Project Charter
Project Overview
Scope of work
TimeLine
Budget Information
Project important stakeholders and Organization
Assumptions
Risk Analysis
Project Plan
Task schedule
Resource Plan
Calculate the budget plan and cash flow
Project Charter
1. Project Overview
1.1 Business Background
Nowadays, more and more people use mobile phone instead of
computer to scan the web page, and if we use web to check
information, its easy to find that the font is too small and the operation
is inconvenient. So, we can build a mobile app to simplify the previous
web page and make the main information more clearly. In addition, this
mobile app can improve the opening speed compared with inputting
address of a web page. Users can use MyCUHK system much easier and
faster.
1.2 Objective
Develop a new mobile app of MyCUHK to help students and teachers in
CUHK search the most important links based on the web page of
MyCUHK more easily and effectively. The app will include several
templates and tools that users can check out class schedule, webmail,
workshop, complete course enrollment, and a new template of users
feedback, where users can post suggestions about our app from user
experience. The app will be accessible free to the public.
2. Scope of work
Business case
Charter
scope statement
WBS
Schedule
budget plan
progress reports
final project presentation
any other documents
required to manage the
project.
Payment
function
Library,
elearning
Remaining
functions in
MyCUHK
3. TimeLine
Project start Date: Oct 9, 2014
Project end Date: Dec 24, 2014
Detailed timeline refer to project plan.
4. Budget Information
The budget consists of Salary, hardware and software. Details
list refer to project plan.
5.1 Project
Manager
5.2 Project
Sponsor
Zheng Huahua
Because he has years of
working experience in
leading various of
projects and teams.
CUHK Board
will be responsible for
the permission and
other policy issues. It
will also help to notify
the APP team if any
MyCUHK server
changes that might
impact MyCUHK Lite
for further actions.
5.3 Organization
Its a function project
chat. Project manager
has the full permission
in the team.
6. Assumptions
Risk Analysis
Risk
1. Security concern for real name login
2. Development mistakes resulting in
developing wrong software functions
4. Development
estimation
effort
under
Risk Analysis
Risk
6. MyCUHK server side changed the
interface without notifying the APP
team in future maintenance.
8. Platform/Technology/Language
migration impact to existing usage
Project Plan
1. Task Schedule
Project Plan
1. Task Schedule
More details for network diagram refer to MyCUHK Lite.mpp
Project Plan
2. Resource Plan
Project Plan
3. Calculate the budget plan and cash flow
And the overall cost is 150004
Project Plan
3. Calculate the budget plan and cash flow
And the overall cost is 150004