Mr. Cardwell has more than 39 years experience in petroleum refinery, petrochemical,
power, and offshore industries. His responsibilities have included plant layout, piping
design and drafting, checking, and supervision of other designers and drafters.
Senior Field Piping Designer – Assigned by Technip to follow construction and solve
piping problems encountered in the construction of NOx reduction project at the
ExxonMobil Billings Montana Refinery. Units involved were a new SCR and CCOB
boiler revamp and installation of Soot Blowers.
Senior Piping Designer – Technip Engineering - PDS IFC iso checker for Valero projects
Port Arthur, Texas. Utilized Smart Plant computer program to check PDS isos of a grass
roots modular Sour Gas Recovery unit and interconnecting pipe racks for major
expansion of the Valero Port Arthur refinery complex.
Senior Piping Designer – Jacobs Engineering - PDS piping layout and design for
definitive estimate model of a ethanol to ethylene conversion facility for Dow Chemical
Company which was to be built in Brazil. Was responsible for PDS conceptual piping
layout and design of the ethylene and propylene compressors area, quench water area,
condensate stripper area, adjacent pipe rack and banks of air cooled exchangers.
Senior Piping Designer/ Checker - Jacobs Engineering - Conoco Phillips Trainer, Penn.
Refinery. Diesel and gasoline systems upgrade and revamp to clean fuels. Locate
piping tie-ins, develop field route piping sketches for cost and engineering estimate.
Senior Piping Designer/ Checker - Jacobs Engineering - Flare Gas Recovery system Deer
Park, Texas Refinery. Checked PSD piping models and isometrics utilizing Smart Plant
Review and approve for Issue for Construction
Piping Team Leader - Park, Texas Refinery Asphalt Crude Unit Tower Replacement,
CITGO Asphalt Refining Company, Savannah, Georgia. Replace existing 75 year old
asphalt crude tower and add two new exchangers to existing unit utilizing Autocad &
flexcad.
Senior Piping Design/Checker - Jacobs Engineering - Clean Fuels Project, Flint Hills
Resources, Corpus Christi, Texas. Checked PSD piping models and isometrics for 75%
of offsite piping and two ISBL units utilizing Smart Plant Design.
Bayport Region Piping Team Leader - Jacobs Engineering - Small Capital Projects,
Equistar/Lyondell Alliance, Houston, Texas. Responsible for piping estimating and
design supervision on multiple small projects for five plants in the alliance. The projects
can be as small as one line or as large as a complete unit revamp.
Area Piping Team Leader - Jacobs Engineering -Grass Root Polypropylene Facility,
Aristech Chemical Company, LaPorte,Texas. The process was based on Montell Loop
reactor technology. Duties included piping supervision for the feed prep, compressors,
degas structure, catalyst prep facility, loop reactors, and blow-down areas.
030227
TOMMY CARDWELL RESUME - PAGE 3 OF 6
Lead Piping Designer - Marine Vapor Recovery and Incineration System, Celanese
Marine Terminal, Bayport, Texas. Helped to develop engineering bid package.
Lead Piping Designer - Continuous Operation Pilot Plant Facility, Phillips Petroleum
Company, Houston Chemical Complex, Texas. This facility produced pharmaceutical
grade polyethylene and polypropylene pellets. Responsible for all piping and
mechanical design plans, section, elevations, and construction isometrics.
CAD Piping Designer - New Compressor Station, Dunn, Arkansas. Used CAD system,
Hewlett Packard 10000 running HOLGUIN CEADS 2000 software.
Participated in three different offshore projects. Duties included process piping systems
layout and design starting at the wellhead manifold, on through the dehydrator,
precipitator, condensate separator, acculator, glycol regenerator, compressors and final
connection to offshore to onshore pipeline, pressure relief vent systems, deck drain
system to skim pile, process drain system to and from sump and waste heat recovery
from electrical generator motor exhausts. Also was involved in final check in piping
fabrication isometrics to ensure that the piping involved had the proper material
030227
TOMMY CARDWELL RESUME - PAGE 4 OF 6
030227
TOMMY CARDWELL RESUME - PAGE 5 OF 6
Employment History:
030227
TOMMY CARDWELL RESUME - PAGE 6 OF 6
030227