Here are some major projects in Qatar. Some projects have already started, other on
the way. It is important to remind that date mentioned in the projects publication is
not always respected.
PEOPLE MOVER SYSTEM IN QATAR EDUCATION CITY
Client: Qatar Foundation
Consultant:
Contractor: Habtoor Leighton Group
Project Value: $124 Million
Project Duration: 3 years
Status: Execution
HLG has been awarded responsibility for the design and construction of Qatars
US$412 million People Mover System in Education City, which is one of the
countrys first rail projects.
HLGs scope of works, valued at US$124 million, incorporates the design and
construction of track-work, tram-stops and a depot facility, which includes
maintenance workshops and administration buildings. HLG is part of the Siemens
Tram Consortium with Siemens WLL Doha and Siemens AG from Germany.
The People Mover System is located in Dohas Education City. Being built for Qatar
Foundation for Education, Science and Community Development, and is intended to
reduce the flow of traffic within Education City, by allowing students to park their cars
in purpose-built multi-storey car parks and travel free of charge on a battery-powered
tram system to their destination within Education City.
LUSAIL DEVELOPMENT FOR PRIMARY INFRASTRUCTURE
Client: Lusail Real Estate Development Company (LREDC)
Consultant: QPM
Contractor: MIDMAC YUKSEL JV
Project Value:
Project Duration: 3 years
Status: Execution
The Project comprises of Engineering, Procurement, Construction and
Commissioning of major parts of Road A1, A6, D11 & A10 at Lusail with Junctions
12, 13, and 14, Wadi Underpass, Tunnels T1 & T2, Southern and Marina
Interchanges including Underpass, Bridges, Arch, and Tunnel. The total length of the
roads is 7.5 km. The scope of works include design and construction of a 4.6 km
deep storm water tunnel of 2.4-3 m diameter with 15 shafts. Utilities, irrigation,
electrical substations, road lighting, traffic signals, district cooling and gas distribution
are also in the scope.
MESSAEEID
Client: Qatar Petroleum
Consultant: Iberdrola
Contractor: Seattle Contracting Company
Project Value:
Project Duration:
Status: Execution
Prepared by Mounif Kilani, ECC Kuwait
Page 1/8
Page 2/8
Page 3/8
Page 4/8
Page 5/8
Page 6/8
Multiple Areas
Expressway Programme Projects
3,700,000,000 Q.R.
In progress
Roads
01 October 2011
Second quarter of 2017
QD/SBG Group
Design Consultant 1: Parsons International
Design Consultant 2: Dar Al Handasah
Parsons International
Page 7/8
Lusail Expressway
Area
Sector
Total Cost
Status
Type
Start Date
Expected completion date
Construction company
Consulting company
Supervision consultant:
Programme Manager:
Multiple Areas
Expressway Programme Projects
3,500,000,000 Q.R.
In progress
Roads
17 November 2012
Second quarter of 2017
Hyundai Engineering and Construction
Design Consultant: AECOM Middle East Ltd
CDM Smith
KBR
AlMuntazah Street
Area
Sector
Total Cost
Status
Type
Start Date
Expected completion date
Construction company
Consulting company
Supervision Consultant:
Multiple Areas
Expressway Programme Projects
2,300,000,000 Q.R.
In progress
Roads
01 July 2012
Fourth quarter of 2016
Al Jaber Transport & General Contracting LLC
Design Consultant: AECOM Middle East Ltd.
Parsons International