Federal Register / Vol. 73, No.

76 / Friday, April 18, 2008 / Notices 21121

before the BoV shall be in accordance biological, physical, and cultural through President Roads to the Reserved
with 41 CFR 102–3.140(c), section environments. This decision Channel would be deepened to 48 feet
10(a)(3) of the FACA, and this incorporates analyses contained in the and its 600-foot-wide reaches widened
paragraph. The DFO and BoV FEIS, comments provided during formal to between 800 and 900 feet, with
Chairperson may, if desired, allot a public comment and review periods, additional width in the bends. The 40-
specific amount of time for members of and an evaluation of the ability of each foot lower reach of Reserved Channel
the public to present their issues for alternative to meet the Purpose and and its turning area would be deepened
BoV review and discussion. Direct Need for the Proposed Action. Hawaii to 48 feet, with the turning area also
questioning of BoV members or meeting was selected primarily because it is best widened to 1600 feet. The 40-foot
participants by the public is not able to meet the Army’s strategic President Roads Anchorage would be
permitted except with the approval of defense and national security needs in deepened to 48 feet. The second
the DFO and Chairperson. the Pacific Theater. A fuller rationale for improvement would deepen the existing
FOR FURTHER INFORMATION CONTACT: Or the decision can be found in the Record 40-foot lane of the Main Ship Channel
to attend this BoV meeting, contact Mr. of Decision. from the Reserved Channel Turning
Scotty Ashley, USAFA Programs Dated: April 11, 2008. Area upstream to just below the Third
Manager, Directorate of Airman Addison D. Davis, IV, Harbor Tunnel to a depth of 45 feet, to
Development and Sustainment, Deputy improve access to the Massport Marine
Deputy Assistant Secretary of the Army
Chief of Staff, Manpower and Personnel, (Environment, Safety, and Occupational Terminal in South Boston. The third
AF/A1DOA, 1040 Air Force Pentagon, Health). improvement would deepen a portion of
Washington, DC 20330–1040, (703) 695– [FR Doc. E8–8296 Filed 4–17–08; 8:45 am] the 35-foot Mystic River Channel lane to
3594. 40 feet to improve access to Massport’s
BILLING CODE 3710–08–M
Medford Street Terminal. The fourth
Bao-Anh Trinh, and final improvement would deepen
Air Force Federal Register Liaison Officer. the 38-foot Chelsea River Channel to 40
DEPARTMENT OF DEFENSE
[FR Doc. E8–8372 Filed 4–17–08; 8:45 am] feet, with minor widening in the bridge
BILLING CODE 5001–05–P Department of the Army; Corps of approaches and the bend between the
Engineers bridges. In conjunction with work in the
Federal channels, the Massachusetts
DEPARTMENT OF DEFENSE Availability of the Draft Feasibility Port Authority would deepen vessel
Report and Supplemental berths at the Conley Terminal and
Department of the Army Environmental Impact Statement and Marine Terminal. Terminals on the
Draft State Environmental Impact Chelsea River would also deepen their
Availability of the Record of Decision
Report for the Boston Harbor Deep berths to match the new channel depth.
(ROD) for the Permanent Stationing of
Draft Navigation Improvement Project A total of about 12.1 million cubic yards
the 2/25th Stryker Brigade Combat
Team (SBCT) AGENCY: Department of the Army, U.S. (cy) of parent material, and 1.2 million
Army Corps of Engineers, DOD. cy of rock, would be removed by
AGENCY: Department of the Army, DoD. dredging and placed at the
ACTION: Notice of availability.
ACTION: Notice of availability. Massachusetts Bay Disposal Site
SUMMARY: The U.S. Army Corps of (MBDS). Beneficial use opportunities for
SUMMARY: The Deputy Chief of Staff of the dredged material have been
Engineers, New England District in
the Army, G–3/5/7 has reviewed the identified and would be considered
partnership with the Massachusetts Port
Final Environmental Impact Statement further during final design of the
Authority (Massport) has prepared a
(FEIS) for the Permanent Stationing of project. Those beneficial use
joint Draft Supplemental Environmental
the 2/25th SBCT and has made the opportunities include: creation of rock
Impact Statement and State Draft
decision to proceed with all facets of reefs in Massachusetts Bay and Broad
Environmental Impact Report (DSEIS/
Alternative A. Alternative A Sound, and using the non-rock material
DEIR) examining improvements to deep-
permanently stations the 2/25th SBCT at as cover at the former Industrial Waste
draft navigation channels in Boston
Schofield Barracks Military Reservation Site, which overlaps the MBDS. This
Harbor, Boston, MA. Four separate
(SBMR) while conducting the required joint Federal and State document builds
improvements were developed. The first
training at military training sites in on the lessons learned from the final
examined deepening the outer and
Hawaii. This alternative is summarized EIR/S prepared in June of 1995 for the
lower harbor’s existing 40-foot channel
in the Army’s ROD and described fully previous navigation improvement
system to provide deeper access to
in Chapter 2 of the FEIS. project in Boston Harbor.
Massport’s Conley Terminal in South
ADDRESSES: The ROD can be accessed at Boston for containership traffic. All DATES: Submit comments on or before
http://www.aec.army.mil. depths are referenced to minus mean June 2, 2008.
FOR FURTHER INFORMATION CONTACT: lower low water (MLLW). Navigation ADDRESSES: Comments should be
Public Affairs Office, U.S. Army channel depths of between 45 to 50 feet
Environmental Command, Building submitted to Colonel Curtis L. Thalken,
were examined, with a depth of 48 feet District Engineer, U.S. Army Corps of
E4460, 5179 Hoadley Road, Attention: recommended, with an additional two
IMAE–PA, Aberdeen Proving Ground, Engineers, New England District, 696
feet in the entrance channel. Under this Virginia Road, Concord, MA 01742.
MD 21010–5401; telephone: 410–436– plan the following project features
2556; facsimile: (410) 436–1693. The would be improved: the 40-foot lane of FOR FURTHER INFORMATION CONTACT: Ms.
Public Affairs Office is open during the Broad Sound North Entrance Catherine Rogers, (978) 318–8231.
pwalker on PROD1PC71 with NOTICES

normal business hours Monday through Channel would be deepened to 50 feet SUPPLEMENTARY INFORMATION: The U.S.
Friday 9 a.m. to 5 p.m. Eastern time. and widened through the bend at Finn’s Army Corps of Engineers is authorized
SUPPLEMENTARY INFORMATION: The FEIS Ledge. The 40-foot lane of the Main to conduct this Feasibility Study by a
assessed the potential environmental Ship Channel from the Broad Sound Senate Subcommittee on Public Works
consequences of the alternatives on the North Entrance Channel upstream Resolution dated September 11, 1969.

VerDate Aug<31>2005 17:38 Apr 17, 2008 Jkt 214001 PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 E:\FR\FM\18APN1.SGM 18APN1
21122 Federal Register / Vol. 73, No. 76 / Friday, April 18, 2008 / Notices

The DSEIS/DEIR is available on-line of carryover storage at San Vicente and DEPARTMENT OF DEFENSE
on the New England District’s Web page 50,000 acre-feet of carryover storage at
at http://www.nae.usace.army.mil/ Moosa Canyon) and the No Action Department of the Navy
projects/ma/BHNIP/ Alternative, as required by NEPA. As
BostonHarbor_draft_FeasibilitySEIS.zip Notice of Availability of Finding
the project proponent and applicant, the
and at the following local libraries: Water Authority selected Alternative 1 AGENCY: Department of the Navy, DoD.
Boston Libraries—25 Parameter Street, as its preferred alternative. The ACTION: Notice.
20 City Hall Avenue, 18 Barnes Avenue, proposed CSP requires authorization
666 Boylston Street, Boston City Hall, pursuant to section 404 of the Clean SUMMARY: Pursuant to Section 102(2)(C)
179 Main Street, 646 West Broadway, Water Act for approximately 0.34 acre of of the National Environmental Policy
276 Meridan Street; Chelsea Library— fill placement in jurisdictional waters of Act (NEPA) of 1969 and the Council on
569 Broadway; Revere Library—179 the United States, including wetlands, Environmental Quality regulations (40
Beach Street; and the Winthrop CFR parts 1500–1508), implementing
to construct an expansion of the existing
Library—2 Metcalf Square. If you wish procedural provisions of NEPA, and
San Vicente Dam to store approximately
to receive a copy of the Executive Executive Order (EO) 12114,
Summary or an electronic copy of the 100,000 acre-feet of carryover storage
Environmental Effects Abroad of Major
DSEIS/DEIR, please contact Ms. water.
Federal Actions, the Department of the
Catherine Rogers, Ecologist, U.S. Army FOR FURTHER INFORMATION CONTACT: Navy (DON) gives notice that a
Corps of Engineers, New England Questions or comments concerning the combined Finding of No Significant
District, Evaluation Branch, 696 Virginia Final EIR/EIS should be directed to Mr. Impact (FONSI)/Finding of No
Road, Concord, MA 01742. Robert R. Smith, Jr., Regulatory Project Significant Harm (FONSH) has been
A public meeting to solicit comments issued and is available for Carrier Strike
has been scheduled for 1 p.m. on Manager/Team Leader San Diego Field
Office, U.S. Army Corps of Engineers, Group Composite Training Unit
Tuesday, May 20, 2008, on the second Exercise (CSG COMPTUEX) April/May
floor of the Black Falcon Cruise Los Angeles District, 16885 W. Bernardo
2008.
Terminal, One Black Falcon Avenue, Drive, Suite 300A, San Diego, CA 92127,
Boston, MA. (858) 674–6784. Alternatively, DATES: The effective date of the finding
comments can be submitted is April 14, 2008.
Dated: April 8, 2008.
electronically to: ADDRESSES: Electronic copies of the
Curtis L. Thalken, combined FONSI/FONSH are available
robert.r.smith@usace.army.mil.
Colonel, Corps of Engineers, New England for public viewing or downloading at
District. SUPPLEMENTARY INFORMATION: Paper http://www.navydocuments.com.
[FR Doc. E8–8202 Filed 4–17–08; 8:45 am] copies of the Final EIR/EIS will be made FOR FURTHER INFORMATION CONTACT:
BILLING CODE 3710–24–P available to the public for review at the Commander, Second Fleet Public
following: the San Diego County Water Affairs, Commander Phillips, telephone:
Authority offices at 4677 Overland 757–443–9822 or visit http://
DEPARTMENT OF DEFENSE Avenue, San Diego, CA 92123; the www.navydocuments.com.
Department of the Army, Corps of Lakeside Public Library, 9839 Vine
SUPPLEMENTARY INFORMATION: CSG
Engineers Street, Lakeside, CA 92040; and the
COMPTUEX (April–May 2008) is a
Valley Center Public Library, 29200 major Navy Atlantic Fleet training
Notice of Availability for the Final Cole Grade Road, Valley Center, CA exercise proposed to occur in April and
Environmental Impact Report/ 92082. A CD copy of the document may May 2008 in the offshore Jacksonville
Environmental Impact Statement for be obtained by contacting Ms. Kelley Operating Area (OPAREA) and adjacent
the Carryover Storage and San Vicente Gage at the San Diego County Water military installations. The purpose of
Dam Raise Project (CSP), San Diego Authority at the address above, or by e- this exercise is to certify naval forces as
County, CA mailing Ms. Gage at kgage@sdcwa.org. A combat-ready. Activities conducted
AGENCY: Department of the Army, U.S. copy of the Final EIR/EIS is also during the exercise include air-to-
Army Corps of Engineers, DoD. available online at the Water Authority’s ground (ATG) bombing at land ranges,
ACTION: Notice of availability.
Web site: http://www.sdcwa.org/. Combat Search and Rescue (CSAR),
Interested parties are invited to provide Maritime Interdiction Operations (MIO),
SUMMARY: Pursuant to section 102(2)(c) their comments on the Final EIR/EIS, Naval Gunfire, Fast Attack Craft/Fast
of the National Environmental Policy which will become a part of the official Inshore Attack Craft (FAC/FIAC), and
Act (NEPA) of 1969 (as amended), the record and will be considered in the Anti-Submarine Warfare (ASW),
U.S. Army Corps of Engineers, Los final decision. Written comments must including use of mid-frequency active
Angeles District (Corps) Regulatory be received on or before May 19, 2008 (MFA) sonar.
Branch, in coordination with the San and should be submitted to the contact The FONSI is based on analysis
Diego County Water Authority (Water listed above. A Record of Decision contained in a Comprehensive
Authority), has completed a Final (ROD) will be issued by the Corps no Environmental Assessment (EA)
Environmental Impact Report/ earlier than 30 days after the Notice of addressing environmental impacts
Environmental Impact Statement (EIR/ Receipt for the Final EIR/EIS is associated with land-based training for
EIS) for the Carryover Storage and San published in the Federal Register. Major Atlantic Fleet Training Exercises
Vicente Dam Raise Project (CSP). Four on the East and Gulf Coasts of the U.S.
alternatives were co-equally analyzed in Dated: April 8, 2008. The FONSH is based on analysis
pwalker on PROD1PC71 with NOTICES

the EIR/EIS, including Alternative 1 Mark Durham, contained in a Comprehensive Overseas


(100,000 acre-feet of carryover storage at Acting Chief, Regulatory Branch. Environmental Assessment (OEA) and
San Vicente), Alternative 2 (100,000 [FR Doc. E8–8282 Filed 4–17–08; 8:45 am] Supplement to the Comprehensive OEA
acre-feet of carryover storage at Moosa (SOEA) for environmental impacts
BILLING CODE 3710–KF–P