Annex 1.

2
Typical Delegation of Duties & Authority to a Resident Engineer
In accordance with Sub-Clause 3.2 of the General Conditions of Contract (GCC), I hereby further
delegate authority to Mr ____ as detailed below. All references to Sub-Clause numbers shall expressly
include reference to any associated Particular Conditions of Contract (PCC). Therefore, separate
reference is not made to the PCC, except where for any reason including clarity it is necessary to refer
to a specific Sub-Clause in the PCC. Multiple delegations against a particular Sub-Clause generally
follow the same sequence in which the circumstance occurs in the text of the Sub-Clause.
GCC Sub
Clause No
1.3

Heading

Delegation

Communications

1.8

Care and Supply


of Documents

To receive copies of the Contractors Documents.

1.9

Errors in the
Employers
Requirements

To receive notices.

1.12

Confidential
Details

To require disclosure of confidential and other information.

2.1

Right of Access
to the Site

To receive notices.

2.3

Employers
Personnel

Mr ......... is included in Employers Personnel.

3.1

Engineers
Duties and
Authority

To receive communications.
To issue communications within the limitations confirmed
elsewhere in this notification of delegation.

Mr ......... is authorised to exercise the authority attributable to


Mr, subject to the delegations stated herein.
Delegation of authority to Mr ......... does not preclude the
requirement for Mr ......... to seek the approval of the Employer
where expressly required in the Contract.
In sub clause (a), Mr ......... is authorised to act for the Employer.
In sub clause (c), reference to the Engineer shall include any
person with delegated authority properly issued under the Contract.

PCC SubClause No
3.1

Engineers
Duties and
Authority

3.2

Delegation by
the Engineer

3.3

Instructions of
the Engineer

3.7

Management
Meetings

To require meetings.
To record decisions, prepare and issue records of the meetings.

4.1

Contractors

To require details to be submitted by the Contractor.

Annex 1-2 Delegation to RE

In respect of emergencies, Mr ......... is authorised to act on Mr.


.s behalf, subject to the provision of reference to Mr.
Crossman for prior approval for matters subject to Clause 13.
Mr ......... has no authority to issue further delegations.
To issue instructions in writing only relating to remedying of
any defects or to safety.

Page 1 of 5

GCC Sub
Clause No

Heading

Delegation

General
Obligations

To receive notifications of alterations.

4.2

Performance
Security

To receive a copy of the Security.

4.3

Contractors
Representative

4.4

Subcontractors

Sub-Clause (c): To receive notices.

4.6

Co-operation

To receive documents.

4.7

Setting Out

To issue notifications of setting out.


To receive notices.

4.9

Quality
Assurance

To receive procedures and compliance documents.

4.12

Unforeseeable
Physical
Conditions

To receive notices.
To inspect physical conditions.
To review other physical conditions.
To take due account of evidence foreseen by the Contractor.

4.16

Transport of
Goods

To receive notices.

4.17

Contractors
Equipment

To issue consents to the Contractor.

4.20

Employers
Equipment and
Free-Issue
Material

To receive notices.

4.21

Progress Reports

To receive monthly reports.

4.22

Security of the
Site

To notify the Contractor of relevant Personnel.

4.23

Contractors
Operations on
Site

4.24

Fossils

5.1

General Design
Obligations

5.2

Contractors
Documents

5.4

Technical
Standards and

Annex 1-2 Delegation to RE

To receive the Contractors proposals and/or all notifications for


all consents required by this clause.

To agree additional areas for Contractors operations.


To receive applications for, and to issue of consents, in respect
of operations.
To receive notices of discovery.
To receive notices in respect of delay/Cost.
To receive proposals in respect of designers and design subcontractors.
To receive notices of error, fault or defect.

To receive Contractors Documents.

To receive notice of proposed modification.


To require further Contractors Documents.

To receive notices, and if appropriate, proposals.

To determine compliance.
Page 2 of 5

GCC Sub
Clause No

Heading

Delegation

Regulations
5.6

As-Built
Documents

To receive copies of records.


To receive copies of drawings, and to issue consent as to details.
To review drawings.

5.7

Operation and
Maintenance
Manuals

To receive copies of provisional and final manuals.

6.5

Working Hours

To receive advice.

6.7

Health and
Safety

To receive accident reports.


To require reports.
To receive Contractors Safety Methodology.

6.10

Records of
Contractors
Personnel and
Equipment

To receive details.

7.2

Samples

To receive samples.
To review samples

7.3

Inspection

To receive notices.
To carry out examinations etc

7.4

Testing

To agree time and place of testing.


To issue notices to attend tests.
To issue instructions.
To receive notices.
To receive reports of tests.
To endorse reports of tests, subject to prior consultation with M.
Pettersson.
To endorse reports and/or issue certificates.

7.5

Rejection

8.3

Programme

To receive programmes
To issue notices of non compliance.
To receive notices of future events.
To require submittal of estimates and/or proposals.

8.9

Consequences of
Suspension

To receive notices.

8.11

Prolonged
Suspension

To receive requests.
To receive notices.

8.12

Resumption of
Work
Contractors
Obligations

To examine the Works.

To receive notices.

9.1

Annex 1-2 Delegation to RE

To reject Plant, Materials, design or workmanship.


To require Plant, Materials, design or workmanship to be
retested.

Page 3 of 5

GCC Sub
Clause No

Heading

Delegation

9.2

Delayed Tests

9.3

Retesting

9.4

Failure to Pass
Tests on
Completion

To order repetitions, after consultation with Resident Engineer

10.1

Taking Over of
the Works and
Sections

To receive notices of readiness for Take Over.

10.2

Taking Over of
Parts of the
Works

To receive Contractors requests.


To receive notices of Costs.

10.3

Interference with
Tests on
Completion

To receive notices of time and/or Costs.

11.6

Further Tests

To require repetition of tests.

11.8

Contractor to
Search

To require searches.

12.2

Delayed Tests

To receive notices.

12.4

Failure to Pass
Tests after
Completion

To receive notices.

13.1

Right to Vary

To receive notices.

13.2

Value
Engineering

To receive submittals.

13.3

Variation
Procedure

To receive notices.
To require repetition of tests, after consultation with Resident
Engineer

All matters relating to Variations (other then properly instructed


day works) are subject to Sub-Clause 3.5.
To request proposals.
To receive responses, and Contractors proposals.
To receive acknowledgments.

13.6

Day work

To receive quotations.
To receive statements as prescribed.
To countersign statements and return copies.
To receive priced statements.

13.7

Adjustments for
Changes in
Legislation

To receive notices.

14.2

Advance
Payment

To receive statements.

14.3

Application for

To receive copies.

Annex 1-2 Delegation to RE

Page 4 of 5

GCC Sub
Clause No

Heading

Delegation

Interim Payment
Certificates
14.10

Statement at
Completion

To receive copies.

14.11

Application for
Final Payment
Certificate

To receive copies.
To require details.

17.4

Consequences of
Employers Risks

To receive notices

18.1

General
Requirements for
Insurances

To receive notices.

20.1

Contractors
Claims

To receive notices.
To monitor and/or instruct record keeping.
To receive copies of records.
To receive and/or require particulars.

Please confirm by return receipt of this letter.


Yours faithfully,
Marzzena Pettersson
Team Leader