River Kayibu
BILL OF QUANTITIES
A.
SUMMARY
Bill of Quantities
DIVISION-1
USD:
DIVISION-2
USD:
DIVISION-3
USD:
USD:
SUB-TOTAL-A:
B.
Add
Provisional Sum for Physical
Contingencies (5% of A)
USD:
SUB-TOTAL-B:
USD:
TOTAL (A+B) :
USD:
USD:
ng River Kayibu
Project Title: Construction of 3 - Bridges 50m long River Kaya, 20m long River Koni and 20m long River Kayibu
DIVISION-1: GENERAL AND SITE FACILITIES
BoQ
Item
No.
Pay
Item
No.
USD:
Quantity
LS
PS
PS
a) Relocation Cost
PS
108(1)
1.2
113(1)
113(1)
130.8(b)
130(15)
816(1)
USD:
Unit
108(1)
1.4
Amount
Description of work
1.1
1.3
Unit Rate
Reference
Specificati
on no.
816
1.5
131(1)
131(1)
Allow for providing and maintaining Project Sign Boards in the format
acceptable to the Engineer.
no.
1.6
133(1)
133
Providing and fixing Marble stone for foundation laying both end of the bridge
as per direction of Engineer
PS
1.7
132(1)
132
Allow for providing all necessary Insurances for workforce for all risks
L.S.
1.8
132(2)
132
Allow for providing all necessary bonds and securities as are required and
detailed in the Tender Documents, Conditions of Contract or this Specification
under this contract
L.S.
TOTAL (DIVISION-1)
Project Title: Construction of 3 - Bridges 50m long River Kaya, 20m long River Koni and 20m long River Kayibu
DIVISION-2: BRIDGE CONSTRUCTION WORKS
A. FOUNDATION WORKS
Reference
BoQ Item Pay Item
Specification
No.
No.
no.
2.1
201(1)
201
2.3
302(1),
302(2)
302.3
Description of work
All clearing and grubbing necessary for the performance of the work
Sq.m.
covered by the Contract in accordance with the Specifications.
a)
i)
b)
302(1),
302(2)
302
i)
b)
302(3)
Unit Quantity
302.3
Unit Rate
Amount
USD:
USD:
600
cu.m
250
cu.m
40
sq.m
90
180
2.5
1004(1)
2.5(1)
2.11
2.12
2.13
1001(1)
1002(1)
804(1)
1002
804
P.S
cu.m
P.S
cu.m
Reference
Specification
no.
Description of work
Unit Quantity
Unit Rate
Amount
USD:
USD:
B. SUB-STRUCTURE WORKS
2.14
1001(1)
1001
2.15
1001(1)
1001
2.16
2.18
1002(1)
1001(2)
1002
1001
Mixing and casting in-situ cement concrete Grade-30 (Cylinder Strength) for
RCC works in different components of the sub structure (including pile cap)
including metal, sand, preparing of formworks & fitting/fixing, scaffolding,
laying, vibrating, curing and finishing i/c all labour, tools, equipments,
plants, nails, reterder/admixture compounds, water/ice cubes etc. complete
in conformity with drawing and specification direction of the Engineer
except supply of cement, and formwork materials (black laminated ply
wood).
Mixing and casting in-situ cement concrete Grade-35 (Cylinder Strength) for
RCC works in Bearing seat of the sub structure including metal, sand,
formworks preparing & fitting/fixing, scaffolding, laying, vibrating, curing
and finishing i/c all labour, tools, equipemnts, plants, nails,
reterder/admixture compounds, water/ice cubes etc.complete in conformity
with drawing and specification direction of the Engineer except supply of
cement and formwork materials (black laminated plywood).
cu.m
120
cu.m
15
20
15
cu.m
Reference
Specification
no.
Description of work
Unit Quantity
Unit Rate
Amount
USD:
USD:
C. SUPER-STRUCTURE WORKS
2.19
1002(1)
1002
2.20
1001(1)
1001
2.21
1003(1)
1003
2.25
1001(1)
1001
2.26
1010(1)
1010
22
110
tonne
85
cu.m
12
2.26(1)
a)
300x300x60
nos.
2.26(2)
b)
400x400x100
nos.
L.m.
23
L.m
25
2.27
1009(1)
1009
2.27(1)
2.29
Fitting, fixing and installation of Expansion Joints in Deck of the the Bridge
in accordance with the drawing, specification and direction of the Engineer
i/c all labours, tools, equipments, plants etc. complete except the supply of
Expansion joint steel angle and filler materials.
a)
706(1)
706
Fixing rain water down pipe in walkway area using pipes (75 mm dia. PVC)
to facilitate the drainage of any water collected at the walkway of the
superstructure, as given in the drawings or as directed by the Engineer, and
in accordance with these specifications except supply of 75mm PVC pipe.
SUB-TOTAL-C:
Reference
Specification
no.
Description of work
TOTAL (DIVISION-2)
Unit Quantity
Unit Rate
Amount
USD:
USD:
Project Title: Construction of 3 - Bridges 50m long River Kaya, 20m long River Koni and 20m long River Kayibu
DIVISION-3: SLOPE PROTECTION WORKS
BoQ Pay Reference
Item Item Specificati
No.
No.
on no.
3.1 804(1)
3.2
302(1
),
302(2
)
804
302.3
3.2(1)
3.3
302(1
),
302(2
)
3.4 805(1)
3.5 302(1)
302.3
805
302
Description of work
Supply and laying the Rip Rap (450mm thick) on geo textile for
embankment and slope protection and erosion control, furnished
and constructed in accordance with these specifications and in
conformity with lines grades and dimensions and at locations shown
on drawings or established by the Engineer i/c labour, tools, plants,
equipments etc. complete.
Excavation for foundations of piers, abutments and wing walls in
unclassified soil including leveling ramming of bottom of the
excavation and except supply of backfill materials of structures with
approved material as mentioned below:
a) 0 to 3.00m depth
Excavation for foundations of piers, abutments and wing walls in
weather rock including all type of bolder up to 3m3 size (if available
in site) including leveling of bottom of the excavation and except
supply of backfill materials of structures with approved material as
mentioned below:
Gabion wall for embankment and slope protection and erosion
control (for abutment protection), furnished and constructed in
accordance with these specifications and in conformity with lines
grades and dimensions and at locations shown on drawings or
established by the Engineer; i/c labour, tools, equipements, plants
etc. complete except supply of Gabion wires and stone blocks.
Earthwork in cutting/filling for Slope protection works.
TOTAL (DIVISION-3):
Unit Quantity
Unit Rate
Amount
USD:
USD:
cu.m
200
cu.m
50
cu.m
10
cu.m
75
cu.m
75
0
0