Beruflich Dokumente
Kultur Dokumente
After the generator dryout is declared completed, short circuit tests on the
generator with short circuits at different locations of the bus are carried
out. During these tests the operation and stability of the protective relays
are checked. Proper planning and prior arrangement with the appropriate
agencies at site is called for to carry-out the tests sequentially and
continuously so that minimum time is taken to complete the tests and thus
minimizing the period of no-load running of the TG set.
2.1
In the unit lock out relay 86 U, the outgoing wires are removed for
preventing operation of 86G and 86 GT during testing (i.e. tripping of
boiler and turbine).
2.2
Ensure that the operation of 86 U would trip only the field breaker.
2.3
Rotor Earth Fault:This protection is recommended to be tested and kept operative prior to
the commencement of the generator dryout itself.
By extending the a.c. auxiliary supply to I and II rotor E/F relays the
operation of these relays are checked by making a temporary short of the
positive pole of the generator field to ground. Test with 20V field voltage
has been found to suffice.
3.0
15.75 KV 3 phase short:(a) 3-phase short circuit made (location 1 in the enclosed sketch) after the
15.75 KV line side CTs, for the generator dryout is retained. Close the
field breaker and slowly increase the excitation.
During the tests, currents are measured in the following relays.
87G
87GT
21
40
37-1
37.2
46
i)
ii)
During this test the following are checked:The pickup of the overall diff. Relay (87GT); back up impedance
relay (21G)
Non-operation of Gen. Diff. Relay (87G) proving its stability for
external faults (Even upto 60% rated stator current).
(b) 3-phase short circuit shifted to a location before the 11 KV line side
CTs (location 3 in the enclosed sketch) closoe the field breaker
and slowly increase the excitation.
Check operation of Gen. Diff. Relay (87G). All the three flags should
appear.
Measurement differential current in the neutral side CTs and
voltage across relay terminals when the relay picks up.
(c) Checking of inter turn fault relay R6
4.0
15.75 KV 2 phase Short:Make a 2 phase Short circuit between R and Y phases on the 15, 75 KV
side (location of the short same as in 3 b). Close the field breaker and
increase the excitation. Check for the following. Checking should be done
rapidly to avoid rotor heating during this 2-phase short circuit test.
Generator Impedance back up relays 21G.
5.0
6.0
6.2
Measure and record the voltage across the stator earth fault relay
terminals 64G.
6.3
Measure and record leakage current in the rotor earth fault circuit.
6.4
6.5
6.6
Raise the voltage to 110% (or 130% depending on site requirement) and
check operation of over fluxing relay.
6.7
Check the under voltage relay of the losos of excitation relay 40. Record
the pick-up and drop out values during the voltazge building up.
7.0
6.6 KV 3 Phase Short:- (Tests are carried out individually for Bus 1-A
and Bus 1-B).
All the links for the unit auxiliary and main transformers are made through.
Measure and record the IR value of the complete generator, bus ducts,
PTs and transformer windings.
7.1
7.2
3-phase short circuit on the unit Aux-transformer shifted to the 6.6 KV side
after the CTs. (Locattion 6, 7 in the enclosed sketch).
400 KV, 3-phase Short:3-phase short circuit made on 400 KV side after the CTs. (Location 4 in
the enclosed sketch).
The bus bar protection CT Secondary leads are kept shorted to prevent
operation of bus bar protection relays.
Close the Field breaker and gradually increase the excitation to circulate
about 60% of the rated current of the machine.
8.1
Check the non-operation of the overall differential relay (87 GT) proving
its stability for external faults.
Measure CT Secondary currents in the 400 KV over current relays.
8.2
8.3
8.4
8.5
Check stability of reverse power protection. After the tests remove the
short circuit made on the HV Side.
9.0
400 KV Single phase Ground 51G:On the 400 KV side ground R-phase to create a single ground fault. Close
field breaker. Check the operation of relay on gradual excitation. After test
remove the ground.
10.0
400 KV Breaker Operation:All the protections 86G, 86U and 86T are in service. Repeat DG tests of
the protective relays and satisfactory operation of all relays is ensured.
Check all the alarm and annunciation systematically. Keep the HT
isolators open. Close the 400 KV breaker. Check the breaker operation
both by manual and by ready operation. Ensure satisfactory closing and
tripping operation of the breaker with necessary interlocks.
11.0
400 KV Bus A & B:Check phase sequence of the 220 KV Bus A PT Secondary terminals at
the appropriate UCB terminals (RYB clockwise). Check phase sequence
of the 220 KV Bus B PT Secondary Terminals at the appropriate UCB
terminals (RYB clockwise). Check polarity of PTS by measuring voltages
R-R1, Y-Y1, B-B1 etc.
12.0
400 KV Forward Charging:Take a shutdown on the 400 KV Bus B (or A) and de-energise the bus
from the existing grid. After ensuring that the bus is dead, close the 220
KV isolators and the breaker to bus B. Bring the TS set to rated speed
and build up voltage gradually to rated value thus forward charging the
Bus B.
Check the voltages and phase aequence of the incoming and running bus.
Check secondary voltages and phase sequence of 400 KV PT of Bus B,
in the respective UCB terminals. Check the generator 11 KV PT
Secondary Voltage and phase secuence (RYB Clock-wise) in the
respective UCB terminals. The phase sequence and polarity should tally
with that checked from the secondary of 400 KV PTs measured above.
Set proper tap on the main transformer.
As the rated voltage, put the synchronizing switch into ON position. The
check synchronizing relay should operate after a slight time delay with the
green lamp glowing on the synchronizing panel. Close the synchroscope
switch. The synchroscope should indicate 12-0 clock position with bright
lamp.
13.0
Unit Trip:
After the above tests, Co-ordinate all the agencies and prepare for a unit
trip.
Keep the Master Feul Trip (MFT) out of circuit. BY manually operating the
relay contacts of 87G trip the unit:(a)
Observe that lock out relays 86G, 86T and 86U operates with
respective annunciations.
(b) Observe operation of field breaker trip 220 KV breaker trip, and the
turbine trip. Reset all the relays and bring back turbine to rated
speed. Arrange for synchronizing the set.
14.0
Synchronising:Return the shut down on 400 KV Bus B and energise the bus from the
existing grid. Build up rated voltage on the generator. Adjust the frequency
to the running (grid) frequency. Put the synchronizing switch and the
synchroscope switch to ON position. When the green lamp appears
synchronise the set by closing the 4500 KV breaker.
Record the date and time of synchronization.
15.0
Loss of Excitation:
After synchronizing, with the machine delivering certain active load to the
grid (say 10 MW), check that the impedance relay is stable for forward
reactive power (Say 40 MVAR).
15.1
With current to the relay reversed (keeping trip wire out) check the
operation of relay at a certain MVAR.
15.2
Under voltage relay has been checked during the open circuit test of the
generator.
15.3
15.4
With current connections and trip restored to normal conditions the relay s
kept in service.
16.0
SYSTEM
FOR
BOILERS
IN
INTRODUCTION:
With Indis launching massive power development programme Bharat Heavy
Electricals Ltd., (BHEL) introduced in late 70s Large capacity Boilers or Steam
Generators in the Indian Power Scene, in collaboration with Combustion
Engineering, U.S.A. These modern large capacity steam generators are
designed to burn a variety of fuels and are expected to operate at divergent
complex conditions. Generally , any boiler furnace burning any or all types of
fuels is susceptible to explosion or implosion resulting in extensive damage to
equipment and or personnel. History of Boiler operation reveals that most ofo the
furnace explosions occur during start-up/shut down. Some of the attributable
causes are:i)
ii)
iii)
iv)
v)
Operation of large capacity boilers therefore demands very safe & reliable
operating procedures. Regardless of how alert the of operators are, mistakes
often happen. Under some circumstances human response time is not quick
enough to prevent accidents. Since elements controlled are large in numbers
and complex in nature, human element is gradually substituted by automatic
features in Burner Management and control systems for such boilers.
Furnace Safeguard Supervisory System or FSSS introduced by BHEL in
their boilers is one such system and is designed to ensure the execution of a
safe and ordely operating sequence during strart-up and shut-down of the
complex fuel firing equipment with minimum operator intervention.
TANGENTIAL FIRING:
The furnice deasign of such boilers is based on the tangential firing concept.
In a tangential fired furnace, the air and fossil fuels such as pulverized coal,
ii)
iii)
iv)
v)
vi)
Flame scanning.
vii)
i)
System Cabinet:
The most complex part is the system cabinet which is usually located in
the control equipment room. This cabinet houses the system logic and is
responsible for processing of all incoming signals/commands/feed-back
and issue output command for field devices through interposing relays.
This system also interface, secondary air-control sub-system and other
boiler automatic control loops.
ii)
iii)
Field Devices:
The field devices form the rest of the system and consists of local or boiler
front hardware such as pilot ignitors, fuel valves, positioning devices,
pressure switches & flame scanners. Almost all these devices provide
status signal and receive command signals from the system logic cabinet.
The system is functionally checked out and fully similated in the factory
before shipment to site.
commands. It also takes care of the safety/ protection functions of the corner and
issues the corner trip commands.
SECTION 2
Digital Hardware:
Back ground:
Relay based FSSS is in use in the power station for quite some time now. The
components used in implementing the relay logic include control contactors, latch
relays, Electro-pneumatic timers for On/Off delays, etc.
For maximisng availability, two reliable control supplies are used in the system
namely 110VAC and 220VDC. The DC supply is taken from station battery while
the AC supply is derived from dual source with a back-up feeder and changeover
panel or from UPS.
In case of loss of AC power the trip functions are achieved by the DC logic
whereby an oil trip valve or pulveriser is tripped by the DC power. In case of
failure of the DC source, the trip functions are achieved by closing the corner
nozzle valves, feeders and hot air gates which operate on 110V AC.
With the emergence of solid state semi-conductor technology and the availability
of high reliability components the system logic functions could easily be realized
using solid state technology ensuring improvement with increased unit
availability, low maintenance cost.
Apart from these advantages the solid state equipment offered size reduction,
lower power consumption, use of lower operating voltages etc. facilities such as
improvement in man-machine communication, a systematic fault annunciation
philosophym hierarchical and decentralized structuring of the control system
contribute greatly to improved automation which has become a necessity in more
complex control system being used now-a-days.
DEVELOPMENT OF HARDWARE:
Keeping in view the above advantages of the solid state system BHEL developed
a hardware family of cards called CEMODIC for digital logic control application.
This comprises of a family of printed circuit ** for Binary control in power plant
through which FSSS system is being realised.
BHEL introduced the hardware for FSSS system for Thermal Power Stations and
some are already in operation. At the component level CMOS was chosen as the
basic technology for integrated circuits. This was done as this technology was
then well proven and used in industrial systems. It offers well know advantages
b)
c)
Field devices being located in the most noiseprone areas of the plant,
these inputs are provided with surge suppressor elements for
protection against voltage transients, conforming to relevant
International Standards.
partitioning of the system is strictly maintained. For each drive or valve in the
system a drive control module has been assigned which would issue open/close
command to the drive, monitor its field status and ammunciate the same on
operators console. The protection command to the drive control module assumes
highest priority.
The partitioning of the system is maintained by using different set of modules for
each corner control, elevation control, etc. the modules for control of various
elevations are mounted in separate cubicle sections. In these cubicles, the
modules controlling each corner are housed in separate racks. The drive control
modules for the elevations are mounted on the lowest racks.
The elevation control logic is built using the group control and general purpose
logic modules. The unit is also built using the general purpose logic modules.
The output commands to the field drives are issued through the interposing
relays mounted in the respective elevation cubicles.
POWER SUPPLY:
The system operates on + 24V DC. The 24V DC power supply to the system is
derived from two battery backed power supply sources. Each battery is sized to
cater the full load current for a period of appx. 30- minutes after a loss of power.
One feeder from each of the sources is brought to the FSSS panel and
subsequently taken to the distribution module in each elevation. In the
distribution modules these power supplies are monitored for over / under voltage
& then diode tioneered to form the elevation supply bus. Zeners are mounted on
the supply buses to arrest the switching transients.
FAULT ANNUNCIATION SYSTEM:
The fault annunciation philosophy is built so as to simplify the locatiosation of
fault in the system.
In case of fault in the system the following annunciations are available which
enable the operator to easily identify of the type of fault.
a)
b)
c)
A LED on the Buffer module in top rack glows indicating the type of
fault.
d)
Another LED on the front plate of the drive control/input module glows
identifying the drive where the fault has occurred.
SYSTEM ARCHITECTURE:
To meet very stringent reliability and very high availability criteria of a furnace
protection system, a highly effective fault tolerant system architecture is
necessary. Further FSSS being a hierarchically distributed system the
decentralized structure should also be reflected in the control system
architecture.
service conditions 2 probes are continuously giving reference and third one
comes into service when one of the two fails.
LOAD REFERENCE:
Beyond 20% of the load, load reference comes into service. For this load
controller has to be switched on. When the machine is on load, load reference
comes into service For this load controller has to be switched on when the
machine is on load, load reference is more accurate than speed reference. Load
limiter is also available. By selecting the set point on load limiter, the load is
controlled in that limit.
FREQUENCY REFERENCE:
With this the load will get varied to maintain the frequency constant. In our
country it is very difficult to operate in this mode. Hence it is not put in operation.
REFERENCE SET POINT (SPEED / LOAD) BLOCK:
This occurs at various conditions. It blocks the status of turbine for further raising
of speed / load due to the following conditions.
1)
2)
3)
4)
70.5 RPS
64.3 RPS
80.3 RPS
EXAMPLE OF SGC
02
WAITING
TIME
MONITERING
TIME
COMMAND
&
03
WAITING
TIME
MONITERING
TIME
- OR GATE
&
AND GATE.
NUMERICAL
SYMBOL
MA
Mk
MY
MAAA MAB MAC MAD MAW MAL MAG MAN MAV MAX MAJ LB
LBA LBB LBC LBW -
Heat In change
C
D
G
CP
CT
CT
CY
CL
Measuring instruments
Close loop control
circuts
Processing of Measured
Values.
Electrical Equipment
Pressure Measurements
Temperature Measure monts.
Position Measurements
Vibration, Expansion
Measurements
Level Measurements
CCA 1
2
3
4
5
CCJ
1
2
3
4
5
8
10
11
12
START UP OF TURBINE:
PREPATION
START UP
OIL SYSTEM ESTABLISHED
OPERATION
BARRING GEAR OPERATION
SHUT DOWN
TURBINE PROTECTIONS CHECKED
STAND STILL
TURBINE PROTECTIONS:
1)
2)
3)
4)
5)
CHEMICAL ANALYSIS OF
STEAM PURITY
6)
7)
8)
9)
10)
11)
12)
13)
PRE PARATION:
LINE CLEARS RETURNED
POWER SUPPLY READY
INSTRUMENTS? RECORDS, DAS,AIR CONDN OF UCB ON
DM PLANT GENERATION ON
COMPRESSORS ON SERVICE
OIL PLANT ON OPERATION
HYDROGEN PLANT ON OPERATION H2, Co2 CYLINDERS
CIRCULATING WATER SYSTEM COOLING TOWER,-IN
OPERATION
DRG COOLING WATER SYSTEM IN OPERATION
LEVEL INDEAERATOR - OK
ELECTRICAL ACTUATORS OPERATION CHECKED
LEVEL IN BOILER DRUM - OK
LEVEL IN HOTWELL- OK
LEVEL IN MAIN OIL TANK -OK
PROTECTIONS OF BFPS, CEP,S CHECKED, IR
VALUES OF ALL H.T. MOTORS CHECKED
AOP
AOP
EOP
AOP
AOP
EOP
STEP 2:
1
2
1
2
OFF
ON
OFF
ON
OFF
OFF
CHECK 2
STEP 1:
SLC
SLC
SLC
AOP
AOP
EOP
AOP
AOP
EOP
STEP 2:
1
2
1
2
ON
OFF
OFF
OFF
ON
OFF
CHECK 3
STEP 1:
SLC
SLC
SLC
AOP
SOP
EOP
AOP
AOP
EOP
STEP 2:
1
2
1
2
OFF
OFF
ON
ON
OFF
OFF
CHECK 4
STEP 1:
SLC
SLC
SLC
JOP
JOP
JOP
JOP
1
2
1
1
OFF
ON
ON
OFF
STEP 2:
Switch off JOP 1
Result:
JOP 2 Comes in auto.
VACUUM SYSTEM:
CHECK CONDENSER ON SPRING SUPPORTS WITHOUT PROPS
CIRCULATING WATER SYSTEM CHARGED
CONDENSATE PUMP ON SERVICE IN RE CIRCULATION
THROUGH GSC
TURBINE ON TURNING GEAR
DRAIN OPERATION:
VACUM ACHIEVED
MS, HRH STARINER DRAINS OPEN
AUTOMATIC CONTROL
INTERFACE IN AUTO
DUMPING OPERATION
STEAM PURITY OK
DRAINS AFTER EXTN NRVS
2,3,4,5,6 OPEN
ROLLING STARTS
SYNCHRONISING
CHARGING OF LP & HP
HEATERS
**
CCA 1
2
3
4
5
CCJ 1
2
3
4
5
8
10
11
12
START UP OF TURBINE
****
MICRO PROCESSOR BASED PASS
1.1
SYSTEM DESCRIPTION
The proposed FSSS is foro a 210MW Boiler with six coal and three oil
elevations. The system design is based on BBCs control philosophy using
procontrol P system hardware. The system has a decentralized
hierarchical structure. The proposed configuration is for a functionally
distributed but geographically centralized system. All the electronic
modules of the control system for the FASS will be housed in panels
placed in the control room.
1.3
1.4
1.5
The sequencing and interlocking of the elevation start / stop is done by the
programmable processor modules (70PR03) mounted on the local bus.
These processor modules commnicate exclusively via the local bus. They
receive the status information and process them in accordance with
instructions, preprogrammed in the non-volatile memory of the module
and transmit results via the local bus.
1.6
PROTECTION
As mentioned earlier the protection functions of the individual drives are
taken care by the respective drive control modules. Additionally protection
signals of the important drives i.e. nozzle valves, pulverisers would also be
processed by the programmable processor module (70PR03) on the same
local bus and trip command issued through the output modules. This trip
command would be in parallel to the command issued by the drive control
module. This further enhances the safety of the boiler.
1.7
INTRAPLANT BUS
The status of drives in the local buses for various elevations are
communicated to the local buses for unit trips purge etc via the intra plant
bus. Similarly, the permissive condition / trip conditions are communicated
from the local bus for unit trip / purge to the local bus for various
elevations via the intraplant bus.
Two entirely independent intra plant bus system are used for transmission
of redundant signals from the local buses. The two intra plant bus systems
are physically and electrically independent. The transmission sequences
on the intraplant bus are controlled by the address transmitter, and the
transmission takes place through co-axial cable. Two nos of address
transmitters are installed on each intraplant bus in a redundant mode. The
various measures taken to ensure transmission reliability on the intraplant
bus like time tolerance, parity bits, cyclic transmission etc together with the
bus redundancy ensure the total system integrity for boiler protection.
1.8
1.9
2.0
DIAGNOSTIC STATION
The diagnostic station with CRT and keyboard provides a window to the
whole process. It is the central working station for the dialogue with the
entire control and monitoring system. This station is capable of modular
expansion and performs the following functions:
- Continuous
Indication and logging of the system hardware alarms in clear text. The
failure of any drive control, input module field cable short circuit etc is
alarmed on the diagnostic station.
- On request
Indication / logging of local bus signals
Indication / logging of internal operational values.
Indication / logging of marshelling links in the local bus / intraplant bus
couplers.
Optimising of control loops (remote setting control parameters)
Print out of programme contents of programmable modules.
Hence in case of failure of any start / stop sequence it is possible to get a
display of various field input criterions, processor status etc on the
diagnostic station and localize the faulty field component. A printer can be
connected to the diagnostic station for getting a hard copy.
2.1
3.
SME 0 =
Station failure
Interconnection of all SME outputs from central modules (e.g
bus traffic director, power supply) which shut down an entire
station in the event of a disturbance.
SME 1 =
SME 2 =
SME 3 =
SME 1 =
SMS
Simulation
Inter connection of all SME outputs from all modules etc. In
addition to activation of the annunciation output the
disturbances detected also have an influence on the function
of the module concerned depending on the type of
disturbance.
4.
POWER SUPPLY
The power supply required for the operation of the procontrol P system is
24V DC with a permissible voltage variation from 22.5 to 30V DC. The
standard practice for procontrol system envisages 2 battery backed power
sources. The 2 feeders are diode auctioneered in the supply distribution
modules placed in various cubicles. These distribution modules further
feed the local buses placed within the cubicles.