
10
Units
GW1
GW2
GW3
GW4
GW5
GW6
GW7
GW8
Hazen
uS/cm
NTU
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
mg/l
7.5
2
Agreeable
UO
165.9
2
105.0
53.0
60.0
12.5
5.2
<0.2
0.01
14.0
7.5
0.3
2.6
15.6
3.2
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.02
<0.05
<0.01
0.01
<0.01
<0.001
Absent
Absent
<2
7.2
1
Agreeable
UO
144.0
2
90.0
46.0
56.0
11.3
4.2
<0.2
<0.01
10.5
6.0
0.2
2.0
14.2
2.6
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.01
<0.05
<0.01
<0.01
<0.01
<0.001
Absent
Absent
<2
7.4
2
Agreeable
UO
278.0
2
180.0
101.0
110.0
26.8
8.2
<0.2
0.03
16.0
8.1
0.4
6.0
18.3
5.6
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.04
<0.05
<0.01
0.04
<0.01
<0.001
Absent
Absent
<2
7.6
3
Agreeable
UO
591.0
3
380.0
233.0
192.0
60.3
20.0
<0.2
0.06
62.5
13.0
0.6
10.9
28.3
10.2
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.06
<0.05
<0.01
0.10
<0.01
<0.001
Absent
Absent
<2
7.2
2
Agreeable
UO
252.0
2
164.0
93.0
100.0
24.5
7.6
<0.2
0.03
15.8
8.0
0.4
5.8
17.5
5.0
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.04
<0.05
<0.01
0.04
<0.01
<0.001
Absent
Absent
<2
7.4
2
Agreeable
UO
267.0
2
174.0
97.0
104.6
25.6
8.0
<0.2
0.03
16.2
8.4
0.4
5.9
18.0
5.3
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.02
<0.05
<0.01
0.04
<0.01
<0.001
Absent
Absent
<2
7.5
3
Agreeable
UO
431.0
2
280.0
157.0
166.2
38.2
15.0
<0.2
0.04
24.3
12.8
0.6
13.0
27.0
8.5
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.04
<0.05
<0.01
0.06
<0.01
<0.001
Absent
Absent
<2
7.5
2
Agreeable
UO
365.0
2
235.0
136.0
150.0
34.7
12.0
<0.2
0.05
14.8
10.2
0.4
11.7
21.5
7.8
<0.001
<0.02
<0.1
<0.01
<0.01
<0.01
<0.01
<0.01
<0.01
0.22
<0.05
<0.01
0.18
<0.01
<0.001
Absent
Absent
<2
MPN/100 ml
C3-51
3.8
The time of day at which noise occurs, for example high noise levels at night in
residential areas are not acceptable because of sleep disturbance; and
The location of the noise source, with respect to noise sensitive land use, which
determines the loudness and period of exposure.
The environmental impact of noise can have several effects varying from Noise
Induced Hearing Loss (NIHL) to annoyance depending on loudness of noise. The
environmental impact assessment of noise due to construction activity, and
vehicular traffic can be undertaken by taking into consideration various factors like
potential damage to hearing, physiological responses, annoyance and general
community responses. Noise monitoring has been undertaken for 24 hours duration
at each location.
3.8.1
C3-52
FIGURE-3.8.1
NOISE MONITORING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-53
TABLE-3.8.1
DETAILS OF NOISE MONITORING LOCATIONS
Location
Code
Location
(Village)
N1
N2
N3
N4
N5
N6
N7
N8
N9
N10
Project site
Sayatanr village
Garadih village
Sonahatu village
Jaherdih village
Barenda village
Marangkiri village
Mahuldih village
Tilapiri village
Hesadih village
Distance from
Boundary
(km)
4.2
6.5
8.5
4.8
0.5
2.5
2.9
1.0
3.0
Direction w.r.t
Plant Boundary
Present Settings
WSW
W
WNW
NW
N
NE
E
SE
SSW
Rural
Rural/Residential
Rural/Residential
Rural/Residential
Rural/Residential
Rural/Residential
Rural/Residential
Rural/Residential
Rural/Residential
Rural/Residential
(L10 - L90)2
+ -----------60
Lday is defined as the equivalent noise level measured over a period of time during
day (6 am to 10 pm).
Lnight is defined as the equivalent noise level measured over a period of time during
night (10 pm to 6 am).
A noise rating developed by E P A for specification of community noise from all the
sources is the Day-Night Sound Level, (Ldn).
C3-54
Locations
Project Site
Sayatanr village
Garadih village
Sonahatu village
Jaherdih village
Barenda village
Marangkiri village
Mahuldih village
Tilapiri village
Hesadih village
Area
Code
A
B
C
D
Category of Area
Industrial Area
Commercial Area
Residential Area
Silence Zone
L10
L50
L90
Leq
Ld
Ln
Ldn
46.2
45.4
43.5
42.1
44.2
46.7
44.5
45.9
45.3
44.2
42.5
41.5
39.7
38.2
40.6
42.9
40.8
42.2
41.7
40.4
38.9
37.7
36.2
34.4
36.9
39.4
37.2
38.6
38.0
36.9
43.4
42.5
40.6
39.2
41.5
43.8
41.6
43.1
42.6
41.3
44.1
43.4
41.2
40.2
42.0
44.6
42.4
43.6
43.1
42.1
40.0
38.3
36.8
35.7
37.7
40.3
39.3
39.1
38.8
37.8
47.3
45.9
44.2
43.1
45.0
47.7
46.3
46.5
46.1
45.2
3.8.2.4 Observations
a)
The daytime noise levels at the residential locations ranged between 40.2 - 44.6 dB
(A). The maximum value of 44.6 dB (A) was recorded at Barenda village (N6) and
VIMTA Labs Limited, Hyderabad
C3-55
the minimum value of 40.2 dB(A) was recorded at the Sonahatu village (N4). It is
observed that the day time noise levels at maximum residential locations are within
the prescribed limit of 55 dB (A).
b)
The night time noise levels were ranged between 35.7 to 40.3 dB (A). The
maximum value was recorded at Barenda village (N6) and the minimum value was
recorded at the Sonahatu village (N4). It is observed that the night time noise
levels at maximum residential locations are within the prescribed limit of 45 dB (A).
The activities which contributed to the baseline levels are normal rural/residential
activities including local rural traffic. There are no industrial activities in the study
area.
3.9
3.9.1 Introduction
Ecological evaluation aims at developing and applying methodologies to assess
the relevance of an area for nature conservation. As such, it is to support the
assessment of the impact of a proposed development by providing guidance on
how to describe the ecological features within the area affected, how to value
them, and how to predict the value losses caused by the development. The
evaluation of the ecological significance of an area can be undertaken from
different perspectives and consequently with different objectives. One of such
perspectives focuses on the conservation of the biological diversity or biodiversity.
Among the human activities that pose the highest threat to the conservation of
biodiversity are the developmental projects in particular. Such projects represent
artificial elements that cut through the landscape and interfere with the natural
habitat and its conditions by emissions that may be solid, liquid and or gaseous.
This in turn influences the abundance and distribution of plant and animal
species, i.e., the biodiversity of the area is impacted.
The secondary data is usually existing and obtainable from the governmental
agencies or the scientific literature. This information is typically complemented by
field visit, site surveys and sample collection. The description of the actual
ecological assessment provided by the ecological baseline study serves to set a
reference for the subsequent impact analysis. Moreover, it helps decision-makers
and EIA reviewers to become familiar with the environmental features and the
needs of the study area.
3.9.2 Objectives
The present study was undertaken with the following objectives to assess both
terrestrial and aquatic habitats of the study area:
14
To assess the nature and distribution of vegetation in and around the proposed
project site;
C3-56
3.9.3 Methodology
To achieve the above objectives a detailed study of the area was undertaken with
the proposed project site as its center. The different methods adopted were as
follows:
Primary data collection for flora through random sampling method for trees,
shrubs and herbs from the selected locations to know the vegetation cover
qualitatively;
Faunal studies by taking transect in the study area to spot the fauna and also
to know the fauna through secondary indictors such as pugmarks, scats, fecal
pallets, calls and other signs;
Sourcing secondary data with respect to the study area from published
literature.
The locations for terrestrial and aquatic ecological studies are shown in Figure3.9.1 and the details are given in Table-3.9.1.
C3-57
FIGURE-3.9.1
MAP OF ECOLOGICAL SAMPLING LOCATIONS
VIMTA Labs Limited, Hyderabad
C3-58
TABLE-3.9.1
ECOLOGICAL SAMPLING LOCATIONS
Station
Location
Distance from
the Site (km.)
Direction
0.5
1.9
8.0
7.6
1.5
6.7
N
NNE
NE
ESE
E
SSW
5.5
6.2
6.2
2.7
NNE
E
W
N
Terrestrial
TE-1
Near village Baranda
TE-2
Near village Pandudih
TE-3
Near village Kalimati
TE-4
Near village Garadih
TE-5
Near village Mahuldih
TE-6
Near village Marankiri
Aquatic
AE-1
River Subarnarekha near village Dungdung
AE-2
At junction of Subarnarekha and Rauru
AE-3
River Kanchi near village Garadih
AE-4
River Kanchi near village Birdih
3.9.4
3.9.6
Baranda
Mahil
Tetuldih
Pepride
Rohardhi
Garadih
Bhusadih
Chatam
Mukrub
Sapuram
Barukande
Distance from
Plant Site
0.5
0.6
1.7
2.9
4.0
4.1
4.6
4.7
5.8
6.9
7.9
8.2
Direction
N
E
NNE
S
ESE
ESE
SSW
SE
NE
ESE
SSW
NE
C3-59
which is also the most dominant species in the region. Large areas of this land is
covered with regenerating B. monosperma. High amount of human pressure can be
seen on the existing vegetation.
Most of the trees have been felled or lopped and as a result the regeneration has
occurred. Other species that are represented include asan, bel, kusum, mango,
drumsticks, australian acacia, jamun and Eucalyptus sp. The understory is mainly
composed of Lantana camara, Eupatorium sp. and Ipomea carnea.
The core zone is used by the fauna mostly for transient passage. It was noted that
no sensitive species occurs in this area, nor was this area represented by a
permanent habitat of any species that has conservation importance. The animals
which pass through this area and in the vicinity of the villages are wild boar, hare,
Indian fox and the avifauna observed in this area was represented by spotted dove,
ringed dove, indian myna, larks, pied myna, indian roller, black drongo, jungle
babblers.
3.9.7
Buffer Zone
Hills: Most of the hill slopes and hill tops are barren due to rocky exposed surfaces
and steep slopes which do not allow any vegetation to grow. As shown in the
Figure-3.9.2 most of the hill ranges occurring in the study area show similar
desolate habitat.
Foothills and Hill Slopes: The areas which are on the lower slopes with less steep
elevation are covered with vegetation. This occurrence of vegetation is due to
availability of top soil with some boulders and rocky outcrops. These forest areas
are degraded and show signs of high anthropogenic pressure. There are no large
trees occurring but mostly regenerated growth of large trees which have been cut
down over the years. This forest type is mostly represented by Shorea robusta,
Delonix regia, Bauhinia recemosa, Schleichera oleosa, Phyllanthus emblica,
Madhuca indica, Albizia margninata, Terminalia elliptica, T. chebula and T.
tomentosa
Vegetation near Villages and Rivers: The most dominant species in this area is
Butea monosperma. Uniform stands of B. monosperma can be seen on the village
fringe, riverside and forest fringe near the foot hills. These stands do not have large
old grown trees but mostly regenerating stumps and poles as well as new
regeneration in the form of seedlings and saplings. These seedlings and saplings
represent the undergrowth and replace the shrubby vegetation.
Villages do show typically large trees of fruit bearing species such as Tamarindus
indica, Ficus bengalensis, F. religosa, Agle marmelos, Schleichera oleosa, Madhuca
indica, Azadirachta indica, Sygygium cumini, Acacia sp., drumsticks and species of
bamboo.
Many roads side plantation have been carried out by the forest department. The
block plantation carried out in the study area comprises of uniform stands of Shorea
robusta, Eucalyptus hybrids (Figure-3.9.3) and australian acacia.
C3-60
Family
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Meliaceae
Mimosaceae
Mimosaceae
Mimosaceae
Myrtaceae
Anacardiaceae
Annonaceae
Poaceae
Caesalpinaceae
Compositae
Caesalpinaceae
Cyperaceae
Moraceae
Moraceae
Papaveraceae
Agavaceae
Convolvulaceae
Compositae
Cacataceae
Capparidaceae
Convolvulaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Life Form
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Hemicrptophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Therophyte
Therophyteq
Therophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Hemicryptophyte
Phanerophyte
C3-61
Family
Meliaceae
Rhamanaceae
Poaceae
Poaceae
Compositae
Verbinacaee
Verbinaceae
Sapindaceae
Ruteceae
Myrtaceae
Combretaceae
Life Form
Phanerophyte
Phanrophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Anacardiaceae
Annonaceae
Arecaceae
Caricaceae
Chenopodiaceae
Compositae
Cruciferae
Cruciferae
Cruciferae
Cucurbitaceae
Cucurbitaceae
Fabaceae
Fabaceae
Fabaceae
Fabaceae
Liliaceae
Liliaceae
Malvaceae
Malvaceae
Myrtaceae
Pepavaraceae
Rutaceae
Sapindaceae
Solanaceae
Solanaceae
Umbelliferae
Umbelliferae
Phanerophyte
Phanerophyte
Geophyte
Therophyte
Geophyte
Therophyte
Therophyte
Therophyte
Geophyte
Therophyte
Therophyte
Geophyte
Therophyte
Hemicryptophyte
Therophyte
Geophyte
Geophyte
Therophyte
Therophyte
Phanerophyte
Hemicrptophyte
Therophyte
Phanerophyte
Therophyte
Geophyte
Hemicryptophyte
Geophyte
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Meliaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
C3-62
Family
Myrtaceae
Poaceae
Life Form
Phanerophyte
Phanerophyte
Acanthaceae
Acanthaceae
Acanthaceae
Acanthaceae
Acanthaceae
Acanthaceae
Acanthaceae
Acanthaceae
Agavaceae
Agavaceae
Aizoaceae
Aizoaceae
Alangiaceae
Amaranthaceae
Amaranthaceae
Amaryllidaceae
Anacardiaceae
Anacardiaceae
Annonaceae
Annonaceae
Apocyanaceae
Apocyanaceae
Apocyanaceae
Apocyanaceae
Apocyanaceae
Asclepiadaceae
Asclepiadaceae
Asclepiadaceae
Asclepiadaceae
Asclepiadaceae
Bignoniaceae
Bignoniaceae
Bombacaceae
Burseraceae
Cacataceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Cannaceae
Capparidaceae
Capparidaceae
Capparidaceae
Capparidaceae
Capparidaceae
Combretaceae
Combretaceae
Combretaceae
Combretaceae
Combretaceae
Compositae
Compositae
Compositae
Compositae
Therophyte
Phanerophyte
Therophyte
Therophyte
Hemicryptophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyteq
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Therophyte
C3-63
Technical Name
Echinops echinatus
Eclipta alba
Eclipta prostrate
Emilia lajerium
Lactuca punctate
Parthenium hysterophorus
Tridax procumbens
Vernonia cinera
Vicoa indica
Xanthium strumariumk
Evolvulus alsinoides
Evolvulus numalaris
Ipomea aquatic
Ipomea tuba
Oldenlandia umbellate
Raphanus sativus
Cuscuta reflexa
Cymbopogon jwarancusa
Cyperus aristatus
Setaria glauca
Shorea robusta
Acalypha lanceolata
Antidesma diandrum
Bridelia retusa
Bridelia superba
Emblica officinale
Euphorbia geniculate
Euphorbia hirta
Euphorbia hyperocifolia
Euphorbia neruri
Euphorbia nivula
Euphorbia piluliflora
Euphorbia tricauli
Jatropha gossypifolia
Mallotus philippinus
Phyllanthes asperulatus
Phyllanthes emblica
Phyllanthes nirurii
Phyllanthes reticulates
Alysicarpus hamosus
Crotalaria medicagenia
Dalbergia paniculata
Tephrosia purpuria
Flacourtia indica
Flacourtia latifolia
Eulaliopsis binate
Hyptis suavalens
Leucas aspera
Leucas longifolia
Ocimum americanum
Ocimum canum
Ocimum sanctum
Asparagaus racemosus
Dendrophthe falcate
Loranthus sp
Ammania baccafera
Diospyros melanoxylon
Diospyros Montana
Lawsonia inermis
Abutilon indicum
Family
Compositae
Compositae
Compositae
Compositae
Compositae
Compositae
Compositae
Compositae
Compositae
Compositae
Convolvulaceae
Convolvulaceae
Convolvulaceae
Convolvulaceae
Convolvulaceae
Cruciferae
Cuscutaceae
Cyperaceae
Cyperaceae
Cyperaceae
Dipterocarpaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Euphorbiaceae
Fabaceae
Fabaceae
Fabaceae
Fabaceae
Flacourtiaceae
Flacourtiaceae
Poaceae
Labiatae
Labiatae
Labiatae
Labiatae
Labiatae
Labiatae
Liliaceae
Loranthaceae
Loranthaceae
Lythraceae
Lythraceae
Lythraceae
Lythraceae
Malvaceae
Life Form
Therophyte
Therophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Hydrophyte
Hemicryptophyte
Therophyte
Therophyte
Epiphyte
Hemicrptophyte
Therophyte
Hemicryptophyte
Phanerophyte
Therophyte
Hemicryptophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Epiphyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
C3-64
Technical Name
Gossypium herbaceum
Hibiscus gibbosa
Hibiscus micronthus
Hibiscus ovalifolia
Hibiscus rosa-cianensis
Hibsicus caesus
Malvastrum coramandalicum
Sida orientalis
Azadirachta indica
Acacia Arabica
Acacia auriculiformis
Acacia catechu
Acacia cenescens
Acacia fernacea
Acacia intinsia
Acacia leucophloe
Mimosa hamate
Parkinsonia aculata
Pithocolobium dulce
Ficus benghalensis
Ficus carica
Ficus glomerata
Ficus hispida
Ficus racemosus
Ficus religiosa
Ficus gibbosa
Psidium guava
Sygygium cumini
Boerheavia chinensis
Boerheavia diffusa
Jasmimum arborens
Jussiaea suffraticosa
Careya arborea
Phoenix aculis
Argemone Mexicana
Erythrina indica
Fumaria indica
Lathyrus sativus
Medicago aureus
Medicago indica
Medicago lymorpha
Medicago polymorpha
Mucuna prurita
Oogeinia oojensis
Paspalum strobilanthus
Passiflora foetida
Sesamum indicum
Apluda mutica
Aristida adscensionsis
Arthraxon prionoites
Cenchrus ciliaris
Cenchrus setifgera
Chloris dolichosta
Chloris variegate
Cyanodactylon sp
Dactylectinium annualatum
Dichanthium annulatum
Digetaria bicornis
Digetaria Segetaria
Eragrostis biferia
Family
Malvaceae
Malvaceae
Malvaceae
Malvaceae
Malvaceae
Malvaceae
Malvaceae
Malvaceae
Meliaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Mimosaceae
Moraceae
Moraceae
Moraceae
Moraceae
Moraceae
Moraceae
Moraceae
Myrtaceae
Myrtaceae
Nyctaginaceae
Nyctaginaceae
Oleaceae
Onagraceae
Palmae
Palmae
Papaveraceae
Papillionaceae
Papillionaceae
Papillionaceae
Papillionaceae
Papillionaceae
Papillionaceae
Papillionaceae
Papillionaceae
Papillionaceae
Passifloraceae
Passifloraceae
Pedaliaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Life Form
Therophyte
Therophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phaneophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Hydrophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Hemicryptophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Hemicryptophyte
Phanerophyte
Hemicryptophyte
Phanerophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Therophyte
Geophyte
Therophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
C3-65
Technical Name
Eragrostis tenella
Ichnocarpus frutens
Inperata cylendrica
Ischaemum rugosum
Panicum milliria
Panicum notatum
Saccharum munja
Saccharum officinarum
Sachharum spontanseum
Themeda quadrivalvis
Tragus biflorus
Vivevera zizanoides
Polygala ererptera
Eichhornia cressipes
Portulaca oleracea
Punica granulatum
Delphinium ajacus
Zizyphus mauritiana
Tinospora cordifolia
Zizyphus jujube
Rhus mysoorensis
Rosa indica
Adina cordifolia
Borreria hispida
Borreria stricta
Canthium diddynum
Cestrum diurnum
Cestrum nocturnum
Combretum ovalifolium
Cordia dichotoma
Cordia myxa
Cordia rothri
Gardenia latifolia
Gardenia lucida
Gmelina arborea
Helictris isora
Heliotropium indicum
Ixora arborea
Ixora parviflora
Ixora singapuriens
Oldenlandiua corymbosa
Randia dumatorum
Aegle marmelos
Atalantia monophylla
Citrus liminoites
Citrus limon
Citrus media
Feronia elephantum
Murraya exotica
Murraya koenigii
Salmalia malabarica
Casearia graveolens
Sapindus emerginatus
Scherebera sweitenoides
Schleichera oleosa
Achras sapota
Madhuca latifolia
Ailanthes excels
Capsicum annulatum
Datura alba
Family
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Poaceae
Polygalaceae
Pontederiaceae
Portulacaceae
Puniaceae
Ranunculaceae
Rhamanaceae
Rhamnaceae
Rhamnaceae
Rosaceae
Rosaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rubiaceae
Rutaceae
Rutaceae
Rutaceae
Rutaceae
Rutaceae
Rutaceae
Rutaceae
Rutaceae
Salmaliaceae
Samydiaceae
Sapindaceae
Sapindaceae
Sapindaceae
Sapotaceae
Sapotaceae
Simaroubaceae
Solanaceae
Solanaceae
Life Form
Therophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Hemicryptophyte
Therophyte
Hemicryptophyte
Hemicryprophyte
Hemicryptophyte
Therophyte
Therophyte
Hydrophyte
Therophyte
Therophyte
Phanerophyte
Phanrophyte
Therophyte
Phanerophyte
Phanerophytes
Therophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Theophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Hemicryptophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
C3-66
Technical Name
Datura fastulosa
Datura metal
Lycopersicum esculentus
Nicotiana plubigera
Physalis minima
Solanum nigrum
Solanum xanthocarpum
Symplocos racemosa
Grewia abutifolia
Grewia salivifolia
Grewia subinaqualis
Sterculia villosa
Triumferta pilosa
Lantana camara
Tectona grandis
Vitex negundo
Vitex negungo
Cissus quadrangularis
Vitis vermifera
Fagonia cretica
Family
Solanaceae
Solanaceae
Solanaceae
Solanaceae
Solanaceae
Solanaceae
Solanaceae
Styraceae
Tiliaceae
Tiliaceae
Tiliaceae
Tiliaceae
Tiliaceae
Verbinacaee
Verbinaceae
Verbinaceae
Verbinaceae
Vitaceae
Vitaceae
Zygophyllaceae
Life Form
Therophyte
Therophyte
Therophyte
Hemicryptophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
Phanerophyte
Phanerophyte
Phanerophyte
Therophyte
Therophyte
Phanerophyte
Phanreophyte
Phanerophyte
Therophyte
Therophyte
Therophyte
Phanerophyte
C3-67
C3-68
C3-69
Fauna: With reference to the authenticated map given by the forest department,
Ranchi- Jharkhand it reveals that there are no wildlife sanctuaries, national parks,
biosphere reserves and migratory corridors within the study area. The authenticated
map of the study area is given as Annexure-IV15.
The commonly occurring species in the core zone do not represent a permanent
habitat of any species of conservation importance. Most of the species use this area
as transit and are accidental passersby. The species such as common fox, wild boar
and wild hare were reported to occur in this area.
The commonly occurring avifauna was represented by Indian robin, cattle egret, red
vented bulbul, babblers, spotted munia, cormorant, darter and pond heron. The
most abundant and prevalent species were of collared dove, spotted dove, blue rock
pigeon. The recorded wild animal species in the core and the buffer zone of the
study area and their conservation status as per the Wildlife (Protection) Act, 1972 is
presented in Table-3.9.4 below.
TABLE-3.9.4
FAUNA FROM THE STUDY AREA
Sr.
Scientific Name
No.
Core Zone
Aves
1
Milyus migrans
2
Corvus splendens
3
Turdoides striatus
4
Pycnonotus cafer
5
Saxicoloides fulicata
6
Columba livia
7
Streptopelia decaocto
8
Streptopelia chinensis
9
Copsychus saularis
10
Acridotheres tristicus
11
Passer domisticus
12
Cinnyris asiatica
13
Megalaima merulinus
14
Eudynamis scolopaceus
15
Centropus sinensis
16
Psittacula Krammeri
17
Coracias benghalensis
18
Merops orinetalis
19
Merops leschenaultia
20
Alcedo atthis
21
Microfus affinis
22
Milvus migrans
23
Bubulcus ibis
24
Ardeola grayii
Reptiles
25
Calotes versicolor
26
Bangarus cirulis
27
Naja naja
English Name/
Local Name
Conservation status as
per WPA (1972)
Common Kite
House crow
Jungle babbler
Red vented bulbul
Indian robin
Blue Rock Pigeon
Collard Dove
Spotted Dove
Magpie Robin
Common myna
House Sparrow
Purple Sunbird
Indian Cuckoo
Koel
Crow Pheasant
Rose ringed parakeet
Indian Roller
Common Bee Eater
Chestnut headed Bee Eater
Common Kingfisher
House swift
Pariah kite
Cattle Egret
Pond Heron
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Part-IV
Authenticated map of the study area indicating no wild life sanctuaries, national parks, tiger reserve from
the chief wild life warden, Jharkhand as per ToR-9
15
C3-70
English Name/
Local Name
Bull frog
Common Toad
Bandicoot
Common mongoose
Hare
House rat
Jackal
Langur
Monkey
Squirrel
Wild fox
Wild Boar
Conservation status as
per WPA (1972)
Sch-IV
Sch-IV
Sch-IV
Part-II of Sch-II
Sch-IV
Sch-IV
Part-II of Sch-II
Part-I of sch-II
Part-I of Sch-II
Sch-IV
Part-I of Sch-II
Sch-III
Lime butterfly
Common crow
Common sailor
Common grass yellow
Emigrant
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Common Kite
Jungle crow
House crow
Jungle babbler
Red vented bulbul
White browed Bulbul
Indian robin
Red Jungle fowl
Blue Rock Pigeon
Collard Dove
Spotted Dove
Magpie Robin
Indian Oriole
Brahmny Myna
Common myna
Weaver bird
Spotted munia
House Sparrow
Loten's sunbird
Purple Sunbird
Indian Cuckoo
Koel
Crow Pheasant
Rose ringed parakeet
Lorikeet
Indian Roller
Common Bee Eater
Chestnut headed Bee Eater
Common Kingfisher
House swift
Common Indian Nightjar
Barn Owl
Brahmny kite
Pariah kite
Darter
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-V
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-V
C3-71
3.9.8
English Name/
Local Name
Little Egret
Cattle Egret
Pond Heron
Conservation status as
per WPA (1972)
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Part-IV
Bull frog
Bufo
Sch-IV
Sch-IV
Bandicoot
Bat
Bat
Common mongoose
Field mouse
Hare
House rat
Jackal
Langur
Monkey
Squirrel
Wild fox
Wild Boar
Crimson rose
Lime butterfly
Peacock pansy
Great eggfly
Common crow
Common sailor
Common grass yellow
Emigrant
Sch-IV
Sch-IV
Sch-IV
Part-II of Sch-II
Sch-IV
Sch-IV
Sch-IV
Part-II of Sch-II
Part-I of sch-II
Part-I of Sch-II
Sch-IV
Part-I of Sch-II
Sch-III
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Sch-IV
Aquatic Biodiversity
Phytoplankton: Phytoplankton forms the basis of food chain in any aquatic
water body. The diversity and abundance of phytoplankton mainly depends on the
region, type of water body, either lentic or lotic, the nutrient flux in the system
and the sunlight available for photosynthesis. These factors together form the
dynamics of phytoplankton productivity over the seasons. The phytoplankton of a
given water body determines the zooplankton populations and the fish
productivity of the ecosystem.
Phytoplankton group reported from four locations are Basillariophyceae,
Chlorophyceae, Myxophyceae and Euglenophyceae members. About 22 species of
phytoplankton were reported from all the locations. Dominance of Bacillariophyceae
members followed by Myxophyceae were observed in the studied samples. The
highest percentage was Cymbella sp. and Spirulina sp. and the lowest percentage
was of Synedra sp. during study period.
Zooplankton: The zooplankton of the aquatic water body are the primary
consumers and also in cases secondary producers which play an important role
C3-72
for the fisheries of that system. The diversity and abundance of zooplankton also
depends on whether the water body is eutrophic or oligotrophic. They also are
good representatives of the ecosystem health. The amount and type of pollutants
in the water body determine the type of zooplankton species. Species of copepod
will usually dominate in the tropical region while more eutrophicated waters with
high nutrient or organic loads will harbour high number of crustaceans and
arthropods. The less polluted waters will have more of cladocerans and rotifers.
Percentage composition of zooplankton varied among different locations. Among the
zooplankton group, Brachionous sp (Rotifera) had highest percentage composition
and the lowest percentage composition was of Asplancha sp in the total
zooplankton. Cypris sp and Cyclops sp. also occurred in the sampled water bodies.
On the basis of type of species their proportional dominance and the overall
diversity of both phyto- and zooplankton it can be concluded that water bodies are
oligotrophic to slightly mesotrophic in nature due to inflow and runoff from the
surrounding areas. The list of plankton recorded in fresh water bodies from the
study during the study period are presented in Table-3.9.5 below.
TABLE-3.9.5
LIST OF PLANKTON & ZOOPLANKTON RECORDED DURING STUDY PERIOD
Sr. No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
3.9.9
Phytoplankton
Pediastrum duplex
Actinastrum sp
Coelatrum sp
Synedra ulna
Synedra acus
Gomphonema sp
Navicula gracilis
Pinnularia sp
Nitzshia sp
Cymbella pucilla
Cymbella cymbiformsis
Cymblella rombhoides
Achnanthes sp
Eunotia sp
Cyclotella sp
Oscillatoria sp
Spinulina sp
Chroococcus sp
Microcystis aerusinosa
Nostoc sp
Rivularia sp
Anabaena sp
Zooplankton
Keratella sp
Diaptomus sp
Daphnia sp
Ceriodaphnia sp
Brachionus sp
Amoeba sp
Diaphanosoma sp
Macrothrix sp
Asplancha sp
Cypris sp
Cyclops sp
Conclusions
From the field observations it can concluded that the forests in the study area are
under high anthropogenic pressure and show signs of degradation in the form of
tree cutting, lopping, poaching, grazing, collection of NTFPs and habitat
fragmentation.
C3-73
As per the MOEF and the forest department, Jharkhand reveals that there are no
wildlife sanctuaries, national parks/biospheres reserves and migratory corridors in
10 km radius from the proposed site boundary. As per the records of the Botanical
Survey of India there are no plants of conservation importance in the study area.
On comparing the checklist given in the Schedule-I of the Wildlife (Protection) Act
1972 and the list of wildlife recorded from the study area, it can be concluded that
there are no schedule-I species found in the study area.
3.10
C3-74
Distribution of Population
As per 2011 census, the study area consisted of 1,47,066 persons inhabited in
144 villages covering in two districts of Jharkhand and one district of West
Bengal. The distribution of population in the study area is shown in Table3.10.1.
TABLE-3.10.1
DISTRIBUTION OF POPULATION
Particulars
No. of households
Male population
Female population
Total population
Male population (0-6 years)
Female population (0-6 years)
Total population (0-6 years)
% of 0-6 years population
Average household size
% of males to the total population
% of females to the total population
Sex ratio (no of females per 1000
males)
Density
0-3 km
6405
14513
14321
28834
2174
2184
4358
15.11
4.50
50.33
49.67
3-7 km
11292
25947
24906
50853
3931
3686
7617
14.98
4.50
51.02
48.98
7-10 km
15042
34389
32990
67379
5274
4937
10211
15.15
4.48
51.04
48.96
0-10 km
32739
74849
72217
147066
11379
10807
22186
15.09
4.49
50.89
49.11
987
232
960
308
959
290
965
282
The study area has an average household size of 4.49 as per 2011 census.
Population Density
The density of population reveals that the study area has an overall density of 282
persons per km2 (PP km2) as per 2011 census reports.
Sex Ratio
The configuration of male and female indicates that the males constitute to about
50.89% and females to 49.11% of the total population as per 2011 census data.
The study area on an average has 965 females per 1000 males, which is little
higher than the rural sex ratio of both West Bengal and Jharkhand (West Bengal
rural sex ratio 961 and Jharkhand rural sex ratio 953).
3.10.4 Social Structure
In the study area, as per 2011 census, 7.92% of the population belongs to
Scheduled Castes (SC) and 22.00% to Scheduled Tribes (ST). Overall the data of
social stratification reveals that the SC and ST % to population is more than 29%,
which is found to be very significant. The SC and ST community are marginalized
and they are considered at low level of social strata and calls for a special
attention in Social Impact Management Plan for improving their socio-economic
status, apart from preservation and protection of their art, culture and traditional
rights of livelihood.
VIMTA Labs Limited, Hyderabad
C3-75
0-3 km
1717
5.95
6694
23.22
8411
29.17
28834
3-7 km
4343
8.54
9118
17.93
13461
26.47
50853
7-10 km
5588
8.29
16547
24.56
22135
32.85
67379
0-10 km
11648
7.92
32359
22.00
44007
29.92
147066
3-7 km
25947
24906
50853
3931
3686
7617
17453
10894
28347
61.57
38.43
7-10 km
34389
32990
67379
5274
4937
10211
22464
13760
36224
62.01
37.99
0-10 km
74849
72217
147066
11379
10807
22186
49450
30486
79936
61.86
38.14
34.32
33.34
33.62
21.42
55.74
20.42
53.76
20.73
54.35
The male literacy i.e. the percentage of literate males to the total literates of the
study area works out to be 61.86%. The percentage of literate female to the total
literates, which is an important indicator for social change, is observed to be
38.14% in the study area as per 2011 census records.
3.10.5.1 Occupational Structure
The occupational structure of residents in the study area is studied with reference
to main workers, marginal workers and non-workers. The main workers include
10 categories of workers defined by the census department consisting of
VIMTA Labs Limited, Hyderabad
C3-76
Particulars
Total population
Total workers
Work participation rate (%)
Total main workers
% of main workers to total
5
population
6
Marginal workers
% of marginal workers to total
7
population
8
Non-workers
% of non-workers to total
9
population
Source: District Census Hand Book-2011
3.11
0-3 km
28834
16295
56.51
6515
3-7 km
50853
25478
50.10
12614
7-10 km
67379
34040
50.52
15698
0-10 km
147066
75813
51.55
34827
22.59
24.80
23.30
23.68
9780
12864
18342
40986
33.92
25.30
27.22
27.87
12539
25375
33339
71253
43.49
49.90
49.48
48.45
C3-77
3.11.2 Methodology
3.11.2.1 Vehicular Count
The vehicles plying in both the directions were counted continuously for 12 hours at
one location. The vehicles were counted every hour and recorded under respective
category. The maximum traffic count in an hour is termed as peak hour traffic. The
vehicles were categorized under various heads like trucks/tankers, buses, multi
axles, cars, 2/3 wheelers, cycles and bullock carts.
3.11.2.2 Categorization of Traffic
The engine driven vehicles were categorized into various heads viz. light motor
vehicles (LMV) as two wheelers (scooters, motor cycles etc.), three wheelers
(auto rickshaws, 3-wheel tempo etc.), medium motor vehicles (cars, jeeps),
tractors (6 wheelers), minibuses and mini trucks (8 wheelers); heavy motor
vehicles such as buses, trucks and tankers (10 wheelers).
3.11.3 Results and Discussion
The summary of daily traffic count for the location was monitored during the study
period is summarized in Table-3.11.1 and % of composition of the vehicles are
given in the Table-3.11.2.
It was observed that the 2/3 wheelers, cars/jeeps and trucks/buses forms the
major volume of the traffic. The total traffic PCU of this road is minimal.
3.11.3.1Presentation of Results
The present level of traffic has been converted to Passenger Car Units (PCU) at this
location as per the conversion factors stipulated by Indian Road Congress (IRC).
The Passenger Car Unit (PCU) recorded at the selected traffic location, which is
towards Tata to Sili road is about 698 PCU.
TABLE-3.11.1
TRAFFIC DENSITY (VEHICLES/DAY)
Code
Location
Two Wheelers
(Bicycle/
Scooter/
Motorcycle)
Four
Wheelers
(Car/Jeep)
Tractors
Buses/
Trucks
Multi
Axles
Total
PCUS
TABLE3.11.2
COMPOSITION OF EXISTING TRAFFIC VOLUME
Code
Note:
Total
No. Of Vehicles
% Composition
Vehicles
LMV
MMV
HMV
LMV
MMV
HMV
T1
612
381
138
93
62.26
22.54
15.20
LMV-Light Motor Vehicles (scooter, motorcycle & auto rickshaw etc.)
MMV-Medium Motor Vehicles (car, jeep, tractor, mini bus, mini trucks)
HMV-Heavy Motor Vehicles (bus, trucks and tankers)
****
C3-78
4.0
4.1
4.2
C4-1
premises. The top soil if any will be stacked in earmarked area and will be used in
greenbelt development at project site.
The land use of plant site which is currently wasteland/single crop agricultural
land will be converted to industrial land use category. This will be an irreversible
impact.
The soil at the project site predominantly consists of silt clay. The sub-strata of this
area is not rocky, however for construction of civil foundations, permissions as
required for blasting will be taken from concerned authorities. The contour relief is
about 20 m with mild slopes so the site needs very little grading, filling and leveling.
So there will not be any need for external borrow areas. The project site is gradually
sloping towards south-east.
The construction activities will result in loss of topsoil to some extent in the plant
area and waste disposal area. The topsoil requires proper handling like separate
stacking so that it can be used for green belt development. Apart from very
localized construction impacts at the plant site, no significant adverse impact on soil
in the surrounding area is anticipated.
Mitigation Measures
The following mitigation measures will be adopted for soil and land environment:
After completion of the construction phase, the surplus earth will be utilized to
fill up the low lying areas, the rubble will be cleared and all un-built surfaces
will be reinstated;
The top soil from the excavated areas will be preserved in separate stacks for
re-use during the plantation;
Species selected in this plantation will be native, fast growing with rich canopy
and they will be easily adaptable to local conditions. Their ability to combat
localized pollution is the prime factor for their selection and placement in the
planting grid/pattern. Most of the varieties shall be eco-friendly i.e. generate
lot of oxygen while helping reduce/absorb gases and dust;
There will be minimum concreting of the top surfaces so that there is a scope
for maximum ground water recharge due to rainfall; and
C4-2
Proper and prior planning, appropriate sequencing and scheduling of all major
construction activities will be done, and timely availability of infrastructure
supports needed for construction will be ensured to shorten the construction
period vis--vis to reduce pollution;
Truck carrying soil, sand, stone dust, stone will be duly covered to avoid
spilling and fugitive emissions;
C4-3
It will be ensured that all construction equipment and vehicles are in good
working condition, properly tuned and maintained to keep emission within the
permissible limits and engines turned off when not in use to reduce pollution;
Mitigation Measures
C4-4
be taken up during the monsoon season. In-plant roads will be paved to arrest
fugitive dust emission.
Soil binding and fast growing vegetation will be grown within the plant premises
to arrest the soil erosion. Toilets with packaged sewage treatment plants will be
constructed at site for workers.
4.2.5 Noise Environment
The major sources of noise during the construction phase are vehicular traffic,
construction equipment like dozers, scrapers, concrete mixers, cranes, pumps,
compressors, pneumatic tools, saws, vibrators etc. The operation of these
equipment will generate noise ranging between 85-90 dB (A) near the source at
1-m distance. These noises will be generated within the plant boundary and will
be transient in nature.
C4-5
Landlessness;
Joblessness;
Homelessness;
Marginalization;
Loss of access to common property; and
Social-disintegration, Loss of kinship.
It is pertinent to mention that these risks combine economic, social and cultural
impoverishment.
Any company undertaking such projects must study these risks in great detail in
order to formulate appropriate strategies and framing development plans to
restore the livelihood of the PAPs. The project proponent of the proposed
integrated steel plant has taken all the possible mitigation measures in
minimizing the any adverse impact on the population in core zone due to the
establishment of the project. Apart from this, a systematic plan is made after
conducting social impact assessment.
4.2.7.1 Positive Impacts of the Project during the Construction Phase
The project study area both core zone and buffer zone population will have
positive impact of the project due to adequate inputs being proposed by the
project proponent besides offering the benefits of royalty and other revenue to
the state exchequer. Any company will have its own community development
policy and would try to implement the same. Company would also be providing
direct employment in the project besides large number of villagers would get
indirect employment due to self-employment opportunities available. Following
direct and indirect employment opportunities will be created during the
construction phase and would further consolidate with more exhaustive
opportunities due to cascading effect of the project establishment.
C4-6
C4-7
4.3
Land use;
Topography and climate;
Air quality;
Traffic;
Water resources and quality;
Noise levels;
Ecology; and
Solid waste management; and
Socio-economic aspects.
C4-8
C4-9
exhaust gas carries along with it particulate matter, oxides of sulphur and
nitrogen as major pollutants, are then cleaned in electrostatic precipitator (ESP,
designed for <50 mg/Nm3 dust emission) before lettwqing them out into the
atmosphere through ID fan and stack.
e) Blast Furnace
Flue gas from hot stoves is the main emission source from the operation of blast
furnace. Hot stoves are fired with blast furnace and CO gas for heating air fed to
blast furnace. Flue gas generated in the hot stoves is discharged to the
atmosphere through stacks. This flue gas contains particulate matter (in very
small quantity) and oxides of sulphur and nitrogen. Oxides of nitrogen are formed
due to the high temperature of the stoves.
In addition to the above emissions, fugitive emissions also occur during charging
and in cast house. During charging, normally a sealed charging system is
provided but since the furnace pressure is higher than atmospheric pressure, the
components present in BF gas along with particulate matter may be emitted.
f) Pig Casting
The pig casting facilities will cast surplus hot metal during poor take off of hot
metal from steel melting shop. The casting of pig iron generates fugitive
emissions, mainly arising from contact between hot metal and slag and ambient
oxygen. The main pollutants in the fugitive emissions are particulate matter with
some amount of sulphur dioxide.
g) Slag Granulation Plant (SGP)
The process of treating blast furnace slag involves pouring the molten slag
through a high-pressure water spray in a granulated head. Due to high-pressure
water spray no particulate matter is expected to be emitted.
h) De-sulphurisation
A de-sulphurisation unit for hot metal pre-treatment to ensure consistent supply
of homogenous and low sulphur hot metal to the BOF has been envisaged. The
process of de-sulphurization generates fugitive emissions. The exhaust air
generated in the process is contaminated with particulate matter.
i) Basic Oxygen Furnace (BOF) Shop
The objective of basic oxygen furnace (BOF), in steel making is to burn (oxidise)
the undesirable impurities contained in the metallic feedstock. The main elements
are thus converted into oxides are carbon, silicon, manganese, phosphorus, and
sulphur. The purpose of this oxidation process is:
C4-10
The following emissions of off gases are generally recognized in BOF area:
Oxygen blowing and BOF gas secondary off gases are generated during;
Secondary off-gases are generated during:
Removal of undesirable impurities (to the maximum possible extent);
BOF charging;
Tapping of liquid steel and slag from BOF and ladles; and
Continuous casting.
Air pollution control system comprising of suction hood, duct and bag filters are
provided in the existing BOF, for bulk material charging system, mixer and deslagging systems. However due to different operational problems sometimes the
pollution control systems are not functioning properly. Due to which the fumes
generated due to puffing in the converters escape into the BOF shop. Further, the
fumes generated during charging and tapping of converters are also not
controlled at times. The fugitive emissions in the area will be limited within the
limits given below:
i) Respirable particulate matter: 2000 mg/m3
ii) Suspended particulate matter: 5000 mg/m3
iii) SO2: 250 mg/m3
iv) NOx: 150 mg/m3
j) Secondary Refining Facilities
The secondary refining is not an emission intensive process except for some
fugitive dust emissions during the process. Necessary fume extraction system has
been envisaged for the process.
k) Coke Oven
The operation of a coke oven battery comprises the following activities:
-
Coal charging;
Heating / firing of the chambers;
Coking;
Coke pushing; and
Coke quenching.
During the coke making, heating of the coke oven chambers is carried out by
burning coke oven / BF gas as fuel and the resultant flue gas is led to the stacks.
Excess coke oven / BF gas is transported via pipeline to large gas holders to
utilize these gases for power generation and plant heating needs.
VIMTA Labs Limited, Hyderabad
C4-11
During operation of coke ovens fugitive emissions are also generated during
charging, pushing, and quenching activity. However, CPCB/MOEF prescribed
emission standard for coke oven emission shall be met.
l) Raw Material Handling Complex (RMHC)
Necessary pollution control facilities in the form of dust extraction / dust
suppression system will be provided to restrict the emitted pollutant within
statutory norms. Dust extraction system provided will discharge air after cleaning
to limit the dust content in the emitted air within statutory norms.
m) Captive Power Plant
Fugitive and stack emissions from the power plant will contribute to increase in
concentrations of PM, SO2, and NOx pollutants.
The mitigative measures recommended in the plant are:
C4-12
o) Cement Plant
The particulate matter will be the major concern during the cement
manufacturing process. The particulate matter will be emitted through point
source as well as with line source as fugitive emission.
The ambient air quality will be maintained as per the specific Environmental
Management Program and adhered to the gazette notification 16 th November,
2009.
4.3.3.2 Air Modeling
Particulate matter, sulphur dioxide (SO2) and oxides of nitrogen (NOx) emissions
will be the main pollutants in the proposed integrated steel plant. The incremental
ground level concentrations from the proposed facilities have been estimated by
using dispersion modeling.
For prediction of maximum ground level concentrations (GLCs), the air dispersion
modeling software (AERMOD version 7.1.0) was used. AERMOD is steady state
advanced gaussian plume model that simulates air quality and deposition fields
upto 50 km radius. AERMOD is approved by USEPA and is widely used software.
It is an advanced version of industrial source complex (ISCST3) model, utilizes
similar input and output structure to ISCST3 sharing many of the same features,
as well as offering additional features. The model is applicable to rural and urban
areas, flat and complex terrain, surface and elevated releases and multiple
sources including point, area, flare, line and volume sources.
Dispersion modeling using AERMOD requires hourly meteorological data. Site
specific data recorded during pre-monsoon 2014 at project site is used for
executing modeling studies. The site specific meteorological data is processed
using AERMET processor.
Model Set-up
Parameter
Model name
Model type
Topography
Averaging time
Source type
Boundary limits
Co-ordinate system
Receptor height
Anemometer
Surface meteorological data
Upper air data
Details
AERMOD (Version 7.1.0)
Steady state gaussian plume air dispersion model
Rural, flat
24 hours
Point source
10 km X 10 km
Uniform polar grid
0
10 m
Site specific data processed by AERMET
Upper air estimator using AERMET processor
The details of proposed stack emissions in the proposed integrated steel plant are
given in Table-4.2.
VIMTA Labs Limited, Hyderabad
C4-13
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
TABLE-4.2
DETAILS OF STACK EMISSIONS FROM THE PROPOSED PLANT
Sr.
No.
Plant Name
Pellet Plant
1
Pellet Plant-1
2
Pellet Plant-1
3
Pellet Plant-2
4
Pellet Plant-2
Sinter Plant
1
Sinter Plant-1
2
Sinter Plant-1
3
Sinter Plant-1
4
Sinter Plant-1
5
Sinter Plant-1
6
Sinter Plant-2
7
Sinter Plant-2
8
Sinter Plant-2
9
Sinter Plant-2
10
Sinter Plant-2
DR Plant
1
DR Plant-1
2
DR Plant-1
3
DR Plant-1
Blast Furnace
1
Blast Furnace-1
2
Blast Furnace-1
3
Blast Furnace-1
4
Blast Furnace-1
5
Blast Furnace-2
6
Blast Furnace-2
7
Blast Furnace-2
8
Blast Furnace-2
Coke Oven
Stack Attached to
Pollution
Control
Equipment
Flue
Type
Stack
Height
(m)
Stack
Dia
(m)
Temp
(oC)
Velocity
(m/s)
Flow Rate
(Nm3/hr)
PM
(g/s)
Pellet ESP
Machine Discharge
Pellet ESP
Machine Discharge
ESP
Bag Filter
ESP
Bag Filter
C
DD
C
DD
100
30
100
30
5
1.5
5
1.5
115
45
115
45
27.6
18.7
27.6
18.7
1,500,000
111,220
1,500,000
111,220
Sinter Machine
Dedusting
Sinter Storage Dedusting
Sinter Machine
Dedusting
Sinter Machine
Dedusting
Sinter Storage Dedusting
Sinter Machine
Dedusting
ESP
Bag Filter
Bag Filter
ESP
Bag Filter
ESP
Bag Filter
Bag Filter
ESP
Bag Filter
C
DD
DD
C
DD
C
DD
DD
C
DD
130
65
65
130
65
130
65
65
130
65
7.7
4.5
4
7.7
4.5
7.7
4.5
4
7.7
4.5
190
60
30
190
60
190
60
30
190
60
20.2
7.7
4.5
20.2
7.7
20.2
7.7
4.5
20.2
7.7
Reformer
Bag Filter
DD
40
30
30
4.5
0.9
0.9
180
65
55
Stove
Casthouse East
Casthouse West
Stockhouse
Stove
Casthouse East
Casthouse West
Stockhouse
ESP
Bag Filter
Bag Filter
Bag Filter
ESP
Bag Filter
Bag Filter
Bag Filter
C
DD
DD
DD
C
DD
DD
DD
60
40
40
40
60
40
40
40
3.5
5
5
3.5
3.5
5
5
3.5
200
40
40
40
200
40
40
40
SO2
(g/s)
NOx
(g/s)
20.8
1.5
20.8
1.5
12.5
12.5
-
58.3
58.3
-
2,174,400
396,000
198,000
2,174,400
396,000
2,174,400
396,000
198,000
2,174,400
396,000
30.2
5.5
2.8
30.2
5.5
30.2
5.5
2.8
30.2
5.5
90.6
90.6
90.6
90.6
-
90.6
90.6
90.6
90.6
-
32.6
10.7
12.7
1,228,034
21,562
26,411
0.5
0.3
0.3
95.9
0.1
-
20.6
24.5
24.5
19.7
20.6
24.5
24.5
19.7
450,000
1,650,000
1,650,000
650,000
450,000
1,650,000
1,650,000
650,000
3.8
13.8
13.8
5.4
3.8
13.8
13.8
5.4
3.8
3.8
-
6.3
6.3
-
C4-14
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
Sr.
No.
Plant Name
1
Coke Oven-1
2
Coke Oven-1
3
Coke Oven-1
4
Coke Oven-1
5
Coke Oven-1
6
Coke Oven-2
7
Coke Oven-2
8
Coke Oven-2
9
Coke Oven-2
10
Coke Oven-2
Steel Melting Shop
1
SMS-1
2
SMS-1
3
SMS-1
4
SMS-1
5
SMS-1
6
SMS-1
7
SMS-2
8
SMS-2
9
SMS-2
10
SMS-2
11
SMS-2
Reheating Furnace
1
HSM
2
Wire Rod Mill
3
Bar Mill
4
Medium Section Mill
5
Heavy Section Mill-1
6
Heavy Section Mill-1
7
Plate Mill
8
Tin Plate Mill
Cold Rolling Mill
1
Cold Rolling Mill
2
Cold Rolling Mill
Stack Attached to
Flue
Type
Pollution
Control
Equipment
ESP
ESP
Bag Filter
Bag Filter
ESP
ESP
ESP
Bag Filter
Bag Filter
ESP
BOF-1
BOF-2
BOF-3
Fume Extraction System
LHF - 3 Nos.
RH - 1
BOF-1
BOF-2
Fume Extraction System
LHF - 2 Nos.
RH - 1
Reheating
Reheating
Reheating
Reheating
Reheating
Reheating
Reheating
Reheating
Furnace-3 Nos.
Furnace
Furnace
Furnace
Furnace
Furnace
Furnace
Furnace
Pickling Line
Annealing Furnace
Stack
Dia
(m)
4.2
4.2
3
3
2
4.2
4.2
3
3
2
Temp
(oC)
Velocity
(m/s)
Flow Rate
(Nm3/hr)
PM
(g/s)
C
C
DD
DD
C
C
C
DD
DD
C
Stack
Height
(m)
165
165
40
40
50
165
165
40
40
50
200
200
55
55
150
200
200
55
55
150
11.9
11.9
20.8
20.8
15.1
11.9
11.9
20.8
20.8
15.1
375,000
375,000
480,000
480,000
120,000
375,000
375,000
480,000
480,000
120,000
ESP
ESP
ESP
Bag Filter
Bag Filter
Bag Filter
ESP
ESP
Bag Filter
Bag Filter
Bag Filter
C
C
C
DD
DD
DD
C
C
DD
DD
DD
60
60
60
40
60
30
60
60
40
60
30
2
2
2
5.5
3
0.6
2.5
2.5
5.5
3
0.8
60
60
60
60
50
60
60
60
60
50
60
14.8
14.8
14.8
20.9
12.8
10.9
15.8
15.8
20.9
12.8
12.4
ESP
ESP
ESP
ESP
ESP
ESP
Bag Filter
Bag Filter
C
C
C
C
C
C
DD
DD
100
80
80
80
80
80
65
47
4.2
3
3
3
3
3
4.5
1.5
293
318
318
325
320
320
300
150
Bag Filter
Bag Filter
DD
DD
30
40
1.2
1.5
45
120
SO2
(g/s)
NOx
(g/s)
5.2
5.2
6.7
6.7
5.2
5.2
6.7
6.7
-
41.7
41.7
8.0
8.0
41.7
41.7
8.0
8.0
-
36.5
36.5
6.67
6.67
36.5
36.5
6.67
6.67
-
150,000
150,000
150,000
1,600,000
300,000
10,000
250,000
250,000
1,600,000
300,000
20,000
2.1
2.1
2.1
13.3
2.5
0.1
3.5
3.5
13.3
2.5
0.2
4.17
4.17
4.17
6.94
6.94
-
8.33
8.33
8.33
13.89
13.89
-
9.5
5.8
5.8
7.1
6.7
6.7
5.1
22.3
250,000
75,000
75,000
90,000
80,000
80,000
150,000
100,000
2.1
0.6
0.6
0.8
0.7
0.7
0.6
1.1
3.5
1.0
1.0
1.3
1.1
1.1
2.1
1.1
6.94
2.08
2.08
2.50
2.22
2.22
6.3
1.9
9.4
9.5
36,000
46,000
0.3
0.5
0.5
1.0
C4-15
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
Sr.
No.
Plant Name
3
Galvanizing Line
4
Colour Coating Line
5
Electrical Steel
Lime Plant
1
Lime Plant-1
2
Lime Plant-2
3
Lime Plant-3
4
Lime Plant-4
5
Lime Plant-5
Dolo Plant
1
Dolo Plant-1
2
Dolo Plant-2
Cement Plant
1
Slag Cement Plant
2
Raw mill/ Kiln
3
Cement mill
4
Coal mill
5
Cooler
6
Packer-I
7
Packer-II
8
Packer-III
Captive Power Plant
1
Power Plant-1
2
Power Plant-2
3
Power Plant-3
Incinerator
1
Incinerator-1
2
Incinerator-2
Stack Attached to
Annealing Furnace
CCL
HDGL Stack
Pollution
Control
Equipment
Bag Filter
Bag Filter
Bag Filter
Flue
Type
Stack
Dia
(m)
1.5
1
2
Temp
(oC)
Velocity
(m/s)
Flow Rate
(Nm3/hr)
PM
(g/s)
DD
DD
DD
Stack
Height
(m)
40
40
65
120
40
150
4.2
18.6
12.6
20,000
50,000
100,000
SO2
(g/s)
NOx
(g/s)
0.2
1.4
0.2
0.6
0.4
1.1
Kiln
Kiln
Kiln
Kiln
Kiln
Bag
Bag
Bag
Bag
Bag
Filter
Filter
Filter
Filter
Filter
DD
DD
DD
DD
DD
55
55
55
55
55
2
2
2
2
2
130
130
130
130
130
14.4
14.4
14.4
14.4
14.4
120,000
120,000
120,000
120,000
120,000
1.0
1.0
1.0
1.0
1.0
0.30
0.30
0.30
0.30
0.30
0.17
0.17
0.17
0.17
0.17
Kiln
Kiln
Bag Filter
Bag Filter
DD
DD
55
55
2
2
130
130
14.4
14.4
120,000
120,000
1.0
1.0
0.30
0.30
0.17
0.17
ESP
ESP/Bag House
ESP/Bag House
ESP/Bag House
ESP/Bag House
ESP/Bag House
ESP/Bag House
ESP/Bag House
C
C
C
C
C
C
C
C
40
100
35
62
62
30
30
30
1.5
5.0
1.4
2.3
4.5
0.8
0.8
0.8
60
140
90
40
230
40
40
40
10.5
15.0
7.0
7.0
12.0
7.0
7.0
7.0
60,000
212.0
8.8
27.6
112.6
3.3
3.3
3.3
69.4
-
192.1
-
CPP-1
CPP-2
CPP-3
ESP
ESP
ESP
C
C
C
275
275
275
5.5
5.5
5.5
150
150
150
24.9
24.9
24.9
1,500,000
1,500,000
1,500,000
41.7
41.7
41.7
500.0
500.0
500.0
333.3
333.3
333.3
Incinerator-1
Incinerator-2
ESP
ESP
C
C
30
30
0.5
0.5
50
50
9.2
9.2
6,000
6,000
0.1
0.1
0.20
0.20
0.33
0.33
SCP
Kiln
Cement mill
Coal mill
Cooler
Packer-I
Packer-II
Packer-III
0.8
10.6
0.44
1.38
5.63
0.17
0.17
0.17
Source-JSW
ESP- Electro Static Precipitator, HSM-Heavy Section Mill, CPP-Captive Power Plant, SCP- Slag Cement Plant, SMS- Steel Melting Shop
C4-16
The simulations have been carried out to evaluate SO2, NOx and PM likely to be
contributed by the proposed integrated steel plant. For the short-term
simulations, the concentrations were estimated to obtain an optimum description
of variations in concentrations over the site in 10 km radius covering 16
directions. The predicted results for PM, SO 2 and NOx are presented in Table-4.3
and isopleths showing the incremental concentrations are shown in Figure-4.1 to
Figure-4.3.
TABLE-4.3
PREDICTED SHORT-TERM MODELLING RESULTS (24-HOURLY)
Pollutants
Particulate matter (PM10)
Sulphur dioxide (SO2)
Nitrogen oxides (NOx)
Maximum Incremental
Levels (g/m3)
18.41
44.05
39.46
Distance
(km)
1.4
2.8
2.8
Direction
SE
SE
SE
PM (PM10)
SO2
NOx
Max
Baseline
52.7
12.2
16.0
Concentrations (g/m3)
Incremental
Resultant
Concentration
18.41
71.11
44.05
56.25
39.46
55.46
NAAQS Limits
100
80
80
C4-17
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
PROJECT TITLE:
COMMENTS:
ug/m^3
8000
SOURCES:
73
18.410
6000
441
2
4
OUTPUT TYPE:
Concentration
4000
-2000
12
-4000
-8000
-6000
UCART1
-8000
-6000
-4000
-2000
2000
4000
6000
8000
10000
PLOT FILE OF HIGH 1ST HIGH 24-HR VALUES FOR SOURCE GROUP: ALL
2000
16.000
-10000
RECEPTORS:
MAX:
18.41448 ug/m^3
12.000
MODELER:
1:138,000
4 km
4.000
PROJECT NO.:
2.000
FIGURE-4.1
SHORT TERM 24 HOURLY INCREMENTAL GLCS OF PM
C4-18
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
PROJECT TITLE:
COMMENTS:
ug/m^3
8000
SOURCES:
44.060
70
10
6000
RECEPTORS:
40.000
441
4000
OUTPUT TYPE:
Concentration
20
25
-2000
15
10
25
15
-4000
-6000
20
15
-8000
10
UCART1
-10000
-8000
-6000
-4000
-2000
2000
4000
6000
8000
10000
PLOT FILE OF HIGH 1ST HIGH 24-HR VALUES FOR SOURCE GROUP: ALL
15
10
2000
30
35.000
10
10
MAX:
44.05551 ug/m^3
30.000
25.000
MODELER:
1:138,000
4 km
15.000
10.000
PROJECT NO.:
5.000
FIGURE-4.2
SHORT TERM 24 HOURLY INCREMENTAL GLCS OF SO2
C4-19
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
PROJECT TITLE:
COMMENTS:
ug/m^3
10
8000
SOURCES:
39.460 70
6000
10
RECEPTORS:
441
4000
35.000
OUTPUT TYPE:
Concentration
10
30
15
-2000
25
20
25
10
-4000
20
15
-6000
-8000
10
UCART1
-10000
-8000
-6000
-4000
-2000
2000
4000
6000
8000
10000
PLOT FILE OF HIGH 1ST HIGH 24-HR VALUES FOR SOURCE GROUP: ALL
MAX:
15
10
2000
15
10
25.000
MODELER:
SCALE:
15.000
1:138,000
4 km
10.000
PROJECT NO.:
5.000
FIGURE-4.3
SHORT TERM 24 HOURLY INCREMENTAL GLCS OF NOx
VIMTA Labs Limited, Hyderabad
C4-20
Additional Recommendations
Good house keeping shall be maintained in the plant premises; road sweeping
machine shall be used to clean road;
The trucks and other vehicles shall be maintained and serviced regularly to
reduce air emissions; and
C4-21
The arrangement for the storage, issue, collection and maintenance of respiratory
protective equipment should be located in an uncontaminated place and easily
accessible by employees.
4.3.3.4 Fugitive Dust Emissions & Control Measures1
The following technologies and requirements as per CPCB guidelines are
recommended for control of dust and fugitive emissions for the proposed project.
These will be strictly implemented.
Sr. No
1
Technologies/Current Practices
Coke Ovens
In
coke
ovens,
the
volatile
materials released during cooking
flows from the oven to the byproduct plants where ammonia,
benzol, xylene, toluene, tar, pitch
and tar acids are recovered. The
operations are associated with
fugitive and stack emissions. The
PAH compounds released during
cooking
operation
as
fugitive
emissions
are
carcinogenic
in
nature.
The
technologies
available
control the pollution are
Requirements
to
HPLA system
Hydraulic door and door frame
cleaner
Doors with double knife edge
and rope sealing
Water sealed AP caps
Screw feeder
Sintering Plant
3
4
An action plan to control and monitor secondary fugitive emissions as per ToR-39
C4-22
Sr. No
6
7
8
Technologies/Current Practices
Lime Dolomite Plant
ESP, bag filter / multiclones for
process and work zone dust
emissions
Raw Material Handling Units
Enclosures and water sprinkling
system
Cement Plant
ESP, bag filter / multiclones for
process and work zone dust
emissions
Requirements
Effective operation and maintenance
of ESP / bag filter / multiclones for
process and work zone dust emissions
Improvements in the systems
controlling fugitive emissions
for
C4-23
C4-24
C4-25
C4-26
C4-27
kiln): Multi cyclone-scrubber based de-dusting facility; and Induration unit: ESP
based de-dusting facility.
DR Plant
The crushing and screening operation for raw material preparation will be carried
out in enclosed area. Centralized de-dusting facility (collection hood and suction
arrangements followed by suitable de-dusting units with bag filter or ESP and the
emissions will be finally discharged through stack.
Water sprinkling arrangement will be provided at raw material heaps and on land
around the crushing and screening units.
Belt conveyors and transfer points of belt conveyors will be provided with
enclosures to control fugitive dust emission. Water sprays/ sprinklers will be
provided at strategic locations for dust suppression during raw material transfer.
Blast Furnace
A number of measures have been considered to control the emission from the
blast furnaces:
Coal Dust Injection (CDI)
Coal dust injection (CDI) in BF has been planned at the rate of about 150 kg/t hot
metal. The CDI has an economic as well as an environment advantage. Direct
injection of coal as reducing agent facilitates replacing part of the required coke. It
is considered that for every kg of coal dust injected approximately 0.8 kg of coke
requirement is reduced.
Coal dust injection system will be introduced involving handling, screening and
drying and pulverisation system for coal. During this handling and drying, dust will
be generated. To control this dust, dust extraction system comprising bag filter
(pulse jet type), fan, suction hood, duct and stack have been envisaged.
Gas Cleaning System
A gas cleaning plant (GCP) comprising of dust catcher, scrubber and wet ESP will
be installed.
BOF Convertors / LF and BOF Gas Cleaning System
The dust cleaning (of primary gases) system will be of venturi scrubber type.
Secondary Refining
During secondary refining process, the gases generated during mixing and
desulphurization process will be contaminated with dust. A centralised secondary
dust and fume extraction system for converters and LFs will comprise of bag filter
suction hood, ducts and stacks.
VIMTA Labs Limited, Hyderabad
C4-28
Fugitive emission sources from this project are associated with various activities
which are summarized as below:
Transfer of raw materials from the point of extraction to storage, handling and
processing locations along roads;
Unloading of materials;
Material conveying between processing stages; and
VIMTA Labs Limited, Hyderabad
C4-29
For the purpose of effective prevention and control of fugitive emissions, the plant
will implement the following measures:
Unloading Section
Measures for effective prevention and control of fugitive emissions to be provided
for the unloading section are given in Table-4.5.
TABLE-4.5
CONTROL MEASURES IN THE UNLOADING SECTION
Sr.
No.
1
Control Measures
Proposed
Enclosure
would
be
provided for all unloading
operations
Details
The enclosures for the unloading sides could be
flexible curtain type material covering up to
height of dumpers discharge from the roof.
A dust suppression system would be provided
through spray water. The amount of water
sprayed would preferably be optimized by
employing proper design of spray system.
Suitable systems will be adopted to reduce the
problems like choking, jamming of the moving
parts.
3
4
Control Measures
Proposed
All transfer point locations
would be fully enclosed.
Airborne dust at all transfer
operations / points would
be controlled either by
spraying
water
or
by
extracting to bag filter.
Belt
conveyors
would
preferably be closed.
Fugitive emissions will be
generated
mainly
from
transfer
and
junction
Details
The enclosures from all sides with the
provision for access doors, which shall be
kept, closed during operation. Spillages would
be periodically removed.
Either water spray system would be provided
for suppressing the air borne dust or dry
extraction cum bag filter with adequate
extraction volume.
This will avoid wind blowing of fines.
Bag filters will be provided with appropriate
suction devices to control the fugitive
emissions.
C4-30
Sr. No.
Control Measures
Proposed
points, product hopper area
and loading points.
Details
In area where provision of bag filter and other
control device is not feasible, waterspraying
arrangements shall be made, particularly
manganese / dolomite /coke yard, wagon
tippler and truck tippler.
Details
The enclosure walls shall cover minimum
two sides up to roof level.
The dry GCP dust would be sent to closed
silos and will be reused in the sinter plant.
Roads
Measures for effective prevention and control of fugitive emissions to be provided
for the roads are given in Table-4.8.
TABLE-4.8
CONTROL MEASURES ON THE ROADS
Sr.
No.
1
2
3
4
5
Details
C4-31
APC measures is presented in Table 4.9. Air pollution control measures envisaged
above will be designed suitably so as to meet the air emission norms. The table
indicates design target and control measures at respective sources.
TABLE-4.9
EMISSION NORMS FOR AIR POLLUTION CONTROL (APC) MEASURES
Sr.
No
1
Production
Unit/
Facilities
Coal
handling
/
coke sorting
plant
Raw
materials
handling
section
Coke oven
battery
DE stacks
Combustion stack
Fugitive emissions:
5% PLD
1% PLL
4% PLO
BaP:
Work
zone
(Battery
top) : 5 ug/m
Other units in coke
ovens:
2 ug/m
Stack emissions:
PM 50 mg/m3
SO2 800 mg/m3
NOx 500 mg/m3
Dust outlet: 50 mg/N
m3
Work zone dust
level: < 5 mg/ m3
Sinter plant
Raw
feed
proportioning building,
sinter
cooler,
air
cleaning by DE system
comprising of ESP
Pellet plant
Dust
suppression
system for raw material
preparation & handling.
DR plant
-Raw
material
preparation & handling
centralized de- dusting
facility bag filter/ ESP
Blast
furnaces
Design Target
- BF stock house by DE
system
- BF cast house by DE
system: ESP
Sr.
No
8
Production
Unit/
Facilities
Steel
melting
shop
10
11
Lime
plant
raw
material bunker building
- de-dusting by bag
filter.
- Lime sizing plant dedusting by bag filter.
12
Cement
Plant
-Centralised
secondary
fume
extraction system
for converters /
LFs
with
bag
filter.
Waste flue gas
through bag filter
(fabric)
Low
burners
- ESP
NOx
ESPs
and
filters
efficiency
99.9%)
Bag
with
of
Design Target
Impact of transporation of raw materials and finished products as per ToR-37 and ToR-67
C4-33
TABLE-4.10
INPUT TO THE MODEL
Raw Material
Truck capacity (T)
No. of trucks
Emission Factors
CO (g/km/vehicle)
NOx (g/km/vehicle)
Emission Rate
CO (g/s)
NOx (g/s)
Details
35
400
6.0
9.3
0.27
0.43
Presentation of Results
The predicted CO and NOx concentrations from additional vehicular traffic are
presented in Table-4.11 and the isopleths showing the incremental
concentrations for CO and NOx are shown in Figure-4.4 to Figure-4.5
respectively.
TABLE-4.11
PREDICTED PEAK HOURLY AIR POLLUTION
DUE TO ADDITIONAL TRAFFIC
Sr. No.
1
2
Parameter
Carbon monoxide
Oxides of nitrogen
Concentration (g/m3)
4.0
6.5
C4-34
Category of Road
Two lane roads (7 m) with earthen shoulders
4-lane highway with earthen shoulders
Maximum Carrying
Capacity (PCU/day)
15,000
35,000
Further, the necessary strengthening and widening of the connecting road will be
taken up by JSW-JSL.
4.3.5 Impact on Water Resources and Water Quality
Impact on water resources and quality are discussed under three sub-headings,
namely surface water resources, ground water resources and water quality.
The total water requirement for the proposed project will be about 80 Million
Gallons per day (MGD), i.e. about 15150 m 3/hr including water requirement for
the proposed CPP. About 46.7 MGD of the required water will be sourced from
Subarnarekha river, which flows at a distance of about 2.4 km from the plant site
in north direction and remaining 33.3 MGD of required water will be drawn from
Chandil dam (downstream).
4.3.5.1 Impact on Water Regime
The impact of proposed project on water regime may be in different ways and on
surface or ground water or both. Water environment may be affected by the
proposed project in terms of disturbing natural water course or change in
drainage pattern of the area, quantity and quality due to drawl of water,
discharge of polluted water/wastewater by contaminated leachate from
disposal/dumping of solid waste etc.
C4-35
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
PROJECT TITLE:
COMMENTS:
8000
0.50
1.50
ug/m^3
4.500
SOURCES:
6000
RECEPTORS:
4.090
OUTPUT TYPE:
4.000
0.50
4000
0.50
-2000
-4000
-6000
-8000
-6000
-4000
-2000
2000
4000
6000
8000
PLOT FILE OF HIGH 1ST HIGH 24-HR VALUES FOR SOURCE GROUP: ALL
2000
SLINE1
0.50
-8000
Concentration
MAX:
UCART1
-10000
441
4.08728 ug/m^3
3.500
3.000
MODELER:
2.500
2.000
SCALE:
1:138,000
4 km
1.500
1.000
PROJECT NO.:
0.500
FIGURE-4.4
ISOPLETHS SHOWING INCREMENTAL CONCENTRATIONS FOR CO
C4-36
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
PROJECT TITLE:
COMMENTS:
ug/m^3
8000
SOURCES:
6.510
RECEPTORS:
441
6000
OUTPUT TYPE:
4000
6.000
Concentration
-8000
-6000
-4000
-2000
SLINE1
UCART1
-10000
-8000
-6000
-4000
-2000
2000
4000
6000
8000
10000
PLOT FILE OF HIGH 1ST HIGH 24-HR VALUES FOR SOURCE GROUP: ALL
2000
MAX:
6.50937 ug/m^3
5.000
MODELER:
4.000
3.000
SCALE:
1:138,000
4 km
2.000
PROJECT NO.:
1.000
FIGURE-4.5
ISOPLETHS SHOWING INCREMENTAL CONCENTRATIONS FOR NOx
C4-37
The estimated water requirement for the project is about 80 million gallons per
day (MGD) (132.7 MCM per annum), out of which 46.7 MGD (77.4 MCM per
annum) of water will be drawn from Subarnarekha river in the upstream and 33.3
MGD (55.3 MCM per annum) of water will be drawn from Chandil dam in the
downstream at about 45 km south from the proposed plant site.
The flow monitoring data of CWC at Muri on Subarnarekha river between 1997-98
and 2007-08 indicates that the monsoon flow range between 202 MCM 682
MCM and the non-monsoon flow range between 32 MCM 339 MCM. The nonmonsoon flow during 2000-2001 and 2005-2006 was very low at 66 MCM and 32
MCM respectively. Suitable impounding arrangements in the form of a pickup weir
or intake well at the river source will have to be considered to meet the plant
water requirement, along with dedicated pipeline or open channel. It is not
proposed to draw surface water from Subarnarekha river during the lean season.
Chandil dam across Subarnarekha river is a composite dam which is 720.10 m
long and 56.5 m high with a gross storage of 1963 hm (1963 MCM) and live
storage of 1611 hm (1611 MCM) at Maximum Water Level (MWL)/Full Reservoir
Level (FRL) 192 m. As the proposed surface water withdrawal from Subarnarekha
3
C4-38
FIGURE-4.6
PRE-DEVELOPMENT DRAINAGE NETWORK
VIMTA Labs Limited, Hyderabad
C4-39
FIGURE-4.7
POST-DEVELOPMENT DRAINAGE NETWORK
VIMTA Labs Limited, Hyderabad
C4-40
river is 77.4 MCM with suitable pickup weir or intake well during only monsoon
period and the requirement from Chandil dam is also minimal at 3.43% of the live
storage, no major impact on Subarnarekha river or Chandil dam is envisaged.
4.3.5.4 Water Quality
In order to combat industrial pollution and to comply with guidelines laid down by
the statutory authority, suitable treatment units and neutralization pits will be
provided to control water pollution in different water system units. Attempts will
be made to achieve zero discharge as far as practicable by making use of bleed
water from cooling tower and other effluent water for dust suppression.
Wastewater generated from different areas of plant will be treated to the desired
extent and recycled in the re-circulating system as far as possible, facilitating
adequate reuse of water. Backwash water generated from different pressure
filters will be treated in a treatment plant having sludge disposal facilities. The
treated water will be reused in the direct cooling circuit.
Considering the following factors 1) zero discharge from the proposed project,
2) waste disposal mechanism and 3) analysis results of all the surface and ground
water samples are within desirable limits of ISO: 10500, impact on surface and
ground water quality is not envisaged.
Material conditioning i.e. for slurrying, quenching, mill scale removal, rinsing
etc;
Air pollution control i.e. for wet scrubbing of air pollutants; and
Heat transfer i.e. water used for protecting the equipment by cooling
refractory and shell of equipment. Overall, approximately 75% of water use is
for heat transfer. Accordingly, a considerable portion of water supplied is lost
by evaporation. Evaporation losses include slag quenching at blast furnaces
and basic oxygen furnaces, coke quenching, spray chamber cooling at casters
and evaporation in cooling towers. However, wastewater discharges from any
plant mainly depend upon the water usage and type of use.
C4-41
Wastewater discharges from an integrated steel plant can be broadly divided into
two parts. Non-contact water discharges and contact water discharges. Water is
used in a series of heat exchangers in coke oven gas treatment, blast furnaces,
basic oxygen furnaces and rolling operations and boilers. This non-contact water
is generally contaminated with high dissolved solids comprising of salts of calcium
and magnesium, which were originally present in the raw / feed water. Due to
repeated re-circulation and high temperature concentration of these salts starts
to built up necessitating bleeding off of some part of circulating water. Water is
also used for contact cooling e.g. quenching, Coke oven gas treatment, slag
handling etc. This contact water discharges may be contaminated with different
pollutants and needs to be treated prior to discharges.
The unit wise wastewater generations are given below:
a) Sinter Plant
Wastewater may be generated in sinter plant if wet scrubbers are used for
pollution control facilities. However, in this project dry ESPs are used in the sinter
plant for pollution control, which does not generate any effluent. Further, the
water requirement /consumption in sinter plant is very less and no water is
required for process purposes and as such no wastewater is generated from the
process.
b) Pellet Plant
In pellet plant, water is mainly used for wetting the ore additive mix before
feeding into balling mills for making balls. Further, in the balling discs controlled
water is used for adjusting final moisture content of the green balls. Further, the
water requirement / consumption in pellet plant are very less and as such no
wastewater is generated from the process.
c) DR Plant
In DR plant, water is required for cooling of the reduced material. The cooling
water is collected in trough below the cooler and sent to cooling tower for cooling.
The cooled water is re-circulated. Due to repeated re-circulation and high
temperature concentration of dissolved salts starts getting built up necessitating
bleeding off of some part of circulating water from the indirect cooling circuit.
d) Blast Furnace
Blast furnace requires a considerable quantity of water. Water required is mainly
for direct contact water used in the gas coolers / wet scrubbers, which cleans the
blast furnace gas. This water is treated in settling tank / clarifier for removal of
suspended solids and the overflows are recycled to the gas scrubbers.
Only the final blows down from the re-circulated systems are being discharged.
The blow down will conform to the following quality:
pH 6.5 - 8.5
Suspended solids 100 mg/l
C4-42
Parameter
pH of the treated effluent
Suspended solids
Phenol
Cyanide
Ammonical nitrogen
Free ammonia
Range
Between 6.0 to 8.0
Not more than 100 mg/l
Not more than 1.0 mg/l
Not more than 0.2 mg/l
Not more than 50 mg/l
Not more than 5.0 mg/l
C4-43
Sr No
vii)
viii)
ix)
x)
Parameter
Oil & grease
Nitrate Nitrogen
BOD (3 days, 27C)
COD
Not
Not
Not
Not
more
more
more
more
than
than
than
than
Range
10 mg / l
10 mg/l
30 mg/l
250 mg/l
The wastewater treated in the effluent treatment plant will be reused in the
plant;
C4-44
Oil separators will be installed in compressor house of power plant and other
units also like SMS, Stores, DRI and garage etc to ensure oil content in drain
water will be within prescribed limits;
The sewage effluent after treatment in sewage treatment plant will be used
for greenbelt development.
C4-45
AIR
CLARIFLOCCULATOR
AMMONIA STRIPPED
COKE OVEN
EFFLUENT
EQUALISATION TANK
NUTRIENT (H3PO4)
THICKENER
1st STAGE AERATION
NaOCl
OVER FLOW
MIXER
CHLORINE CONTACT TANK
FIGURES 4.8
SCHEMATIC FLOW DIAGRAM OF PROPOSED B.O. PLANT OF COKE OVEN
EFFLUENT STREAM
VIMTA Labs Limited, Hyderabad
C4-46
The back wash from the filters is sent to the settling tank for removal of
particulates. The settled sludge is sent to sinter plant for agglomeration. Quality
of this discharged water will be continuously checked and as required will be
treated to meet statutory norms.
Treatment of Plant Sanitary Wastewater
The sanitary wastewater will be treated in sewage treatment plant.
Treatment of Wastewater from Indirect Cooling Circuit Streams
In the proposed project, the wastewater generated from indirect cooling circuits
of sinter plant, blast furnace, BOF and rolling mill are not normally contaminated
with any major pollutants. However, occasional discharges are made as bleed off
when there is built up of dissolved solids in the circulating water due to repeated
circulation. The dissolved solids are mainly different salt constituents of calcium
and magnesium already present in water. Thus major portion of water will be recirculated after necessary physical treatment e.g settling, cooling etc.
Cooling Tower Blow Downs from Direct Cooling Circuit Streams
It is noted that the re-circulating water in cooling towers gets contaminated with
the dust & dissolved solids, necessitating blow down. It is proposed that all
cooling towers be provided with side stream pressure filters to reduce the volume
of blow down. The cooling towers shall be designed to operate at high cycles of
concentrations to conserve water.
Summary of Proposed Wastewater Treatment Scheme
In view of the above stated proposals for wastewater treatment and disposal for
various production facilities, a summarized list of the same is presented in below:
Sr.
No.
1
Production unit/facilities
Coke ovens by-products recovery
plant
2
3
4
The wastewater generated from BF gas cleaning plant after physical treatment
will be reused in the system;
Cooling Tower blow downs of indirect cooling water system shall be used for
slag quenching and as make up to direct contaminated cooling water circuits
and surplus if any would be stored in the treated wastewater lagoon for inplant use (eg. Green belt, floor washing, plant road dust suppression etc);
Blown down water from Blast Furnace re-circulation system will be reused in
Slag Granulation Plant as make-up water to SGP re-circulation water system;
Blow down water from BOF re-circulation system will be reused in SMS slag
yard for spraying on hot slag; and
Blow down water from power plant will be reused for pig casting machines.
Through cascaded reuse of blow-down, the water scheme ensures practically zero
discharge from the industrial water circuit. However, in such huge operation of
ISP some water will be discharged, which will meet the statutory norm.
The typical water pollutants and suggested treatment and or disposal in the
integrated steel plant are given in Table-4.13.
TABLE-4.13
WATER POLLUTANTS TREATMENT AND DISPOSAL
Sr. No.
1
Pollutants
Oil
Rolling oil
Lubricants
Fuel oil
Hydraulic oil
2
Suspended Solids
Scale
Rolling mills
Burden fines
Source
Coal
and
coke fines
Heat
Cooling
Treatment/Disposal/Use
Waste oil will be collected and
sold to authorized recyclers
Floor spills soaked up on
adsorption compound; cutting oil
will be and sold to authorized
recyclers
Spills segregated by dykes and
incinerated
Spills segregated and collected
to sell to authorized recyclers
Recovery and used in sintering
plants
Used in sintering plant
Used in sintering plant
Cooling towers and recirculation
C4-48
Sr. No.
Pollutants
water
Boiler blow
down
Source
cooling air conditioners and
heat exchanges
Steam plant
Treatment/Disposal/Use
after cooling
Recovered to heat feed water
The effluent and sewage analysis report of existing JSW Vijayanagar plant is
given in Table-4.14. Water balance flow diagram is shown in Figure-4.9. The
water circulating & make up water requirement is given in Table-4.15. The
schematic diagrams of proposed raw water treatment plant and STP are given in
Figure-4-10 and Figure-4.11.
Most of the water is used for cooling purposes. The wastewater arising from the
plant will be treated in effluent treatment plant and will be re-utilized for the plant
purposes.
No effluent discharge is envisaged due to recycling into the plant operation.
Hence, there will be no impact on the water regime due to the effluents from the
proposed steel plant.
TABLE-4.14(A)
RESULTS OF EFFLUENT ANALYSIS
Sr. No. Parameters
1
pH
2
Suspended Solids
3
Dissolved Solids
4
Oil & Grease
5
BOD - 5 days, 20C
6
Chloride (as Cl)
7
Sulphates (as SO4)
8
Cyanides (as CN)
9
Pesticides
10
Iron (as Fe)
11
Arsenic (as As)
12
Boron (as B)
13
Lead (as Pb)
14
Zinc (as Zn)
Source-JSW Vijayanagar Plant
Standards
5.5-9
100 mg/l
2100 mg/l
10 mg/l
100 mg/l
600 mg/l
1000 mg/l
0.2 mg/l
Absent
3 mg/l
0.2 mg/l
2 mg/l
0.1 mg/l
5 mg/l
Guard Pond I
7.38
58
469
0.9
8
115
104
Nil
Absent
0.04
<0.01
<0.01
<0.01
<0.01
Guard Pond II
7.67
23
826
0.6
6
204
116
Nil
Absent
0.16
<0.01
<0.01
<0.01
<0.01
TABLE-4.14(B)
RESULTS OF SEWAGE ANALYSIS
Sr. No. Parameters
1
pH
2
Suspended Solids
3
BOD - 3 days, 27C
4
COD
Source-JSW Vijayanagar Plant
Standards
5.5-9
30 mg/l
20 mg/l
250 mg/l
Raw Sewage
7.38
28
110
224
Treated Sewage
7.4
24
18
90
C4-49
FIGURE-4.9
WATER BALANCE
VIMTA Labs Limited, Hyderabad
C4-50
FIGURE-4.10
SCHEMATIC DIAGRAM OF PROPOSED RAW WATER TREATMENT PLANT
VIMTA Labs Limited, Hyderabad
C4-51
FIGURE-4.11
SCHEMATIC DIAGRAM OF PROPOSED STP
VIMTA Labs Limited, Hyderabad
C4-52
TABLE-4.15
CIRCULATING & MAKE UP WATER REQUIREMENT
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
Plant Facilities
RMHS
Beneficiation plant
Pellet plant
Coke oven plant
Sinter plant
Blast furnace with PCM
Direct reduction plant
SMS
Continuous casting machine
(Billet/Bloom/Shaped Bloom Caster)
Slab caster
Wire rod mill
Medium section mill
Heavy section mill
Hot strip mill
Plate mill
Bar mill
Cold rolling mill complex
Oxygen plant
Lime & dolo calcination plant
Captive power plant
Cement plant
Coking & non-coking coal washery
Township
Power & blowing station
Compressed air station
Lab
ACVS
Fire fighting
Miscellaneous
Drinking
Total Process Water
Treatment Loss
Total Raw Water Required
2700
4660
60
200
6840
759
521
263
2000
34650
9918
4200
2286
4191
15177
23239
4200
5213
8333
1260
20158
26417
1333
242
2,27,278
34
25
10
450
167
892
175
75
57
105
270
1501
75
125
208
70
2250
189
52
240
793
40
30
180
250
450
530
13537
721
15150
Pollutants
Suspended solids
Suspended solids
Suspended solids
Oils,
suspended
solids,
ammonia, phenols etc.
Suspended solids, oil &
grease
pH and dissolved solids
Temperature,
dissolved
solids
Control System
Catch pits
Clarifier, thickener
Clarifier, thickener
Oil, organics and ammonia
removal in BOD plant
Settling tanks fitted with oil &
grease trap
Neutralizing pit
For re-use
Canteens, toilets
C4-53
The new plant aims at zero discharge concept. In case of problem in water
recovery/reuse system, during wet season maximum 200 m3/hr, occasional
discharge can be anticipated for a short period of time meeting the discharge
norm. It is presumed that after completion of the project the water environment
will improve significantly.
4.3.5.6 Impact on Ground Water Quality
The proposed plant does not envisage any ground water drawl during the
operation and hence nominal impact will be there during construction phase.
There will not be any major adverse impact on ground water.
The waste disposal area around any industry is one of the major factors
deteriorating ground water quality, if the water leached from the waste dumps
contains toxic substances. In the proposed plant, waste material will be dumped
in secured land fill sites and inert wastes will be dumped in low lying area. All
other solid wastes are reused / recycled or sold out.
Contaminants can migrate directly into ground water from below ground sources
(e.g., storage tanks, pipelines) that lay within the saturated zone. Additionally
contaminants can enter the ground water system from the surface by vertical
leakage through the seals around well casings, through wells abandoned without
proper procedures, or as a result of contaminant disposal of improperly
constructed wells (Boulding & Ginn 2004). Generally, three processes can be
distinguished which govern the transport of contaminants in ground water:
advection, dispersion and retardation.
Dispersion and density/viscosity
differences may accelerate contaminant movement, while retardation processes
can slow the rate of movement. Some contamination problems involve two or
more fluids. Examples include air, water and organic liquids in the unsaturated
zone, or organic liquids and water in an aquifer. Tracers are useful for
characterizing water flow in the saturated and unsaturated zone.
Any pollutants coming in contact with surface water will follow the topography
and surface drainage course/storm water drains and reach Domra nadi running
westeast along southern boundary. The pollutants infiltrating vertically through
soil and reaching shallow ground water will move along the direction of ground
water table movement direction with a hydraulic conductivity of 0.083 m/day
towards Subarnarekha river.
A review of the results of the chemical analysis of water samples revels that
quality of ground water is potable in general and observed to be within the
prescribed ISO: 10500 limits. The results also do not show any toxic or heavy
metals more than desirable limits indicating that there is no contamination in the
vicinity of the proposed project area. When there is no toxic or heavy pollutant
available in ground water and since 83.33% of the samples fall in calcium
4
Ground water modeling showing pathways of pollutants as per ToR-43 and ToR-54
C4-54
bicarbonate and rest fall in sodium bicarbonate water types, the pathways for
these dominant constituents representing TDS, hardness, calcium and sodium
have been prepared. The area considered for modelling covers an aerial distance
of 2.60 km towards north, 6.0 km towards east, 2.5 km towards south and 4.4
km towards west of the proposed project area. The area considered for modelling
and pollutant pathways for TDS, hardness, calcium and sodium are presented in
Figure-4.12, Figure-4.13A to Figure-4.13D respectively. The dispersion
pattern of these constituents reveals that their movement is from the drainage
divide along the catchment boundary of the proposed project site towards south
west. Any pollutants joining the ground water of deeper aquifer will move towards
southwest from the proposed project site. Effective management practices
ensuring zero discharge from the proposed project and proper waste disposal
mechanism will not allow any pollutants migrating to ground water and further
movement along the pollutant pathways.
Mitigation Measures
C4-55
FIGURE-4.12
MAP SHOWING MODEL BOUNDARY AND GROUND WATER SAMPLES
VIMTA Labs Limited, Hyderabad
C4-56
FIGURE-4.13A
MODEL SHOWING PATHWAYS FOR TDS IN GROUND WATER
FIGURE-4.13B
MODEL SHOWING PATHWAYS FOR HARDNESS IN GROUND WATER
VIMTA Labs Limited, Hyderabad
C4-57
FIGURE-4.13C
MODEL SHOWING PATHWAYS FOR CALCIUM IN GROUND WATER
FIGURE-4.13D
MODEL SHOWING PATHWAYS FOR SODIUM IN GROUND WATER
VIMTA Labs Limited, Hyderabad
C4-58
The wastewater treated in the effluent treatment plant will be reused in the
plant;
Oil separators will be installed in compressor house of power plant and other
units also like SMS, stores, and garage etc to ensure oil content in drain
water will be within prescribed limits;
The sewage effluent after treatment in sewage treatment plant will be used
for greenbelt development.
C4-59
The plant is designed for complete recirculation of water except during monsoon.
Water balance for the plant is indicated in the Figure-4.8.
4.3.6
r
L p 2 L p1 20 log 2
r1
VIMTA Labs Limited, Hyderabad
(1)
C4-60
Where Lp2 and Lp1 are sound pressure levels (SPLs) at points located at distances
r2 and r1 from the source. The combined effect of all the sources then can be
determined at various locations by the following equation.
L p (total) 10 log 10
( L p1 / 10)
10
( L p 2 / 10)
10
( L p 3 / 10)
(2)
.........
Where, Lp1, Lp2, Lp3 are noise pressure levels at a point due to different sources.
Based on the above equations, an user-friendly model has been developed. The
details of the model are as follows:
The major noise generating sources from the proposed plant are listed in Table4.17. These are considered as input to the noise model.
TABLE-4.17
NOISE LEVELS FROM THE PROPOSED PLANT
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Sources
Blast furnace-1
Blast furnace-2
SMS-I
SMS-II
Oxygen plant
Rolling mills-I
Plate mill
Rolling mills-II
Rolling mills-III
DR plant
Pellet plant-I
Pellet plant-II
Lime & Dolo Calcination plant
Sinter plant-I
Sinter plant-II
Cement plant
Base mix yard I
Base mix yard-II
Beneficiation plant
Captive power plant
Coal washery-I
Coal washery-I
Coke oven plant-I
Coke oven plant-II
Coal yards
Co-ordinates (m)
X
Y
532.6
00
385.1
889.1
1179.5
667.6
868.5
1202.3
1526.6
795.3
229.6
731.7
-282.0
-111.9
254.6
-562.2
-257.2
118.3
567.1
1050.0
1420.7
1581.1
1819.6
2111.5
1087.4
322.6
00
-611.9
-296.4
-29.9
-1247.0
-1129.6
-961.5
-758.4
715.2
672.6
969.2
384.6
826.6
1041.9
701.3
1050.7
1277.4
1381.1
1755.3
2060.6
1814.0
1953.7
2142.0
2220.3
Expected Noise
Levels dB(A)
90-110
90-105
90-105
90-115
85-95
95-115
95-105
95-110
95-110
95-115
85-105
85-105
90-105
95-115
95-115
95-110
85-95
85-95
85-115
85-115
85-110
90-110
95-115
95-110
85-105
C4-61
Direction
N
NE
E
SE
S
SW
W
NW
C4-62
-10000
10000
-8000
-6000
-4000
-2000
2000
4000
6000
8000
10000
10000
8000
8000
6000
6000
4000
4000
2000
2000
-2000
-2000
-4000
-4000
-6000
-6000
-8000
-8000
-10000
-10000
-8000
-6000
-4000
-2000
2000
4000
6000
8000
-10000
10000
FIGURE-4.14
NOISE DISPERSION CONTOURS
VIMTA Labs Limited, Hyderabad
C4-63
Noise level can be reduced by stopping leakages from various steam lines,
compressed air lines and other high pressure equipment;
Providing noise proof cabins to operators where remote control for operating
noise generating equipment is feasible;
C4-64
The air compressor, process air blower, pneumatic valves should be provided
with acoustic enclosure;
The noise control system will be designed to form an integral part of the
plant;
All the openings like covers, partitions shall be designed properly; and
Inlet and outlet mufflers will be provided which are easy to design and
construct.
C4-65
Sinter plant;
Blast furnace;
DR plant;
Basic oxygen furnance;
Coke oven & by-product plant;
Different rolling mills;
Lime & dolomite plant; and
Captive power plant.
Source of generation and characterisation of solid wastes as per ToR-56 and ToR-59
C4-66
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
TABLE 4.19
SOURCE OF GENERATION AND TYPICAL CHARACTERISATION OF SOLID WASTES
Unit
BF Plant
Type of Waste
Source of Generation
BF flue dust
BF sludge
BF slag
BF operation
Fe(t) : 37.00
C : 23.69
SiO2 : 9.01
Al2O3 : 7.26
TiO2 : 0.87
CaO : 6.37
MgO : 5.46
MnO : 2.02
P2O5 : 0.25
S : 0.27
Fe(t) : 20-30
FeO : 7-12
Fe2O3 : 25-35
C : 30-40
S : 0.5-0.8
P : 0.09-0.12
Na2O : 0.1-0.2
K2O : 0.5-0.7
ZnO : 0.2-0.4
CaO : 8-10
SiO2 : 5.0-7.0
MgO : 0.3-0.5
Al2O3 : 0.8-1.3
MnO : 0.5-0.8
CaO : 30-31
SiO2 : 32-33
Al2O3 : 18-22
MgO : 8-10
FeO : 0.2-0.6
MnO : 1.5-3.0
Not Applicable
Not Applicable
C4-67
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
Unit
Type of Waste
Source of Generation
S : 1.5-1.7,
DR Unit
Spent
refractories
Sludge
De-dusting dust
Hot metal
Pretreatment
Unit
BOF Shop
Hot metal
pretreatment
dust
Hot metal
pretreatment
slag
BOF dust /
sludge
Not Applicable
Ash: 60-70%
C: 18-22%
H2O: 3.5%
VM: 2%
Calorific Value: 800 kCal/kg
Ash: 70%
C: 20 25%
VM:2%
Mithyleblue value 50-100
Ash: 70%
C: 20 25%
VM:2%
Mithyleblue value: 50-100
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
BOF Dust
Fe(t) : 52.25
SiO2 : 5.92
Al2O3 : 1.1
TiO2 : 0.43
CaO : 18.26
MgO : 5.98
MnO : 2.59
P2O5 : 0.36
S : 0.18
BOF Sludge
Not Applicable
C4-68
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
Unit
Refractory
Materials Plant
Continuous
Casting Plant
Type of Waste
Source of Generation
BOF slag
BOF
Spent
refractories
Limestone /
Dolomite Fines
Lime / Calcined
dolomite fines
Spent
refractories
RMP sludge
Caster scale
Fe(t) : 50.84
CaO : 15.39
SiO2 : 2.19
P : 0.17,
MgO : 4.31
Al2O3 : 0.71
S : 0.29
Na2O : 0.51
K2O : 0.06
Zn : 1.10
C : 2.58
CaO : 40-50
FeO : 20
SiO2 : 15-17
P2O5 : 2.45
MgO : 3.9-4.5
MnO : 4.5
Al2O3 : 5.2-6.3
-
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Not Applicable
Fe(t) : 62-68
FeO : 60-70 Fe2O3 : 15-25
C : 0.3-0.5
S : 0.12-0.25
P : 0.15-0.25
Not Applicable
Not Applicable
C4-69
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
Unit
Type of Waste
Source of Generation
Na2O : 0.05-0.1
K2O : 0.01-0.03
ZnO : 0.04-0.06
CaO : 0.3-0.5
SiO2 : 0.8-1.5
MgO : <0.01
Al2O3 : 0.1-0.2
MnO : 0.3-0.5
Caster Sludge
Spent
Refractories
Mill Scales
Mill Sludge
Not Applicable
Not Applicable
Fe(t) : 62-68
FeO : 60-70 Fe2O3 : 15-25
C : 0.3-0.5
S : 0.12-0.25
P : 0.15-0.25
Na2O : 0.05-0.1
K2O : 0.01-0.03
ZnO : 0.04-0.06
CaO : 0.3-0.5
SiO2 : 0.8-1.5
MgO : <0.01
Al2O3 : 0.1-0.2
MnO : 0.3-0.5
Fe(t) : 64.4
CaO : 0.6
SiO2 : 4.0
P : 0.085
MgO :0.22
MnO :0.44
Al2O3 : 1.85
TiO2 : 0.07
Cr2O3 : 0.08
LOI : 0.4
Not Applicable
Not Applicable
C4-70
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
Unit
Coke Oven
Plant
By-Products
Plant
Mineral
Oil/synthetic oil
used as
lubricants in
hydraulic
operations /
other uses
Batteries
Type of Waste
Spent
refractories
Spent
refractories
Decanter tar
sludge
Tar storage tank
residues
Tarry & acidic
wastes
BOD plant
sludge
Spent / wash /
lubricant
Lead acid
batteries
Source of Generation
Oil : 10-11
-
Not Applicable
-
Not Applicable
As per Category 13.3 of Schedule
I
As per Category 1.2 & 13.4 of
Schedule I
As per Category 1.2 & 17.1 of
Schedule I
As per Category 34.3 of Schedule
I
As per Category 5.1 & 20.2 of
Schedule I
C4-71
Analysis results of solid waste from existing JSW Vijayanagar plant is given in
Table-4.20.
TABLE-4.20 (A)
CHEMICAL COMPOSITION OF SOLID WASTE
Chemical Composition
Iron (as Fe2O3), %
Carbon as C, %
Silica (as SiO2), %
Aluminium (as Al2O3), %
Calcium (as CaO), %
Magnesium (as MgO), %
Titanum(asTiO2),%
Phosphorous(as P2O5), %
Sodium (as Na2O), %
Potassium (as K2O), %
Zinc(as ZnO), %
Sulphur
BF Sludge
54.13
21.1
9.67
7.87
2.44
1.09
0.21
Nil
0.35
0.36
1.7
Nil
SMS Sludge
75.6
1.6
1.98
0.48
25.75
7.5
0.04
0.12
Traces
0.13
0.086
0.1
TABLE-4.20 (B)
CHEMICAL COMPOSITION OF SOLID WASTE
Chemical Composition
Iron (as Fe2O3), %
Silica (as SiO2), %
Aluminium (as Al2O3), %
Calcium (as CaO), %
Magnesium (as MgO), %
Titanum(asTiO2),%
Phosphorous(as P2O5), %
Sodium (as Na2O), %
Potassium (as K2O), %
Zinc(as ZnO), %
Sulphur
BF Slag
0.525
33.21
20.01
33.06
10.28
0.82
Nil
0.42
0.41
Nil
0.78
BOF Slag
(ungranulated)
26.24
15.76
1.18
48.01
10.27
0.88
1.82
0.039
0.35
Nil
0.026
BOF Slag
(granulated)
30.76
14.36
2.2
48.7
5.8
0.81
1.68
0.021
0.31
Nil
0.018
TABLE-4.20 (C)
CHEMICAL COMPOSITION OF SOLID WASTE
Chemical Composition
Iron (as Fe2O3), %
Carbon as C, %
Silica (as SiO2), %
Aluminium (as Al2O3), %
Calcium (as CaO), %
Magnesium (as MgO), %
Titanum(asTiO2),%
Phosphorous(as P2O5), %
Sodium (as Na2O), %
Potassium (as K2O), %
Zinc(as ZnO), %
Sulphur
Source : JSW Vijayanagar plant
Mill Scale
BF Flue Dust
99.05
0.9
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
Nil
0.043
52.39
28.79
9.2
5.47
3.1
1.31
0.21
0.11
0.16
0.2
0.44
0.18
SMS Secondary
Dedusting
Baghouse Dust
48.02
4.4
5.84
3.8
24.9
6.84
0.28
0.23
0.23
0.89
1.97
0.31
Slime
55.6
Nil
8.25
5.84
0.5
0.24
0.2
0.7
Nil
Nil
Nil
0.02
C4-72
The details of hazardous and non-hazardous waste generated from the proposed
integrated steel plant and quantity of waste are presented in this section.
4.3.10.1 Hazardous Waste
The hazardous waste such as waste oil, lead acid batteries and oil soaked cotton
waste will be generated. Lead acid batteries will be sold to authorized
users/recyclers approved by JSPCB. The oil soaked cotton waste will be
incinerated in BOF.
4.3.10.2 Non-Hazardous Waste
The main solid waste generated in the proposed steel plant will be BF slag, BOF
slag which is non hazardous waste. Other solid waste includes gas cleaning plant
sludge, dust from ESP, bag filter and dust extraction system and refractory debris
etc. this solid waste except refractory will be completely reused in sinter plant
and coal fines will be used in the power plant. Further, oil soaked cotton waste,
organic wastes from steel plant, paper, plastics and waste bag filters will be
generated. The details of solid waste and hazardous waste generated from the
proposed steel plant are given in Table-4.217 and Table-4.22.
TABLE-4.21
SOLID WASTE GENERATION AND DISPOSAL
Sr. No
1
Generation TPA
Proposed disposal
98 % granulated and sold to
Cement plants, 2% treated in dry
pits and used for land fill
BOF slag is granulated , metalics
separated and used in
construction
30,00,000
14,80,000
Sludge
1,29,000
1,51,000
4
A
B
5
A
B
Ash
9
7
Solid waste
Slag
Rolling mills
Dusts
Flue dust from Blast furnace
Dust from bag filter
58,00,000
38,000
1,49,000
1,06,572
3,43,428
38,000
7,50,000
16,00,000
50,000 -1,00,000
C4-73
TABLE-4.22
HAZARDOUS WASTE GENERATION AND ITS DISPOSAL
Sl. No
Category
1
2
3
4
5
6
Quantity KL or T/Yr
@ 10 MTPA
2,750 KL / Year
450 t
Proposed disposal
7,32,16,000 KL
Regenerated in ARP
315 t
8,172 t
8.7 t/y
59 t/y
Slag Utilization
Steel slag utilization :
1.
The proposed BOF process of steel making leads to generation of following a) Converter slag : (160 180 kg/tlc). Called convertor slag
b) Hot metal pretreatment slag ( 20 kg/tcs) and
c) Ladle furnace slag : ( 20 kg/tcs).
2.
O3
24.3
SiO2
9.7
AlO3
49.9
CaO
4.3
MgO
1.1
SO3
HMPT slag is separately collected, crushed , and the iron bearing materials are
removed. The non metallic slag, is fed to sinter plant through base mix or
through proportioning bins as a replacement of limestone in sintering.
b)
This slag is produced in the proposes of steel making in BOF convertors. Ths slag
contains residual metallics s needs to be removed. The composition of steel slag
is given below;
Fe2
6.1
O3
24.4
SiO2
11.9
AlO3
49.1
CaO
4.2
MgO
2.2
SO3
The molten slag is poured into pits in the slag bay and is allowed to cool.
VIMTA Labs Limited, Hyderabad
C4-74
Water is sprayed on the hot slag to facilitate faster cooling. The slag is then
processed in a series of crushers and screens to separate metallic components.
The metallic compoment (10% 15%) is recycled back to the BOF convertors as
coolant. The non metallic portion of BOF slag is proposed to be processed and
used under;
c)
3.
O3
22.1
SiO2
11.6
AlO3
35.5
CaO
13.8
MgO
<1.0
SO3
(ii)
The nonmetallic portion of LD slag contains free lime and magnesia. This
advantage has been used in construction of roads / highways as slag
bound materials. In this process, LD slag and granulated BF slag in
different proportions are mixed and rolled to produce a cementations base
for roads.
This concept is widely practiced in Europe, and Japan. this is being
investigated in Indian steel plants. This has the potential to reduce the
thickness of highways by 25-30% and can help greatly in reducing the use
of natural materials in the construction sector.
This process can also used for producing gabions, boulders, etc for use in
protection of coastal areas. In Japan, these are called ferro form
(ii)
BOF slag as construction aggregates: The BOF steel slag has excellent
properties and is ideally suited for use in the following area.
C4-75
a)
b)
Ballast in railways
Aggregates in highways / roads
c)
HMPT Slag
:
Convertor Slag
:
:
:
:
:
LHF Slag
C4-76
Different types of solid wastes are generated from integrated steel plant. The
source of solid waste generation along with their re-use, re-cycle, utilization and
disposal methodology are given in Table-4.239.
C4-77
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
TABLE-4.23
SOLID WASTE GENERATION THEIR RE-USE, RE-CYCLE,
UTILIZATION AND DISPOSAL
Sr. No
Type of Solid
Waste
BF slag
BOF Slag
8
9
Lime/dolo
Fines
Mill scale
Re-use
Within Plant
Cement plant
4
5
6
7
Re-utilization
Recycle
Reused
in
sinter
plant as sinter mix.
Used in BF
mite
Cement Plant
-Used in plant for making
refractory mortars in captive
mortar shops
- Making / repairing plant roads
Re-used in sinter plant
Dumped for
Future Use
Sold
Sold
to
cement
manufacturers
/
glass
manufactures
-Will be sold to parties for building roads
(aggregate for road making, rail track ballast,
land filling, after conditioning as it contains lime
which if used before conditioning then it swells),
civil engineering works, etc.
-Soil conditioner as it contains P2O5, especially at
places where PH is acidic as in heavily leached
soils of Ranchi region.
-Used in sinter @of 3% only due to high P2O5.
Sold to cement manufacturers
Sold as material for making road embankment
or for filling low lying areas
Ash dump
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-4
Impact Assessment and Mitigation Measures
Sr. No
10
Type of Solid
Waste
BF flue dust
Re-utilization
Recycle
Dumped for
Future Use
Re-use
Within Plant
15%)
Used in pellet plant
Sold
Reused
in
sinter
plant as sinter mix.
11
BF GCP sludge
-Reused in sinter Used in sinter plant after plant as sinter mix pelletisation
after pelletisation
12
BOF sludge
Reused
in
sinter Used in sinter plant
plant & BF
13
Sinter ESP dust
Recycled in sinter plant
Recycle of waste means utilization of waste in the same process from which it has been generated
Reuse of waste means utilization of the waste in any process other than the process from which the waste has been generated. The process utilizing
the waste may be within the plant or out side the plant. In case of utilization outside plant, the waste is sold to firm utilizing the waste
Disposal means dumping of waste in designated areas.
C4-79
The following shop wise specific management measures will be adopted for solid
waste:
Sinter Plants
100% recycling of LD sludge, mill scale, lime and dolomite dust, SP sludge,
and ESP dust;
100% recycling of return sinter fines;
Complete utilization of 10 mm LD slag; and
BF flue dust utilization in Sinter Plant.
DR Plant
DRI process dust 100% used - reused in sinter plant as sinter mix. Unused
quantity sold to parties for brick making, land filling and to oil refineries as
replacement of activated carbon; and
DRI de-dusting dust 100% used - reused in sinter plant as sinter mix. Unused
quantity sold to parties for brick making & land filling.
Blast Furnaces
Under size limestone, dolomite & lime fines recycled 100% to sinter plant;
Utilisation of refractory grog made from used refractory bricks for mortar
manufacturing of different grades (25% raw material input is from grog);
Ladle covering compound in SMS using LD slag;
Waste Mg-C bricks for production of new bricks for converter bottom, coating
and patching materials for converter vessels; and
Reduction of refractory consumption.
Rolling Mills
100% recycling of mill scales.
C4-80
The impact of air pollutants on vegetation due to the proposed integrated steel
plant is identified and quantified by using air dispersion modeling.
The simulations have been done to evaluate PM, SO 2 and NOx likely to be
contributed by the proposed plant. The resultant concentrations are estimated as
71.11 g/m3 for PM, 56.25 g/m3 for SO2 and 55.46 g/m3 for NOx
concentrations of pre-monsoon season which is within the limits as per National
Ambient Air Quality Standards. Hence, a marginal impact is envisaged due to
proposed steel plant on the surrounding forest areas.
Since the unit will be operating on zero discharge process, no adverse impact on
aquatic ecology is envisaged. The plant drainage system will be suitably designed
such that the storm water does not carry any pollutants. Suitable de-silting
check dam will be provided so that the steam, down stream are not effected.
As per the Forest Working Plans, there are no identified migratory paths for major
and minor wild life in the project site and the study area. The identified avi-fauna,
which are observed in the project site and in the study area, are local migrants
only. Therefore, the proposed plant operations are not likely to have any adverse
impact on the paths for avifauna.
The impacts on the reserve forest blocks have been computed based on the SO 2
incremental concentration over the reserved/protected forests. There are 12
protected/reserve forest blocks present in 10 km radius. The incremental
concentrations over the reserve forests are given in Table-4.24.
VIMTA Labs Limited, Hyderabad
C4-81
The predicted and resultant concentrations will be well within the limits of 100
g/m3 for PM, 80 g/m3 for SO2 and 80 g/m3 for NOx in sensitive areas as per
NAAQMS. Hence, there will be limited impact on the forests in the study area.
TABLE-4.24
INCREMENTAL CONCENTRATIONS AT FORESTS
Sr.
No.
1
2
3
4
5
6
7
8
9
10
11
12
Distance
from Plant
Site
Boundary
(km)
0.5
0.6
1.7
2.9
4.0
4.1
4.6
4.7
5.8
6.9
7.9
8.2
Direction
from Plant
Site
NW
ESE
ESE
S
ESE
ESE
SSW
SE
NE
ESE
SSW
NE
Incremental
Concentration (g/m3)
Winter Season
PM
SO2
NOx
2
8
7
5
5
5
5
3
3
5
30
25
23
23
23
9
14
5
5
36
24
20
17
18
10
13
8
Proper control of fugitive dust from sources inside plant including open
stockyards and to keep all de-dusting systems in prefect conditions. The dedusting systems provided in shops will be regularly monitored and the level of
dust in working zone will be reported to the management for necessary
control action;
Keeping plenum ventilation systems of premises in perfect working order to
avoid accumulation of dust on equipment inside the pressurized room. Regular
cleaning of air filters;
Keeping air conditioning plants in perfect running condition for
control/instrumentation rooms;
Proper functioning of pollution control systems to minimise dust fall on plant
and outside areas;
C4-82
Based on the environmental monitoring for dust, gases, toxic chemical, noise
& vibration, the workers exposed to these will be regularly checked in medical
unit and results will be intimated to management;
Workers exposed to noise prone areas will be medically checked and proper
noise protective equipment will be supplied to them and will be encouraged to
use the same;
Spot cooling facilities will be provided for workers exposed to high heat
generating shops and will be checked periodically. If necessary, rotation of
duties is advised;
Proper attention is given to township water quality so that water borne
disease may not affect residents; and
More doctors in township hospital and plant medical unit will be additionally
trained in the field of occupational health as policy matter.
Employment potential;
Increased business opportunity;
Improvement in health and education facilities;
Better living standards; and
Access to improved infrastructure facilities.
C4-83
generation and above all better economic integration of the area with the major
market and trade centers within and outside the districts.
4.3.13 Impact on Socio-Economic Aspects After the construction of Project
This section of the chapter deals with the demographic, social and economic
impact of the study area of JSW Jharkhand Steel Ltd proposed 10 MTPA
integrated steel plant. The proposed project site is free from human settlements
and all the villages are situated at a considerable distance from the plant area,
except few villages, which are within one km radius of plant area. However, the
project is expected to result in improvements in the socio-economic levels in the
study area.
4.3.13.1 Positive Impacts of the Project
There will be number of positive changes on the socio-economic conditions of the
project study area villages as well as the population. There will be a natural
change, due to industrialisation process, in the scenario leading into the socioeconomic development of project core zone area and also the buffer zone.
Considering project size and investment, it is expected to create direct and
indirect impact on:
Employment potential;
Increased business opportunity;
Improvement in health and education facilities;
Better living standards; and
Access to improved infrastructure facilities.
C4-84
C4-85
persons of different skills and trades. The local population is the largest group
among these employees. The employment potential ameliorates economic
conditions of these families directly and provide employment to many other
families indirectly who are involved in business and service oriented activities.
This in-turn will improve the socio-economic conditions of the area.
Impact on Human Settlements
The project area is free from habitants. Hence no resettlement is required.
However, the project proponent is committed to implement rehabilitation or
restoration of livelihood programs. A detailed tribal development plan, social
impact assessment and rehabilitation plan prepared by BAIF, New Delhi and
enclosed as Annexure-XVI.
4.3.13.3 Impacts on Public Health and Safety
The discharge of waste materials (stack emission, wastewater and solid wastes),
from process operations can have potential impact on public safety and health.
The impact from the discharge of waste products is not expected to be significant
since, the adverse impacts on ambient air, water and soil quality are predicted to
below.
It is predicted that the impacts on public safety will be very low, due to the
effective safety system and safety management available in the plant. Overall,
the impact on public safety and health from the proposed project activities are
likely to be insignificant.
4.3.13.4 Impacts on Cultural Resources
There are no historical monuments or ancient temples within the study area.
GLCs concentration levels in ambient air are well within the standards and no
major adverse effect predicted is envisaged.
4.3.13.5 Impact on Other Sensitive Locations
There are no buildings of public interest and monuments notified by
archaeological department in and around the proposed plant area. Thus, there
will not be any major adverse impact on the tourist/religious or historical
important places due to project.
4.4
10
C4-86
TABLE-4.25
PLAN FOR THE IMPLEMENTATION OF THE RECOMMENDATIONS OF
CREP GUIDELINES FOR INTEGRATED IRON & STEEL INDUSTRY
Sr. No.
1
CREP Recommendations
Coke Oven Plants
Action Plan
Blast Furnace
Direct inject of reducing agents
Solid
Waste
Management
Hazardous
Waste
Hazardous Wastes
Charge of tar sludge / ETP sludge to coke
oven.
Inventorization of the hazardous waste as
per hazardous waste (M&H) rules, 1989 as
amended in 2000 and implementation of
the
rules.
(tar sludge, acid sludge, waste lubricating
oil and type fuel falls in the category of
Hazardous Waste)
Will
be
complied
by
installation
of
control
equipment like ESP/bag
filters
for
removal
of
process emission
Will
be
complied
by
installation
of
ESP/bag
filter/wet
scrubber
for
control of air emissions and
flue emission will be utilised
in proposed power plant
BF slag will be used in own
cement plant and will also
be supplied to other cement
industries/brick
manufacturer.
SMS slag is proposed to be
reutilized to the extent
possible.
ETP sludge/tar sludge to be
used in coke ovens to the
extent possible shall be
explored
Used oil/spent oil will be
sold to authorized persons.
Control measures will be
taken
according
to
hazardous waste as per
Hazardous Waste (M&H)
Rules, 1989
C4-87
Sr. No.
6
CREP Recommendations
Water Conservation / Water Pollution
To reduce specific water consumption to 5
m3/T for long products and 8 m3/T for flat
products.
To operate the CO-BP effluent treatment
plant efficiently to achieve the notified
effluent discharge standards.
Action Plan
Will be complied
Continuous
stack
monitoring
system
and
online ambient air quality
monitoring stations will be
installed.
Will be complied
9
10
Will be complied
Will be complied
C4-88
Sr. No.
CREP Recommendations
analysis facilities for air and water
pollutants. Also to impart elaborate
training to the manpower so that realistic
data is obtained in the environmental
monitoring laboratories.
To Improve overall house keeping.
11
SIP/DRI Plant
Inventorisation of DRI plant to install proper
air pollution control equipment to control
primary and secondary emissions.
* As per rebuilding schedule submitted to CPCB/MoEF
Action Plan
Will be complied
The following CREP guidelines for thermal power plant will be implemented for the
captive power plant of the proposed project.
TABLE-4.26
PLAN FOR THE IMPLEMENTATION OF THE RECOMMENDATIONS OF CREP
GUIDELINES FOR CAPTIVE POWER PLANT
Sr. No.
1
CREP Recommendations
Implementation
of
Environmental
Standards
(emission & effluent) in non-compliant* Power
Plants (31 & 27) Placement of order for pollution
control
equipment,
Installation & commission :
For existing thermal power plants, a feasibility study
shall be carried out by Central Electricity Authority
(CEA) to examine possibility to reduce the
particulate matter emissions to 100 mg/Nm3. The
studies shall also suggest the road map to meet 100
mg/Nm3 wherever found feasible. CEA shall submit
the report.
New / expansion power projects to be accorded
environmental clearance on or after 1.4.2003 shall
meet the limit of 100 mg/Nm3 for particulate matter
Install/activate
opacity
meters/continuous
monitoring systems in all the units, with proper
calibration system.
Development of guidelines / standards for mercury
and other toxic heavy metals emissions.
Review of stack height requirement and guidelines
for power plants based on micro meteorological
data.
Implementation of use of beneficiated coal as per
GOI Notification: power plants will sign fuel supply
agreement (FSA) to meet the requirement as per
the matrix prepared by CEA for compliance of the
6
7
8
Action Plan
Proposed
captive
power plant will be
complied
with
environmental
standards
Not applicable as this
is proposed captive
power plant.
Will be complied
Will be complied
Will be complied
Will be complied
C4-89
Sr. No.
notification
CREP Recommendations
as
short
term
Action Plan
measure.
10
Will
be
suitably
complied
Will
be
suitably
complied
complied
11
Will
be
suitably
12
Will be complied
13
14
15
Will be complied
Will be complied
Will be complied
C4-90
TABLE-4.27
PLAN FOR THE IMPLEMENTATION OF THE RECOMMENDATIONS OF CREP
GUIDELINES FOR CEMENT PLANT
Sr. No.
1
4
5
6
7
8
9
10
11
12
CREP Guideline
Cement Plants, which are not complying with notified
standards, shall do the following to meet the standards:
Augmentation of existing Air Pollution Control Devices
Replacement of existing Air Pollution Control Devices
Cement Plants located in critically polluted or urban
areas (including 5-km distance outside urban boundary)
will meet 100 mg/Nm3 limit of particulate matter and
continue working to reduce the emission of particulate
matter to 50 mg/Nm3
The
new
cement
kilns
to
be
accorded
NOC/Environmental Clearance w.e.f. 01.04.2003 will
meet the limit of 50 mg/Nm3 for particulate matter
emissions
CPCB will evolve load based standards
CPCB and NCBM will evolve SO2 and NOx emission
standards
The Cement industries will control fugitive emissions
from all the raw material and products storage and
transfer points. However, the feasibility for the control of
fugitive emissions from limestone and coal storage areas
will be decided by the National Task Force (NTF). The
NTF shall submit its recommendations within three
months
CPCB, NCBM, BIS and Oil refineries will jointly prepare
the policy on use of petroleum coke as fuel in cement
kiln.
After performance evaluation of various types of
continuous monitoring equipment and feedback from the
industries and equipment manufacturers, NTF will decide
feasible unit operations/sections for installation of
continuous monitoring equipment. The industry will
install the Continuous Monitoring Systems (CMS).
Trippings in kiln ESP to be minimized as per the
recommendation of NTF
Industries will submit the target date to enhance the
utilization of waste material
Action Plan
Will be complied
Will be complied
Will be complied
Not Applicable
Not Applicable
Will be complied
Not Applicable
-
Not Applicable
Waste fly ash from
power plant will be
utilised for cement
making
to
the
extent possible.
Not Applicable
-
****
VIMTA Labs Limited, Hyderabad
C4-91
5.0
5.1
Selection of Process
Manufacture of iron and steel starting from raw materials is the output of various
complex metallurgical process and, therefore, highly technology oriented. In
order to select an appropriate process route for production of iron and steel, a
large number of factors affecting these technologies need to be examined. Some
of these important factors are:
There are two established process routes for production of steel viz.
1. Blast Furnace-Basic Oxygen Furnace route; and
2. Direct Reduction- Electric Arc Furnace route.
Approximately 75% of the worlds hot metal is produced through the BF-BOF
route and it is generally accepted that the BF will continue to be the dominant
means of hot metal production.
BF-BOF process route for production of steel from iron ore consists of reduction of
iron ore using metallurgical coke as a reducing agent in a Blast Furnace (BF) and
refining the metal in a Basic Oxygen Furnace (BOF), where oxygen is blown into
molten iron in order to reduce its carbon content. This route requires
metallurgical coke.
On account of inadequate availability of coking coal in some parts of the world,
another technique, the DRI-EAF method has been used perfected over the years.
In the DRI-EAF technique, steel scrap or Directly Reduced Iron (DRI) are
charged into an Electric Arc Furnace (EAF) and is melted using graphite
electrodes. The steel is then refined to the required specifications.
The steel produced by the above-mentioned techniques is either cast into flat
products (hot rolled coils, plates etc) or into long products (bars, rods, rails and
structural shapes). While the long products are primarily used in the construction
sector, the flat products find application in white goods, automobiles etc.
Hot rolled coils are further processed in cold rolling mills to produce cold rolled
steel products and are obtained by passing hot rolled steel coils/strips through
pressurized rolls at room temperature to reduce thickness.
BF/BOF processes mainly requires iron ore and coke/coking coal where as DRIEAF process requires scrap or sponge iron and non-coking coal.
C5-1
It is proposed to adopt BF-BOF process for this proposed steel plant, which is
used widely in the world due to flexibility and large scale of operation.
The status of technologies prevailing in all production areas and selection of the
optimum ones for the proposed steel complex have been deliberated in the
following sections viz.
Pelletising;
Sintering;
Coke making
Iron making;
Steel making;
Casting; and
Rolling.
5.1.1 Pelletising
For the blast furnace normal feed materials are lump iron ore sinter and pellets
along with coke, limestone and other flux materials. Due to depletion of rich iron
ore, large amount of experiments were conducted in the usage of lesser rich iron
ore of about 63.5% Fe content as against the preferred 67.5% Fe content.
Technological improvements have led to the use of pellets in every aspect to
achieve higher productivity point of view, reduced coke requirement, as well as
better burden chemistry or production point of view. The pellet & sinter
combination is highly recommended for the Blast Furnace operation.
The proposed pelletisation plant will be designed to produce 2 x 4.0 million
tonnes of pellets. This pellet plant will utilize the beneficiation plant product to
produce BF grade pellets to be used in the blast-furnace.
Pelletising turns fine grained iron ore (even low grade iron ore) into balls of a
certain diameter, which are suitable for blast furnace and direct reduction. Iron
ore is crushed and the impurities are removed. The ore mix is moistened and a
binding agent is added. The iron-rich ore is heated with a binding agent to create
durable marble sized "green pellets in rotating drums or on rotary discs. These
green pellets are dried and indurate at temperatures of more than 1000C. This
can take place in shaft furnaces or on a travelling grate. The pellets have
excellent physical and metallurgical properties and can be easily transported, due
to their high strength and suitability for storage. The pelletisation process
involves three steps:
Prior to the formation of pellets, water is added to iron ore fines to adjust the
moisture content to approximately 9 % and the ore is mixed with small amounts
of binding agents such as bentonite (approximately 0.5 %) and flux such as
limestone, lime olivine and dolomite (1-5 %). These give the pellets the proper
VIMTA Labs Limited, Hyderabad
C5-2
physical and metallurgical properties needed for further processing. Mixing takes
place in continuously operating drum or pan-type mixers of suitable capacity.
Pellets are formed either in pelletizing discs or drums, drums usually being
connected to roller screens used for separating undersized pellets. The pellets
thus formed have low mechanical strength they are hardened in travelling grate
coupled with drying and furnace.
5.1.2 Sintering
Sintering is a technology for agglomeration of iron ore fines into useful blast
furnace burden material. The raw materials used are: iron ore fines (-10 mm),
coke breeze (-3 mm), limestone & dolomite fines (-3 mm) and other metallurgical
wastes. The proportioned raw materials are mixed and moistened
in a mixing drum and are loaded on sinter machine. The raw material mix is
segregated so that the coarse materials settle at the bottom and fines onto the
top. The top surface of the mix is ignited through stationary burners at 1200 oC. A
high temperature combustion zone is created in the charge-bed due to
combustion of solid fuel of the mix and regeneration of heat of incandescent
sinter and outgoing gases. Sinter is produced as a combined result of locally
limited melting, grain boundary diffusion and re-crystallization of various
components. On the completion of sintering process, finished sinter cake is
crushed and cooled. The cooled sinter is screened and is dispatched to blast
furnace.
5.1.3 Coke Making
Coke is one of the prime requirements for production of hot metal through blast
furnace route. Considering the level of technological development in the
coke making area and total requirement of blast furnace coke in the blast
furnace, installation of recovery type coke oven batteries have been envisaged.
The complex is proposed to be equipped with four (4), stamp charged 6.3 m tall
coke oven batteries of each oven. The gross coke generated in the coke ovens
will be screened. BF coke & nut coke will be sent to the blast furnace and coke
fines/ coke breeze generated in the plant will be utilized in the sinter plant. The
coke
making
technology
would
include
pre-carbonization
and
post
carbonization technologies like selective crushing of coal, stamp charging, coking
in high capacity ovens, cooling of coke, screening & gas cleaning facilities.
In blast furnace, lump iron ore, sinter, pellets, metallurgical coke, lime stone, flux
materials are charged and the reaction of the carbon in coke and the oxygen in
the blast both acts as reductant and fuel thus separating iron from iron oxide.
This gets collected into hearth as molten iron (which is tapped at intervals)
molten slag, input materials to blast furnace are in solid form but the output is in
liquid form.
Blast furnace is, by far, the most established process for production of hot metal.
The process has been continuously improved over many years to increase
productivity and quality of hot metal. In fact, the blast furnace still continues to
be the dominant means of hot metal production for the iron and steel industry.
Nevertheless, this technology has some limitations like dependence on
VIMTA Labs Limited, Hyderabad
C5-3
metallurgical coke and elaborate supporting facilities (coke ovens etc.). However,
the latest developments, as narrated below, have retained its predominant
status:
In BOF scrap, hot metal, limestone, nut coke and other flux materials are charged
and oxygen is blown from the top. Oxidized iron react with the carbon and forms
pure iron with depletion of carbon thus resulting in liquid steel. The quantum and
pressure of oxygen determines the time for making hot metal to liquid steel with
occluded gases and slag particles. The output from BOF are liquid steel, slag and
iron rich fumes/gases.
Ladle Refining
Presently, refining operation of steel is carried out in a separate ladle with electric
heating arrangement along with alloy addition and rinsing arrangement.
Important factor which led to the usage of ladle refining process is that main
vessel to be used for melting as well as primary refining whereas ladle furnace to
be used for final or secondary refining. In ladle refining furnace, following
treatment is possible:
In addition to the ladle refining process some of the low carbon steel products
need further purification of the steel in the form of removal of occluded gases as
well as other foreign impurities which are detrimental in the final properties of the
rolled products. For this reason RH-TOB (Rhuhrstahl Hereaues-Top Oxygen
Blowing) degassing facilities with vacuum as well as argon purging have been
envisaged. With the RH-TOB degassing facility following treatments are possible:
C5-4
Plant Facilities
Beneficiation Plant
Pellet Plant
Coke Oven Plant
Sinter Plant
Blast Furnace
Direct Reduction Plant
BOF Converter
Ladle Furnace
RH-TOP
Billet Caster
Bloom Caster
Shaped Bloom Caster
Slab Caster
Capacity
29.0 MTPA
2 x 4.0 MTPA
2 x 3.0 MTPA- Recovery type ovens with CDQ
having stamp-charging facilities & by-products
2 x 7.8 MTPA
2 x 5500 m3 (2 x 4.9 MTPA)
1.2 MTPA
3 x 180 T + 2 x 280/300 T
3 x 180 T + 2 x 280/300 T
1 x 180 T + 1 x 280/300 T
2 x 6 strand
1 x 6 strand
2 x 3 strand
2 x 2 strand
C5-5
5.2
Plant Facilities
Wire Rod Mill
Bar Mill
Medium Section Mill
Heavy Section Mill
Hot Strip Mill
Plate Mill
Cold Rolling Mill
Galvanizing Line
Tin Plate Mill
Electrical Steel
Colour Coating Line
Oxygen plant
Lime Calcination Plant
Dolo Calcination Plant
Captive Power Plant
Cement Plant
Coking Coal Washery
Non-Coking Coal Washery
Capacity
1.0 MTPA
1.0 MTPA
1.2 MTPA
2 x 1.1 MTPA
4.5 MTPA
1.5 MTPA
2.3 MTPA
1.0 MTPA
1.0 MTPA
1.0 MTPA
1.0 MTPA
3 x 2500 TPD
5 x 600 TPD
2 x 600 TPD
3 x 300 MW
6.0 MTPA
5.52 MTPA
2.30 MTPA
of
Alternate Site-I
Ichagarh-Nimdih
IchagarhNimdih/Saraikela
Kharswan
1/2 km from Kukru
73 E/16 & 73 I/4
23o 04 15N to
23 o 09 22N
85 o 56 05E to
86 o 04 56E
15 km form NH-32
40 km from SH
(Silli Ranchi SH)
from
1 km Latemda
railway station
site
RL 200 m
Alternate Site-III
Barenda
Sonahatu/Ranchi
1/2 km from
Barmasia
73 I/7
1 km from Barenda
23 o 26 26N to
23 o 09 24N
85 o 18 14E to
86 o 20 50E
10 km form NH-32
Km from SH
(Chandakiyari Barmasia SH)
10 km Gourinath
dham &
20 km - Purulia
railway station
RL 220 m
73E/11, 73 E/12,
73 E/15,73 E/16
23 o 0845N to
23 o 1157N,
85 o 4756E to
85 o 5011E
16.1 km from NH33
20 km from SH
(Ranchi- Silli SH)
12 km Torang
railway station
RL 245 m
C5-6
Alternate Site-I
Ichagarh-Nimdih
Subernarekha river 1 km
Ranchi-80 km
Chandil, 40 km
Raiyati land 84%
Govt. land 14%
Forest land 2%
15.0%
82.5%
0.5%
2.0%
Alternate Site-III
Barenda
Subernarekha river2.4 km
30.0%
65.0%
5.0%
Nil
12.0%
88.0%
Ranchi 50 km
Muri, 25 km
Rayati Land : 88%
Govt. Land : 12%
8837 acres
1655
3680 acres
70
Nil
Nil
3800 acres
Nil
Nil
Chandankiary
Nil
13 km, S
Dalma Wildlife
Sanctuary
60 km, S
Dalma Wildlife
Sanctuary
39 km, SE
Dalma Wildlife
Sanctuary
Nil
Nil
Nil
Subarnarekha River
1 km
Coal : 113 km, NW
Iron : 113 km, SW
Gobai River-5 km
Damodar River- 25
km
130 km, NW
170 km, SW
Subarnarekha
River2.4 km
96 km, NW
107 km, SW
Namkum
The site-3 (near Barenda Village) has been selected, considering the following:
C5-7
C5-8
FIGURE-5.1
LOCATION MAP OF ALTERNATIVE SITES
VIMTA Labs Limited, Hyderabad
C5-9
5.3
Project concept note (PCN) and project design document (PDD) will be prepared
after detail engineering.
Benefits
Pulverized coal injection in BF replaces part of the coke used to fuel the chemical
reaction, reducing coke production, thus saving energy. The increased fuel
injection requires energy from oxygen injection, coal and electricity and
equipment to grind coal.
The maximum injection depends on the geometry of the BF and impact on the
iron quality (e.g., sulphur). Coal dust injection system will be introduced involving
handling, screening, drying and pulverisation system for coal. CDI has an
economic as well as an environmental advantage as it directs injection of coal into
BF as reducing agent which reduces coke requirement (for every kg of coal
injected approximately 0.8 kg. of coke requirement is reduced).
Benefits
C5-10
Waste heat utilization has been envisaged preheating the sinter mix before
feeding to sinter bed. For the same ignition furnace with post heat hood and pre
heating (before ignition furnace) will be installed just after the sinter mix drum
feeder. Hot air from waste heat recovery system of sinter cooler will also be used
for preheating of raw material before ignition furnace and post heat hood after
ignition furnace.
Approximately 2500C to 3500C hot air for the combustion is supplied from
waste heat recovery system of sinter cooler. De-dusting system shall be
provided at inlet of combustion air fan to supply clean hot air from discharge of
cooler. The hot air for combustion shall have control by having intake in cold air.
The ignition temperature shall be 1200 13000C. Pilot burners shall be provided
for start up and safety.
Benefits
Fuel savings in terms of reduction in coke consumption and steam;
Exhaust heat recovery;
NOx, SOx and particulate emissions reduction; and
Increased productivity, yield, and cold strength.
Use of Continuous Casting Technology
Coke oven is the equipment to carbonize coal to make coke and discharge
periodically coke at around 1000 deg. C. This coke is cooled by the inert gas
instead of water. The major advantages are:
C5-11
6.0
6.1
General
To ensure compliance to environmental regulation and also to maintain healthy
environmental conditions around the integrated steel plant, several measures
have been proposed in the Environment Management Plan (EMP) for mitigation of
adverse environmental impacts. These shall be implemented as per proposal and
shall be monitored regularly.
A monitoring strategy shall be ensured that all environmental resources, which
may be subject to contamination, are kept under review and hence monitoring of
the individual elements of the environment will be done. A major part of the
sampling and measurement activities will be concerned with long term monitoring
aimed at providing an early warning of any undesirable changes or trends in the
natural environment that could be associated with the plant activity.
This is essential to determine whether the changes are in response to a cycle of
climatic conditions or due to plant activities. During the operation phase,
Environment Management Department (EMD) will undertake all the monitoring
work to ensure the effectiveness of environmental mitigation measures. The
suggestions given in the environmental monitoring programme will be
implemented by the EMD by following an implementation schedule.
In case of any alarming variation in ground level concentration in ambient air,
stack emission, work zone air, water quality or noise monitoring results.
Performance of air pollution control equipment, effluent treatment facilities,
wastewater discharge etc., will be discussed in the EMD and any deviation from
the prescribed norms will be reported to the higher management for immediate
rectification action. In addition to the monitoring programme, the following will
also be done to further ensure the effectiveness of mitigation measures:
Comprehensive environmental audits will be carried out for the entire plant
operation to check for compliance with standards / applicable norms by
inhouse experts. Third party environmental audits will be carried out once in
every year;
In addition to the above, all necessary steps would be taken to implement the
measures suggested by MOEF in CREP for integrated iron and steel industry;
and
6.1.1 Meteorology
Automatic continuous meteorological station will be installed in the plant and the
observations recorded will be used in respect of the project. The following
parameters will be recorded regularly:
VIMTA Labs Limited, Hyderabad
C6-1
The emissions from all major stacks will be monitored once in a month using the
manually operated stack monitoring equipment. However, the frequency of
monitoring will be discussed with JSPCB and frequency may be increased as
required in accordance with the stipulation of JSPCB or other statutory
authorities.
C6-2
C6-3
Monitoring Schedule1
Environmental monitoring schedules are prepared covering various phases of
project advancement, such as construction phase and regular operational phase.
Action plan and monitoring schedule to follow NAAQ standards as per ToR-34
C6-4
TABLE-6.1
ENVIRONMENTAL MONITORING DURING PROJECT CONSTRUCTION STAGE
Sr.
No.
1
Potential
Impact
Air emissions
Noise
Action to be Followed
All
equipments
are
operated within specified
design parameters.
Vehicle
trips
to
be
minimized to the extent
possible
Maintenance of DG set
emissions
to
meet
stipulated standards
Ambient air quality within
the
premises
of
the
proposed
unit
to
be
monitored.
Gaseous
emissions
(SO2, HC, CO, NOx)
Equipment
to
be
maintained in good working
order.
Night working is to be
minimized.
Generation
of
vehicular
noise
Noise to be monitored in
ambient air within the plant
premises.
Wastewater
discharge
Soil erosion
Drainage and
effluent
management
Waste
management
Parameters for
Monitoring
Random checks of
equipment
logs/
manuals
Vehicle logs
No untreated discharge to
be made to surface water,
groundwater or soil.
Protect topsoil stockpile
where possible at edge of
site.
Ensure drainage system
and
specific
design
measures
are
working
effectively.
The design to incorporate
existing drainage pattern
and avoid disturbing the
same.
Implement
waste
management
plan
that
identifies and characterizes
every
waste
arising
associated with proposed
The
ambient
air
quality will conform to
the standards for PM,
SO2, NOx, and CO
Frequency of
Monitoring
Periodic
Periodic
during
site clearance &
construction
activities
Periodic
emission
monitoring
As per CPCB/
SPCB
requirement or
on monthly basis
whichever
is
earlier
Regular
during
construction
activities
Daily records
Maintenance
of
records of vehicles
Spot Noise recording
Daily records
No discharge hoses
shall be in vicinity of
watercourses.
Effective
cover
in
place.
Visual inspection of
drainage and records
thereof
Comprehensive waste
management
plan
should be in place and
available
for
inspection on-site.
As
per
CPCB/SPCB
requirement or
on
quarterly
basis whichever
is earlier
Periodic
during
construction
activities
Periodic
during
construction
activities
Periodic
during
construction
activities
Periodic
check
during
construction
activities
C6-5
Sr.
No.
Potential
Impact
Action to be Followed
activities
and
which
identifies the procedures
for collection, handling &
disposal of each waste
arising.
Non-routine
events and
accidental
releases
Health
Environmental
management
cell/ unit
10
Loss of flora
and fauna
Parameters for
Monitoring
Compliance with MSW
Rules,
1998
and
Hazardous
Wastes
(Management
and
Handling Rules), 2003
Mock
drills
and
records of the same
Frequency of
Monitoring
Periodic
during
construction
activities
All
relevant
parameters including
HIV
Responsibilities
and
roles will be decided
before
the
commencement
of
work.
Regular
ups
check
During
site
clearance phase
During
construction
phase
C6-6
TABLE-6.2
ENVIRONMENTAL MONITORING DURING OPERATIONAL PHASE
Sr.
No.
1
Potential
Impact
Air Emissions
Action to be Followed
Stack emissions from all
major units and CPP boilers
to
be
optimized
and
monitored
Stack emissions from DG set
to
be
optimized
and
monitored
Ambient air quality within
the
premises
of
the
proposed unit and nearby
habitations to be monitored.
Exhaust from vehicles to be
minimized by use of fuel
efficient vehicles and well
maintained vehicles having
PUC certificate.
Measuring onsite
data of
meteorology
Noise
Vehicle
trips
to
be
minimized to the extent
possible
Noise
generated
from
operation
of
power
boilers/cooling towers to be
optimized and monitored
Parameters for
Monitoring
Gaseous emissions
(PM,
SO2,
CO,
NOx)
Gaseous emissions
(SO2,
HC,
CO,
NOx)
PM,
RPM, SO2,
NOx, CO and HC.
November
notification
2009
Frequency of
Monitoring
Continuous
monitoring
using
on-line
equipment
during operation
phase
Periodic during
operation phase
As per CPCB/
JSPCB
requirement or
on weekly basis
whichever
is
earlier
Vehicle logs to be
maintained
Wind
speed,
direction,
temp.,
relative humidity
and rainfall.
Vehicle logs
Continuous
monitoring
using
on-line
weather station
during operation
phase
Daily records
Periodic during
operation phase
Maintain
records
of vehicles
Regular check ups
Periodic
operation
Periodic
operation
Discharge norms
for effluents
Periodic during
operation phase
Noise
generated
from
operation of DG set to be
optimized and monitored
DG sets to generate less
than 75 dB(A) Leq at 1-m
from the source
Wastewater
discharge
during
phase
during
phase
C6-7
Sr.
No.
Potential
Impact
Action to be Followed
Compliance of wastewater
discharge to standards
Water quality
and water levels
Emergency
preparedness,
such as fire
fighting
Maintenance of
flora and fauna
Waste
management
6.3
Drainage and
effluent
management
10
Soil quality
11
Health
Compliance
of
treated
sewage to standards
Ensure drainage system and
specific design measures are
working effectively.
Design
to
incorporate
existing drainage pattern
and avoid disturbing the
same.
Monitoring
used
water
quality, groundwater quality
around
ash
pond
and
ground water levels
River
water
quality
downstream to discharge
Contaminants such as VOCs
to be reduced by providing
adequate ventilation
Fire protection and safety
measures to take care of fire
and explosion hazards, to be
assessed and steps taken
for their prevention.
Vegetation, greenbelt /
green cover development
Implement
waste
management
plan
that
identifies and characterizes
every
waste
arising
associated with proposed
activities
and
which
identifies the procedures for
collection,
handling
&
disposal of each waste
arising.
Maintenance of good soil
quality
Employees
and
migrant
labour health check ups
Parameters for
Monitoring
pH,
TSS,
TDS,
BOD,
COD
&
temperature
Comprehensive as
per GSR 422(E)
Visual inspection
of drainage and
records thereof
Frequency of
Monitoring
Once in a week
during operation
phase
Once
in
a
season
Periodic during
operation phase
Comprehensive
monitoring as per
IS 10500
Periodic during
operation phase
Groundwater level
in meters bgl
As per IS 10500
Once in a week
Monitoring
of
indoor
air
contaminants such
as CO, CO2 and
VOCs.
Mock drill records,
on site emergency
plan,
evacuation
plan
As per CPCB/
SPCB
requirement
Local/native
species
Records of solid
waste generation,
treatment
and
disposal
Periodic
operation
Periodic
operation
Physico-chemical
parameters
and
metals.
All
relevant
parameters
including HIV
Periodical
monitoring
at
ash pond site
Regular
check
ups
Periodic during
operation phase
during
phase
during
phase
C6-8
6.5
Recommendations
Air pollution control
measures
Water pollution control
measures
Noise control measures
Ecological preservation and
up gradation
Time Requirement
Before commissioning of respective
units
Before commissioning of the units
Schedule
Immediate
Immediate
Immediate
Immediate &
Progressive
Parameters/
Function
Frequency
Ambient
Air
Fugitive
Emission
Stack Gas
Source
Emission
24
hr
continuous
once per month
Yes
PM2.5 samplers
Yes
Stack
Monitoring
kit (manual)
On
line
stack
monitoring
along
with
accessories
for
monitoring
SO2, NOx, CO2, CO
& PM
PM
No
Yes
Particulate
matter, SO2, NOx,
CO2 & CO
24
hr
continuous
once per month
All stack once
per month
Continuous
No
Yes
C6-9
Parameters/
Function
20
21
22
pH meter
Conductivity meter
AAS along with
Graphite furnace,
hydride generator
and cold vapor
technique
Digital
MicroBalance
Digital top load
balance (range 1
to 500 g)
Filtration
2
1
1
23
24
25
Stack Gas
Source
Emission
Continuous
O2%
CO%
SO2 mg/m3
NOx mg/m3
NO mg/m3
CxHy PPM
Ambient temp
Noise levels
No
Yes
As and when
required
Once per month
Yes
Yes
Yes
Continuous
Daily
Regularly
Regularly
As and when
required
Twice in a week
Twice in a week
As and
required
Daily
CO
analyser
1
CO
(NDIR)
9
Gas
1
Benzene (C6H6)
chromatograph
10
High
pressure
1
Benzo-a-pyrine
liquid
(BaP)- particulate
chromatograph
phase only
(HPCL)
Meteorological Monitoring
11
Automatic weather
1
Meteorological
monitoring station
parameters
Water Monitoring & Chemical Analysis
12
Ion analyser with
1
NH3. CN,F
auto-titrate
13
Hot air oven
1
Moisture content
&
drying
of
samples
glassware
14
Hot plate
2
O&G
Iron
&
various
purpose
like
boiling
digestion
of
sample
15
Muffle furnace
1
Digestion at temp,
up to 10000 C
16
BOD incubator
1
BOD
17
BOD
apparatus,
1 set of 6
BOD
Oxitop
18
DO meter
1
BOD
Spectrophotometer
with COD digestion
assembly
Ambient
Air
Fugitive
Emission
Yes
PM10, PM2.5
19
Frequency
COD,
Phenol
NO3-N
PO4-P
pH
TDS
Heavy metals in
water, As & Ni
analysis
in
Ambient air
Daily
Daily
As and
required
when
when
No
Weighing
Daily
Weighing
Daily
SS/MLSS
Daily
C6-10
6.6
26
27
28
Fuming chamber
29
Water bath
30
Vacuum pump
31
Turbidity meter
32
Parameters/
Function
Distillation
Preservation
chemicals
samples
For Exhaust
of
and
Evaporation
sample
Hardness,
alkalinity etc.
Turbidity
In Lot
Frequency
of
Ambient
Air
Fugitive
Emission
Stack Gas
Source
Emission
when
when
when
when
when
Daily
Regularly
As and
required
As and
required
As and
required
As and
required
As and
required
6.7
Description of Item
Air pollution control system
Water pollution control system
Solid
waste
management
system
Greenbelt development and
others
Post project monitoring
Total
Capital Cost
(Rs in Crores)
845
350
535
Recurring Cost
(Rs in Crores)
50
21
32
14
6
1750
1
1
105
Greenbelt Development3
6.7.1 Objective
The main objective of the green belt is to provide a barrier between the plant and
the surrounding areas. The green belt helps to capture the fugitive emissions and
to attenuate the noise generated in the plant apart from improving the aesthetics
of the plant site. In order to control the industrial pollutants, dense tree
plantations are necessary.
2
3
C6-11
Shrubs and trees will be planted in encircling rows around the project site;
The short trees (<10-m height) will be planted in the first rows (towards plant
side) of the green belt. The tall trees (>10 m height) will be planted in the
outer rows (away from plant side);
Planting of trees in each row will be in staggered orientation (triangular form);
In the front row, shrubs consisting of Albizia sp., Peltoforum etc. will be
grown;
Since the trunks of the tall trees are generally devoid of foliage, it will be
useful to have shrubs in front of the trees so as to give coverage to this
portion; and
The spacing between the trees will be maintained slightly less than the normal
spaces, so that the trees may grow vertically and slightly increase the
effective height of the green belt.
Should
Should
Should
Should
Should
C6-12
Local Name
Babul
Bael
Chattin
Sharifa
Kathal
Barhar
Safed kachna
Camel foot tree
Kachnar
Kandla
Palas
Papitha
Karonda
Nimbu
Mabola
Amla
Anjir
Dumar
Jungli anjir
Gamhar
Sabubal
Aam
Champaka
Guava
Bhelwa
Kathjamun
Imli
Badam
Copper pod
Sirsh
Korai
Kachnar
Sisso
Family
Mimosaceae
Rutaceae
Apocyanaceae
Annonaceae
Moraceae
Moraceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Caesalpinaceae
Fabaceae
Caricaceae
Apocyanaceae
Rutaceae
Ebanaceae
Euphorbiaceae
Moraceae
Moraceae
Moraceae
Fabaceae
Mimosacaae
Anacardiaceae
Magnoliaceae
Myrtaceae
Anacardiaceae
Myrtaceae
Caesalpinaceae
Combretaceae
Caesalpinaceae
Mimosaceae
Mimosaceae
Caesalpinaceae
Fabaceae
Fabaceae
The above mentioned species not only resist water stress but also covers the
ground quickly and also have wider soil adaptability.
6.7.4 Greenbelt Area
The greenbelt will be developed along the periphery of the plant and all open
spaces within the plant area covering an area of 1150 acres (465 ha) and
vegetation density of about 2500 trees/ha. Accordingly, about 11,62,500 saplings
will be planted. The survival rate will be maintained more than 90%. The
complete greenbelt will be developed in five years. The development plan is given
in Table-6.7.
VIMTA Labs Limited, Hyderabad
C6-13
TABLE-6.7
GREENBELT DEVELOPMENT PLAN
Sr. No.
1
2
3
4
5
6
Period
1st Year
2nd Year
3rd Year
4th Year
5th Year
6th to 10th Year
Total
Area (ha)
46.5
46.5
46.5
46.5
46.5
232.5
465
No. of Trees
1,16,250
1,16,250
1,16,250
1,16,250
1,16,250
5,81,250
11,62,500
The layout plan of the green belt and tree cover in plant area, ash pond area, slag
disposal area and township is shown in Figure-6.1.
6.8
Land Use
Area
(sq.km)
Run-off
Coefficient
1.66
0.00
2.73
0.36
0.97
29.25
34.97
0.5
0.7
0.7
0.2
0.25
0.3
0.44
Residential land
Industrial land
Barren land
Forest land
Scrub land
Cultivated land
Total/average
Annual
Rainfall
(m)
1.4549
1.4549
1.4549
1.4549
1.4549
1.4549
1.4549
Annual
Run-off
(MCM)
1.21
0.00
2.78
0.10
0.35
12.77
17.21
Monsoon
Rainfall
(m)
1.2714
1.2714
1.2714
1.2714
1.2714
1.2714
1.2714
Monsoon
Run-off
(MCM)
1.06
0.00
2.43
0.09
0.31
11.16
15.04
C6-14
The proposed project brings some changes in the land use which will alter the
run-off and volume of surface water availability. Post-development run-off values
calculated for different land uses are presented in Table-6.9. The effective area
contributing run-off after deducting waste disposal and water reservoirs/ponds is
33.76 sq.km. The annual volume of surface water available from the catchment of
proposed plant and township site after development is estimated at 21.29 MCM
while the volume of water available during monsoon period is 18.61 MCM. The
review of the pre and post development annual and monsoon run-off estimations
reveal that there is a slight increase in run-off availability due to proposed project
plant.
TABLE-6.9
POST-DEVELOPMENT ANNUAL & MONSOON RUN-OFF
FROM THE WATERSHED
Sr.
No.
1
2
3
4
5
6
Land Use
Residential land
Industrial land
Barren land
Forest land
Scrub land
Cultivated land
Total/Average
Area
(sq.km)
Run-off
Coefficient
2.87
8.70
2.40
4.61
0.97
14.21
33.76
0.5
0.7
0.7
0.2
0.25
0.3
0.44
Annual
Rainfall
(m)
1.4549
1.4549
1.4549
1.4549
1.4549
1.4549
1.4549
Annual
Run-off
(MCM)
2.09
8.86
2.44
1.34
0.35
6.20
21.25
Monsoon
Rainfall
(m)
1.2714
1.2714
1.2714
1.2714
1.2714
1.2714
1.2714
Monsoon
Run-off
(MCM)
1.83
7.74
2.14
1.17
0.31
5.42
18.61
After considering 50% as the safe run-off, balance surface water available can be
utilized for roof top harvesting and surface water harvesting in the form of
recharge pits, check dams, percolation tanks etc., with suitable location specific
designs. As part of water conservation and harvesting measures, JSW will
construct and operate rain water harvesting structures in the proposed project
area. This will reduce fresh water consumption of the plant to a considerable
volume. A storm water pond is proposed in the southern part of the proposed
project area to collect a portion of natural run-off through storm water drains.
Roof top rain water harvesting can also be adopted to meet the critical water
requirements and augmenting ground water recharge. Roof top rain water
harvesting, which involves the collection of rain water from the roof of the
buildings and its storage in the surface ponds or storm water pond or recharge to
ground water through recharge pits can play an important role in conservation of
water. It is proposed to construct the recharge pits taking the advantage of roof
top rain water in the vicinity of proposed bore well locations.
The storm water drains and roof top rain water diversions shall be maintained
properly to carry only clean water without having any contact with pollutants
from the waste, spills and other contaminant material.
C6-15
FIGURE-6.1
GREENBELT DEVELOPMENT PLAN
C6-16
FIGURE-6.2
RAIN WATER HARVESTING NETWORK
****
VIMTA Labs Limited, Hyderabad
C6-17
7.0
ADDITIONAL STUDIES
This chapter describes the technical presentation of the draft EIA report before The
Board of JSPCB, public consultation for the proposed project, risk assessment and
disaster management plan, occupational health and safety issues.
7.1
Sr.
No
Compliance
The drainage network in the proposed plant
site initiates from the hill range about 1.50
km towards north of the proposed plant site
and have up to 3rd order streams joining
Domra nadi running west-east along the
southern
boundary
and
joining
Subarnarekha river. The drainage network
in the proposed area joins Subarnarekha
river. It is proposed to divert the flow safely
in the development area of the plant site
and leave natural course as it is in the
open/green belt area maintaining the
natural flow along the boundaries of
development within proposed plant site.
Drainage in the open and green belt areas is
undisturbed and that in the development
area is diverted along the boundaries of
development and project site to continue
the natural run-off joining Domra nadi in the
south.
The run-off from the developed area
including plant, facilities, roads etc., and
C7-1
Sr.
No
5
6
10
Compliance
drainage from the roofs are routed through
storm water drains. These storm water
drains are laid alongside the road just
outside the boundary of the development.
Few small ponds which do not have active
storage will be disturbed during the
development process. The run-off water
routed through the storm water drains will
be collected in a storm water pond,
proposed in the south eastern part of the
site.
The run-off water routed through the storm
water drains will be collected in a storm
water pond, proposed in the southeastern
part of the site and will be utilized in
plantation.
The quality of ground water will be
maintained and it will be regularly
monitored as per the frequency prescribed
by
JSPCB
during
the
post
project
monitoring.
Continuous Ambient Air quality monitoring
station (AAQMS) will be installed at our
township.
Online monitoring system to monitor
emission from all major stacks will be
installed prior to commissioning of the plant
All solid waste will be disposed off properly
as per MSW (M&H) Rules-2013 & Hazardous
waste (M.H & TB) Rules, 2008.
JSWJSL
will
request
Government
of
Jharkhand (GoJ) to setup a centralized TSDF
facility for industry.
JSWJSL will set up the TSDF facility as per
the statutory norms in the land identified by
Govt. of Jharkhand.
Authorized agency will be identified.
Sr.
No
Compliance
river Subernarekha at upstream of Ranchi
and of Downstream of Chandil river will be
installed prior to commissioning of plant.
A-3,
Chandra
The public hearing was conducted on 21/9/2014 near Bank of India, Barenda
village, Sonahatu Block, Ranchi District, Jharkhand. Public hearing was started
with the welcoming of people present in the public hearing by Shri R.N. Choubey,
Director (Projects) on behalf of project proponent. Thereafter, people have been
informed by Shri Iqbal Alam Ansari, Additional DistrictMagistrate (Law and
Order), Ranchi who was presiding the public hearing that it is proposed to
establish 10.0 MTPA Integrated Steel Plant and 900 MW captive power plant
under the proposed project.
Later Regional Officer, Jharkhand State Pollution Control Board was requested by
Addl. Dist. Magistrate to give a brief about public hearing. Accordingly Regional
officer has highlighted about the procedure and purpose of public hearing. He said
that the questions, suggestions and doubts raised during public hearing will be
replied by the project proponent and the same will be compiled and will be sent
to ministry of Environment and Forests, Government of India, New Delhi. Then,
the project proponent was asked to give a brief about the proposed plant and the
measures to be taken to control pollution.
VIMTA Labs Limited, Hyderabad
C7-3
Shri B.K. Choudhary, Environment consultant M/s Vimta Labs limited, Hyderabad
explained the people about proposed project.
After presenting executive summary, Regional Officer requested the villagers to
raise their questions, suggestions to the management. People present in the
public hearing, welcomed the proposed project by company management, and
submitted their opinion and reactions, in which demands like providing
employment, providing suitable value for land, education, health, establishment
of technical institutions, providing schools, colleges , hospitals etc., along with
providing employment to land losers were raised. The main demand from the
villagers is to establish and operate the plant in pollution free environment. Unit
representative present in the hearing Shri R.N. Choubey, Director Projects while
focusing on all the points raised by the villagers, assured that education, health,
school, college, facility of hospital, providing suitable compensation for the land,
overall development of surrounding villages under CSR etc. will be ensured and
work will be done in a pollution free environment. The points, questions,
suggestions raised by villagers will be resolved through Village Committee.
Thereafter, Additional District Magistrate in his address appreciated the villagers
to co-operate in smooth conduction of public hearing and raising their
suggestions, points, questions peacefully. He directed project proponent to
extend necessary co-operation to the villagers and solve their problems and
implement their suggestions / points and also to take corrective measures for
pollution control by establishing suitable equipment and to run them in a
systematic way. Thereafter, the public hearing was declared closed.
About 397 people attended the public hearing. The list of people attended public
hearing and the minutes of the public hearing are enclosed as Annexure-XVII.
The photographs taken during the Public hearing are shown in Figure 7.2. The
comments/issues raised during the public hearing and replies to public hearing
comments along with budgetary action plan by project proponent are given below
in the Table-7.2.
C7-4
FIGURE-7.1(A)
PUBLIC HEARING NOTIFICATION
C7-5
FIGURE-7.1(B)
PUBLIC HEARING NOTIFICATION
C7-6
FIGURE-7.2(A)
PHOTOS OF PUBLIC HEARING
VIMTA Labs Limited, Hyderabad
C7-7
FIGURE-7.2(B)
PHOTOS OF PUBLIC HEARING
VIMTA Labs Limited, Hyderabad
C7-8
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-7
Additional Studies
TABLE-7.2
PUBLIC HEARING ISSUES AND ACTION PLAN
Sr.
No
1
Name and
Address of the
villagers
present
Shri Sadananda
Mahto,
VillBarenda
Raised Questions/
Suggestions/ issues etc.
There should be proper arrangement
for
controlling of environmental pollution with the
establishment of the project
Shri
Satyanarayan
Simhadev, VillBarenda
Shri
Harish
Chandra
Pramanik,
VillChokahatu
Shri
Surendra
Munda
Vill- Chokahatu
Reply/
commitment
made by PP
Shri R. N. Choubey,
Director
(Projects)
has assured general
public in his address
that the amount for
the land will be paid
through
Gram
Sabha as per the
rates fixed and the
same is being paid.
Similarly a mention
is made in the
registry deed about
the
employment.
Local
landless
people will be given
priority
in
the
employment.
Modern and suitable
equipment (Such as
Bag
filters,
ESP,
Cyclone, ETP, STP
etc.)
will
be
arranged to control
water, air and noise
pollution prior to
commissioning the
project.
Water,
Electricity,
Action Plan
Financial Allocation
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-7
Additional Studies
Sr.
No
10.
Name and
Address of the
villagers
present
Shri
Madan
Singh
Munda,
Vill-Napra
Shri
Amitabh
Mishra,
Vill- Barenda
Shri
Durga
charan Sahu
Vill-Sonadih
Shri
Viswarath
Mahto
Vill-Charkodih
Raised Questions/
Suggestions/ issues etc.
Reply/
commitment
made by PP
Action Plan
School,
College,
Hospital, Road etc.
facilities
will
be
provided under CSR
in the villages of 10
kms radius of the
project.
Payment
for
the
non-ownership land
will be made to
Government and the
present cultivator in
the land will also be
paid
suitable
compensation.
Financial Allocation
C7-10
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-7
Additional Studies
Sr.
No
11
Name and
Address of the
villagers
present
Shri Jagbandhu
Mahto
Vill- Mahil
Raised Questions/
Suggestions/ issues etc.
Industry should be established. We are not
opposing it. Cost of the land was decided by
few people. This should be done collectively.
Govt land which was settled to Raiyats is to be
considered for suitable compensation.
12
Shri
Jagatpal
Viswakarma,
Chakodih
13
Shri
Yudhister
Mahto
Marankiti
14
Shri
Kesav
Mahto Kamalesh,
Ex-MLA
Silli
Reply/
commitment
made by PP
Action Plan
Financial Allocation
C7-11
7.2
Risk Assessment1
7.2.1 Introduction
Industrial activities, which produce, treat, store and handle hazardous
substances, have a high hazard potential to safety of man and environment at
work place and outside. Recognizing the need to control and minimize the risks
posed by such activities, the Ministry of Environment & Forests have notified the
Manufacture Storage & Import of Hazardous Chemicals Rules in the year 1989
and subsequently modified, inserted and added different clauses in the said rule
to make it more stringent. For effective implementation of the rule, Ministry of
Environment & Forests has provided a set of guidelines. The guidelines, in
addition to other aspects, set out the duties required to be performed by the
occupier along with the procedure. The rule also lists out the industrial activities
and chemicals, which are required to be considered as hazardous.
The proposed project will be producing steel from iron ore and other raw
materials. During the process of manufacture of steel and other associated
materials hazardous gases are generated which are stored and used within the
plant process. In addition to this also some other hazardous chemicals, which are
required in the manufacture of steel or produced as a by-product, being stored
and handled in plant. The major chemicals handled / stored by the plant includes
coke oven gas (COG), blast furnace gas (BF gas), basic oxygen furnace gas (BOF
gas), LPG, different acids etc. In view of this, proposed activities are being
scrutinized in line of the above referred manufacture, storage and import of
hazardous chemicals rules and observations / findings are presented in this
chapter.
7.3
7.4
Hazard Identification
The following two methods for hazard identification have been employed in the
study:
C7-12
7.4.1
Identification of hazardous units and segments of plants and storage units based
on relative ranking technique, viz. fire-explosion and toxicity index (FE&TI).
Hazardous Properties
UN 1016. Dangerous Goods Class 3 Flammable Gas
UN 2034. Dangerous Goods Class 3 Flammable Gas
UN 1971. Dangerous Goods Class 3 Flammable Gas
UN 1016. Dangerous Goods Class 3 Flammable Gas
UN 1972. Dangerous Goods Class 3 Flammable Gas
UN 1203. Dangerous Goods Class 3 Flammable Liquid
UN 1202. Dangerous Goods Class 3 Flammable Liquid
TABLE-7.4
HAZARDOUS MATERIALS STORED, TRANSPORTED AND HANDLED
A
Material
Blast furnace
monoxide)
BOF gas
(carbon monoxide)
LPG
5
6
HFO
LDO
2
2
gas
(carbon
No. of
Tanks
2
Capacity
(Storage Condition)
50,000 m3
gaseous, ambient temperature
pressure
50,000 m3
gaseous, ambient temperature
pressure
50,000 m3
gaseous, ambient temperature
pressure
50 T
liquid & pressurized
1000 m3
250 m3
and
and
and
C7-13
TABLE-7.5
PROPERTIES OF FUELS USED IN THE PLANT
Chemical
Codes/Label
TLV
MP
UEL
7.4.2
:
:
:
TLV
Flammable
50 ppm
-191.45
MP
c
-205
Flammable
-252.8
-259.2
74
Flammable
1000 ppm
-161.5
-187.8
15
Flammable
50 ppm
-191.45
-205
74
12.5
Flammable
Flammable
Flammable
1000 ppm
-0.5
371
>350
-187
-
<-60
54.4
>62
8.5
6
5
1.8
0.7
0.5
14
FBP
FBP
FP
LEL
:
:
:
FP
UFL
LFL
74
12.5
BFG is a by-product of the iron making process and is used as a fuel gas. It is an
odourless, colourless and toxic gas. Its toxic properties are due to the presence of
carbon monoxide (CO) (typically 21-25% v/v) in the gas. In confined space, it can
form explosive mixture.
BFG is a very low heating value fuel (CV=800-900 Kcal/nm3), containing inerts of
approximately 58% nitrogen and 17% carbon monoxide. Therefore, the gas is only
likely to support stable combustion at elevated temperature, or with a permanent
pilot flame. BFG may be ignited by a high ignition source such as a permanent pilot
flame. BFG may be ignited by a high ignition source such as a welding torch.
However, the resulting combustion is slow.
BFG is not typically considered an explosion hazard for the following reasons:
COG is toxic and flammable gas and has a very strong odour. Its toxic properties
are due to the presence of CO (typically 9% v/v) in the gas. COG has a specific
gravity of 0.43 and therefore, is a very buoyant gas, which tends to disperse rapidly
when released to the atmosphere.
VIMTA Labs Limited, Hyderabad
C7-14
The high concentration of hydrogen and methane in COG suggests that the gas can
be ignited by a low ignition energy (e.g., static). Therefore, the probability of
ignition of COG leaks is likely to be high relative to other flammable gases.
COG is a corrosive gas due to the presence of hydrogen and sulphides (H2S=2500
mg/Nm3). This has significant implications for the maintainability of COG systems,
because COG pipework frequently develops small corrosion holes.
Carbon Monoxide
In addition to the BFG, COG and liquid oxygen, JSW-JSL will also use LPG. LPG is a
big fire and explosion hazard. Primarily, LPG is associated with the severe fire and
explosion hazards, i.e., boiling liquid expanding vapour explosion (BLEVE) under
sustained ignition and also vapour cloud explosion (VCE). BLEVE can be caused by
an external fire near the storage vessel causing heating of the contents and
pressure build-up. While tanks are often designed to withstand great pressure,
constant heating can cause the metal to weaken and eventually fail.
An unconfined (i.e., in open space) vapour cloud explosion (VCE) is possible only
when a large amount comes from a rupture of line/leak from large hole and
accumulates in the open space as a cloud while moving along the wind. If the
mixture of cloud and air is in the flammability range and some ignition source is
available on its way, it ignites and subsequently releases the energy on the point of
ignition in the form of a blast wave. It is called vapour cloud explosion (VCE). The
human injury and loss of property in case of VCE depends upon the mass involved
in the explosion and the location of the center of explosion.
A flammable release of gas that does not ignite at the leak source, or has a delayed
ignition, can produce a large vapour cloud, which covers a significant area. In the
absence of significant confinement or obstruction, ignition of the cloud results in a
low velocity flame front with minimal over pressure effects, known as a flash fire
and typically results (initially) only in impacts within the flammable cloud.
7.4.3
C7-15
1989 in conjunction with Environment Protection Act, 1986. This is referred here as
GOI Rules 1989. For the purpose of identifying major hazard installations, the rules
employ certain criteria based on toxic, flammable and explosive properties of
chemicals.
A systematic analysis of the fuels/chemicals and their quantities of storage has been
carried out, to determine threshold quantities as notified by GOI Rules, 1989 and
the applicable rules are identified. Applicability of storage rules are summarized in
Table-7.6.
TABLE-7.6
APPLICABILITY OF GOI RULES TO FUEL/CHEMICAL STORAGE
Sr.
No.
1
2
3
4
5
6
Chemical/ Fuel
Listed in
Schedule
3(1)
3(1)
3(1)
3(1)
3(1)
3(1)
7.5
7.5.1
Methodology
Total
Quantity
2x50,000 m3
2x50,000 m3
2x50,000 m3
3x50 T
2 x 1000 m3
2x250 m3
200
15
200
15
200
15
25 MT
25 MT
200
200 MT
200 MT
Capacity
1,00,000 m3
LPG
HFO
LDO
3 x 50 T
2 x 1000 m3
2 x 250 m3
1,00,000 m3
1,00,000 m3
Hazard Identified
Toxic vapor cloud/
Vapour cloud explosive
Toxic vapor cloud/
Vapour cloud explosive
Toxic vapor cloud/
Vapour cloud explosive
BLEVE
Pool fire
Pool fire
C7-16
TABLE-7.8
PRELIMINARY HAZARD ANALYSIS FOR THE WHOLE PLANT IN GENERAL
PHA
Category
Description of
Plausible
Hazard
If there is any
leakage
and
eventuality
of
source
of
ignition.
Highly
inflammable
nature of the
liquid fuels may
cause fire hazard
in the storage
facility.
Environmental
factors
7.5.3
Recommendation
Provision
--
Degree of Hazard
0-60
61-96
97-127
128-158
159-up
Light
Moderate
Intermediate
Heavy
Severe
By comparing the indices F&EI and TI, the unit in question is classified into one of
the following three categories established for the purpose (Table-7.9).
TABLE-7.9
FIRE EXPLOSION AND TOXICITY INDEX
Category
I
II
III
Certain basic minimum preventive and protective measures are recommended for
the three hazard categories.
C7-17
7.5.4
Chemical/ Fuel
Total Capacity
F&EI
Category
TI
Category
2 x 50,000 m3
53.29
13.61
III
2 x 50,000 m3
63.32
5.6
2 x 50,000 m3
53.29
13.61
III
3 x 50 T
2 x 1000 m3
2 x 250 m3
101.90
22.91
19.82
III
I
I
5.43
15.26
9.55
I
III
II
Conclusion
Results of FE&TI analysis show that the storage of carbon monoxide gas, hydrogen
& methane gas, LPG, HFO and LDO falls in category of Light to moderate
category.
7.6
7.6.1
Introduction
Consequences of worst-case/major credible emergency scenarios and likely dangers
to be associated in the proposed JSW-JSL plant near Barenda village have been
assessed through dispersion modeling, consequence and risk analysis.
Consequence analysis deals with the study of physical effects of potential dangers
associated with hazardous chemicals, their storage and operation etc. For
flammable and explosive chemicals like LPG, consequence on humans/animals and
structures are studied in terms of heat radiations and over pressures. For toxic
chemicals like carbon monoxide, consequence on human/animals are studied in
terms of concentration and dose-response relationships. The physical impact of heat
radiation, over pressure and toxic concentration are shown in Table-7.11.
The consequence modeling for different release scenarios for proposed JSW-JSL
plant has been carried out using the model ALOHA- Area Locations of Hazardous
Atmospheres developed by NOHAA and USEPA. Aloha predicates the rate at which
chemical vapors may escape into the atmospheres from the leaking/ruptured tank.
C7-18
TABLE-7.11(A)
DAMAGE DUE TO INCIDENT RADIATION INTENSITIES
Sr.
No.
1
Incident
Radiation
(kW/m2)
37.5
25.0
19.0
12.5
4.5
1.6
--
1% lethality in 1 min.
Causes pain if duration is longer than
20 sec, however blistering is un-likely
(First degree burns)
Causes no discomfort on long
exposures
TABLE-7.11(B)
EXPOSURE TIME NECESSARY TO REACH THE PAIN THRESHOLD
Radiation Level (kW/m2)
Time to Pain Threshold (Seconds)
19.9
2
11.7
4
9.5
6
4.7
16
1.7
60
Source: Techniques for Assessing Industrial Hazards by World Bank
TABLE-7.11(C)
PHYSCIAL IMPACT OF EXPLOSION OVER PRESSURE
Pressure
(psig)
0.1
0.7
1.0
2
3
4
5
7
10
300
C7-19
TABLE-7.11(D)
PHYSICAL IMPACT OF TOXIC CONCENRATION
Concentration Level
Short-Tem Exposure
Limit (STEL)
Immediately Danger to
Life and Health (IDLH)
Lethal Concentration at
50% mortality (LC50)
Fatal Level
7.6.2
Observed Effect
Maximum concentration of the substance to which workers can
be exposed for a period upto 15 minutes without suffering (a)
Intolerable irritation (b) Chronic or irreversible tissue change
(c) narcosis of sufficient degree to increase accident proneness,
impair self rescue, or materially reduce worker efficiency,
provided that no more than 04 excursion per day are
permitted, with at least 60 minutes between exposure periods,
and provided that daily TLV is not exceeded.
An atmospheric concentration of any toxic, corrosive or
asphyxiant substance that poses an immediate threat to life or
would cause irreversible or delayed adverse health effects or
would interfere with an individuals ability to escape from a
dangerous atmosphere. If IDLH values are exceeded, all
unprotected people must leave the area immediately.
LC stands for Lethal Concentration. LC values usually refer to
the concentration of a chemical in air but in environmental
studies it can also mean the concentration of a chemical in
water. For inhalation experiments, the concentration of the
chemical in air that kills 50% of the test animals in a given
time (usually half to four hours) is the LC50 value
Death
7.6.3
C7-20
remote. Such scenarios are considered in the assessment of likely dangers in and
around the plant with respect to the ultimate preparedness measures.
7.6.4
Day
Incoming Solar Radiation
Strong
Moderate
Slight
A
A-B
B
C
C
A-B
B
B-C
C-D
D
B
C
C
D
D
Night
Amount of over cast
>4/8
low <3/8
low
cloud
cloud
E
D
D
D
E
E
D
D
C7-21
7.6.5
TABLE-7.13(B)
FLAMMABLE AND EXPLOSIVE LEVELS CONSIDERED FOR CONSEQUENCE ANALYSIS
Vulnerable Zones
Red zone: severely affected
zone
Orange
zone:
moderately
affected zone
Yellow zone : low impact zone
7.7
Radiation
(kW/m2)
LPG
Intensity
Levels for
Explosion
Overpressure
(psi) Levels for LPG, CO
and Hydrogen
37.5 (kW/m2)
7 psi
12.5 (kW/m2)
3 psi
4.5
(kW/m2)
1 psi
C7-22
C7-23
Scenario
Accidental release of
12750 kg of carbon
monoxide (CO) into
the atmosphere due to
catastrophic failure of
BF gas holder
Accidental release of
2128 kg of carbon
monoxide (CO) into
the atmosphere due to
catastrophic failure of
CO gas holder
Wind
Speed*/
Stability
Class
2B
2D
1(psi)
2(psi)
82
84
78
78
73
73
1.5F
696
1280
1900
93
86
82
2B
2D
248
360
447
623
743
994
34
36
30
32
27
28
1.5F
367
632
1000
43
39
36
C7-24
FIGURE-7.3(A)
ACCIDENTAL RELEASE OF CO INTO THE ATMOSPHERE LEADING TO
TOXIC VAPOR CLOUD
FIGURE-7.3(B)
ACCIDENTAL RELEASE OF CO INTO THE ATMOSPHERE LEADING TO
VAPOUR CLOUD EXPLOSION
VIMTA Labs Limited, Hyderabad
C7-25
74
58
579
346
269
The vulnerable impact distances for explosion associated with hydrogen after
worst case release from BF/CO holder in terms of explosion overpressure levels
under D; 2 m/s for early ignition. Maximum impact distance corresponding to
moderate damage level of 3 psi for BF gas holder is 74 m and CO gas holder is
346 m from the holder area.
In addition, for planning purposes, the consequence impact zones
(severe/moderate/low) under stability class D, 2 m/s for the worst-case release
scenarios considered are depicted in plant layout of JSW-JSL. These drawings
show the locations and areas in JSW-JSL coming under severe/moderate/low
impact zones corresponding to various concentration levels of toxic vapour cloud
of hydrogen.
C7-26
FIGURE-7.4(A)
EXPLOSION ASSOCIATED WITH HYDROGEN DUE TO CATASTROPHIC
RELEASE OF BF GAS INTO THE ATMOSPHERE FROM HOLDER
FIGURE-7.4(B)
EXPLOSION ASSOCIATED WITH HYDROGEN DUE TO CATASTROPHIC
RELEASE OF CO GAS INTO THE ATMOSPHERE FROM HOLDER
VIMTA Labs Limited, Hyderabad
C7-27
7.7.6 Consequence Results for Fire and Explosion Scenarios for LPG
Since the worst-case release scenario of LPG release are Boiling Liquid Expanding
Vapor Explosion (BLEVE) and unconfined Vapor Cloud Explosion (VCE), the impact
factors considered are radiation intensity and explosion overpressure. The three
heat radiation levels of 37.5 kW/m 2, 12.5 kW/m2 and 4.5 kW/m2 and three
explosion overpressure levels of 7 psi, 3psi and 1 psi corresponding to severe
moderate and low damage levels have been considered respectively.
Maximum affected downwind distances (in m) due to heat radiation and explosion
over pressure level of LPG (stability class: D and wind speed =2.0 m/s)
BLEVE/Fire ball scenarios are given in Table-7.16 and Figure-7.5.
TABLE-7.16 (A)
THERMAL RADIATION LEVELS DUE TO
FAILURE OF LPG BULLET
Scenario
BLEVE due to catastrophic failure of a
LPG Bullet (45 MT)
TABLE-7.16 (B)
EXPLOSIVE OVER PRESSURE LEVELS DUE TO
FAILURE OF LPG BULLET
Scenario
Vapour cloud explosion due to
catastrophic rupture of LPG bullet
(45 MT)
7.7.7 Consequence Analysis Results for Pool Fire Scenario for HFO and LDO Storage
Tanks
The maximum capacity of storage of HFO and LDO are 2x1000 KL and 2X 250 KL
respectively. The most credible failure is the rupture/hole of the storage tank. As
a worst case, it is assumed that the entire contents leak out into the dyke
forming a pool, which may catch fire on finding a source of ignition. The radiation
intensities for rupture of HFO and LDO storage tank is given in Table-7.17 and
Figure-7.6.
TABLE-7.17
THERMAL RADIATION DUE TO FAILURE OF HFO AND LDO TANKS
Scenario
Failure
of
storage tank
Failure
of
storage tank
HFO
LDO
<10
13
25
C7-28
FIGURE-7.5(A)
THERMAL RADIATION LEVELS DUE TO
FAILURE OF LPG BULLET
FIGURE-7.5(B)
EXPLOSIVE OVER PRESSURE LEVELS DUE TO
FAILURE OF LPG BULLET
VIMTA Labs Limited, Hyderabad
C7-29
FIGURE-7.6(A)
THERMAL RADIATION DUE TO FAILURE OF HFO TANKS
FIGURE-7.6(B)
THERMAL RADIATION DUE TO FAILURE OF LDO TANKS
VIMTA Labs Limited, Hyderabad
C7-30
Particles dispersed in the air with minimum size (typical figure is 400
microns);
Dust concentrations must be reasonably uniform; and
Minimum explosive concentration for coal dust (33% volatiles) is 50 gm/m 3.
Identification of Hazards
The various hazards associated, with the plant process apart from fuel storage have
been identified and are outlined in Table-7.18.
C7-31
TABLE-7.18
HAZARD ANALYSIS FOR PROCESS IN THE PLANT
Sr. No.
1
2
3
Blocks/Areas
Coal storage in open yard
Coal handling plant
including bunker area
Boilers
Hazards Identified
Fire, spontaneous combustion
Fire and/or dust explosions
Fire (mainly near oil burners), steam
explosions, fuel explosions
Fires in
a) Lube oil system
b) Cable galleries
c) Short circuits in
i) Control rooms
ii) Switch-gears
Explosion due to leakage of hydrogen and fire
following it.
Fire in cable galleries and switch-gear/control
room
Fire
Risk Rank
3
3
3
Electrocution
Consequences of Interest
Potential for single fatalities, onsite
only
Potential for single fatalities, onsite
only
Potential for single fatalities, onsite
only
Potential for single fatalities, onsite
only
Potential for single fatalities, onsite
only
impact
impact
impact
impact
impact
C7-32
The hazardous event scenarios and risks in general at this facility can be
adequately managed to acceptable levels by performing the recommended
safety studies as part of detailed design, applying recommended control
strategies and implementing a safety management system.
7.8
Buildings and plant structures designed for cyclone and seismic events (where
appropriate), to prevent structural collapse and integrity of weather (water)
proofing for storage of dangerous goods;
Provision for adequate water capacity to supply fire protection systems and
critical process water;
Provision and integrity of process tanks, waste holding tanks and bunded
areas as per relevant standards;
7.8.1 Disasters
A disaster is a catastrophic situation in which suddenly, people are plunged into
helplessness and suffering, as a result, need protection, clothing, shelter, medical
and social care and other necessities of life.
Disasters can be divided into two main groups. In the first, disasters resulting
from natural phenomena like earthquakes, volcanic eruptions, storm surges,
cyclones, tropical storms, floods, avalanches, landslides, forest fires etc. The
second group includes disastrous events occasioned by man, or mans impact
upon the environment. Examples are armed conflict, industrial accidents,
radiation accidents, factory fires, explosions and escape of toxic gases or
chemical substances, river pollution, mining or other structural collapses, air, sea,
2
C7-33
rail and road transport accidents and can reach catastrophic dimensions in terms
of human loss.
There can be no set criteria for assessing the gravity of a disaster in the abstract
since this depends to a large extent on the physical, economic and social
environment in which it occurs. What would be considered a major disaster in a
developing country, ill equipped to cope with the problems involved, may not
mean more than a temporary emergency elsewhere. However, all disaster bring
in their wake similar consequences that call for immediate action, whether at the
local, national or international level, for the rescue and relief of the victims. This
includes the search for the dead and injured and removal of debris and social
care, the provision of temporary shelter to the homeless food, clothing and
medical supplies, and the rapid re-establishment of essential services.
7.8.2 Objectives of Disaster Management Plan (DMP)
The disaster management plan is aimed to ensure safety of life, protection of
environment, protection of installation, restoration of production and salvage
operations in this same order of priorities. For effective implementation of the
disaster management plan, it will be widely circulated and personnel training
given through rehearsals/drills.
The disaster management plan would reflect the probable, consequential
severalties of the undesired event due to deteriorating conditions or through
Knock on effects. Further, the management should be able to demonstrate that
their assessment of the consequences uses good supporting evidence and is
based on currently available and reliable information, incident data from internal
and external sources and if necessary the reports of outside agencies.
To tackle the consequences of a major emergency inside the factory or immediate
vicinity of the factory, a disaster management plan has to be formulated and this
planned emergency document is called Disaster Management Plan.
The objective of the industrial disaster management plan is to make use of the
combined resources of the plant and the outside services to achieve the
following:
C7-34
7.8.3
Flood Hazard
Central Water Commission has a river flow monitoring station on Subarnarekha
river in Muri at about 20 km upstream from the proposed plant site and the data
collected from this is presented below:
Latitude
Longitude
Altitude above sea level
Catchment area
Zero of gauge
Mode of observation
Highest water level/date
Danger level
:
:
:
:
:
:
:
:
23 22 00 N
85 48 00 E
241.96 m
1330 km
231.00 m
By wading/boat
243.4 m/1973
238.12 m
The event of highest water level 243.40 m occurred on 12.10.1973 flooded low
lying areas along Subarnarekha river near Muri. The water level during second
flood event occurred on 09.07.2008 was 238.12 m just touching the danger level.
Considering 194.00 m as danger level at nearest location on Subarnarekha River
with a 5.20 m of water level rise above danger level during worst flood event
based on 30 year monitoring data of CWC, Muri, a flood hazard zonation map has
been prepared and presented in Figure-7.7. The lowest ground elevation at
proposed project site is 210 m amsl and is 11 m above the worst flood level
occurred on 12.10.1973. Hence chances of proposed plant site getting flooded are
very less.
7.9
Emergencies
7.9.1
Fire consequences can be disastrous, since they involve quantities of fuel either
stored or in dynamic inventory in pipelines or in nearby areas. Toxic releases can
affect persons working around. Preliminary hazard analysis has provided a basis
for consequences estimation. Estimation can be made by using various pool fire,
tank fire consequence calculations. During the study of risk assessment, the
natures of damages are worked out and probability of occurrence of such hazards
is also drawn up.
C7-35
FIGURE-7.7
FLOOD HAZARD ZONATION BASED ON FLOOD OCCURRENCE DATA
VIMTA Labs Limited, Hyderabad
C7-36
7.10
Emergency Organization
It is recommended to setup an emergency organization. A senior executive who
has control over the affairs of the plant would be heading the emergency
organization. He would be designated as site controller. As per the general
organization chart, would be designated as the incident controller. In the case of
stores, utilities, open areas, which are not under the control of the production
heads, senior executive responsible for maintenance of utilities would be
designated as incident controller. All the incident controllers would be reporting to
the site controller.
Each incident controller, for himself, organize a team responsible for controlling
the incidence with the personnel under his control. Shift incharge would be the
reporting officer, who would bring the incidence to the notice of the incidence
controller and site controller.
Emergency coordinators would be appointed who would undertake the
responsibilities like fire fighting, rescue, rehabilitation, transport and provide
essential and support services. For this purposes, security incharge, personnel
department, essential services personnel would be engaged. All these personnel
would be designated as key personnel.
In each shift, electrical supervisor, electrical fitters, pump house incharge, and
other maintenance staff would be drafted for emergency operations. In the event
of power or communication system failure, some of the staff members in the
office/plant offices would be drafted and their services would be utilized as
messengers for quick passing of communications. All these personnel would be
declared as essential personnel.
C7-37
C7-38
In the event of failure of electric supply and thereby internal telephone, sets
up communication point and establishes contact with the emergency control
center (ECC);
Organizes medical treatment to the injured and if necessary will shift the
injured to nearby hospitals;
Mobilizes extra medical help from outside, if necessary;
Keeps a list of qualified first aiders of the factory and seek their assistance;
Maintains first aid and medical emergency requirements;
Makes sure that all safety equipment are made available to the emergency
team;
Assists site controller with necessary data and coordinate the emergency
activities;
Assists site controller in updating emergency plan, organizing mock drills
verification of inventory of emergency facilities and furnishing report to the
site controller;
Maintains liaison with civil administration;
Ensure availability of canteen facilities and maintenance of rehabilitation
center;
He will be in liaison with site controller/incident controller;
Ensure transportation facility;
Ensures availability of necessary cash for rescue/rehabilitation and emergency
expenditure;
Controls rehabilitation of affected areas on discontinuation of emergency; and
Makes available diesel/petrol for transport vehicles engaged in emergency
operation.
C7-39
Emergency Facilities
Intercom, telephone;
P & T telephone;
Self contained breathing apparatus;
Fire suit/gas tight goggles/gloves/helmets;
Hand tools, wind direction/velocities indications;
Public address megaphone, hand bell, telephone directories;
(internal, P&T) factory layout, site plan;
Emergency lamp/torch light/batteries;
Plan indicating locations of hazard inventories, plant control room, sources of
safety equipment, work road plan, assembly points, rescue location vulnerable
zones, escape routes;
Hazard chart;
C7-40
One fire station building has been envisaged, where all the fire personnel will be
stationed. All fire related signal from various units shall receive in this building to
take necessary action to extinguish and control the fire.
To meet any eventuality of fire, fire-fighting vehicles (one crash fire tender and
one dry power tender) have been considered.
C7-41
All plant units, office buildings, stores, laboratories etc will be provided with
adequate number of portable fire extinguishers to be used as first aid fire
appliances. The distribution and selection of extinguishers will be done in
accordance with the requirement of IS: 2190-92.
Hydrant System
The fire hydrant network system has been envisaged for the plant. Internal
hydrants will be provided at suitable locations and at different levels inside the
major plant units. Yard hydrants will be provided normally along the road and in
the close vicinity of the units to meet the requirement of water for extinguishing
fire. Hydrant system shall have dedicated pump house, pumps, water storage
and piping network etc.
Unattended and vulnerable electrical premises like electrical control rooms, cable
tunnels, MCC, transformer rooms, switch gear room, oil cellers, etc will be
provided with automatic fire detection and alarm system.
Installation like transformers of MSDS will be provided with fire detection and
emulsifier (high velocity water spray) system. Water spray system (MVWS) shall
be provided for the natural gas/LPG storage area.
7.11.5 Location of Wind Sock
On the top of the administration block, top of each production blocks, wind socks
would be installed to indicate direction of wind for emergency escape.
7.11.6 Emergency Medical Facilities
Stretchers, gas masks and general first aid materials for dealing with chemical
burns, and inhalations, fire burns etc. would be maintained in the medical center
as well as in the emergency control room. Private medical practitioners help
would be sought. Government hospital would be approached for emergency help.
Apart from plant first aid facilities, external facilities would be augmented. Names
of medical personnel, medical facilities in the surrounding area and near towns
would be prepared and updated. Necessary specific medicines and antidotes for
emergency treatment of burns patients and for those affected by toxicity would
be maintained.
Breathing apparatus and other emergency medical equipment would be provided
and maintained. The help of nearby industrial management in this regard would
be taken on mutual support basis.
C7-42
7.11.7 Ambulance
An ambulance with driver availability in all the shifts, emergency shift vehicle
would be ensured and maintained to transport the injured or affected persons. A
number of persons would be trained in first aid so that, in every shift first aid
personnel would be available.
7.12
Emergency Actions
Stop feed;
Dilute contents;
Remove heat;
Deluge with water; and
Transfer contents.
C7-43
7.13
General
C7-44
Organization
Communications
Specialized Knowledge
Details of specialist bodies, firms and people upon whom it may be necessary to
call i.e. those with specialized chemical knowledge, laboratories.
Voluntary Organizations
Chemical Information
Meteorological Information
C7-45
FIGURE-7.8
ACTION PLAN FOR HANDLING OFF SITE EMERGENCY
VIMTA Labs Limited, Hyderabad
C7-46
Humanitarian Arrangements
Public Information
Arrangements for
(a) Dealing with the media press office;
(b) Informing relatives, etc.
Arrangements for:
(a) Collecting information on the causes of the emergency;
(b) Reviewing the efficiency and effectiveness of all aspects of the emergency
plan.
7.14.2 Role of the Emergency Co-ordinating Officer
The various emergency services will be co-ordinated by an emergency
coordinating officer (ECO), who will be designated by the district collector. The
ECO will liase closely with the site main controller. Again depending on local
arrangements, for very severe incidents with major or prolonged off-site
consequences, the external control will be passed to a senior local authority
administrator or even an administrator appointed by the central or state
government.
7.14.3 Role of the Local Authority
The duty to prepare the off-site plan lies with the local authorities. The
emergency planning officer (EPO) appointed will carry out his duty in preparing
for a whole range of different emergencies within the local authority area. The
EPO will liase with the works, to obtain the information to provide the basis for
the plan. This liaison will ensure that the plan is continually kept up-to-date.
It will be the responsibility of the EPO to ensure that all those organizations which
will be involved off site in handling the emergency, know of their role and are
able to accept it by having for example, sufficient staff and appropriate
equipment to cover their particular responsibilities. Rehearsals for off-site plans
will be organized by the EPO.
7.14.4 Role of Police
Formal duties of the police during an emergency include protecting life and
property and controlling traffic movements.
C7-47
C7-48
7.15
The occupational health problems envisaged at this stage can mainly be due to
constructional accident and noise.
To overcome these hazards, in addition to arrangements to reduce it within TLVs
personal protective devices should also be supplied to workers.
C7-49
Boiler suit;
Safety belt/lime mans safety belt;
Leather hand gloves;
Asbestos hand gloves;
Acid/alkali proof rubberized hand gloves;
Canvas cum leather hand gloves with leather palm;
Lead hand glove;
Electrically tested electrical resistance hand gloves;
Industrial safety shoes with steel toe;
Rubber boots (alkali resistant); and
Electrical safety shoes without steel toe and gum boots.
Full fledged hospital facilities should be made available round the clock for
attending emergency arising out of accidents, if any. All working personnel should
be medically examined at least once in every year and at the end of his term of
employment. This is in addition to the pre-employment medical examination.
7.15.2 Safety Plan
Safety of both men and materials during construction and operation phases is of
concern. The preparedness of an industry for the occurrence of possible disasters
is known as emergency plan. The disaster in the plant is possible due to leakage
of hazardous chemicals, collapse of structures and fire/explosion etc.
Keeping in view the safety requirement during construction, operation and
maintenance phases, steel plant has formulated safety policy with the following
regulations:
To take steps to ensure that all known safety factors are taken into account
in the design, construction, operation and maintenance of plants, machinery
and equipment;
To keep all operations and methods of work under regular review for making
necessary changes from the point of view of safety in the light of experience
and upto date knowledge;
To provide appropriate facilities for fist aid and prompt treatment of injuries
and illness at work;
C7-50
C7-51
constituted in each area of work. The circle would consist of 5-6 employees from
that area. The circle normally should meet for about an hour every week.
7.15.5 Safety Training
A full fledged training center will be set up. Safety training will be provided by the
safety officer with the assistance of faculty members called from corporate
center, professional safety institutions and universities. In addition to regular
employees, limited contractor labors are also provided safety training.
To create safety awareness safety films will be shown to workers and leaflets etc.
will be distributed.
Some precautions and remedial measures proposed to be adopted to prevent
fires are:
Reliable and dependable type of fire detection system with proper zoning and
interlocks for alarms are effective protection methods for conveyor galleries;
House keeping of high standard helps in eliminating the causes of fire and
regular fire watching system strengthens fire prevention and fire fighting; and
C7-52
C7-53
C7-54
The dispersion pattern of TDS, hardness, calcium and sodium reveals that their
movement is from the drainage divide along the catchment boundary of the
proposed project site towards south west. Any pollutants joining the ground water
of deeper aquifer will move towards southwest from the proposed project site.
Effective management practices ensuring zero discharge from the proposed
project and proper waste disposal mechanism will not allow any pollutants
migrating to ground water and further movement along the pollutant pathways.
7.17
7.18
R & R Study
The social impact assessment including resettlement and rehabilitation (R&R) of
the project affected persons (PAP) has been conducted by M/s. BAIF
Development Research Foundation, New Delhi as per R & R policy of
Jharkhand state. The Detailed SIA and R&R report is enclosed as Annexure-XVI.
All the possible socio-economic mitigation measures will be adopted while
planning the project site.
By paying a comprehensive compensation package for different losses and
introduction of income generating schemes the PAFs are likely to generate
income that was prevailing before the land and property for the project.
Apart from this the proponent has already established track record of good
practices in CSR initiatives, which will continue in this project also, which would
ultimately improve the living standards by developing basic individual and
community infrastructure.
****
VIMTA Labs Limited, Hyderabad
C7-55
8.0
PROJECT BENEFITS
The growth of the steel industry significantly contributes to economic growth of a
nation as it generates employment both directly and also due to development of
ancillary industries. Peripheral development takes place due to need of
infrastructure facilities and due to more influx of money through the area, overall
importance of the area increases and overall the infrastructure and the living
conditions will improve.
8.1
8.2
8.3
Employment Potential
The proposed project implementation will generate employment both directly and
also due to development of ancillary industries. During the construction period,
the project is going to create substantial employment and income. A large portion
of these is likely to trickle down to the local people. Besides this, many persons
from the study area will get employment on permanent basis for actual operation
of the plant in the form of skilled or semiskilled or unskilled labour. Thus,
substantial amount of employment and income are expected to be generated for
the local people. Hence, it can be ascertained that the project is going to have
significant employment and income effects. The estimated manpower
requirement at the operational stage of the integrated steel complex is 10000.
In the case of indirect employment, the effect will be quite strong and
widespread. Besides direct employment, the project is expected to generate
substantial indirect employment in other sectors. So far as indirect employment is
concerned, the effect will be very strong and widespread specifically, in ancillary
industries, services and transport sectors. In view of the above, it can be
C8-1
justifiably concluded that the proposed integrated steel plant will have
tremendous positive employment and income effects. Overall assessment of the
employment and income effects indicates that the creation of additional capacity
will have strong positive direct as well as indirect impact on employment and
income generation.
8.4
8.4.1 Education
The interest towards higher technical education due to the expectation of getting
jobs nearby their home will drive local people towards education. This will be
more visible especially from non-agricultural sources such as ancillary industries
in the area.
The capacity additions are expected to increase such aspirations by bringing
opportunities of many direct & indirect employment for the local people. The
general awareness towards the importance of technical education is expected to
increase as a result of the proposed project.
The project will have positive impact on the level of education of the people of the
study area.
8.4.2 Industrialization around Integrated Steel Complex
Steel plants by nature serve as the nuclei for development of small-scale
industries in the areas around them. These small-scale units usually have
input/output linkages with the steel plants. The demand for spares, assemblies
and sub-assemblies by steel plants are generally met through the supply (of
these items) from small-scale units located nearby.
The proposed project is likely to accelerate such industrialization through Bubble
Effects in the study area. It is important to note that the small-scale units are
usually labour-intensive and high priority industries from socio economic
development point of view.
The proposed project is expected to serve as centre of significant small-scale
industrial economy around it complemented by the services sector. This is
expected to play a major role in the future economic and social development of
this area.
8.4.3 Pattern of Demand
The socio-economic assessment reveals that the respondents spend major portion
of their disposable income on food items. However, the respondents are heavily
influenced by the changing demand pattern of fast growing Indian consumer
VIMTA Labs Limited, Hyderabad
C8-2
society. There has been a tendency among the respondents of allocating higher
expenditure on non-food items although their basket of consumption has only few
items other than food. With the implementation of the proposed project and
development of the locality, existing demand pattern is likely to continue, which,
indicates more importance on consumer goods and quality products. This will
increase the local consumer goods market, thus creating more income
opportunities to the local people.
8.5
health
centre
for
national
health
Health camps for family planning, dental, old aged, HIV/AIDS, TB, malaria and
other communicable diseases;
Promoting rural health insurance by creating awareness and subsidy; and
Training and
volunteers.
awareness
programmes
for
health,
hygiene
and
sanitation
C8-3
C8-4
The project will help in improving the basic facilities like medical facilities,
educational, transport etc. The roads will be constructed and improved in the area
under community development program of the project. A total budget of Rs. 175
crores with capital cost of Rs. 93.28 crores and recurring cost of Rs 81.72 crores
is proposed for CSR activities. The capital and recurring expenses will be incurred
phase-wise in proportion to the implementation of the project. The capex cost will
be followed by the recurring cost. The budgetary allocation for the CSR activities
is given in Table-8.1 and detailed CSR action plan is given in Table-8.2.
C8-5
TABLE-8.1
BUDGET FOR PROPOSED CSR PROGRAMS
Sr.
No.
Category
1
2
3
4
5
6
Health programs
Water and sanitation
Education programs
Sports and culture
Livelihoods
Community
infrastructure
development including green belt
development
Supporting vulnerable persons
Management cost (Rs. in Crores)
Grand Total
7
8
Capital
Expenses
(Rs. In
Crores)
25.00
18.00
06.28
04.00
10.00
Recurring Expenses
(Rs. In Crores)
Total
(Rs. In
Crores)
20.33
10.35
04.00
04.40
05.25
45.33
28.35
10.28
08.40
15.25
25.00
08.98
33.98
0
05.00
93.28
03.41
25.00
81.72
03.41
30.00
175
TABLE-8.2
DETAILED CSR ACTION PLAN
Sr.
No.
1
CSR Programs
Health
Programme
Action Plan
Mobile medical unit (MMU) with doctor,
pharmacist, lab technician, community health
worker
and
diagnostic
facilities
in
collaboration with technical support agencies
like Help-age India (Best Practice)
Partnership with government primary health
center for supplementing national health
programs like polio, TB, and malaria etc.
Health camps for family planning HIV/aids
and other communicable diseases
Promoting rural health insurance by creating
awareness and subsidy
Training and awareness programs for health,
hygiene and sanitation volunteers
Total Approx.
Budget in
Crores
16.5
10
7
7
4.83
45.33
Water and
Sanitation
Programme
20
7
1.35
28.35
Education
Programme
Strengthening
of
school
buildings/
establishing model aganwadies/ balwadies in
collaboration with ICDS and adult education
centers drinking water supply and toilets in
schools
Setting up of village school, library ,computer
training, ITI's
Strengthening of mid - day meal program by
improving quality of food, kitchen in the
0.94
1.54
6.3
C8-6
CSR Programs
Action Plan
Total Approx.
Budget in
Crores
1.5
10.28
2.1
1.4
1.4
3.5
8.4
Livelihoods
Development
Programme
2
1.25
7
5
15.25
Community
Infrastructure
28
3.5
0.7
1
0.3
0.48
33.98
Supporting
Vulnerable
Persons
2.71
0.7
3.41
Management
Cost
30
175
****
VIMTA Labs Limited, Hyderabad
C8-7
9.0
ADMINISTRATIVE ASPECTS
9.1
Organization Policy
The importance of environment management has been recognised
management very early and JSWJSL has taken necessary steps
environmental aspects and mitigate those aspects which generate
the plant, respond to impacts on its own captive population and
peripheral areas.
by JSWJSL
to identify
pollution in
also in the
The above objective has been intended to be achieved through the following:
i) Improvement in the quality and appropriateness of raw materials as per
design philosophy;
ii) Using automation & computer control to have improvement on technology and
on working condition;
iii) Pollution monitoring and environmental management plan;
iv) Augmenting & implementation of occupational health set up including regular
medical monitoring of employees;
v) A well developed safety management system;
vi) Preparation of emergency/disaster management plan and a properly trained
group to meet the emergency situations;
vii) Green belt development inside the plant;
viii) Development of awareness among employees towards environmental
conservation; and
ix) R & D activities with respect to specific pollution problems.
JSWJSL management has given maximum importance for adopting latest clean
technologies for keeping the pollution to minimum levels. This is well evident
from the fact that a separate environment management department (EMD) will
exist in integrated steel plant headed by senior officer with an environmental
laboratory well equipped with latest monitoring instruments. The EMD will be the
nodal agency within the plant to deal with all environmental issues arising out
VIMTA Labs Limited, Hyderabad
C9-1
operation of various plant units and for ensuring compliance with all the
statutory requirements, including:
Environmental clearance conditions;
Consent to operate conditions; and
Hazardous waste authorization.
9.2
9.3
C9-2
FIGURE-9.1
CORPORATE ENVIRONMENTAL POLICY OF JSW
VIMTA Labs Limited, Hyderabad
C9-3
AVP (EMD)
Sr. Manager/AGM
(SE&FS)
Manager
SR.Environment Scientist
/ Env Lab
Jr. Manager
Dy. Manager
Jr. Manager
Analytical Chemist
Technician
Technician
FIGURE-9.2
ORGANIZATIONAL STRUCTURE OF ENVIRONMENTAL MANAGEMENT
****
VIMTA Labs Limited, Hyderabad
C9-4
10.0
10.1
Introduction
M/s. JSW Jharkhand Steel Limited (JSWJSL) proposes to establish 10.0
million tonnes per annum (MTPA) capacity integrated steel plant (ISP) along with
900 MW captive power plant (CPP) and township near Barenda village, Sonahatu
block in Ranchi district of Jharkhand state.
10.2
Plant Facilities
Beneficiation plant
Pellet plant
Coke oven plant
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Sinter plant
Blast furnace
Direct reduction plant
BOF converter
Ladle furnace (LF)
RH-TOP
Billet caster
Bloom caster
Shaped bloom caster
Slab caster
Wire rod mill
Bar mill
Medium section mill
Heavy section mill
Hot strip mill
Plate mill
Cold rolling mill
Galvanizing line
Tin plate mill
Electrical steel
Colour coating line
Oxygen plant
Lime calcination plant
Dolo calcination plant
Captive power plant
Cement plant
Coking coal washery
Non- coking coal washery
Capacity
29.0 MTPA
2 x 4.0 MTPA
2 x 3.0 MTPA- recovery type ovens with
CDQ having stamp-charging facilities
and by-products
2 x 7.8 MTPA
2 x 4.9 MTPA
1.2 MTPA
3 x 180 t + 2 x 280/300 t
3 x 180 t + 2 x 280/300 t
1 x 180 t + 1 x 280/300 t
2 x 6 strand
1 x 6 strand
2 x 3 strand
2 x 2 strand
1.0 MTPA
1.0 MTPA
1.2 MTPA
2 x 1.1 MTPA
4.5 MTPA
1.5 MTPA
2.3 MTPA
1.0 MTPA
1.0 MTPA
1.0 MTPA
1.0 MTPA
3 x 2500 TPD
5 x 600 TPD
2 x 600 TPD
3 x 300 MW
6.0 MTPA
5.52 MTPA
2.30 MTPA
C10-1
Baseline Environment
The study area generally represents undulating land with winds blowing
predominantly from northwest and southwest. The nearest IMD station is at
Ranchi at a distance of about 50 km from the project site.
The baseline environment quality has been monitored during pre monsoon season
(summer) 2014. With regard to the air quality in the study area, the
concentrations of particulate matter (PM10 and PM2.5), sulphur dioxide (SO2) and
oxides of nitrogen (NOx) and other pollutants levels are within the stipulated
standards as per 16th November, 2009 Notification. The contributors to the air
quality in the region are predominantly rural, residential activities, domestic coal
burning, traffic and unpaved open surfaces in the region. There are no major
operating industries in the study area.
C10-2
The water quality in the area covering surface and ground water sources in the
region is in compliance with the stipulated standards of IS:10500. The baseline
water quality does not reflect any major industrial contamination in the region.
The soil in the project site is predominantly clayey and the NPK values are in
sufficient quantity as compared to soil classification given by Indian Council of
Agricultural Research, New Delhi. The soil quality does not appear to have any
visible contamination. However, the surfaces in the region appear to be dusty due
to traffic and windblown dust.
Ambient noise levels were measured at ten locations around the project site. The
day time and night time noise levels in all the rural/residential locations were
observed to be within the permissible limits.
The study area (10 km radius) has a total population of 1,47,066 persons as per
2011 census data. Total male population is about 50.89% and total female
population is around 49.11%. The total literacy rate is 54.35% in the region
which is moderate.
From the field observations, it can be concluded that the forests in the study area
are under high anthropogenic pressure and show signs of degradation in the form of
tree cutting, lopping, poaching, grazing, collection of NTFPs and habitat
fragmentation. As per the MOEF and the forest department, Jharkhand reveals that
there are no wildlife sanctuaries, national parks/biospheres reserves and migratory
corridors in 10 km radius from the proposed site boundary. As per the records of
the Botanical Survey of India, there are no plants of conservation importance in the
study area. On comparing the checklist given in the Schedule-I of the Wildlife
(Protection) Act 1972 and the list of wildlife recorded from the study area, it can be
concluded that there are no schedule-I species found in the study area.
To assess the existing traffic density in the study area, traffic survey was
conducted one (1) location. It is observed that during the study period, traffic
load is reported to be observed mainly during day time. It was also observed that
the 2/3 wheelers, cars/jeeps and trucks/buses forms the major volume of the
traffic. The total traffic PCU of this road is minimal.
Thus, the monitoring of environmental attributes like ambient air, water quality,
soil characteristics, noise levels, terrestrial and aquatic ecology etc. indicates that
the pollution concentrations are within the permissible limits. Based on the
baseline environmental data of the area, the proposed project is environmentally
feasible as it has sufficient buffer assimilative capacity.
10.4
C10-3
During the design phase, all efforts have been made to adopt latest state of art
technology and to install adequate pollution control measures for different
processes and de-dusting stacks and for different fugitive emission sources.
During the construction phase, the following mitigation measures will be
employed to reduce the pollution level to acceptable limits:
Proper and prior planning, appropriate sequencing and scheduling of all major
construction activities will be done, and timely availability of infrastructure
supports needed for construction will be ensured to shorten the construction
period vis--vis to reduce pollution;
Truck carrying soil, sand, stone dust, stone will be duly covered to avoid
spilling and fugitive emissions;
It will be ensured that all construction equipment and vehicles are in good
working condition, properly tuned and maintained to keep emission within the
permissible limits and engines turned off when not in use to reduce pollution;
C10-4
C10-5
During the operation of the plant, the total water requirement will be about 80
million gallons per day (i.e. about 15150 m3/hr) including the water requirement
for the proposed captive power plant.
The wastewater generated from each process unit will be treated adequately and
re-used/re-cycled within the process. The proposed plant aims at zero discharge
concept. In case of water recovery/re-use system, during wet season, maximum
200 m3/hr, occasional discharge can be anticipated for a short period of time
meeting the discharge norms.
10.4.3 Solid and Hazardous Waste Management
The main solid waste generated in the proposed steel plant will be BF slag, BOF
slag which is non-hazardous waste. Other solid waste includes gas cleaning plant
sludge, dust from ESP, bag filter and dust extraction system and refractory debris
etc., this solid waste except refractory will be completely reused in sinter plant
and coal fines will be used in the power plant. Further, oil soaked cotton waste;
organic wastes from steel plant, paper, plastics and waste bag filters will be
generated. The details of non-hazardous and hazardous waste generated from
the proposed integrated steel plant and its disposal are given in Table-10.2 &
Table-10.3.
TABLE-10.2
SOLID WASTE GENERATION AND DISPOSAL
Sr. No
1
Solid waste
Generation TPA
Proposed disposal
98 % granulated and sold to
Cement plants, 2% treated in dry
pits and used for land fill
BOF slag is granulated , metalics
separated and used in
construction
Slag
30,00,000
14,80,000
Sludge
1,29,000
1,51,000
4
A
B
5
A
B
Ash
Rolling mills
Dusts
Flue dust from Blast furnace
Dust from bag filter
58,00,000
38,000
1,49,000
1,06,572
3,43,428
38,000
7,50,000
16,00,000
50,000 -1,00,000
C10-6
TABLE-10.3
HAZARDOUS WASTE GENERATION AND ITS DISPOSAL
Sr. No
Category
Quantity KL or T/Yr
@ 10 MTPA
1
2
2750 KL / Year
450 t
8.7 t/y
59 t/y
3
4
5
73216000 KL
Proposed Disposal
Sold to authorised parties
Regenerated in ARP
Regenerated in ARP
315 t
8172 t
C10-7
The tree species selected for green belt include the native species, which will be
planted in several rows with a tree density of 2000-2500 trees/ha with adequate
width around the plant boundary and maintained as per CPCB guidelines. The
inter-spaces will be planted with grasses, bushes and hedges. Greenbelt is thus a
set of rows of trees planted in such a way that they form an effective barrier
between the plant and the surroundings so that community noise impact and air
pollution will be reduced to a great extent.
10.4.6 Socio- Economics
The proposal implementation will generate employment both directly and also
due to development of ancillary industries. During the construction period, the
project is going to create substantial employment and income. A large portion of
these is likely to trickle down to the local people. Besides this, many persons
from the study area will get employment on permanent basis for actual operation
of the plant in the form of skilled or semiskilled or unskilled labour. Thus,
substantial amount of employment and income are expected to be generated for
the local people. Hence, it can be ascertained that the project is going to have
significant employment and income effects. The estimated manpower
requirement at the operational stage of the integrated steel complex is 10000.
In the case of indirect employment, the effect is quite strong and widespread.
Besides direct employment, the project is expected to generate substantial
indirect employment in other sectors. So far as indirect employment is
concerned, the effect is very strong and widespread specifically, in ancillary
industries, services and transport sectors. In view of the above, it can be
justifiably concluded that the proposed of integrated steel plant will have
tremendous positive employment and income effects. Overall assessment of the
employment and income effects indicates that the creation of additional capacity
will have strong positive direct as well as indirect impact on employment and
income generation.
10.5
C10-8
constituted in each area of work. The circle would consist of 5-6 employees from
that area. The circle normally should meet for about an hour every week.
A full fledged training center will be set up. Safety training will be provided by the
safety officer with the assistance of faculty members called from corporate
center, professional safety institutions and universities. In addition to regular
employees, limited contractor labors are also provided safety training.
All the potential occupational hazardous work places such as iron ore handling,
dolomite, limestone, coal handling and storage areas will be monitored regularly.
The health of employees will be monitored once in a year for early detection of
any ailment due to exposure to noise, respirable dust and hazardous chemicals.
The audiometry and lung function tests will be included in this surveillance
program.
10.6
The project will help in improving the basic facilities like medical facilities,
educational, transport etc. The roads will be constructed and improved in the area
under community development program of the project. Capital cost of Rs. 175
Crores is proposed for CSR activities. The capital and recurring expenses will be
incurred phase-wise in proportion to the implementation of the project. The
recurring cost will be followed by the capex cost. The budgetary allocation for the
CSR activities and EMP cost towards measures is given in Table-10.4 and Table10.5 respectively.
TABLE-10.4
BUDGET FOR PROPOSED CSR SCHEMES
Sr.
No.
Category
1
2
3
4
5
6
Health programs
Water and sanitation
Education programs
Sports and culture
Livelihoods
Community
infrastructure
development including green
belt development
Supporting vulnerable persons
Management cost (Rs. in Crores)
Grand Total
7
8
Capital
Expenses
(Rs. In
Crores)
25.00
18.00
06.28
04.00
10.00
Recurring
Expenses (Rs. In
Crores)
Total
(Rs. In
Crores)
20.33
10.35
04.00
04.40
05.25
45.33
28.35
10.28
08.40
15.25
25.00
08.98
33.98
0
05.00
03.41
25.00
03.41
30.00
93.28
81.72
175
C10-9
TABLE-10.5
COST PROVISION FOR ENVIRONMENTAL MEASURES
Sr.
No.
1
2
3
4
5
10.7
Description of Item
Air pollution control system
Water pollution control system
Solid
waste
management
system
Greenbelt development and
others
Post project monitoring
Total
Capital Cost
(Rs in Crores)
845
350
535
Recurring Cost
(Rs in Crores)
50
21
32
14
6
1750
1
1
105
Conclusions
The proposed integrated steel plant will have certain level of adverse impacts on
the local environment. However, with the judicious implementation of the
proposed pollution control and environment management measures, even the
adverse impacts anticipated due to construction and operation of the proposed
steel plant will be mitigated/contained. Further, development of this project will
have many beneficial impacts/effects in terms of bridging the steel demand and
supply gap and providing employment opportunities that will be created during
the course of its setting up and as well as during the operational phase of the
project.
Thus, in view of considerable benefits from the project and controllable adverse
environmental impacts, the proposed project will be most advantageous to the
region as well as to the nation.
****
C10-10
11.0
DISCLOSURE OF CONSULTANTS
11.1
Introduction
The Environmental Impact Assessment (EIA) and Environment Management Plan
(EMP) report has been prepared by carrying out various scientific studies. Studies
have been carried out by engaging scientists/engineers/experts of Vimta Labs
Limited, India and its empanelled associates. The list of experts involved in
different studies is given below:
Sr. No.
1
2
3
4
Study
Environmental impact assessment study
including environment management plan
Detailed hydro geological study
Remote sensing and land use/land cover
studies
Upper air measurement studies (SODAR)
Consultants
Vimta
Labs
Limited,
Hyderabad, India
Multi
Tech
Services,
Hyderabad, India
Multi
Tech
Services,
Hyderabad, India
Eco Tech Instruments, New
Delhi, India
VIMTA shall provide the services in accordance with national and international
norms;
C11-1
VIMTA shall implement quality systems as per ISO/IEC 17025 and applicable
Good Laboratory Practices (GLPs) & Good Clinical Practices (GCPs), to
generate technically valid results/data; and
VIMTA shall ensure that all its personnel familiarize with the policies and
procedures of the quality system and implement the same in their work.
Environment;
Analytical;
Clinical Reference Lab;
Clinical Research;
Preclinical;
Molecular Biology; and
Research and Development.
The environment division of VIMTA Labs Limited (VLL) has its presence all over
India and other countries including a strong association with international
consultants like Japan Bank for International Cooperation (JBIC), Kennametal Inc.
- USA, Rudal Blanchard UK, E&E Solutions Japan, NAPESCO & Kuwait National
Petroleum Corporation Kuwait, Marafiq and Haif Consultants Saudi Arabia and
others. Vimta Labs Limited has the following credentials:
C11-2
C11-3
C11-4
C11-5
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-11
Disclosure Of Consultants
The details of the persons involved in the preparation of present EIA/EMP report is presented below:
DETAILS OF PERSONNEL INVOLVED IN CURRENT EIA/EMP STUDY VIMTA LABS LTD
Sr. No.
Name
In House Experts
1
Mr. M. Janardhan
Qualification
M. Tech (Env)
Position
Contribution
Experience
Co-ordination
Sr. Manager
Co-ordination
Manager
Expert
M.Sc., Ph.D
M. Tech (Env)
M.S.W
Group Leader
Expert
Group Leader
Expert
6
7
M.Sc., M. Tech
(Env)
P.hD (Ecology)
M.Tech (Env)
Env Scientist
Env Engineer
Expert
Expert
M.Tech (Env)
Env Engineer
Expert
Sr. Scientist
Expert
10
M.Sc (Env)
Sr. Scientist
Expert
11
M. Tech (Env)
Engineer
Expert
12
M.S.W
Scientist
Expert
13
M. Tech (Env)
Tr. Engineer
Trainee
14
M. Tech (Env)
Tr. Engineer
Trainee
15
16
B. Sc
B.Com
Quality Auditor
Dy Manager
Quality Check
Secretarial
Support
C11-6
Environmental Impact Assessment for the Proposed 10.0 MTPA Integrated Steel Plant, 900 MW Captive Power Plant and
Township near Barenda Village, Sonahatu Block, Ranchi District, Jharkhand State
Chapter-11
Disclosure Of Consultants
Sr. No.
17
18
Name
Mr. P. Krishna
Qualification
I.T.I (Civil)
Position
Jr. Engineer
Contribution
Cartography
I.T.I (Civil)
Jr. Engineer
Cartography
B.Sc. (Mining
Engineering)
Empanelled
Consultant
Expert
Empanelled Experts
19
Mr. V.K.Bhatnagar
Experience
About 14 years of experience in the field of environmental and civil
drawings
About 13 years of experience in the field of environmental and civil
drawings
20
M.Sc. (Applied
Geology)
Empanelled
Consultant
Expert
21
M.Tech (Chemical
Engineering)
Empanelled
Consultant
Expert
****
C11-7