Beruflich Dokumente
Kultur Dokumente
2305
ACCEPTANCE TESTING
of Digital Control Systems for
HV Substations
1.Introduction
The first industrial applications of
Digital Control Systems (DCS) in HV substations go back to the eighties. Since then,
the number of DCS in service grows each
year.
On the one hand the functions implemented up to now in these new control systems differ little from conventional systems,
and on the other hand, the processing and
the exchange of data within the DCS totally
differ from conventional systems : each processor in a DCS does the job of several independent and dedicated units in a conventional system, serial links replace classic
wiring, signals from the switchyard are
acquired once and put at the disposal of the
different processors via serial links instead
of being acquired in each of the dedicated
units. The difference also applies to the way
the systems are tested both during factory
tests and on-site.
Due to the integration of functions in
the DCS, the issue of availability of the DCS
is of a particular importance. As an example, we can consider switchyard control. We
usually distinguish three command levels:
bay level, substation level and remote control centre level. In a conventional system,
these three levels are independent. In a
DCS, depending on the selected architecture for the DCS, the same equipment handles the substation level and the interface
for the remote control centre.
This means that the loss of one equipment could result in the loss of these two
levels. This issue has to be studied during engineering and, to confirm system
23 05
L. UYTTERSPROT (Belgium)
L. GRAINE (France)
W. DIETERLE (Germany)
H. NOGUCHI (Japan)
R. JEANNOT (France)
H. TIMMERMAN (The Netherlands)
G. SCANU (Italy)
C O N T I N U E D
W O R K I N G G R O U P 2305
23 05
Alstom (France)
5. Digital Control
System - Test Procedure
Software evolution
general purpose software (e.g.
UNIX, Windows)
firmware (programming functions implemented by the Manufacturer )
application software (programming functions implemented by
the Manufacturer or the User).
Modification, addition of a data
(database/ wiring)
cover all the test items except the limited ones that can be executed at site
only. This means that except the combination test with site equipment all the
test items shall be executed at factory.
Concerning priority of test items, basic
functions shall be confirmed first, for
example, telecontrol and local control
come first, and are followed by supporting systems. See table 1 which gives
a list of test items.
5.3.2 Test specification and environment
Preparing test specification
It is essential for both user and
manufacturer to jointly thoroughly
check test items and test procedures
in order to avoid omissions and to
clear misunderstandings.
Test items shall be determined so
as to cover entirely the engineering
specifications.
Each test item shall be documented with its purpose, the checking method, the assessment criteria and the density of recursiveness,
e.g. characteristic data collection
under different application modes
and status of operation.
Test specification shall be checked before issue by the different
engineering teams : software, hardware, design, etc.
C O N T I N U E D
Test environment
To create a test environment for the
DCS as close as possible to the real substation, it is preferable to assemble operator console, mimic board and telecontrol
equipment at the factory even if they are
under separate contracts. If this is not possible, for the telecontrol equipment for
example, we recommend to use a simulator instead.
System configuration, equipment and
tools which will be used for the acceptance
test are specified.
5.3.3.Organisation
Test execution and test management
organisations are described in a document
mentioning the distribution of the work
between user and manufacturer, the person who is responsible for the factory
acceptance tests and the person from the
users side who has authority for approval.
5.3.4 Schedule
It is necessary to consider the following critical periods in the schedule :
Possible periods for data amendments and software changes that may be
requested by the user.
Possible periods for software
improvements following faults detected
during the tests.
Periods for analysis and assessment
of the acceptance tests.
5.3.5 Test process and review
Tests shall be executed by using adequate tools to verify elementary and compound functions in short period efficiently. Continuous working tests,
combined tests and tests outside normal
internal data version, system configuration, swap file area and process priority,
etc.
23 05
W O R K I N G G R O U P 2305
5.4.1 Organisation
The responsibility of the project leader
concerns the test document, the organisation of the test team, the execution of the
tests and the transfer of the tested system
to the user. The test team includes experts
in DCS, in protections, in primary equipment, in telecontrol. This test team may if
needed be strengthened with experts from
the manufacturer, depending on the test
teams expertise and on the results of factory acceptance test. Another possibility is
to call the manufacturer for particular
tests. The test team execute the tests
according to the test document.
5.4.2 Test procedure and environment
The tests are executed on site, i.e. in
the substation. The test procedure depends
on the status of the substation. In case of
a replacement of an existing control system, the switching of the primary equipment will be subject to authorisation by
the grid operator. Similarly, precautions
must be taken when executing tests involving telecontrol.
23 05
The team executes the tests according to the test document, and tests results
are recorded in a test file. Faults have to be
repaired as soon as possible and the items
tested again.
When all items are successfully tested,
the user will take over the new installation
and put it in service. This last step concludes the work of the test team.
W O R K I N G G R O U P 2305
C O N T I N U E D
C O N T I N U E D
6. Implications on test
equipment
Having seen what tests to do in different cases factory and site acceptance
tests, new DCS or modification of an existing DCS we can now analyse the required
test equipment.
The following questions will help us
to select the most appropriate test equipment for each application.
Some answers depend on the experience of the user with DCS, others on the
terms of the contract between the user and
the Manufacturer.
Question no. 1 :
Test at substation level or at bay level?
This choice determines the size of the
simulator because the number of
Inputs/Outputs of the simulator is proportional to the number of bays. Technically, tests at the substation level are better
than tests at the bay level because the DCS
will be tested in working conditions similar to the reality. This is particularly important for avalanche testing (representing
enormous status changes) and for testing
functions common to several bays, for
example interlocking, automatism Also,
the cost, the size, the complexity of connecting the simulator increases proportionally to the number of Inputs/Outputs.
The problems related to configuration of
the simulator to make it consistent with the
H.V. installation must not be overlooked.
These different drawbacks have resulted in
substation simulators not being used much
in the case of conventional control systems.
23 05
DCS, where, depending on the local possibilities, some control tests can be
repeated.
In case of activation of an existing
function from the software library, we can
start from the hypothesis that the function
has already been tested during the factory
acceptance tests or, at least that the manufacturer has completely tested the function on a similar DCS. It results that complete tests on a reference DCS are no
longer necessary and the new function can
be directly implemented in the real DCS,
for which only some control tests are
needed. The same reasoning applies to the
modification of the configuration of an
existing function.
W O R K I N G G R O U P 2305
Question n 2 :
Simulation of the primary equipment
or only reading and imposing inputs/outputs? This choice determines the functionality included in the simulator. In the
second case - reading and imposing
inputs/outputs - there is no functionality
in the simulator. The simulation of the primary equipment requires functionality
such as switch on and switch off with corresponding feedback signals and realistic
response time, energy monitoring, simulation of abnormalities
Question n 3 :
Necessity of sophisticated tests like
measurement of response time of the
DCS, simulation of a high quantity of
events, ?
This choice may influence the technology used to build the simulator : it is
easier to generate an avalanche test with
a digital simulator than with a relay based
simulator.
Question n 4 :
What do we test? (See figure 1)
DCS only
DCS and remote control
all secondary equipment in the substation (except protection relay, auxiliaries)
W O R K I N G G R O U P 2305
C O N T I N U E D
Consequences
Place where to connect
Functionality to include
the simulator
in the simulator
What do we test ?
DCS only
via connectors in replacement of
the links with the bay
via test cards in the DCS
Simulation of
primary equipment
secondary equipment installed
between DCS and primary equipment
Or only reading outputs and
imposing inputs
7. Conclusions
We recommend to analyse carefully
the problem of overall testing of DCS from
the very start of engineering because it has
impacts on engineering, on test equipment, on project planning, on the terms
of the contract between the Manufacturer
and the user.
It was not possible to advise a universal method for testing DCS. The reasons
are numerous : different DCS architectures, differences in scope - how much is
done by the manufacturer and how much
by the user, different cases - new DCS in
a new substation, new DCS in an existing substation, extension of existing DCS,
software evolution, etc. We hope the
Reader will find in this paper enough ideas
for his own application.
We can emphasise some significant
points raised:
Importance of a test document describing test specifications, test organisation, test procedure, test schedule.
Importance testing all functions,
including those that will be used only later,
all spare bays. This will make easier the test
when it will be necessary to put in service
a new function or a spare bay.
The need in some cases to have a reference DCS same hardware, same software
as the real DCS for test purpose.According
to the case, this reference DCS will be run by
the manufacturer or by the user.
8. References
[1] P. Assailly, A. La Rocca, H. Adam,
Y. Bonnardot : Procedure for the design,
manufacture and commissioning of H.V.
and E.H.V substation control systems within
EDF (CIGRE 1992 Report 23-201).
Remote Control
23 05
DCS only
Remote control
center
DCS
Central Unit
Substation level
Protections
Bay computer
Bay
level
Other
functions
outside
DCS
Control &
Protection
Cubicle
H.V. switchgear
FIGURE 1