Beruflich Dokumente
Kultur Dokumente
2010
Machinery Team
Korean Register of Shipping
Preamble
The world's trade and traffic volume have been rapidly expanded over the last few decades
resulting in environmental damages caused by invasive species in ship's ballast water. The effects
in many areas have been reported that our ecosystem is being disturbed at an alarming rate. Since
the volume of sea-born trade continues to increase, the rate of bio-invasions is also expected to
continuously increase.
In 1988, Canada and Australia first reported on invasive marine species in ballast waters. In
response, IMO adopted, at its assembly in 1993, Res. A. 774(18 ) Guidelines for preventing the
introduction of unwanted aquatic organism and pathogens from ship's ballast water and sediments
discharges. After more than 14 years of complex negotiations between IMO Member States,
the International Convention for the Control and Management of Ships' Ballast Water and
sedimentss (BWM Convention) was adopted at the Diplomatic Conference held at IMO
Headquarters in London on 13 February 2004. This convention will enter into force 12 month
after the date on which not less than 30 states, the combined merchant fleets of which
constitute not less than 35% of the gross tonnage of the world's merchant shipping.
There have been many questions regarding the installation requirements of Ballast Water
Treatment System (BWTS) raised by ship owners and shipyards as the effective date of BWM
convention(2004) is approaching. In response, Korean Register of Shipping outlined reference
information for the selection/installation of BWTS by vessel type.
This interim guidelines is based on the discussions carried out so far and revised edition will be
issued should there be any additional requirements or unified representation set out by IMO or
IACS.
We hope this guidelines would help ship owners, shipyard and field surveyors and encourage
readers to provide advise and guidance for further improvement.
In order to avoid any potential damage to Korea Register, dissemination, distribution or copying of this document
is prohibited without prior permission from the publishing division.
Machinery Team
Table of Contents
Appendix
Machinery Team
The Ballast Water Treatment Convention 2004 (hereinafter the "BWM Conention") consists of a
Preamble, 24 Articles and an Annex which is made up of 24 regulations and 2 appendices. (Refer
to Table. I-1-A BWM Convention).
There are many complicated technical requirements and procedures to meet this convention
where different measures may be taken by different countries resulting in increased complication.
Hence, for the uniform implementation of the BWM convention, IMO set out 14 guidelines (Refer to
Table. I-1-B and Fig. I-1-A).
Of the 14 guidelines, the "Guidelines for Ballast Water Sampling (G2)", "Guidelines for Approval of
Ballast Water Management Systems (G8)", "Procedure for Approval of Ballast water Management
Systems that make use of Active Substances (G9)", "Guidelines for Approval and Oversight of
prototype Ballast Water Treatment Technology programmes (G10)", "Guidelines for Risk
Assessment under Regulation (G7)", "Guidelines on Designation of Areas for Balalst Water
Exchange (G14)" and "Guidelines for Additional Measures regarding Ballast Water Management
including Emergency Situation (G13)" are intended to governments, while the "Guidelines for
Ballast Water Management Equivalent Compliance (G3)", "Guidelines for Ballast Water
Management and Development of Ballast Water Management Plans (G4)", "Guidelines for Ballast
Water Exchange (G6)", "Guidelines for Ballast Water Exchange Design and Construction
Standards (G11)" and "Guidelines on Design and Construction to Facilitate sediments Control on
Ships (G12)" are intended to ship owners and shipyards.
Machinery Team
Article
Article 3 Application
Control of the Transfer of
Harmful Aquatic Organism
Article 4 and Pathogens Through
Ship's Ballast Water
sedimentss
sedimentss Reception
Article 5
Facilities
Article 6
Annex
Article 16
Article 17
Reg.
Reg.
Reg.
Reg.
Reg.
Article 21 Depositary
Article 22 Language
A-1
A-2
A-3
A-4
A-5
Definitions
General Applicability
Exeptions
Exemptions
Equivalent Compliance
Machinery Team
Organization
Section E - Survey and
Certification Requirements for
Ballast Water Management
Appendix
Machinery Team
MEPC Resolution
G1
Res.MEPC.152(55)
G2
Res.MEPC.173(58)
G3
G4
Guidelines
for
Ballast
Water
Management
Equivalent
Res.MEPC.123(53)
Compliance
Guidelines for Ballast Water Management and Development of
Res.MEPC.127(53)
Ballast Water Management Plans
G5
Res.MEPC.153(55)
G6
Res.MEPC.124(53)
G7
Res.MEPC.162(56)
G8
G9
G10
G11
G12
G13
G14
Guidelines
Exchange
on
Designation
of
Areas
for
Ballast
Water
Res.MEPC.151(55)
Machinery Team
MEPC Meetings
The guidelines for application of BWM Convention have been discussed and selected at
MEPC. In this chapter, the details of MEPC meetings as of 2010.12 will be briefly introduced.
2.1 MEPC 59(2009. 7) Meeting
2.1.1 Basic/final Approval Status of Ballast Water Systems that Make Use of Active
Substances.
1) Approval status as of MEPC 58 is listed in BWM.2/Circ.16(2008.10.17) and further
Basic/Final Approval for the sediments of active substances produced during ballast
water treatment will be issued as BWM.2/Circ.**.
Country
Manufacturer
Product
Approval
Korea
HHI
EcoBallast
Germany
Aquaworx
Aqua TriComb
China
COSCO
Korea
NK
NK-03 BlueBallast
Germany
RWO
CleanBallast
Japan
Hitachi
ClearBallast
Netherland
Greenship
Greenship Sedinox
Basic
Approval
Basic
Approval
Basic
Approval
Final
Approval
Final
Approval
Final
Approval
Final
Approval
Related
Document
Status
MEPC59/2/4
Approved
MEPC59/2/8
Approved
MEPC59/2/2
Approved
MEPC59/2/3
Approved
MEPC59/2
Approved
MEPC59/2/5
Approved
MEPC59/2/6
Approved
Machinery Team
not be beneficial to the implementation process and would not stimulate the
installation of new ballast water technologies on board ships, hence concluded that
no change to Assembly A.1005(25) was needed for those constructed in 2010.
2.2 MEPC 60(2010. 3) Meeting
2.2.1 GESAMP-BWWG provided basic approval for the following active substances and encouraged
manufacturers to apply for final approval.
Country
Manufacturer
Product
Korea
Panasia
GloEn-Patrol
Germany
Ecochlor
Ecochlor
Germany
Siemens
SiCURE
South
Africa
Resource Ballast
Tech.
Resource
Denmark
ATLAS-DANMARK
ATLAS-DANMARK
Japan
Toagosei
JEF
China
Sunrui CFCC
Sunrui
Denmark
DESMI
Ocean Guard
21st Century
Blue Ocean Guard
Shipbuilding Co.Ltd
Hyundai Heavy
HiBallast
Industries Co. Ltd.
Korea
Korea
1)
Approval
Final
Approval
Final
Approval
Basic
Approval
Final
Approval
Basic
Approval
Final
Approval
Basic
Approval
Basic
Approval
Basic
Approval
Basic
Approval
Basic
Approval
Basic
Approval
Related
Document
Status
MEPC59/2/7
Approved
MEPC59/2/9
Rejected
MEPC59/2/11
Approved
MEPC59/2/10
Approved
MEPC60/2
Rejected
MEPC60/2/2
Approved
MEPC60/2/3
Approved
MEPC60/2/4
Approved
MEPC60/2/5
Approved
MEPC60/2/6
Approved
MEPC60/2/7
Approved
MEPC60/2/8
Approved
Korea
En-Ballast
Norway
Qingdao Headway
OceanGuard
Germany
Severn Trent
DeNora
BalPure
Basic
Approval
MEPC60/2/9
Approved
Korea
Hyundai Heavy
Industries Co. Ltd.
EcoBallast1)
Final
Approval
MEPC60/2/1
Approved
: Not reviewed by the GESAMP-BWWG, however, it had been deemed to have met all the requirements
for final approval at MEPC 59 and therefore was advised to apply for final approval at MEPC 60.
Accordingly, this system received a final approval at this session.
Machinery Team
(2007.11). The committee encouraged its member states for the prompt ratification of
the BWM convention and installation of the ballast water treatment system before
entry into force of the convention
2.3 MEPC 61(2010. 9) Meeting
2.3.1 The GESAMP-BWWG recommended basic/final approval for the following treatment systems
that make use of active substances.
1)
Country
Manufacturer
Product
Korea
Techone Eco
Purimar
Korea
Aqua ENG
Aquastar
Japan
Kuraray
Kuraray
Japan
FineBallast
Korea
21st Century
Shipbuilding Co.Ltd
ARA Ballast
Norway
Qingdao headway
OceanGuard
Germany
Severn Trent
DeNora
BalPure
Germany
Eka Chem
Ecochlor
Japan
SP-Hybrid
China
Sunrui CFCC
BalClor
Related
Document
Status
MEPC61/2
Approved
MEPC60/2/1
Approved
MEPC60/2/6
Approved
MEPC61/2/5
Approved
MEPC60/2/2
Approved
MEPC61/2/9
Approved
MEPC61/2/8
Approved
MEPC61/2/2
Approved
MEPC61/2/4
Approved
Approval
Basic
Approval
Basic
Approval
Basic
Approval
1)
Final
Approval
Final
Approval
Final
Approval
Final
Approval
Final
Approval
Final
Approval
: No active substances are used. Hence, recommended to apply for government type
approval in accordance with G8.
10
Machinery Team
measurement
regulations
contained
in
Annex
to
the
International
11
Machinery Team
and includes submersibles, floating craft, floating platforms, FSUs and FPSOs.
5) "sedimentss" means matter settled out of Ballast Wataer within a ship.
6) "Ballast Water Capacity" means the total volumetric capacity of any tanks, spaces
or compartments on a ship used for carrying, loading or discharging Ballast Water,
including any multi-use tank, space or compartment designed to allow carriage of
Ballast Water.
7) "Active substance" means a substance or organism, including a virus or a fungus
that has a general or specific action on or against Harmful Aquatic Organisms and
Pathogens.
2.1.2 Definition of Constructed and Major Constructed
1) "Constructed" in respect of a ship means a stage of construction where :
a. the keel is laid; or
b. construction identifiable with the specific ship begins
c. assembly of the ship has commenced comprising at least 50 tonnes or 1 percent of
the estimated mass of all structural material, whichever is less; or
d. the ship undergoes a major conversion
2) "Major conversion" means a conversion of a ship
a. which change its ballast water carrying capacity by 15 percent or greater, or
b. which changes the ship type, or
c. which, in the opinion of the Administration, is projected to prolong its life by ten years
or more, or
d. which results in modifications to its ballast water system other than component
replacement-in-kind. Conversion of a ship to meet the provisions of regulation
D-1 should not be deemed to constitute a major conversion for the purpose of
this Annex.
2.2 Application
2.2.1 Extent of Application
1) Applies to all ships designed to carry ballast water (submersible vessel, floating
vessel, FSUs, and FPSOs
2.2.2 Ships Subject to Survey
1) Except Floating Platform, FSUs or FPSOs, all ships over GT 400 ton are required to
furnish a certificate of survey stipulated by the convention on board ships.
2.2.3 Exceptions
1) Ships not designed or constructed to carry Ballast Water or ships having permanent
ballast water in sealed tanks on ships, that is not subject to discharge
2) Any warship, naval auxiliary or other ship owned or operated by a state and used,
for the time being, only on government non-commercial service.
3) Ships not designed or constructed to carry Ballast Water.
Guideline for Application of BWTS in Ships
12
Machinery Team
Keel Laying
BW Tank(m3)
2009
2010
2011
2012
2013
2014
2015
2016
2017
< 1500
< 2009
1500 ~ 5000
< 2009
> 5000
D1 or D2
D2
D1 or D2
D2
D1 or D2
D2
D2
< 5000
2009 ~ 2011
2012
D1 or D2
D2
5000
-
D2
Table. II-2-A The Year of Entry into Force of Ballast Water related Regulations
2) A BWTS complying with the D-2 Regulation should be installed on board a ship by
the date of first intermediate survey or IBWM special survey after the year of
delivery (Acc. to IOPP certificate).
3) Example A for the above statement
a. Date of Keel Laying :
IOPP)
3
13
Machinery Team
14
Machinery Team
Table. II-2-C D-2 Standards for Ballast Exchange set out in Regulation D-2
2.3.4 Regarding requirements for California and New York, please refer to Appendix B and C.
15
Machinery Team
3.1 General
Approval of Ballast Water Treatment Systems that make use of active substance is conducted at
IMO according to "Procedure for Approval of Ballast Water Treatment Systems that Make Use of
Active Substances (G9)". The purpose of the guideline (G9) is to determine the acceptability of
active substances and preparations containing one or more active substances and their application
in ballast water treatment systems concerning ship safety, human health and aquatic environment.
Basic approval means a pre-approval of the BWTS to comply with the requirements of the BWM
Convention. At basic approval stage, it is to be verified that the application of BWTS has no harm to
environment, human health, properties and resources.
Final approval means approval of ballast water treatment systems that make use of active
substances or preparation to comply with the Convention. Type approval tests in accordance with
"Guidelines for Approval of Ballast Water Management System (G8)" are regarded as a part of the
final approval. Technical assessment for approval of active substances is conducted by BWWG
(Ballast Water Working Group) which is under GESAMP (Group of Experts on Scientific Aspects of
Marine Environmental Protection), where GESAMP-BWWG is a working group of GESAMP under
MEPC. The working group is composed of experts from each field to review the application for the
approval of ballast water treatment systems using active substance submitted by the
Administration.
3.2 Procedure for IMO Type Approval
3.2.1 Approval Procedure for Ballast Water treatment Systems not using Active Substances.
(Guidelines for Approval of Ballast Water Management System (G8))
1) A BWTS that does not make use of an active substance should, without basic or
final approval by IMO, be approved by the Administration for fitting on board ships
according to "Guidelines for Approval of Ballast Water Management System (G8").
2) A typical example of a BWTS that does not make use of active substances is a UV
type.
3) Procedure for type approval according to "Guidelines for Approval of Ballast Water
Management System (G8)" is shown in FIg. II-3-A. Also, registered organizations
which are authorized to conduct the test on behalf of the Administration and test
standards are shown in Table II-3-D.
16
Machinery Team
Issue a Type
Approval Certificate
Inspection
On-board Ships
Fig. II-3-A Type Approval Procedure According to Guidelines for Approval of Ballast Water
Management System (G8)
Table. II-3-D Type Approval Procedure according to Guidelines for Approval of Ballast Water
Management System (G8) [In Korea]
Registered Organizations
Test Items
On-board
Test
Land-based
Test
Environmental
Test
Feasibility
Test
Test Standards
- To comply with D-2 requirements after repeating ballast water
suction storage discharge process 3 times
- Test organism
- Sampling
- Test cycle : more than 5 times per each cycle (PSU), minimum 2
cycles (total 10 times)
- Capacity of control tank and ballast tank should be greater than 200
m3
- Time of sampling : 3 times shortly before/after ballast water treatment
- Vibration Test
- Temperature Test
- Moisture Test
- IP Test
- Power Variation Test
- Incline Test
- EMC Test
- Feasibility for ship's operation
- Performance of Alarm Device and Recording Equipment
- Control and Monitoring System
17
Machinery Team
3.2.2 Procedure for Approval of Ballast Water Management Systems that Make Use of Active
Substances (G9)
1) A BWTS that make use of active substances should, according to "Procedure for
Approval of Ballast Water Management Systems that Make Use of Active Substances
(G9)", acquire basic approval and final approval.
2) Procedures for basic approval and final approval are shown in Fig. II-3-B and Fig.
II-3-C, respectively. The application form for basic approval should include information
of the active substance.
3) Application for final approval should include a result of land-based test for
confirmation that the residual toxicity of the discharge conforms to the evaluation
undertaken for basic approval.
4) The application should be submitted under the name of applying member state and
therefore all contents of the application should be guaranteed by the member state.
- Submission of documents
(laboratorial level)
- Assume discharge period
- Closure of
Evaluation Result
Application
(Manufacturer)
Application
(Member State)
Approval
(IMO/MEPC)
Additional
Comments
Evaluation
(IMO/GESAMP)
- Evaluation and Analysis
of Toxicity
- Report to the Administration
Approval
(IMO/MEPC)
Circulation of
Approval Result
18
Machinery Team
Application
(Manufacturer)
Land-based Test
(Manufacturer + Member
State (Test Facility)]
Application
[Member State]
-Comparing Toxicity of
Discharged Ballast Water with
Approval
the Figure Measured During
(IMO/MEPC)
Basic Approval
Additional
Comments
Evaluation
(IMO/GESAMP)
-Notification of Approval to
the Administration and
Circulation to Member States
Approval
(IMO/MEPC)
Circulation of
Approval Result
Test
Item
Toxicity Test
PSPC
Corrosion Test
Application Form
19
Machinery Team
20
Machinery Team
types of test mentioned in above 1), a type approval is required to be obtained from
the Administration.
3) The feasibility test is conducted by KR on behalf of Korean Government. The
procedure is shown in Fig. II-3-E.
21
Machinery Team
22
Machinery Team
Manufacturer
Remarks
Electrolysis +
Neutralizer
Techcross
Filter+Electrolysis
Filter+Electrolysis,
Chemical
Injection+Neutralizer
Filter+Electrolysis+Inert
Gas Filling
OceanSaver,
NEI
FIlter+AOT
PureBallast
Filter+UV
Filter+Ozone
Special Pipe, NK
Filter+Chlorine Dioxide
EcoChlor
- High Performance
Filter+Chemical
Injection
Peraclean
10
Flocculation+Filter
Hitachi
small amount
products
of
residual
BWTS
Sea
Chest
Physical
Treatment
Ballast Tank
Chemical
Treatment
Neutralization
Overboard
: Treated Ballast Water
: Ballast Water
23
Machinery Team
BWTS
Sea
Chest
Ballast Tank
Photo
Catalysis
Filter
Overboard
: Treated Ballast Water
: Ballast Water
BWTS
Sea
Chest
Gas,
Hydroxyl
Ion
Filter
Cavitation
Ballast Tank
Overboard
: Ballast Water
24
Machinery Team
BWTS
Sea
Chest
Ballast Tank
Overboard
: Ballast Water
BWTS
Sea
Chest
Ballast Tank
Electrolysis
Neutralization
: Treated Ballast Water
Overboard
: Ballast Water
25
Machinery Team
BWTS
Sea
Chest
Ballast Tank
Filter
Magnetic
Separation
Stir
Overboard
: Treated Ballast Water
: Ballast Water
BWTS
Sea
Chest
Ballast Tank
UV
Filter
Overboard
: Treated Ballast Water
: Ballast Water
26
Machinery Team
Below descriptions for various ballast water treatment systems are based on each
manufacturer's website and brochures. Readers should note that there may be changes or
updates in their system configuration, performance, explosion protection design, etc. For
additional information on each products, please refer to Appendix E.
2.1.1 General
1) PureBallast is a ballast water treatment system developed in Norway. This technology
was submitted for approval at MEPC 55 and received Basic Approval and Final
Approval under the name of Norway at MEPC 56 on July 2007. The system consists
of a filer and AOT (Advanced Oxidation Technology) units .
2.1.2 Characteristics
1)
50
self-cleaning
filter
is
used
during
ballasting
operations.
(During
de-ballasting, the filter is bypassed.) This not only blocks the intake of larger
organisms, but also reduces the amount of sediments in the ballast water tanks.
2) Depending on the system flow rate, one or more AOT units comprise the active
stage
of
PureBallast
treatment,
in
which
generated
radicals
that
neutralize
shows
not only stronger oxidizing power compare with other oxidizing agents such as
chlorine, chlorine dioxide, or calcium permanganate but also quick reaction without
leaving toxic substances or residuals. Fig. III-2.1-C and III-2.1-D are diagrams
showing ballast water flow during treatment stage.
27
Machinery Team
28
Machinery Team
29
Machinery Team
2.2.1 General
1) Techcross Inc's Electro-Cleen System was granted Basic Approval of ballast water
treatment system that makes use of active substance by IMO at MEPC 54th on Mar.
2006 and received Final Approval at MEPC 58th on Oct. 2008.
2.2.2 Characteristics
1) Electro-Cleen System uses electrolysis with application of electric current. In the
process of electrolysis, proton ion and hydroxide ion are being released from positive
anode and negative anode, respectively, where sufficient potential of disinfection
forms around the positive anode and the hydroxide ion released from the negative
anode has an outstanding performance in hydrolysing organisms. In other words,
when electrolyze water, it decomposes into various kinds of radicals such as OH,
HCO, O2, H2O2, O3, and Cl- . And since the radicals have high potential differences,
they react fast with almost all organisms.
2) Although radicals are unstable substances that only last for very short period of time,
from few millionth seconds to few seconds, they destroy organisms instantaneously.
Also, residual chlorine prohibits the re-growth of microorganisms in the ballast tank. A
neutralization unit is installed in the discharge line to neutralize the chlorine content
down to nearly zero when de-ballasting,
2.2.3 Components
1) Control PC : controls the ballast water treatment system.
2) ECU : Eletro-Chamber Unit : is a core component of the ballast water treatment
system where electrolysis process actually occurs by high-voltage direct current
transmitted from a Rectifier.
3) Power Distributor : distributes power to the ballast water treatment system.
4) Rectifier : converts the input power supplied by the power distributor to high-voltage
direct current.
5) Auto Neutralization Unit : automatically controls the chlorine contents by a TSU
(TRO(total residual oxidant) sensor unit) during de-ballasting.
30
Machinery Team
31
Machinery Team
2.3.1 General
1) Developed by OceanSaver in Norway, this system was granted basic approval at
MEPC 57th on Mar. 2008 followed by final approval for ballast water management
system that make use of active substances on Oct. 2008.
2.3.2 Characteristics
1) OceanSaver was launched in 2007 as a technology that treats ballast water by pre-filtering
ballast water followed by cavitation and filling nitrogen gas in the ballast tank.
2) However, to enhance its performance, an electrolysis unit was added to the system. The
additional components are as follows :
a. Mechanical Filtration Unit
b. C3T Unit : Hydrodynamic cavitation
c. C2E Unit : Activated water
d. Nitrogen(N2) Supersaturation unit
3) Until the introduction of the electrolysis unit in 2006, the C3T was the main component of
the treatment system. The C3T, as shown in Fig. III-2.3-A, is a device that induces
cavitation inside the chamber to destroy micro-organisms.
4) Because this unit shows low efficiency of destroying micro-organisms and there is a
chance of re-growth of micro-organisms in the ballast tank, the system requires the
ballast to pass the C3T during de-ballasting. Fig. III-2.3-B and III-2.3-C show the
process of ballasting and de-ballasting, respectively.
32
Machinery Team
33
Machinery Team
2.4.1 General
1) CleanBallast developed by RWO received Final Approval at MEPC 59th. This
system consists of 2 major treatment processes, filter and electrolysis.
2.4.2 Characteristics
1) This system consists of a filtering device called DiskFilter that primarily filters solid
matters and sediments, and EctoSys (Electrolysis Unit) that secondarily treats the
remaining micro-organisms. Also, during de-ballasting, the treated ballast water is
being sent to the EctoSys again to destroy the micro-organisms that might have
not been fully destroyed or re-grown in the ballast tank.
2) FIg. III-2.4-A shows a ballasting procedure where organisms greater than 50 are
filtered by the DiskFilter and those smaller than 50 are destroyed by the
EctoSys. Whereas Fig. III-2.4-B shows the de-ballasting procedure where the
treated ballast water is being discharged after passing the EctoSys. Also, III-2.4-C,
III-2.4-D
and
III-2.4-E
are
the
picture
of
Monitor,
DiskFilter
and
EctoSys
34
Machinery Team
35
Machinery Team
2.5.1 General
1) This system uses ozone to treat ballast water and received Basic Approval for ballast water
treatment system that makes use of active substances at MEPC 56th on July 2007 and
Final Approval at MEPC 59th on Aug. 2009.
2.5.2 Characteristics
1) The system consists of an air compressor, an oxygen generator, an ozone generator and
an ozone injector that injects the produced ozone into the ballast pipe.
2) The table in Fig. III-2.5-C shows the specifications of various models.
36
Machinery Team
2.6.1 General
1) CleanBallast developed by Hitachi. Ltd in Japan was granted Basic Approval at
MEPC 57th on Mar. 2008 followed by Final Approval at MEPC 59.
2.7.2 Characteristics
1) This treatment system, as shown in Fig.III-2.6-A, treats ballast water by combining
magnetic
separation
technology
and
coagulation
technology.
In
contrast
to
sterilizatoin-type approaches, the coagulation method does not use chlorine, ozone,
ultraviolet light, or other disinfectants and therefore the risk of residual chemicals
causing secondary contamination is removed. The treatment take place in the
following order : insertion of flocculation agent, magnetic separation, and filter.
Magnetic powder and flocculation agents are added to sea water and the water is
Guideline for Application of BWTS in Ships
37
Machinery Team
roiled to form magnetized floc consisting of plankton, bacteria, mud, and other
materials. When passed through a magnetic separator, the floc adheres to
magnetic disks. Finally, the treated water is filtered by a filter separator, before
being pumped into the ballast tanks.
38
Machinery Team
component
are
shown
39
in
Fig.
III-2.7-E
and
III-2.7-F.
Machinery Team
2) Fig. III-2.8-C is a picture showing actual installation of Sedinox onboard and Fig.
3
40
Machinery Team
2.8.1 General
1) This treatment system taking advantage of filter and UV (ultraviolet light) was developed by
PanAsia and received Basic Approval and Final Approval at MEPC 60th for ballast water
treatment system that makes use of active substances at MEPC 57th
2) The mesh size of the filter is 50 and its operating pressure ranging from 2.5 to 10bar.
2.8.2 Characteristics
1) This system features with automatic back flushing function and various kinds of sensors
and monitoring systems. Since this system uses a filter and UV during treatment stage, it is
almost toxic free and there is no risk of corrosion.
41
Machinery Team
42
Machinery Team
2.9.1 General
1) This system was developed by Resource Ballast Technology(RBT) in South Africa
and granted Basic Approval for ballast water treatment system that makes use of
active substances at MEPC 57th on Mar. 2008 followed by Final Approval at MEPC
60th.
2.9.2 Characteristics
1) The cavitation and the application of the disinfectants all take place within the reactor
vessels (RBT), while the filter removes larger organisms and particulate matter. The
cavitation creates very strong sheer forces that effectively rupture the aquatic
organisms.
Electrodes
mounted
inside
the
reactor
vessels
produce
sodium
43
Machinery Team
2.10.1 General
1) Developed by JFE in Japan, this system uses the combination of filter, cavitation
and sodium hypochlorite. Granted Basic Approval at MEPC 58th and Final
Approval at MEPC 60th.
2.10.2 Characteristics
1) This system treats ballast water by injecting sodium hypochlorite that is stored
onboard a ship at a concentrate of 30 ppm into the ballast water. Fig. III-2.10-A
and III-2.10-B show the treatment processes during ballasting and de-ballasting.
44
Machinery Team
45
Machinery Team
2.11.1 General
1) Developed by Hyundai Heavy Industries Co. Ltd., EcoBallast System was granted
Final Approval at MEPC 60th. This system is composed of two main units : a
filter and a UV reactor. The system is controlled by a programmable logic
controller
installed
in
the
control
panel.
This
system
is
considered
as
46
Machinery Team
2.12.4 UV Reactor
1) The UV Reactor is inserted in the pipe as in Fig. III-2.11-D. The specification of
the UV reactor is shown in Table III-2.11-E.
47
Machinery Team
2.12.1 General
1) Developed by 21st Century Shipbuilding Co.,Ltd., ARA Ballast was granted Basic
Approval at MEPC 60th and Final Approval at MEPC 61st.
water,
which
does
not
need
additional
chemical
substances.
This
48
Machinery Team
2.13.1 General
1) This method using chlorine dioxide was developed by Ecochlor in Germany. The
development was first started in US, however, the system was applied for Basic
Approval in the name of Germany and was granted Basic Approval at MEPC
58th and Final Approval at MEPC 61st.
2) Its initial design was to destroy micro-organisms by inserting chlorine dioxide
produced by reacting sodium chlorate-hydrogen peroxide compound and sulfuric
acid with out a filter. However, a filter was added during approval stage.
2.13.2 Characteristics
1) FIg. III-2.13-A shows the schematic diagram of the system whereas Fig. III-2.13-C
shows the capacity and footprint of various models whose the power consumption
Guideline for Application of BWTS in Ships
49
Machinery Team
50
Machinery Team
2.14.1 General
1) Developed by Severn Trent De Nora, BalPure is consisting of a filter, a electrolyzer and a
neutralizer.
2.14.2 Characteristics
1) A part of the ballast water taken during ballast intake is electrolyzed into high-concentrate
sodium hypochlorite which is then injected into the ballast stream on the discharge side of
the ballast pump. The biocides react with both inorganic and organic species in the ballast
water to provide disinfection.
2) Sodium sulfite, added on the suction side of the ballast pump by a neutralizer, instantly
reacts with residual oxidants and the treated ballast water is safely discharge in to the
ocean. Independent studies have proven that the low concentration of sodium sulfite used
in the BalPure Process is not harmful to local species.
51
Machinery Team
3) Fig. II-2.14-A, III-2.14-B and III-2.14-C show the outlines of the system, ballast water
treatment procedure during intake, and ballast water discharge procedure, respectively.
52
Machinery Team
2.15.1 General
1) OceanGuard received Basic Approval at MEPC 60th and Final Approval at MEPC61st.
2) The system was developed by a technical co-operation between Headway Technology.
Co. Ltd., and Harbin Engineering University.
2.15.2 Characteristics
1) This treatment system uses an AOP (Advanced Oxidation Process) technology which is
the combination of electrolysis and ultrasonic wave type that destroys micro-organisms
through an oxidative breakdown initiated by powerful oxidizing species such as hydroxyl
radicals.
2) When electrolyze sea water, it decomposes into various radicals such as OH, HCO, O2,
H2O2, O3, and OCl- radical. These radicals react fast with almost all organisms due to high
Guideline for Application of BWTS in Ships
53
Machinery Team
potential differences. Although radicals are unstable substances that only last for very short
period of time, from few millionth seconds to few seconds, they destroy organisms
instantaneously. Also, residual chlorine prohibits the re-growth of microorganisms in the
ballast tank.
material,
including bacteria.
(See Fig.
III-2.15-D)
54
Machinery Team
55
Machinery Team
56
Machinery Team
2. Related Regulations
2.1 KR Rules for the Classification of Steel Ships (Hereinafter the KR-Rules) Part 5 Chapter 6
402.2.(2)
All ballast tanks are to be connected to at least two(2) power driven ballast pumps where one of
which may be driven by a propulsion unit. Bilge, sanitary or general service pumps driven by
independent power may be accepted as independent-power ballast pumps, provided that they
are connected properly to the line. However, gravity discharge from top side tanks are to be
complied with 302. 2 (1) (B) of the Guidance. And, where cargo pump is arranged for
de-ballasting in emergency as Pt 7, Ch 1, 1003. 2 (2), the cargo pump may be accepted as
one(1) independent power ballast pumps.
2.2 KR-Rules Part 5 Chapter 6 406.7
2.2.1 Ballast piping system is to be provided with a suitable provision such as a non-return valve or
a stop valve which can be kept closed at all times excluding the time of ballasting and
de-ballasting and which is provided with an indicator to show whether it is open or closed, in
order to prevent the possibility of water inadvertently passing from the sea to the ballast tanks
or of ballast passing from one ballast tank to another. Where butterfly valves(except remote
control valves) are used, they are to be of type with positive holding arrangements, or
equivalents, that will prevent movement of the valve position due to vibration or flow of fluids.
2.2.2 Remote control valves, where fitted, are to be arranged so that they will close and remain
closed in the event of loss of control power. Alternatively, the remote control valves may
remain in the last ordered position upon loss of power, provided that there is a readily
accessible manual means to the valves upon loss of power. Remote control valves are to be
clearly identified as to the tanks they serve and are to be provided with position indicators at
the ballast control station.
2.3 KR-Rules Part 5 Chapter 6 406.7
In case where gravitational ballasting/de-ballasting is intended by using sea chests provided in
the exclusive ballast tanks, double stop valves being operable from a position on the freeboard
deck are to be provided.
57
Machinery Team
2.4 KR Rules for the Classification of Mobile Offshore Units Chapter 10 104.7
2.4.1 The ballast system of semi-submersible structure should comply with follows :
1) The ballast systems are to consist of two or more adequate means by way of
pumps or other suitable apparatuses, and they are to be capable of ballasting and
de-ballasting all compartments even when one of them is out of service.
2) The system is to be capable of raising the unit, starting from a level trim condition
at the deepest normal operating draft, to the severe storm draft, or a greater
distance as may be specified by the Society, within three hours.
3) Ballast pumps, ballast tank valves and sea chest valves are to be provided with a
means of remote control from a central ballast control station.
3. Dangerous space
3.1 General Cargo Ships, Bulk Carriers, and Container Carriers
When carrying flammable cargoes (SOLAS Reg. II-2/19) classified by IMSBC Code or IMDG
Code, according to IEC 60092-506, the cargo area and its ventilation duct are being designated
as dangerous spaces. If carrying Class 2.1, 3(flash point23), 6.1(flash point23), 8
cargoes or Class 4.3 cargoes in bulk, 3-meter radius of the ventilation in/outlet is being
designated as a dangerous space.
3.2 Ro-Ro Vessel, Car Carrier
Although enclosed Ro-Ro or car spaces are categorized as dangerous spaces, if the area or
space is equipped with a mechanical ventilation of minimum 10 change-time per hour and an
alarm system for the failure of ventilation, the dangerous space can be reduced to 450mm
above each deck. In this case, electric equipment with sealing protection against spread of
sparks (IP55 or above) and those whose maximum surface temperature is less than 200 are
allowed to be installed above 450mm of each deck.
3.3 Specially Categorized Area
In specially categorized area, regardless of ventilation capacity, all areas below the
compartment deck are considered dangerous spaces in addition to the requirements in above
3.2.
3.4 Dangerous Space other than Cargo Area
Other than above mentioned areas, a battery room, a paint store and an acetylene store are
also considered as dangerous spaces.
3.5 Installation of BWTS in Confined Space
The electrical installation of BWTS should, as far as practicable, be avoided in the dangerous
spaces mentioned in above 3.1~3.4. However, If the installation is necessary due to ships's
structure, explosion-proof electrical equipment complying with the minimum explosion proof
level of the area should be installed. When installed in enclosed Ro-Ro or Car spaces, except
Guideline for Application of BWTS in Ships
58
Machinery Team
IIB T3 or higher, the installation should be located above 450mm of each platform. Also, the
electrical equipment should be of IP55 or higher and its surface temperature should not exceed
200.
3.6 Please refer to Appendix A for explosion-proof levels and protection types for electrical
installation sorted by cargo types and ship types.
4. Installation of BWTS
4.1 Installation in Engine Room
Fig. IV-1-C shows the schematic diagram of BWTS installation in engine room. Excluding
tankers, most ship's, ballast tanks are considered safe spaces that there is no restriction
whatsoever in relation to the installation of BWTS in engine room. However, If the BWTS is
equipped with an ozone(O3) generator, an ozone detection device that activates alarm in case
of leakage is required to be installed in which the ozone generator is installed. Also, due
consideration should be given to O3 pipes to prevent leakage; for example, using double pipes
or welded joint SUS pipes.
59
Machinery Team
The following items should be additionally considered when installing the BWTS on upper deck
or other areas outside the engine room.
4.2.1 If the BWTS is installed on the upper level of a ship, for example on upper deck, requiring
ballast pipes to be extended to the BWTS, a head loss of ballast pump should be considered.
Also, excessive vacuum may be found in the downstream of ballast water pipes requiring
vacuum valve or other protective measures.
4.2.2 The BWTS should be installed outside the dangerous space as mentioned in above 3.1~3.4.
However, if installed in a Ro-Ro space, car space or cargo space that is considered as a
dangerous space, special measures should be taken for electric installation as mentioned in
3.5~3.6. Also, due consideration should be given to the installation space, if exposed to
physical impacts during loading/unloading.
4.2.3 If the BWTS is equipped with an ozone (O3) generator, an ozone detection devices that
activates alarm in case of leakage is required to be installed in which the ozone generator is
installed. Also, due consideration should be given to O3 pipes to prevent leakage; for
example, using double pipe or welded joint SUS pipe.
4.2.4 If the BWTS is such a type that produces dangerous gases such as hydrogen gas during
treatment process, there is a risk of accumulation of dangerous gases in confined space. For
the reason, discharge pipes should be led to a safe space outside the enclosed space.
4.2.5 When a separate enclosed space is made on weather deck for the installation of BWTS, the
enclosed space may increase the vessel's total DWT, and the change in total DWT may
result in drastic change in the rule requirements that the vessel should comply with. For the
reason, it is recommended to consult with 'Stability, Load Line and Tonnage Team' of this
Society regarding this matter.
4.2.6 The components of BWTS, when installed on weather deck, should have an appropriate IP
grade
and
should
be
arranged
where
protected
from
physical
impacts
during
loading/unloading of cargos.
4.3 Measures for Penetration Parts of Pipes and Cables
The pipe or cable penetration piece, when penetrating a bulkhead or a deck, should be of the
same fire-proof or water proof level to that of the penetrating bulkhead or the deck. Especially,
when the pipe or cable is passing through a bulkhead between safe space and dangerous
space, it should comply with the additional requirements for air tightness. Below Fig. IV-1-E and
Fig.IV-1-F show examples of cable penetration parts. For more details, please refer to
KR-Rules Part 8 Annex 8.2, "Penetrations through Divisions".
60
Machinery Team
5. Particulars
5.1 Alarm and Recording of By-pass
It is stated in the BWM Convention Guidelines G8 4.5.4 that "any by-pass of the BWTS should
activate an alarm, and the by-pass event should be recorded by the Control Equipment ".
By-pass means the flow of untreated ballast water through into ballast tank without passing the
Guideline for Application of BWTS in Ships
61
Machinery Team
BWTS. Any by-pass of the BWTS should be alarmed and recorded. For the reason, all valves
in the by-pass line should be remote-controllable or be equipped with an open/close indicator
for automatic detection of the by-pass event by the control equipment.
5.1.1 Installation in Narrow Space
In general, most ships are equipped with 2 or more ballast pumps whose discharge outlets
are connected to ballast tanks through 2 main ballast pipelines. However, in small ships,
there are cases where the BWTS is connected to only 1 of the main ballast pipe due to
limited installation space. In this case, below design consideration should be taken into
account. Fig. IV-1-G is an example of BWTS installation where only 1 main ballast pipe is
connected to the BWTS.
1) All pipes related to the by-pass of BWTS should be removed, or an automatic alarm
system activated in the event of by-pass should be equipped for all valves that may
cause by-pass when adjusted. And the by-pass event should be recorded by the
control equipment.
2) In most cases, although 2 ballast pumps are used, ballast water is carried through 1
main pipe line. For the reason, design consideration such as over pressure of pipes
or excessive flow of ballast water into the BWTS should be taken into account. (In
general, piping system is designed for abt. 2~3m/s)
Fig. IV-1-G Piping diagram of water ballast where the BWTS is connected to only 1 main ballast
pipe line
5.1.2 Initial operation of BWTS
A BWTS that requires by-pass or re-circulation for some periods during its initial ballasting or
de-ballasting is generally designed to have an automatic interlock function to prevent
filling/discharging of untreated ballast water flow. This design feature is included in the most
Guideline for Application of BWTS in Ships
62
Machinery Team
type approval conditions or stated in the type approval drawings. Especially, when installing
this type of BWTS in existing ships, the type and arrangement of automatic control valves and
interlock valves should be checked, and the capacity of hydraulic power pack should be
sufficient. Also, the initial operation procedure should be included in the operation manual that
is to be furnished onboard the ship.
5.1.3 Eductor for Ballast Water Stripping
Ships having large-capacity ballast tanks such as bulk carriers, often equip with an eductor
for the purpose of striping ballast tanks. If this kind of ship is equipped with a BWTS that
requires post-treatment of ballast water when discharging, the system should be designed so
that all flows through stripping pipes are treated by the BWTS. In addition, all pipes related to
the by-pass of the BWTS should be removed, or an automatic audible/visual alarm system
activated in the event of by-pass should be equipped for all valves connected to the striping
pipes. And the by-pass event should be recorded by the control equipment. Below Fig.
IV-1-H is an example showing a ballast piping system where the stripping eductor is installed.
Fig. IV-1-H Piping diagram of water ballast system with a stripping eductor
5.1.4 Retroactive Application to Existing Ships
In most existing ships, 2 or more ballast pumps are installed and their discharge outlets are
connected to ballast tanks through 2 main ballast pipes. However, in small ships, there are
cases where the BWTS is connected to only 1 of the main ballast pipes due to limited
installation space. In such cases, the following should be considered :
1) All pipes related to the by-pass of BWTS should be removed or, all valves related to the
by-pass should comply with the requirements described in above 5.1.
2) In general, although 2 ballast pumps are used, ballast water is carried through 1 main
pipe line. For the reason, design consideration such as over pressure of pipes or
63
Guideline for Application of BWTS in Ships
Machinery Team
excessive flow of ballast water into the BWTS should be taken into account.
64
Machinery Team
equipped
with
BWTS
having
an
additional
treatment
stage
during
de-ballasting are required to close the valves that are attached to the sea chests at
all times. Also, since by-pass may occur by adjusting the valves, the requirements in
above 5.1 should be complied with.
2) Above 1) should be considered, in particular, if an overflow pipe for ballast exchange
is installed in an existing ship for the purpose of complying with the BWM
Convention D1 (Ballast Water Exchange Method).
5.4 Cargo Holds Used as Ballast Tanks in Case of Emergency
In bulk carriers, there are cases where pipes are installed for the filling of ballast water into
cargo holds for the trimming of draft or maintaining stability in heavy weather. In such cases,
the following should be considered.
5.4.1 Ships equipped with a BWTS requiring additional treatment process during ballast discharge
must additionally treat the ballast water during ballast discharge.
5.4.2 Due consideration should be given to the arrangement of BWTS whose performance may be
affected by sediments or remnants in cargo holds.
Guideline for Application of BWTS in Ships
65
Machinery Team
5.4.3 For a BWTS using inert gas, due consideration should be given to maintaining an inerting
concentration when filling inert gas into the ballast tanks.
5.5 When Using a Ballast Pump for Other Purposes
For ships whose fire pump also serves as the ballast pump, if the BWTS is of
remote-controllable type, the in / outlet valves of the fire pump should be remote-controllable.
The same should be applied when a bilge pump serves as the ballast pump.
5.6 For Ships Having a KR Class Notation of UMA or Above
Ships registered to this Society and having a Class Notation of UMA or above (UMA, UMA1,
UMA2, UMA3) are required to equip with remote-controllable fire pumps according to Pt 9, Ch 3
of the KR-Rules for the Classification of Steel Ships (hereinafter the KR-Rules). Hence, those
using fire pumps also for ballasting should take above into account.
5.7 For Ships Having a KR Class Notation UMA or Above
Ships registered to this Society and having a Class Notation of UMA1 or above (UMA, UMA1,
UMA2, UMA3) are, according to the KR-Rules Pt 9, Ch 3, 502.1, required to equip with a
system that should control ballasting remotely. Hence, for ships with UMA1 or above and having
a BWTS installed onboard, all valves related to filling/discharging of ballast water or operation of
the BWTS should be of remote controllable type.
5.8 Passenger Ships Engaged on International Voyage
The engine room of passenger ships engaged on international voyages is divided into several
sections such as; main engine room, aux. room, pump room, etc. Also, in general, these kinds
of ships are designed to use fire or bilge pumps for ballasting and hence required to meet the
followings. Fig. IV-1-K is an example of BWTS installation in a passenger ship.
5.8.1 There are cases where the fire pumps or bilge pumps that serve as ballast pumps are
scattered in various sections of the engine room. For the reason, the locations or sections in
which the BWTS is to be installed should be carefully reviewed in advance. Where all
components of the BWTS are remote controllable, please refer to above 5.5.
5.8.2 In case where the fire pumps serves as ballast pumps, refer to above 5.5 and 5.6. Also, if fire
pumps that are required to start automatically are commonly used for ballasting, the system
should be designed to supply fire-extinguishing water immediately by automatic starting when
necessary.
5.8.3 In case where a bilge pump serves as a ballast pump, please refer to above 5.1 and 5.5.
Also, due consideration should be given to valve's remote control system because there are
cases where the valves for bilge pipe or bilge pump are required to be remote-controllable in
case of water ingress or etc.
5.8.4 An inlet pipe of the fire pump or a bilge pump, when installed in a separate area, is often led
to a separate sea chest. In this case, the system should be designed such that an alarm
Guideline for Application of BWTS in Ships
66
Machinery Team
should activate when by-pass occurs on any valves subject to ballast water by-pass, and
should be recorded by a control equipment.
67
Machinery Team
5.11.3 If an existing turbine-driven cargo pump is served as a ballast pump, the head of the
turbine-driven cargo pump, which is generally very high, should be take into consideration
when installing the BWTS.
5.11.4 For a BWTS that also treats ballast water during ballast discharge and using a Ballast
Stripping Pump or an Eductor, the location of its components should be carefully
determined during design stage. In this case, above 5.1.3 should be referred to.
5.12 Modification of Ballast Tank
According to the BWM Convention Annex A-1, Reg.5, an existing ship carrying out major
conversion is considered as a new ship. "Major conversion" means the conversion of a ship :
- which changes its ballast water carrying capacity by 15% or greater, or
- which changes the ship type, or
- which, approved by the Administration, is projected to prolong its life by ten years or more,
or
- which results in modification to its ballast water system other than replacement of
components
5.13 Fresh Water Tank
When a fresh water tank is served as a ballast tank, chemicals contained in the fresh water
may potentially be discharged. In this regards, the application of the BWM Convention to
portable water is under discussion at IMO.
5.14 Electric Consumption and Composition of Electric Circuit
Electric load analysis should be carried out and the result should be submitted to this Society
to make sure that the electric power installed on-board is sufficient to cover the increased
electric consumption. Also, electrical equipment of the BWTS should be protected from
overloading or short-circuit.
5.15 Special Considerations for Electrolysis Type BWTS
5.15.1 Electric Pressure Drop
1) In case of an electrolysis type BWTS, DC 36V converted from AC 440V (or 220V)
by means of a rectifier is supplied to the BWTS. In a such case, a large quantity of
electric current flows in the circuit.
2) Therefore, the longer the distance of power transmission, the bigger the electric
pressure drops. For the reason, the length of cables should be within the supplier's
recommendation.
5.15.2 Construction of Cable Runs using Bus-bars
1) The electrolysis type BWTS transmits a large amount of electric current that when
the capacity of BWTS increases, the size and number of cables also increase. For
Guideline for Application of BWTS in Ships
68
Machinery Team
the reason, the Bus-bars are often used to reduce the size of electric installation.
2) Installation of Bus-bars in weather deck or dangerous areas should be avoided. If
installed in dangerous spaces, the Bus-bars should be of explosion proof type.
Specially, when the Bus-bars penetrates a boundary between a safe area and a
dangerous area, explosion and sealing requirements for the penetration parts should
be met. Also, the methods of on-board installation and penetration piece installation
should be approved by this Society.
5.16 Control, Monitoring and Alarm of BWTS
The BWM Convention Guidance 8, Chapter4, describes the requirements of control
equipment, monitoring and alarm equipment.
5.16.1 Control, Monitoring and Alarm of BWTS
1) The amount of injection or the injection level of BWTS that is required for the
treatment of ballast water should be controlled automatically. The control equipment
should be capable of continuous self-monitoring during operation, and operation
related items should be automatically monitored and controled.
2) Malfunction or errors occurring in the system should be monitored. And if these kinds
of problems affect operation of the BWTS, audible/visual alarm should be activated in
all areas in which the ballast water treatment process is regulated.
5.16.2 Operation and Control
1) Operation and control of BWTS should be simple and effective, and all control
should be remote controllable, as far as practicable. However, this does
not
necessarily mean the automation of all valves related to the BWTS, but easy and
effective manual operation is acceptable, except those that may cause BWTS's
malfunction. In such a case, it is recommended that guidelines for the handling
procedure of manual valves when filling/discharging ballast water and piping diagrams
indicating related valves should be posted in all control areas.
2) Ships registered to this Society and having a notation of UMA1 or above are
required that all valves related to the operation of BWTS and ballast pumps should
be remote controllable, and such a system should be interconnected with the existing
remote control devices of the ballast pumps for automatic control.
5.16.3 By-pass and Override
1) Ships equipped with a BWTS should install a means of by-pass or override for the
protection of the ships or their crews in case of emergency. Also, in the event of by-pass,
audible/visual alarm should be automatically activated by the monitoring system and the
by-pass events should be recorded in the control system.
2) In case of existing ships, a BWTS is generally to be installed in one side of the ballast
lines. For the reason, the usage of other ballast lines should be monitored. In relation to
this, suppliers should submit the list of all possible by-pass scenarios considering the
ships's ballast piping arrangement to this Society for review.
Guideline for Application of BWTS in Ships
69
Machinery Team
Oil Tankers
1. General
Fig.IV-2-A ~ IV-2-C show examples of general arrangement of a typical oil tanker, and
Fig.IV-2-D shows an example of typical midship section.
1.1 Fig.IV-2-A shows a general arrangement of an oil tanker where the F.P.T is adjacent to the
cargo tank and the cargo pump room or ballast pump room is located behind the cargo tank.
In general, ballast tanks are of "L type" or "U type" structure arranged around cargo tanks, and
adjacent ballast tanks are classified as dangerous spaces. Therefore, intake/discharge of
ballast water is carried out by using ballast pumps in the pump room. In addition, in case of
large tankers, a separate eductor or a ballast stripping pump is often used. However, in most
cases, filling/discharge of A.P.T is carried out by means of a Bilge, Fire & G/S Pump or Bilge &
Fire Pump installed in the engine room.
70
Machinery Team
71
Machinery Team
Fig. IV-2-E A Typical General Arrangement and Midship Section of a FA Oil Tanker
2. Related Regulations
2.1 KR-Rules Part7, Chapter1 1003.2
Ballast tanks adjacent to cargo oil tanks should comply with followings;
2.1.1 The requirements in this Paragraph are also applied to ballast tanks used as cofferdams at
the fore and after ends of cargo oil tanks.
Guideline for Application of BWTS in Ships
72
Machinery Team
2.1.2 Ballast pipes in ballast tanks adjacent to cargo oil tanks are to be separated from other pipes
and are not to be led to the engine room. For this purpose, an exclusive pump for ballasting
and de-ballasting these tanks is generally to be provided in the pump room. However, if
specially approved by this Society, cargo pumps may be used for the purpose of de-ballasting
in case of emergency only. In addition, ballast tanks are classified as a safe area in case that
tanks are not adjacent to cargo oil tanks. In this case, other requirements set out by this
Society may be applied.
2.1.3 Air pipes of ballast tanks adjacent to cargo oil tanks are to be provided with an easily
replaceable flame screen at their outlets.
2.1.4 Sounding pipes of ballast tanks adjacent to cargo oil tanks are to be led above the weather
deck, unless otherwise approved by this Society.
2.2 KR Guidance Relating to the Rules for the Classification of Steel Ships (hereinafter the
KR-Guidance) Part7, Chapter1 1003.2
In application of the above 2.1 Rules, a ballast piping system for ballast tanks adjacent to
cargo oil tanks is to comply with the following requirements:
2.2.1 Ballast tanks defined as being safe are to be ballasted and de-ballasted by pumps which are
located in gas safe areas. However, they may be de-ballasted by pumps which are located in
dangerous areas, provided that a check valve is fitted on the line for de-ballasting only.
2.2.2 In case where ballast tanks adjacent to cargo oil tanks are intended to be de-ballasted by
cargo oil pumps in an emergency, a spool piece(or blank flange) and a screw-down
non-return valve are to be provided on each ballast pipe at joints with cargo oil pipes. Further,
a warning notice is to be posted stating that spool pieces are to be removed except for
emergencies.
2.3 KR-Rules, Part 7, Chapter 1, 1003.3
A fore peak ballast tank ballasted through pipes serving other ballast tanks in cargo areas is to
meet with the following requirements: (Refer to IACS UR F44)
2.3.1 Openings of vent pies are to be located on open deck separated from ignition sources by the
distance required by IEC 60092-502.
2.3.2 Means are to be provided on open deck to allow measurement of flammable gas
concentrations in a fore peak tank by a suitable portable instrument.
2.3.3 The sounding arrangement to a fore peak tank is to be direct from open deck.
2.3.4 The access to a fore peak tank is to be direct from open deck. Alternatively, indirect access
from open deck to a fore peak tank through an enclosed space may be accepted provided
that :
Guideline for Application of BWTS in Ships
73
Machinery Team
1) In case that the enclosed space is separated from cargo tanks by cofferdams, the access is
to be through a gas tight bolted manhole located in enclosed spaces and a warning sign is
to be provided at the manhole stating that the fore peak tank may only be opened after;
a. it has been proven to be gas free; or
b. any electrical equipment which is not certified safe in the enclosed space is isolated.
2) In case that an enclosed space has a common boundary with cargo tanks and is therefore
hazardous, the enclosed space is to be well ventilated.
2.4 KR-Guidance, Part7, Chapter1, 1003.2
In application of the above 2.3 requirements, ballast piping system for ballast tanks adjacent to
cargo oil tanks is to be dealt with under the following requirements:
2.4.1 Ballast tanks defined as being safe are to be ballasted and de-ballasted by pumps which are
located in gas safe areas. However, they may be de-ballasted by pumps which are located in
dangerous area, provided that a check valve fitted on the line for only de-ballasting.
2.4.2 In case where ballast tanks adjacent to cargo oil tanks are intended to be de-ballasted by
cargo oil pumps in an emergency, a spool piece(or blank flange) and a screw-down
non-return valve are to be provided on each ballast pipe at joints with cargo oil pipes. Further,
a warning notice is to be posted stating that spool pieces are to be removed except for
emergencies.
3. Protection for Dangerous Area and Electrical Equipment
3.1 Dangerous spaces in oil tankers carrying cargo oil having a flash point of 60 or below
For oil takers carrying cargo oil having a flash point of 60 or below, dangerous space is
classified under space 0, space 1, and space 2 according to the probability of existence of
flammable oil mist and its dangerousness, where each class demands different requirements
for electrical installation. Ballast tanks related to the BWTS and a cargo pump room where the
BWTS is likely to be installed are classified as space 1. And spaces up to 2.4m above upper
deck are classified as space 2. Therefore, when installing electrical equipment in the
above-mentioned dangerous spaces, special consideration for explosion-proof requirements
should be taken into account. Fig. IV-2-A~D are examples of typical dangerous spaces in FB
tankers. For more information regarding dangerous spaces and protection of electrical
equipment, please refer to Appendix "Hazardous Areas and Requirements for Electrical
Installation in Each Ship Type", chapter 2.
3.2 Dangerous Spaces in Oil Tankers Carrying Cargo Having a Flash Point Above 60.
In tankers carrying cargo oil having a flash point above 60, cargo tanks, cargo tank
ventilation pipes and inside of cargo pipes are, according to IEC 60092-502 Reg.4.3, classified
as dangerous space 2. Fig. IV-2-E shows examples of areas which are generally classified as
dangerous spaces in FA tankers.
74
Machinery Team
4. Installation of BWTS
4.1 Installation of BWTS in Oil Takers Carrying Cargo Oil Having a Flash Point of 60 or Below.
Fig. IV-2-A, B and C are examples showing dangerous spaces in an oil tanker carrying cargo
oil having a flash point of 60 or below. According to the BWM Convention/Guidelines/G8
Part 4.9, any electrical equipment that is part of the BWTS should be based in a
non-hazardous area, or should be certified by the Administration as safe for use in a
hazardous area. Any moving parts, which are fitted in hazardous areas, should be arranged so
as to avoid the formation of static electricity.
4.1.1 Consideration for the Location of Installation
In oil tankers carrying chemical cargoes having a flash point of 60 or below, the BWTS
should be installed in the areas as mentioned in above 3.1 unless otherwise certified for safe
use in hazardous areas. However, since ballast tanks are classified as hazardous areas, all
related pipes are also classified as space 1. For the reason, electric equipment of the BWTS
such as a treatment unit or sensor that is directly connected to ballast pipes should be of
certified explosion-proof type.
1) Installation in Cargo Pump room or Ballast Pump Room.
The BWTS may be installed in a cargo pump room or ballast pump room, if an oil
tanker has such a space.
the BWTS in a cargo pump room. Any electrical equipment that is part of the
BWTS should be explosion-proof type which is type approved.
75
Machinery Team
76
Machinery Team
Also, filling
of A.P.T where generally considered a safe area is carried out using Bilge, Fire &
G/S Pumps or Bilge & Fire Pumps in the engine room while discharging is carried
out using ballast pumps in the ballast pump room. If above is the case, the
following should be considered.
a. A dedicated BWTS for the treatment of ballast water in A.P.T or F.P.T where
considered as a safe space, should be installed in a safe space such as the
engine room. However, it is to be noted that for those types that require
additional
treatment
generally
designed
process
to
use
during
ballast
77
discharging,
pumps
in
ballast
ballast
piping
pump
system
room
is
during
Machinery Team
discharging and thus use of the BWTS in the engine room may not be
possible.
b. If the BWTS is equipped with an ozone (O3) generator, an ozone detecting
device that activates alarm in case of leakage is required to be installed in
which the ozone generator is installed. Also, due consideration should be given
to O3 pipes to prevent leakage; for example, using double pipes or welded joint
SUS pipes.
c. If the BWTS is such a type that generates hazardous gas such as hydrogen
gas after treatment, the discharge pipe of the hazardous gas should be led to
a safe area outside the enclosed space since the hazardous gas may be
accumulated in the enclosed space.
d. In case that some components of the BWTS installed in the engine room inject
treatment materials to other components of the BWTS in ballast pump room, the
following should be satisfied.
Should only be used during ballast intake
Should not penetrate a bulkhead between an engine room and pump room
but penetrate through a deck.
Pipes with small diameter should be used.
To prevent a back flow in injection pipes, suitable countermeasures (2 sets
of check valves connected in series) should be installed in cargo areas.
Fig. IV-2-J is an example showing blocking up of back flow applied in a
similar piping system.
78
Machinery Team
79
Machinery Team
80
Machinery Team
81
Machinery Team
cases, ballast water is filled/discharged in/out of ballast tanks via 2 main ballast pipes
on the ballast pump's discharge side. However in small ships, there are cases where
the BWTS is installed on only one side of the ballast pipes due to limited installation
space. In this case, the below design considerations should be taken into account.
Fig. IV-2-M is an example where the BWTS is installed on only one side of main
ballast pipes.
1) All pipes related to the by-pass of BWTS should be removed, or an automatic
alarm system activated in the event of by-pass should be equipped for all valves
that may cause by-pass when adjusted. And the by-pass event should be recorded
by control equipment.
2) In general, although 2 ballast pumps are used, ballast water is carried through a
main pipe line. For the reason, design consideration such as over pressure of
pipes or excessive flow of ballast water into the BWTS should be given (In
general, piping system is designed for abt. 2~3m/s)
82
Machinery Team
83
Machinery Team
discharging of ballast water by gravity, such as large oil tankers, are required to have
double stop-valves connected to the sea chest and the valves should be controllable
from freeboard deck. This type of ships can be further categorized into those carrying
out ballast water filling by gravity and those carrying out both filling and discharging by
gravity. Fig. IV-2-O and IV-2-P are examples of a ship carrying out filling and
discharging ballast water by gravity.
5.2.1 A BWTS that Treats During Ballast Water Intake Only
1) Ships equipped with a BWTS that treats ballast water during filling process only
are required to close all valves that are attached to sea chests when filling ballast
water into ballast tanks. Also, valves should comply with the requirements of above
5.1. as by-pass may occur at the valves.
2) Discharging may be carried out by means of gravity.
5.2.2 A BWTS Having an Additional Treatment Stage During De-ballasting
1) Ships equipped with a BWTS that treats ballast water not only during ballast intake but
also during ballast discharge are required to close the valves attached to the sea chests
while filling and discharging ballast water. Also, the valves should comply with the
requirements of above 5.1. as by-pass may occur by adjusting the valves.
84
Machinery Team
85
Machinery Team
86
Machinery Team
In this case, a detector tube led to the weather deck and a portable detector should
be arranged.
5.8.4 The sounding pipe of the F.P.T should be led to the weather deck.
5.8.5 The entrance of the F.P.T should be directly accessible from an open deck. However,
entrance to the F.P.T via a enclosed space may be permitted if following conditions
are met.
1) If the enclosed space is not adjacent to cargo tanks, the entrance of the F.P.T
should be of a gas-tight manhole. In this case, a warning plate describing that the
door should be opened after non-existence of flammable gas in the F.P.T is
checked and electrical equipment other than explosion-proof type is shut off should
be attached on the manhole.
2) If adjacent to cargo tanks, the enclosed space is classified as a dangerous
space, and therefore should comply with all the related requirements. Also, efficient
means of ventilation should be arranged.
5.9 Fire Integrity for Areas where BWTS is Installed.
The BWTS can also be installed in a space inside the deckhouse. In this case, the
said space is defined, according to SOLAS Reg. II-2/3 regulation, as a machinery space
or service space. For the reason, bulkheads or decks of living areas adjacent to the
machinery space or service space are required to have fire integrity of A-0 or above
according to SOLAS Reg. II-2/9 regulation.
5.10 Fresh Water Tank
When a fresh water tank is served as a ballast tank, chemicals contained in fresh water
may potentially be discharged. In this regards, the application of the BWM Convention
to portable water is under discussion at IMO.
5.11 Electric Consumption and Composition of Electric Circuit
Electric load analysis should be carried out and the result should be submitted to this
Society to make sure that the electric power installed on-board is sufficient to cover the
increased electric consumption. Also, electrical components of the BWTS should be
protected from overloading or short-circuit.
5.12 Modification of Ballast Tanks
According to the BWM Convention Annex A-1, Reg.5, an existing ship carrying out
major conversion is considered as a new ship. "Major conversion" means a conversion
of a ship :
1) which changes its ballast water carrying capacity by 15% or greater, or
2) which changes the ship type, or
3) which, approved by the Administration, is projected to prolong its life by ten years
or more, or
4) which results in modification to its ballast water system other than component
Guideline for Application of BWTS in Ships
87
Machinery Team
replacement-in-kind.
5.13 Control, Monitoring and Alarm of BWTS
The BWM Convention Guidance8, Chapter4, describes the requirements of control
equipment and monitoring & alarm equipment.
5.13.1 Control Device and Monitoring and Alarm Device
1) The injection amount or injection level of the BWTS that is required for the
treatment
of
ballast
water
should
be
controlled
automatically.
The
control
88
Machinery Team
Chemical Tankers
1. General
Fig. IV-3-A, B and C are examples showing a general arrangement of a typical chemical
tanker and Fig. IV-3-D is an example of typical midship section of a chemical tanker.
1.1 Fig.IV-3-A shows a general arrangement of a chemical tanker where the F.P.T is
adjacent to cargo tanks, and the cargo pump room or ballast pump room is located in
the AFT of the vessel. In general, ballast tanks are of "L type" or "U type" structure
arranged around cargo tanks and the adjacent ballast tanks are classified as dangerous
spaces. Therefore, filling/discharging of ballast water is carried out by using ballast
pumps installed in the pump room. In addition, in case of large tankers, a separate
eductor
or
ballast
stripping
pump
is
often
used.
However,
in
most
cases,
filling/discharging of the A.P.T is carried out by means of the Bilge, Fire & G/S Pumps
or Bilge & Fire Pumps installed in the engine room.
89
Machinery Team
90
Machinery Team
large chemical tankers, there are cases where a separate eductor or a ballast stripping
pump is used for ballasting/de-ballasting.
Fig.
IV-3-E
shows
general
arrangement
and
midship
section
of
chemical
tankers(NLS tanker) carrying cargos specified in the IBC Code Chapter 18. In general,
ballast tanks are part of the double structure having "L type" or "U type" structure
arranged around cargo tanks and adjacent ballast tanks are classified as safe spaces.
Filling and discharging of each ballast tanks are carried out by means of a Bilge, Fire
& G/S Pump or Bilge & Fire Pump in the engine room or by ballast pumps in the
pump room.
91
Machinery Team
tanks
themselves.
Discharge
arrangements
for
permanent
ballast
tanks
sited
92
Machinery Team
93
Machinery Team
2) When filling is made from open deck according to the preceding (1), the piping
arrangement in cargo tanks is to be such that filling pipes are extended as close
to the bottom as practicable to minimize generation of static electricity.
3. Protection for dangerous spaces and electrical equipment
3.1 Dangerous Spaces in Chemical Tankers Carrying Chemical Cargoes Having a Flash
Point Below 60
For chemical takers carrying chemical cargoes having a flash point of 60 or below,
dangerous space is classified under space 0, space 1, and space 2 according to the
probability of existence of flammable oil mist and its dangerousness, where each level
demands different requirements for electrical Installation. Ballast tanks related to the
BWTS, and a cargo pump room where the BWTS is likely to be installed are classified
as space 1. And a space up to 2.4m above the cargo deck is classified as space 2.
Therefore, when installing electrical equipment in the said dangerous spaces, special
consideration for explosion-protection requirements should be taken into account. Fig.
IV-3-A~D are examples of typical dangerous spaces in chemical tankers. For more
information regarding dangerous spaces and protection of electrical equipment, please
refer to Appendix "Hazardous Areas and Requirements for Electrical Installation in Each
Ship Type", chapter 2.
3.2 Dangerous Spaces in Chemical Tankers Carrying Chemical Cargoes Having a Flash
Point Above 60.
In chemical tankers carrying chemical cargoes having a flash point above 60, cargo
tanks, cargo tank ventilation pipes and the inside of cargo pipes are, according to IEC
60092-502 Reg.4.3, classified as space 2. Fig. IV-3-E is an example of areas that are
generally classified as dangerous spaces in NLS Tankers.
4. Installation of BWTS
4.1 Installation of BWTS in Chemical Tankers Carrying Chemical Cargoes Having a Flash
Point of 60 or below.
Fig. IV-3-A, B and C are examples showing dangerous spaces in chemical tankers
carrying chemical cargoes having a flash point of 60 or below. According to the BWM
Convention/Guidelines/G8 Part 4.9, any electrical equipment that is part of the BWTS
should be installed in a non-hazardous area, or should be certified by the Administration
as safe for use in a hazardous area. Any moving parts, which are fitted in hazardous
areas, should be arranged so as to avoid the formation of static electricity.
4.1.1 Considerations for Installation Location
In chemical tankers carrying chemical cargoes having a flash point of 60 or below,
the BWTS should be installed in the areas as mentioned in above 3.1 unless it is
certified for safe use in hazardous areas. However, since ballast tanks are classified
Guideline for Application of BWTS in Ships
94
Machinery Team
as hazardous areas, all related pipes are also classified as space 1. For the reason,
electric components of the BWTS such as treatment units or sensors that are directly
connected to the ballast pipe should be of certified explosion-proof type.
1) Installation of BWTS in Cargo Pump Room or Ballast Pump Room.
The BWTS may be installed in a cargo pump room or ballast pump room if a
chemical tanker has such a space. Fig. IV-2-I is an outline diagram showing the
installation of the BWTS in the cargo pump room. Any electrical equipment that is
part of the BWTS should be of type approved explosion-proof type.
2) Installation in Areas Other than Engine Room or Pump Room
It is difficult to find a suitable installation space in chemical tankers not having a
cargo pump room or ballast pump room since the installation of the BWTS in the
engine room or accommodation area is prohibited. In this case, the BWTS may be
installed on upper deck. Fig. IV-3-K is an example showing the installation of
BWTS on upper deck. The following should be considered when installing the
BWTS on upper deck.
the
ballast
water
downstream
from
an
elevated
place,
hence
95
Machinery Team
96
Machinery Team
A dedicated BWTS for the treatment of ballast water in A.P.T or F.P.T where
considered a space, should be installed in a safe space such as an engine
room. However, it is to be noted that for those BWTS that require additional
treatment process during discharging, ballast piping is generally designed to use
ballast pumps in the ballast pump room during discharging, thus use of the
BWTS in the engine room may not be possible.
97
Machinery Team
safe area outside the enclosed space since the hazardous gas may be
accumulated in the enclosed space.
d. In case that some components of the BWTS installed in the engine room inject
treatment materials to other components of the BWTS in the ballast pump
room, the following should be satisfied.
Should be only used during filling
Should not penetrate the bulkhead between an engine room and a pump
room but should be injected through a deck.
Pipes with small diameter should be used.
To prevent a back flow in the injection pipe, suitable countermeasures (2
sets of check valves connected in series) should be installed in cargo areas.
Fig.IV-2-J is an example showing blocking up of back flow in similar piping
system.
98
Machinery Team
safe
operation,
the
length
of
cables
should
be
within
manufacturer's
recommendation.
2) Composition of Cable Runs Using Bus-bar
The electrolysis type BWTS, when its capacity become larger, the required electric
current transmission also become larger resulting in increase in size and number
of cables. For the reason, a Bus-bar is often used to reduce the installation space.
In this case, the Bus-bars should be of KR type-approved and be installed in a
trunk whose protection grade is IP54 or above. Installation in dangerous spaces or
on weather deck should be avoided. If installed in dangerous spaces, the Bus-bar
should be explosion-protection type. Particularly, when penetrating a boundary
between a safe area and a dangerous space, fire protection and sealing
requirements for penetrating pieces should be complied with. Also, on-board
installation methods and the details of penetration parts should be approved by this
Society.
4.1.4 General Requirements for Electrical Equipment in Chemical Tanker's Dangerous Area.
According to KR-Rules Part 7 Chapter 6 Section 10, the following requirements should
be satisfied.
1) Electrical installations should be such as to minimize the risk of fire and explosion
from flammable products.
2) Ships carrying a specific cargo which is liable to damage materials that are
normally used in electrical apparatus, due consideration should be given to the
particular characteristics of materials chosen for conductors, insulation and metal
parts, etc. As far as necessary, these components should be protected to prevent
contact with gas or vapour liable to be encountered.
3) If the flash point of a substance is in excess of 60C however being heated within
15C above the flash point, the requirements for cargoes having a flash point not
exceeding 60C may be applied.
4) Independent cargo tanks should be electrically bonded to the hull. All cargo pipe
joints and hose connections having gaskets should be electrically bonded.
5) Disconnection Switch
Each distribution circuit for electrical equipment installed in dangerous spaces
should be provided with multi pole linked isolation switches installed in a safe
space. In addition, the isolation switches are to be clearly labelled to identify the
electrical equipment to be connected with, and further effective means are to be
provided to avert danger due to unauthorized operation of the isolation switches.
6) Monitoring of Insulation Level
Excluding intrinsically safe circuits, feeder and distribution circuits that are in
contact with electrical equipment or run through dangerous spaces are to be
provided with a system that monitors insulation level and activates alarm in case
of abnormal condition.
99
Machinery Team
5) Cable
a. Cables are to be of armored Non-metallic Sheath Type.
b. Cables are to be installed as close to the hull centre line as practicable.
c. Cables are sufficiently distant from decks, bulkheads, tanks and various kinds of
pipes.
d. Cables, which are installed on the passages and the decks, are to be protected
against mechanical damage. Further, the cables and their supports are to be
fitted in such a manner as to withstand expansion and contraction and other
effects of the hull structure.
e. The penetration parts of the cables or cable pipes through decks and bulkheads
of the dangerous spaces are to be constructed so as to maintain gas-tightness
and liquid-tightness as the case may require.
f. When mineral insulated cables are used, special precaution is to be taken to
ensure sound terminations.
g. All metallic protective coverings of power and lighting cables passing through
dangerous spaces, or connected to equipment in such spaces, are to be
earthed at least at each end.
4.1.5 Installation Examples
Fig. IV-3-N and O are examples showing the installation of BWTS in a dangerous
area of chemical tankers carrying chemical cargoes having a flash point below 60.
The ballast treatment equipment and sensors installed in ballast pipes inside the red
box in Fig IV-3-N and O are explosion-proof type and other non-explosion protected
equipment is arranged outside the dangerous spaces. In addition, sensors directly
connected to ballast pipes such as FMU (Flow Meter Unit) are to be of explosion
proof type.
4.2 Chemical Tankers Dedicated to Carry Cargoes Specified in IBC Code Chapter 18.
If the BWTS is installed outside the dangerous spaces as in above 3.2, ballast tanks
are not considered as dangerous spaces and thus the BWTS is not required to be
explosion-proof type.
4.3 Measures for Pipes and Penetration Parts of Cables
The penetrating parts of pipes and cables for the BWTS, when penetrating bulkheads or
decks, are required to be of the same water-tight or fire protection level to that of the
penetrated bulk heads or the decks. Additionally, when the cable is penetrating a
boundary between safe spaces and dangerous spaces, gas-tight requirements should be
complied with. For more details about the penetrating parts, please refer to "KR-Rules
Part 8, Annex 8-2 "Penetrations through Divisions".
100
Machinery Team
101
Machinery Team
102
Machinery Team
This design feature is included in the most type approval conditions or stated in type
approval drawings. Especially, when installing this type of BWTS in existing ships, the
type and arrangement of automatic control valves and interlock valves should be
checked, and the capacity of hydraulic power pack should be sufficient. Also, initial
operation procedure should be included in the BWTS' operation manual that is to be
furnished onboard ships.
5.1.3 Eductor for Ballast Water Stripping
Ships having large-capacity ballast tanks such as chemical tankers, often equip with
an eductor for the purpose of striping ballast tanks. If this kind of ship is equipped
with a BWTS that requires the post-treatment of ballast water when discharging, the
system should be designed so that all flows through stripping pipes are treated by the
BWTS. In addition, all pipes that may enable the BWTS to by-pass should be
removed, or an automatic audible/visual alarm system activated in the event of
by-pass is to be equipped for all valves connected to striping pipes. And the by-pass
event should be recorded by the control equipment.
103
Machinery Team
to the by-pass should comply with the requirements described in above 5.1.
2) In general, although 2 ballast pumps are used, ballast water is carried through 1
main pipe line. For the reason, the design consideration such as over pressure of
pipes or excessive flow of ballast water into the BWTS should be taken into
account.
5.2 Filling and Discharging by Gravity
Ships having sea chests inside ballast tanks therefore carrying out filling & discharging
of ballast water by gravity, such as large chemical tankers, are required to have double
stop-valves connected to the sea chests and valves should be controllable from
freeboard deck. This type of ships can be further categorized into those carrying out
ballast water filling by gravity and those carrying out both filling and discharging by
gravity. Below Fig. IV-3-R and IV-3-S are examples of a ship carrying out filling and
discharging ballast water by gravity.
5.2.1 A BWTS that Treats during Ballast Water Intake Only
1) Ships equipped with a BWTS that treats ballast water during ballast intake only are
required to close all valves that are attached to sea chests when filling ballast
water into ballast tanks. Also, the valves should comply with the requirements of
above 5.1. as by-pass may occur at the valves.
2) Discharge may be carried out by means of gravity.
5.2.2 A BWTS Having an Additional Treatment Stage During De-ballasting
1) Ships equipped with a BWTS that treats ballast water not only during ballast intake but
also during ballast discharge are required to close the valves attached to the sea chests
while filling and discharging ballast water. Also, the valves should comply with the
requirements of above 5.1. as by-pass may occur by adjusting the valves.
104
Machinery Team
treatment
during
discharging
is
installed
onboard,
the
following
should
be
considered.
5.4.1 Cargo tank piping system should be designed so that discharging is possible.
Guideline for Application of BWTS in Ships
105
Machinery Team
5.4.2 There may be oily impurities in cargo tanks which may reduce the performance of
BWTS during discharging. Therefore, due consideration should be given when
choosing or arranging the BWTS.
5.4.3 It is to be considered that a UV lamp type BWTS, whose UV lamps are in directly
contact with ballast water, may have an auto cleaning function, however this function
may not perform well with oily substances.
5.5 When Using Ballast Pump for Other Purposes
For ships whose fire pumps also serve as ballast pumps, if the BWTS is of
remote-controllable type, valves in the in/outlet of the fire pumps should also be
remote-controllable. The same should be applied when bilge pumps serve as ballast
pumps.
5.6 Ships having a KR Class Notation of UMA or Above
Ships registered to KR and having a Class Notation of UMA or above (UMA, UMA1,
UMA2, UMA3) are required to equip with a remote-controllable fire pump according to
KR-Rules Pt 9, Ch 3. Hence, those using the fire pump also for ballasting should take
above into account.
5.7 Ships with a KR Class Notation of UMA1 or above
Ships registered to this Society and having a Class Notation of UMA1 or above (UMA,
UMA1, UMA2, UMA3) are, according to KR-Rules Pt 9, Ch 3, 502.1 , required to equip
with a system that can control ballasting remotely. Hence, for ships with UMA1 or
above and having a BWTS installed onboard, all valves related to the filling/discharging
of ballast water or operation of the BWTS should be remote controllable.
5.8 Astern F.P.T
In principle, it is not allowed to use the BWTS in the pump room for the treatment of
ballast water in the F.P.T, which is considered as a safe space. However, such a case
may be permitted if the following conditions are satisfied (Refer to IACS UR F44).
5.8.1 The F.P.T is considered as a dangerous space.
5.8.2 Air pipe openings of the F.P.T should be installed on weather deck separated from
ignition sources by the distance set out by IEC 60092-502.
5.8.3 There should be a means of measuring concentration of flammable gas in the F.P.T.
In this case, a detector tube led to weather deck and a portable detector should be
arranged.
5.8.4 Sounding pipes of the F.P.T should be led to weather deck.
Guideline for Application of BWTS in Ships
106
Machinery Team
5.8.5 The entrance of the F.P.T should be directly accessible from an open deck. However,
entrance to the F.P.T via a confined space may be permitted if following conditions
are met.
1) If the enclosed space is not adjacent to cargo tanks, the entrance of the F.P.T
should be of a gas-tight manhole. In this case, a warning plate, describing that the
door should be opened after checking non-existence of flammable gas in the F.P.T
or shutting off electrical equipment other than explosion-proof type, should be
attached on the manhole.
2) If adjacent to cargo tanks, the enclosed space is classified as a dangerous
space. Therefore it should comply with all the related requirements. Also, efficient
means of ventilation should be arranged.
5.9 Fire integrity for Areas Where BWTS Is Installed.
The BWTS can also be installed in a space inside the deckhouse. In this case, the
said space is defined, according to SOLAS Reg. II-2/3 regulation, as a machinery space
or service space. For the reason, bulkheads or decks of living areas adjacent to the
machinery space or service space are required to have fire integrity of A-0 or above
according to SOLAS Reg. II-2/9 regulation.
5.10 Fresh Water Tank
When a fresh water tank is served as a ballast tank, chemicals contained in the fresh
water may potentially be discharged. In this regards, the application of the BWM
Convention to portable water is under discussion at IMO.
5.11 Electric Consumption and Composition of Electric Circuit
Electrical load analysis should be carried out and the result should be submitted to this
Society to make sure that the electric power installed on-board is sufficient to cover
the increased electric consumption. Also, BWTS's electrical equipment should be
protected from overloading or short-circuit.
5.12 Modification of Ballast Tanks
According to the BWM Convention Annex A-1, Reg.5, an existing ship carrying out
major conversion is considered as a new ship. "Major conversion" means a conversion
of a ship :
1) which changes its ballast water carrying capacity by 15% or greater, or
2) which changes the ship type, or
3) which, approved by Administration, is projected to prolong its life by ten years or
more, or
4) which results in modification to its ballast water system other than component
replacement-in-kind.
5.13 Control, Monitoring and Alarm of BWTS
The BWM Convention Guidance 8, Chapter4, describes the requirement of control
equipment and monitoring & alarm equipment.
Guideline for Application of BWTS in Ships
107
Machinery Team
of
ballast
water
should
be
controlled
automatically.
The
control
108
Machinery Team
Gas Carriers
1. General
According to the requirements of KR-Rules Part7 Chapter 5 402(IGC Code Reg. 4.2), a
cargo containment system is categorized into Membrane Tank, Semi Membrane Tank,
Independent Tank (Type A, B, and C), and Internal Insulation Tank.
1.1 LPG Carrier
As seen in Fig. IV-4-A ~ B, most LPG tankers have an independent tank type cargo
containment system.
109
Machinery Team
containment systems are maintained at low temperature and low pressure, and
widely applied in medium to large LPG Carriers having cargo tank capacity of 20K,
40K, or 80K.
2) As shown in the midship section of Fig.62, type A LPG carriers having an
independent type cargo containment system have separate hold spaces where the
cargo containment system is confined by the ship's hull structure, and the ballast
tanks are arranged alongside the hold spaces. However, because the hull structure
may act as a 2nd barrier when the cargo space temperature is above -55 under
atmospheric pressure, both Port & STBD side of the hold spaces and parts of the
front side should not be in contact with ballast tanks. In addition, the midship
section of a Type A LPG Carrier is similar to that of a typical single hull bulk
carrier.
3) Installation of ballast pumps in the engine room is accepted according to KR-Rules
Part 7 Chapter 5 307.4 (GC Code Reg. 3.7.4). For the reason, most of the type A
LPG carriers have 2 sets of ballast pumps installed in the engine room in addition
to Bilge, Fire & G/S Pumps or Bilge & Fire Pumps. Filling and discharging of
A.P.T
and
all
ballast
tanks
are
carried
out
by
means
of
ballast
pumps.
Furthermore, in case of large ships, there are cases where a separate ballast
stripping pump such as an eductor is installed.
1.1.2 LPG Carrier-Type C
1) Fig. IV-4-C and D show the general arrangement and midship section of a typical
Type C LPG Carrier, respectively. In general, the Type C cargo tanks have ball or
cylindrical shape. This type is commonly used in medium to small LPG Carrier
having cargo tank capacity below 10K.
2) As shown in the midship section of Fig. IV-4-D, Type A LPG carriers having an
independent type cargo containment system have separate hold spaces where the
cargo containment system is confined by the ship's hull structure, and the ballast
tanks are arranged alongside the hold spaces. Therefore, these ballast tanks are
not in direct contact with the cargo containment system.
3) Installation of ballast pumps in the engine room is accepted according to the
KR-Rule Part 7 Chapter 5 307.4 (IGC Code Reg. 3.7.4). Therefore, most type C
LPG carriers carry out filling or discharging of A.P.T by means of Bilge, Fire &
G/S Pumps or Bilge, Ballast & Fire Pumps in the engine room.
110
Machinery Team
111
Machinery Team
112
Machinery Team
113
Machinery Team
114
Machinery Team
are classified as space 0, and the adjacent ballast tanks and vent pipe surroundings are
classified as space 1. Also, spaces on upper deck above the cargo holds is classified
as space 2.
3.4 LNG Carrier-Membrane Type
As in Fig. IV-4-G and H, the membrane cargo containment system including a primary
and secondary barriers is classified as space 0. And the adjacent ballast tanks and
vent pipe surroundings are classified as space 1. Also, spaces on upper deck above
the cargo hold are classified as space 2.
4. Installation of BWTS
4.1 Installation in Engine Room
Installation of ballast pumps for ballast tanks adjacent to cargo holds is accepted
according to the KR-Rules Part 7, Chapter 5, 307.4 (IGC Code Reg. 3.7.4). Therefore,
in general, gas carriers carry out filling and discharging ballast water by means of the
ballast pump installed in the engine room. For gas carriers requiring a secondary
barrier, although ballast pipes are regarded as space 1, according to the definition of
dangerous space specified in IEC 60092-502, installation of ballast pumps in the engine
room is exceptionally permitted according to the IGC Code. Therefore, installation of
BWTS inside the engine room is deemed not violating the rule requirements. However,
because the ballast pipes are regarded as space 1, the BWTS or sensors for control
and monitoring that are directly connected to the ballast pipes are required to be
explosion-proof type. Also. in order to mitigate the risk of gas leakage from ballast
pipes, a number of flanges or valves that are the cause of the risks should be
minimized. For type C ships not requiring the secondary barrier of cargo containment
system, the ballast tanks are classified as safe spaces and hence as long as the
electric installation is not installed in a dangerous space, the BWTS need not
necessarily be of explosion-proof type.
4.1.1 LPG Carrier-Type C
Fig. IV-4-I is an outline drawing of a Type C LPG Carrier, where the BWTS is
installed in the engine room. In general, filling or discharging of ballast water is
carried out by means of Bilge, Fire & G/S Pumps or Bilge, Ballast & Fire Pumps
which are installed in the engine room.
1) Because the ballast tank of a Type C LNG Carrier is considered a safe space, the
BWTS need not be of explosion-proof type.
2) If the BWTS is equipped with an ozone (O3) generator, an ozone detecting device
that activates alarm in case of leakage is required to be installed in which the
ozone generator is installed. Also, due consideration should be given to O3 pipes
to prevent leakage; for example, using double pipes or welded joint SUS pipes.
3) If the BWTS is such a type that generates hazardous gases such as hydrogen gas
after treatment, the discharge pipe of the hazardous gases should be led to a safe
area outside the enclosed space since the hazardous gas may be accumulated in
Guideline for Application of BWTS in Ships
115
Machinery Team
116
Machinery Team
117
Machinery Team
Fig. IV-4-M Installation of BWTS Outside the Engine Room : LPG Carrier-Type C
Guideline for Application of BWTS in Ships
118
Machinery Team
Fig. IV-4-N Installation of BWTS Outside the Engine Room : LPG Carrier-Type A
2) In case that the BWTS is installed on ship's upper deck requiring ballast water to
be pumped up to the BWTS, head loss of ballast pump should be considered.
Also, excessive vacuum may be found in the ballast pipes when shifting the
Guideline for Application of BWTS in Ships
119
Machinery Team
Fig. IV-4-O Installation of BWTS Outside the Engine Room : LNG Carrier-MOSS Type
Fig. IV-4-P Installation of BWTS Outside the Engine Room : LNG Carrier-Membrane Type
4.3 Matters that Require Attention When Installing BWTS
4.3.1 Measures for Penetration Parts of Pipes and Cables
The penetrating parts of pipes and cables for the BWTS installation, when penetrating
a bulkhead or a deck, are required to be of the same water-tight or fire protection
level to that of the penetrated bulk head or the deck. Additionally, when the cable is
penetrating a boundary between a safe space and a dangerous space, gas-tight
requirements should be complied with. For more detail about the penetrating parts,
please refer to KR-Rules Part 8, Annex 8-2 "Penetrations through Divisions".
4.3.2 Electrical Installation for Ballast Sampling Type BWTS
Those sampling directly from ballast pipes such as a TRO(Total Residual Oxidant)
Guideline for Application of BWTS in Ships
120
Machinery Team
Sensor Unit or a Gas Sensor Unit should be of approved explosion-proof type even
when installed outside the dangerous area. If installed in a safe space, the electrical
equipment should be of appropriate type for the area.
4.3.3 Special Considerations for Electrolysis Type BWTS
1) Voltage Drop over Cable Runs
In the case of an electrolysis type BWTS, AC 440V (or 220V) is converted into
DC 36V by a rectifier so that a large amount of electric current flows in the circuit,
hence the distance of power transmission may be a cause of voltage drop.
Therefore, for safe operation, the length of cables should be within manufacturer's
recommendation.
2) Composition of Cable Runs Using Bus-bar
The electrolysis type BWTS, when its capacity become larger, the required electric
current transmission also become larger resulting in increase of size and number
of cables. For the reason, a Bus-bar is often used to reduce the installation space.
And in this case, the Bus-bar should be of KR type-approved type and be installed
in a trunk whose protection grade is IP54 or above. Installation in dangerous
spaces or on weather deck should be avoided. If installed in dangerous spaces,
the Bus-bar should be explosion-protection type. Particularly, when penetrating a
boundary between a safe area and a dangerous space, fire protection and sealing
requirements for penetrating pieces should be complied with. Also, on-board
installation methods and the details of penetration parts should be approved by this
Society.
5. Particulars
5.1 By-pass Alarm and Recording for BWTS
It is stated in the BWM Convention Guidelines G8 4.5.4 that "any by-pass of the BWTS
should activate an alarm, and the by-pass event should be recorded by the control
equipment". "By-pass" means filling/discharging of untreated ballast water in/out of ballast
tanks without passing the BWTS. Therefore, all valves related to the by-pass event
should be of remote controllable type or be equipped with an open/close indicator so
that automatic detection and alarm is enabled from BWTS's control device.
5.1.1 Installation in narrow space
In general, 2 or more ballast pumps are installed onboard ships, and in most of the
cases, ballast water is filled/discharged in/out of ballast tanks via 2 main ballast pipes
on the ballast pump's discharge side. However in small ships, there are cases where
the BWTS is installed on only one side of ballast pipes due to limited installation
space. In this case, the below design considerations should be taken into account.
Fig. IV-2-M is an example where the BWTS is installed on only one side of the main
ballast pipes.
1) All pipes related to the by-pass of BWTS should be removed, or an automatic
alarm system activated in the event of by-pass should be equipped for all valves
Guideline for Application of BWTS in Ships
121
Machinery Team
that may cause by-pass when adjusted. And the by-pass event should be recorded
by the control equipment.
2) In general, although 2 ballast pumps are used, ballast water is carried through 1
main pipe line. For the reason, design consideration such as over pressure of
pipes or excessive flow of ballast water into the BWTS should be taken into
account (In general, piping system is designed for abt. 2~3m/s)
122
Machinery Team
123
Machinery Team
124
Machinery Team
or service space. For the reason, bulkheads or decks of living area adjacent to the
machinery space or service space are required to have fire integrity of A-0 or above
according to SOLAS Reg. II-2/9 regulation.
5.9 Modification of Ballast Tanks
According to the BWM Convention Annex A-1, Reg.5, an existing ship carrying out
major conversion is considered as a new ship. "Major conversion" means a conversion
of a ship :
1) which changes its ballast water carrying capacity by 15% or greater, or
2) which changes the ship type, or
3) which, in the opinion of the Administration, is projected to prolong its life by ten
years or more, or
4) which results in modification to its ballast water system other than component
replacement-in-kind.
5.10 Control, Monitoring and Alarm of BWTS
The BWM Convention Guidance8, Chapter4, describes the requirements of control
equipment and monitoring & alarm equipment.
5.10.1 Control Device and Monitoring and Alarm Device
1) The injection amount or the injection level of BWTS that is required for the
treatment
of
ballast
water
should
be
controlled
automatically.
The
control
125
Machinery Team
the protection of the ships or their crews in case of emergency. Also, in case of
by-pass, audible/visual alarm should be activated automatically by the monitoring
system and the by-pass event should be recorded in the control system.
2) In case of existing ships, the BWTS is generally to be installed in one side of the
ballast lines. For the reason, the usage of other ballast lines should be monitored.
In relation to this, suppliers should submit the list of situations where by-pass
may occur, considering the ships's ballast piping arrangement, for review.
126
Machinery Team
General
1.1 According to the regulation A-2 of the BWM Convention, discharge of ballast water
should only be conducted by ballast water management in accordance with the provision
of the annex to the convention. Also, article 9 of the BWM Convention provides that a
ship to which the convention applies may, in any port or offshore terminal of another
parties, be subject to inspection by officers duly authorized by that party for the purpose
of determining whether the ship is in compliance with the convention.
1.2 Sampling requirements for complying with regulations D-1 and D-2 of the Convention will
differ as these two regulations have significantly different parameters. In this part of the
guidelines, location of sampling points and installation of sampling devices in compliance
with regulations D-1 and D-2 of the convention will be discussed.
1.3 Although the Convention contains no requirement for provisions of sampling points, the
Guidelines for approval of ballast water management systems (G8) adopted by
resolution MEPC.174(58) do expressly call for the provision of sampling facilities, not
only for the purpose of type approval, but also for the purpose of the Draft Guidelines
for Ballast Water Sampling (G2).
1.4 Currently, there is much discussion on ballast sampling and approval methods at IMO,
and related guidelines will be finalized later.
1.5 Definitions
1) "Sampling point" means that place in the ballast water piping where the sample is
taken.
2) "Sampling Facilities" mean the equipment installed to take the sample.
127
Machinery Team
2.2.1 Sampling should be taken from the discharge line as near to the point of discharge
as practicable. Especially, those requiring ballast water treatment during discharge
must take sample ballast water from the discharge line near to the point of discharge.
2.2.2 In case where the ballast system design does not enable sampling from the discharge
line, other sampling arrangements should be provided.
2.2.3 An exception to this is the case when tanks are emptied through direct overboard
discharge valves in upper side wing tanks, rather than using ballast pumps. In such a
case, sampling from the a tank may be an appropriate approach.
2.2.4 Sampling ballast water via sounding pipes or air vent pipes is against regulation D-2
and hence not appropriate due to following reasons.
1) As a result of extensive scientific investigations, it is concluded that accurate
assessment of the concentration of substances and organisms in the discharge is not
possible.
2) In-tank sampling is allowed only when ballast water treatment occurs during uptake
or in the tank. However, If any part of the treatment process occurs during the
ballast water discharge, the in-tank sampling is not allowed.
2.3 Requirements When Sampling from the Ballast Discharge Line
2.3.1 The sampling point should be determined in a straight part of the discharge line as near to the
ballast water discharge overboard as practicable. The sampling facility should be positioned
such that a representative sample of the ballast water is taken. Also, the sample taken from
the main pipeline at a location where the flowing stream at the sample point is representative
of the contents of the stream. The sample point facilities should be placed at a point where
the flow in the main pipe is fully mixed and fully developed.
2.3.2 The opening of the sample pipe should be chamfered to provide a smooth and gradual
transition between the inside and outside pipe diameters. The length of the straight sample
pipe facing into the flow can vary, but should not usually be less than one diameter of the
sampling pipe. The sampling port should be oriented such that the opening is facing
upstream and its lead length is parallel to the direction of flow and concentric to the discharge
pipe which may require sampling pipes to be "L" shaped with an upstream facing leg if
installed along a straight section of the discharge pipe.
2.3.3 The sampling pipe should be retrievable either manually, or mechanically, or it should
be in a system which can be isolated. Because the potential for the opening and
interior of the sample pipe to become occluded by biological or inorganic fouling, it is
recommended that samplers be designed to be closeable at the opening, removed
between sampling intervals or be easily cleaned prior to sampling.
2.3.4 The sample pipe should be galvanized and be constructed of corrosion resistant
Guideline for Application of BWTS in Ships
128
Machinery Team
material. If flow control of the sample water is required, gate and butterfly valves
should be avoided. For flow control, it is recommended that diaphragm valves or
similar valve type are to be used. Additionally, if flow distribution is required, ball
valve type should be used.
Diso = Dm
Qiso
Qm
129
Machinery Team
130
Machinery Team
131
Machinery Team
No.
Case
Activity
1.
2.
3.
By-pass means the flow of untreated ballast water through or into ballast tank without
passing the BWTS.
2) Automation Arrangements
a. The BWTS should be provided with simple and effective means for its operation
and control. It should be provided with a control system that should be such that
the services need for the proper operation of the Ballast Water Treatment
Equipment are ensured through the necessary automatic arrangements.
b. The Control Equipment should incorporate a continuous self-monitoring function
during the period in which the BWTS is in operation.
c. The Monitoring Equipment should record the proper functioning or failure of the
BWTS.
d. It is recommended that simple means of checking movement, repeatability and
reset ability of the control equipment should be provided as a part of the control
equipment.
1.2.2 Recording and Maintenance
1) All working parts of the BWTS subject to wear or damaged should be easily accessible for
maintenance. The routine maintenance of the BWTS and troubleshooting procedures should
be clearly defined by the manufacturer in the Operating and Maintenance Manual. All
maintenance and repairs should be recorded.
2) Facilities should be provided for checking, at the renewal survey and according to the
manufacturer's instruction, the performance of the BWTS components that take
measurements. A calibration certificate certifying the date of the last calibration check,
should be retained on board for inspection purposes. Only the manufacturer or persons
authorized by the manufacturer should perform the accuracy checks.
3) To facilitate compliance check for Regulation B-2, the Control Equipment should also be able
to store data for at least 24 months, and should be able to display or print a record for official
inspections as required. In the event the Control Equipment is replaced, means should be
provided to ensure the data recorded prior to replacement remains available on board for 24
months.
132
Machinery Team
133
Machinery Team
Continuous Load(kW)
Intermittent Load(kW)
Diversity Factor(%)
Actual Intermittent Load(kW)
Total Load(kW)
Capacity of Generator(kW)
Number of Working Generator
Generator Load Factor(%)
At Port
In/Out
1148
145
40
58
1206
475
3
84.6%
At Cargo
Handling
1123
280.7
40
112.3
1235.3
475
3
86.6%
At Harbor
230.2
194.8
40
77.9
308
475
1
64.8%
3) Table V-1.4.1-B shows an electric load table where a BWTS whose electric consumption
is 60kW is installed onboard the ship. For the calculation, it is assumed that the
highest load is "At Cargo Handling" mode and the ballast pump is operational at this
mode.
Table V-1.4.1-B Electric Load Table Including Electric Consumption of BWTS
Continuous Load(kW)
Intermittent Load(kW)
Diversity Factor(%)
Actual Intermittent Load(kW)
Ballast Treatment System(kW)
Total Load(kW)
Capacity of Generator(kW)
Number of Working Generator
Generator Load Factor(%)
Normal
Seagoing
278.6
198.8
40
79.5
At Port
In/Out
1148
145
40
58
358
475
1
75.3%
1206
475
3
84.6%
At Cargo
Handling
1123
280.7
40
112.3
60
1295.3
475
3
90.9%
At Harbor
230.2
194.8
40
77.9
308
475
1
64.8%
4) In the table, the generator load factor is 90.9% at cargo handling mode, in other word,
the existing power is sufficient to cover the increased load demand. If this figure
exceeds 100%, installation of additional generator should be considered.
1.4.3 Installation in Dangerous Spaces
1) Electrical equipment should not be installed in dangerous spaces. However, an
explosion protected type which is approved for safe use in hazardous areas, may
exceptionally be accepted.
Guideline for Application of BWTS in Ships
134
Machinery Team
2) Only a BWTS approved for safe use in hazardous area may be installed in dangerous
spaces. However, not all parts of the BWTS are type approved for explosion-proof but
only those necessarily be installed in hazardous area are type approved. For the
reason, it is to be checked whether the parts in hazardous area are type approved for
explosion-proof or not.
1.4.4 Protection Against Explosion
1) A dangerous space may, according to IEC, be classified as in table V-1.4.3-A.
Table V-1.4.3-A Classification and Definition of Dangerous Space
Classificaiton of
Dangerous Space
Definition
space 0
space 1
space 2
Code
d
p
e
ia, ib
o
q
m
s
Applicable Zone
1, 2
1, 2
2
0*, 1, 2
1, 2
2
1, 2
1, 2
135
Machinery Team
ships
is
as
follows.
And
the
BWTS
should
be
type-approved
by
the
Administration.
1) Supplier's detail drawings (ship owner or manufacturer) - should include followings :
a. Installation drawings of the BWTS
b. Sampling faculties
c. Pumping and piping arrangements
2) A generic operation and technical manual (Ship owner or manufacturer) - should include
followings :
a. A description of major components and the operation and maintenance of the
BWTS;
b. Normal operation procedures;
c. Procedures for the discharge of untreated water in the event of malfunction of the
Ballast Water Treatment Equipment, maintenance procedures, and emergency
action necessary for securing the ship;
d. A technical section of the manual including adequate information (description and
diagrammatic drawings of the monitoring system and electrical/ electronic wiring
diagrams) to enable faultfinding. This section should include instructions for
keeping a maintenance record;
e. Requirements for the location and mounting of components, arrangements for
maintaining the integrity of the boundary between safe and hazardous spaces
f. A technical installation specification defining the arrangement of the sample piping.
3) A description of BWTS side streams (e.g., filtered materials, centrifugal concentrate, waste
or residual chemicals) including a description of the actions planned to properly manage and
dispose of such wastes (ship owner or manufacturer);
4) A recommended test and checkout procedure specific to the BWTS (ship owner or
manufacturer);
a. Including all the checks carried out in a functional test
5) Machinery arrangements in relation to BWTS installation (ship yard)
6) Machinery arrangements in relation to BWTS installation (ship yard)
7) General arrangement for electrical systems (ship yard)
8) Wiring diagram for power systems (ship yard)
9) Investigation table of electrical load analysis (ship yard)
2.1.2 When installing a BWTS in existing ships, the list of drawings to be approved by
Machinery Team is follows. And the BWTS should be type-approved by the
Administration.
1) Supplier's detail drawings (ship owner or manufacturer) - should include followings :
Guideline for Application of BWTS in Ships
136
Machinery Team
137
Machinery Team
have
been
type-tested
in
accordance
with
the
specifications
for
environmental testing.
c. Specifications for Installation
d. Installation commissioning procedures
e. Initial calibration procedures
2.3.2 The followings are to be verified that :
1) the BWTS installation has been carried out in accordance with the technical installation
specification.
2) the BWTS is in conformity with the Type Approval Certificate of BWTS issued by the
Administration or its representative;
3) the installation of the complete BWTS has been carried out in accordance with the
manufacturer's equipment specification;
4) any operational inlets and outlets are located in the positions indicated on the drawing of the
pumping and piping arrangements;
Guideline for Application of BWTS in Ships
138
Machinery Team
5) the workmanship of the installation is satisfactory and, in particular, that any bulkhead
penetrations or penetrations of the ballast system piping are to the relevant approved
standards;
6) the control and monitoring equipment operates correctly and be able to store records for 24
months, and the records are viewable and printable when required for official survey.
7) the BWTS is provided with sampling facilities so arranged in order to collect
representative samples of the ship's ballast water.
139
Machinery Team
Appendix
Appendix
Hazardous
Areas
and
Requirements
for
Electric
Class 2.1
Class 3
Class 6.1
Class 8
Flammable solids
Class 4.2
Class 4.3
Class 5.1
Oxidizing substances
Class 9
c) MHB
Materials which, when carried in bulk, present sufficient hazards to require specific
precautions
Appendix
3) The ventilation ducts of cargo spaces and areas within 3m of any exhaust
ventilation outlet of cargo spaces
(2) Where equipments such as flanges, valves, pumps, etc are installed in the
enclosed spaces(e.g. pipe space, duck keel) containing the bilge pipes for cargo
spaces, the following types of electrical equipments are accepted to be installed
in the enclosed space unless provided with a minimum overpressure of 25 Pa
according to IEC60092-506.
1) Electrical equipment with the type of protection as permitted in cargo spaces,
or
2) Equipment of protection class Exn, or
3) Electrical equipment which ensures absence of sparks or arcs during normal
operation and whose surface does not reach unacceptably high temperature
Appendix
allowable electrical equipments vary depending on the class of hazardous area.
2.1 Zone 0
(1) Cargo tanks
(2) Cargo ventilation pipes and ducts
(3) Cargo pipes
2.2 Zone 1
(1) Spaces adjacent to cargo tanks such as cofferdams, ballast tanks, etc
Appendix
Appendix
2.3 Zone 2
(1) Areas of 1.5m surrounding zone 1 as specified in 2.2
(2) Areas on open deck over all cargo tank and to the full breadth of the ship plus 3m
fore and aft of the forward-most and aft-most cargo tank bulkhead, up to a height
of 2.4m above the deck
(3) Spaces 4m beyond the cylinder and 3m beyond the sphere defined in 2.2.5)
Appendix
4. Hazardous area in gas carriers
In case of gas carrier, hazardous areas are classified from zone 0 to zone 2 according to
IEC 60092-502, 4.4 depending on likelihood of the presence of an explosive atmosphere
and the level of danger.
4.1 Zone 0
(1) Cargo tanks, slop tanks, cargo pipes, cargo ventilation pipes and ducts
(2) Interbarrier spaces where the cargo tank requires a secondary barrier.
(2) A space separated from a hold space, where cargo is carried in a cargo
Appendix
(3) Enclosed or semi-enclosed spaces in which pipes containing cargo products for boil-off
gas fuel burning system are located, unless special precaution is applied according to
Ch.7, Pt.6 Sec.16 of Rules for the Classification of Steel Ships
4.3 Zone 2
(1) Areas as specified in 2.3
(2) Area within 2.4m of the outer surface of a cargo tank where such surface is
exposed to the weather
Appendix
4.4 Types of explosion proof equipments suitable for each cargo according to IGC Code
Appendix
Requirements for Ballast Water Treatment in California
KR
TECHNICAL
INFORMATION
NO. 2009027/IMO
:
:
:
:
+82-42-869-9346
+82-42-862-6098
kr-clt@krs.co.kr
1 September 2009
Subject : The notice for the application date for each ship and the
approval for Ballast Water Management Plan with regard to BWM
Convention
International Convention for the Control and Management of Ship's Ballast Water and
Sediments, 2004(hereinafter referred to "the convention) was adopted in February 2004
and has not been in effective yet. However, the convention will be retroactively applied
to the existing ships and new ships distinguished by the ship's delivery year of
2009(based on keel laying date) when it is entered into force.
The purpose of this Technical Information is to inform that First, the application date for
each vessel for Ballast water exchange standard(D-1) and Ballast water performance
standard, Second, the approval for Ballast water Management Plan(BWMP) which is dealt
with the procedure of Ballast water exchange and Ballast performance standard for the
ship, Third, the three methods which are described in the convention for Ballast water
exchange standard(D-1).
This Technical Information contains additional information to the previously KR issued
Technical Informations, 2007006/IMO(14 May 2007) and 2009007/IMO(04 March 2009)
which are issued with regard to the BWM Convention.
- Contents -
1. The application date for each vessel for Ballast water exchange
standard(D-1) and Ballast water performance standard(D-2) (Reg.B-3)
: The convention shall be applied to all ships including existing ships as shown in the table.
Page 1/7
Based on ship's keel laying date, the D1 or D2 requirement shall be complied regardless
of the effective date of the convention.
"Constructed" referred in the convention and this technical Information means "ship's
Keel was laid" and "Anniversary date of delivery of the ship" means the day and the
month of each year based on the delivery date referred in IOPP(International Oil
Pollution Prevention) Cert. for the ship.
D1(Reg.D-1) means Ballast Water Exchange Standard and D2(Reg.D-2) means Ballast
Water Performance Standard.
[The application date of D1 and D2 for the existing ships and new ships]
Reg.B-3 Keel laying
BW tank
2009 2010 2011 2012 2013 2014 2015 2016 2017
capacity,
Existing ships ; ships constructed before 2009
less than
1,500
between
Para 1.1 before 2009 1,500 and
5,000
greater than
Para 1.2 before 2009
5,000
Para.1.2 before 2009
D1 or D2
D2
D1 or D2
D2
D1 or D2
D2
less than
5,000
D2
D1 or D2
5,000 or
more
-
D2
D2
1.1 For the existing ship(constructed before 2009), when the convention is
in effective
1) The existing ship shall comply
requirement not later than the first intermediate or renewal survey, whichever occurs
first, after the anniversary date of delivery of the ship in the year 2009 regardless of the
capacity of ballast water tanks.
Page 2/7
2) D2(ballast water performance standard) requirement shall be complied not later than
the following date depending on the capacity of ship's ballast water tank.
a) Ships carrying Ballast water less than 1,500 or greater than 5,000
Not later than the first intermediate or renewal survey, whichever occurs first, after
the anniversary date of delivery of the ship in the year 2016.
b) Ships carrying Ballast water capacity between 1,500 and 5,000
Not later than the first intermediate or renewal survey, whichever occurs first, after
the anniversary date of delivery of the ship in the year 2014.
1.2 For the new ship(constructed on or after 2009), when the convention is
in effective
a) Ships carrying ballast water less than 5,000 which constructed on or after 2009
D2 requirement shall be applied at the time of construction of the ship
(According to Res.A.1005(25), a ship constructed in 2009(2009.01.01 2009.12.31)
with a ballast capacity of less than 5,000 may not be required to comply with regulation
D-2 until its second annual survey, but no later than 31 December 2011 subject to the
approval by the Administration as follows: ).
Notice
However, it should be noted that a ship constructed in 2009(2009.01.01 2009.12.31)
with a Ballast Water Capacity of less than 5,000 shall install BWMS which at least
meets the standard described in regulation D-2 as far as practicable except for the ship
owner's particular request.
b) Ships carrying ballast water more than 5,000 which are constructed between 01
January 2009 and 31 December 2011
D1 requirement shall be applied as soon as the convention is in effective and D2
requirement shall be complied with not later than 31 December 2016.
c) Ships carrying ballast water capacity more than 5,000 which are constructed on or
after 2012
D2 requirement shall be applied at the time of construction of the ship.
Page 3/7
2.1 The application date for approval of Ballast Water Management Plan
1) For existing ships(Constructed before 2009),
For the existing ships, when the convention is in effective, it will be retroactively
applied to the existing ships, therefore BWMP shall be approved not later than the first
intermediate or renewal survey, whichever occurs first, after the anniversary date of
delivery of the ship.
2) For new ships(Constructed on or after 2009),
a) Ships carrying ballast water capacity less than 5,000 which are constructed on or
after 01 January 2009 or Ships carrying ballast water capacity more than 5,000 which
are constructed on or after 01 January 2012
BWMP complying with D2 requirement shall be approved at the time of the
construction of the ships.
b) Ships carrying ballast water capacity more than 5,000 which are constructed
between 1 January 2009 and 31 December 2011
BWMP shall be approved at the time of the construction of the ships because D1
requirement shall be applied as soon as the convention enters into force.
Page 4/7
Page 5/7
a)
Flow-through
Method
means
process
by
which
the
replacement
ballast water is pumped into a ballast tank intended for the carriage of ballast water,
allowing water to flow through overflow or other arrangements.
b) Consideration: where the flow through method is to be used adequate provision
should be made to avoid the risk of over pressurization of ballast tanks or ballast
piping. The installation of additional air pipes, access hatches (as an alternative to deck
manholes), internal overflow pipes (to avoid flowing over the deck) and interconnecting
ballast
trunks
between
tanks
where
applicable
and
possible
may
be
considered. Water on decks and/or direct contact posses a safety and occupational
health hazard to personnel. The design should, where possible, be such that it avoids
water overflowing directly on to decks to avoid the direct contact by personnel with the
ballast water;
Page 6/7
discharging the ballast water through the bottom of the tank at the same flow rate while
maintaining a constant ballast water level in the tank throughout the exchange operation.
Adequate provision should also be made to avoid the risk of over pressurization of
ballast tanks or ballast piping. The hydrodynamic performance of the ballast tank is
crucial to ensure full water exchange and sediment scouring. - the end -
Lim Sam-Taek
Executive Vice President
Statutory Survey Division
Page 7/7
Appendix
Requirements for Ballast Water Treatment in New York
Port Rule
Applicability
The Requirements of New York State Ballast Water Standards are as following.
Organisms, microbes
Organisms 50m or over
Organisms 10m-50m
(New Ship)
0 / m
<0.01 / ml
IMO's standard
(Regulation D-2)
<10 / m
<10 / ml
< 1 cfu / 100ml
< 250 cfu / 100ml
< 100 cfu / 100ml
N.A.
N.A.
There are the relevant information written in original document of VGP including overall
content of Ship Ballast Water Discharges and instruction of Marshall Islands and ICS
(International Chamber of Shipping) explaining approval procedure and extension request of
Ship Ballast Water Discharges in New York State.
The original document of VGP and Marine Guideline No.2-11-10 issued by the Marshall
Islands and MC(10)43 issued by ICS can be available through the following URL
respectively and attached files on this port information.
http://www.epa.gov/npdes/pubs/vessel_vgp_permit.pdf
Marine Guideline No.2-10-11
http://www.register-iri.com/forms/upload/MG-2-11-10.doc
MC(10)43
http://www.marisec.org/icsorange/icscirculars10/MC_10_43%20-%20NYState%20BW%20Requi
rements.pdf
Ship owners/operators are kindly requested to be noticed and pay attention to the above
information against checking for basis compliance with New York State Ballast Water
Standards in the VGP at the time of arriving at New York port.
General Manager
Convention & Legislation Service Team
Korean Register of Shipping
T +82-42-869-9340
F +82-42-862-6098
E kr-clt@krs.co.kr
Disclaimer
Although all possible efforts have been made to ensure correctness and completeness of the contents contained in
this information service, the Korean Register of Shipping is not responsible for any errors or omissions made herein,
nor held liable for any actions taken by any party as a result of information retrieved from this information service.
Appendix
Means to Verify Ballast Water Treatment Systems for
Ships Entering Australian Ports
Regulatory
Applicability
This Port Rule Information is to inform to ship owners/operators the Guideline for the
Port
State
Control of Australia
State,
even
though
the Ballast
Water Management
Convention is not effective, some ships already installed and operated onboard the
type-approved Ballast Water Management System, therefore, the Australia State have plans
to verify whether the ship complies with the specifications and instruction of manufacturer
or not, for the ships which installed onboard the Ballast Water Management System,
berthing in the Australia Port. Therefore, Korean-Register would like to provide the
detailed information as follows in accordance with verification tools for the Ballast Water
Management System and PSC inspection items on a basis of the document which was
submitted by Australia State(MEPC 61/INF.19).
-
Contents
and
is
currently
working
towards
the
ratification
of
the
Ballast
Water
on uptake and discharge, flow rates or retention periods, etc.). These TSPs are being
developed in consultation with BWMS manufacturers, local governments and industry.
1.4 The TSP and associated verification procedure is designed to provide inspection officers
with information to verify that the particular system has been operated in accordance
with the manufacturer's instructions and the ship's ballast water management plan. The
TSP and verification procedure will complement port state control guideline under the
Convention. An example of a TSP and verification checklist is provided at the annex.
Also, Australia invites Member States to consider the benefit of using these tools and
procedures to assist in the inspection and verification of the operation of BWMS, this is
already mentioned through the Marine Environment Protection Committee 61st session
Agenda item 2.
1.5 At the time of MEPC 61st session, on the Treatment System Particulars (TSP)
attached on the document of MEPC 61/INF.19 submitted by Australia State, verification
check items of BWMS which were made for PSC inspection officers are as below.
Sterilisation
Control Panel,
Storage in BW tanks
and discharge,
Cleaning in Place Unit
Maintenance
Data
In addition, attached files are Treatment System Particular (TSP) including functional details
of Ballast Water Management System designed by a specific manufacturer and verification
check items. Accordingly, ship owners/operators are kindly requested to be noticed and pay
attention to the above information against checking for compliance with Treatment System
Particular (TSP) and verification checklists in accordance with PSC inspection of BWMS.
-The end-
General Manager
Convention & Legislation Service Team
Korean Register of Shipping
T +82-42-869-9340
F +82-42-862-6098
E kr-clt@krs.co.kr
Disclaimer
Although all possible efforts have been made to ensure correctness and completeness of the contents contained in
this information service, the Korean Register of Shipping is not responsible for any errors or omissions made herein,
nor held liable for any actions taken by any party as a result of information retrieved from this information service.
Appendix
Questionnaire [BWTS Manufacturers]
Questionnaires in Appendix E were provided by each BWTS manufacturer at the request
of Korean Register to help readers to verify the characteristics of each BWTS (as of Mar.
2010. Please note that there may be changes or updates in their system configuration,
performance, explosion protection design, etc.
7. Techwineco : Purimar
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
1. Please describe about your company
Company name
Techcross
Person in Charge
Mr. J. W. Lee
Telephone No.
02 3775 7777
Fax. No.
02 3775 7788
mike@techcross.net
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
- ECS (Electro-Cleen TM System)
2) Treatment Type (e.g. electrolysis, UV, ozone, ozone+electrolysis, etc.) :
- Electrolysis Disinfection
3) In which process does the ballast water treatment occur ?
Treatment process
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) Consider the maintenance space for ECS components
2) Consider the electric consumption of ECS components
3) Consider the equal flow rate when the ECU(Electro-Chamber Unit)s are operated in
parallel
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
1) ECU300 Model
2) ECU600 Model
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
Explosion
(e.g. ECU, UV chamber)
(Cargo/Ballast)
On-deck
On-deck
Other Space
Pump Room
(Hazardous Area)
(Non-Hazardous Area)
E/R
Proof Type
ECU
O
(Electro-Chamber Unit)
Ballast Water
ANU
Treatment
(Auto Neut. Unit)
Equipment
PRE
(Power Ref. Equip)
Control and
Monitoring
Equipment
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Yes No
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
(Please describe briefly)
NaOcl, Ocl-, OBr-, HoBr
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
The operation range of ECS is from 10% to 110%. In case of the operation range from
100% ~ 110%, the alarm is activated. In case that the operation range over 110%, ECS shut
down automatically.
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
TRO Sensor Unit
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
The sampling is carried out with a manhole in ECS.
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
Toxic
Flammable
Asphyxiant
Others :
No
by
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
1. Please describe about your company
Company name
NK
Person in Charge
Mr. S. J. Park
Telephone No.
051-200-0810
Fax. No.
051-207-2208
Sjpark1@nkcf.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
- NK-O3 BlueBallast System
2) Treatment Type (e.g. electrolysis, UV, ozone, ozone+electrolysis, etc.) :
- Onzone : Side Stream Ozone Injection
3) In which process does the ballast water treatment occur ?
Treatment process
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) To design an inserting line in ballast discharge lines
2) To consider the installation space
3) To arrange an injection piece at the side of a pump discharge in case that ballast pumps
are installed in dangerous area or underwater
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
(m /h)
(kW)
(L x B x H)m
250
36.2
4.2
300
36.5
4.2
600
60.4
6.6
800
68.4
9.1
1000
86.9
8.3
1500
123.2
10.6
2000
148.4
14.5
3000
243.5
17.0
4000
317.6
20.3
5000
385.8
23.9
6000
438.3
25.3
: 8000
613.8
36.8
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
Water
Treatment
Equipment
Control
and
Monitoring
Equipment
E/R
(Cargo/Ballast)
Pump Room
On-deck
(Hazardous
Area)
On-deck
Other Space
Hazardous
Neutralization Unit
Injection
Proof Type
Area)
Treatment Unit
Explosion
(Non-
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Yes No
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
(Please describe briefly)
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
To activate alarm in excess of its capacity or control flow rate
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
TRO Sensor
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast discharge line
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
Toxic
Flammable
Asphyxiant
Others :
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
1. Please describe about your company
Company name
Person in Charge
Hyun-O, Kim
Telephone No.
051-970-1537
Fax. No.
051-831-1399
lab@worldpanasia.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name : GloEn-PatrolTM
2) Treatment Type (e.g. electrolysis, UV, ozone, ozone+electrolysis, etc.) :
Filter + UV Disinfection
The 1st stage is a filter that was specially designed for ballast water applications. It significantly
reduces the sediment load of the ballast water and also removes some of the microorganisms.
The UV unit employs high-intensity, medium-pressure ultra violet (MPUV) lamps to destroy living
microorganisms present in the liquid being treated.
Ballasting
De-ballasting
Ballasting and De-ballasting
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) Installation of Filter back-flushing pump (It depend on ships design) : Option
2)
3)
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
(m3/h)
100
200
300
400
500
600
700
800
900
1000
1500
2000
2500
3000
3500
4000
4500
5000
6000
7000
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Treatment Unit
Ballast
Water
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
(2010.06)
Neutralization Unit
Treatment Others :
Equipment
and
Monitoring
Equipment Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions. : There are no devices which take samples from ballast pipe lines in our BWMS.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Yes No
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
TRO Sensor Unit
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns. None
No.
Question
Answer
(Please describe briefly)
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Alarm: over 20%
Automatic shut down: over 32%
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
None.
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast water discharge line. (after BWMS)
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows. None
No.
Question
Answer
1
No
Toxic
Flammable
Asphyxiant
Others :
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
1. Please describe about your company
SAMGONG VOS CO., LTD
Company name
Person in Charge
Telephone No.
051-200-3080
Fax. No.
051-200-3046
mooki@sam-gong.co.kr
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) Riser loop piping coupled to a ballast pump need to be installed on main deck level.
2) The system requires secondary deck piping for an inert gas system inside the ballast
tank.
3) Since the I.G.G. burns DMA, relevant fire safety protection and ventilation (E/R only)
should be considered.
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
100
17.3
2.5x0.9x1.9 (4.8x3.4x2.4)
200
17.3
2.5x0.9x1.9 (4.8x3.4x2.4)
300
17.3
2.5x0.9x1.9 (4.8x3.4x2.4)
400
24.3
2.5x0.9x1.9 (4.8x3.4x2.4)
500
24.3
2.5x0.9x1.9 (4.8x3.4x2.4)
600
24.3
2.7x1.5x2.2 (5.0x4.0x2.7)
700
24.3
2.7x1.5x2.2 (5.0x4.0x2.7)
800
24.3
2.7x1.5x2.2 (5.0x4.0x2.7)
900
24.3
2.7x1.5x2.2 (5.0x4.0x2.7)
1000
40.3
2.7x1.5x2.2 (5.0x4.0x2.7)
1500
62.3
3.2x1.8x2.6 (5.5x4.3x3.1)
2000
62.3
3.2x1.8x2.6 (5.5x4.3x3.1)
2500
92.3
3.8x2.1x3.0 (6.1x4.6x3.5)
3000
92.3
3.8x2.1x3.0 (6.1x4.6x3.5)
3500
112.3
4.0x2.2x3.4 (6.3x4.7x3.9)
4000
152.3
4.0x2.2x3.4 (6.3x4.7x3.9)
4500
152.3
5.0x2.6x3.6 (7.3x5.1x4.1)
5000
152.3
5.0x2.6x3.6 (7.3x5.1x4.1)
6000
182.3
5.0x2.6x3.6 (7.3x5.1x4.1)
7000
224.5
(m3/h)
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
E/R
Treatment Unit
Ballast
Water
Pump Room
O
Others :
SGG (Stripping
(Cargo/Ballast)
Gas Generator)
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
N/A
NO
Monitoring Others :
Equipment - Control Panel
- Alarm Monitor
Panel
AMP - E/R
NO
Recorder - W/house
- Recorder
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Dissolved Oxygen Monitoring
Yes No (I.S. Type)
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others : N/A
7-1. In the above case and where components are directly fitted in ballast pipe line, please
answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 1 :
Yes No
Dissolved Oxygen Sensor
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
(Please describe briefly)
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
This system controls ballast water flow rate by using a Throttle valve inside the Venturi
Injector.
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
The system is equipped with 2 sets of air blowers (each 50% of system requirement)
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Sounding pipe
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
Toxic
Flammable
Asphyxiant
Others :
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
1. Please describe about your company
HYUDAI HEAVY INDUSTRY CO., LTD
Company name
Person in Charge
Kim, Ha Jong
Telephone No.
052-202-6327
Fax. No.
052-202-6330
bogoos@hhi.co.kr
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
HiBallast
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) To install a booster pump for the operation of the system.
2) Not suitable for hazardous area (Explosion proof type to be developed later)
3) Require a mechanical vent. system
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
100
200
300
< 33 kW
400
500
< 48 kW
600
4000x3500x2000
700
800
900
1000
< 92 kW
1500
< 133 kW
2000
< 176 kW
2500
< 216 kW
4000x3500x2000
7000x3500x2000
3000
3500
4000
4500
5000
< 430 kW
6000
< 507 kW
8000x3500x2000
7000
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
Water
Treatment
Equipment
Control
and
Monitoring
Equipment
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous
(Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Treatment Unit
NO
Neutralization Unit
NO
NO
NO
Yes
N/A
NO
N/A
NO
NO
Conductivity Sensor
Unit
Flow Meter Unit
Others :
(LOP, AVU)
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Dissolved Oxygen Monitoring
Yes No
E/R
(Ballast or Cargo)Pump Room
Others : Require additional cabinet on
deck
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
HOCl (hypochlorite )
OCl- (hypochlorite ion)
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Alarm and recording in the event of excessive flow
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Gas Leak Detector
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast water discharge line(50A)
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
Toxic
Flammable
Asphyxiant
Others :
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
1. Please describe about your company
21st Century Shipbuilding Co., Ltd
Company name
Person in Charge
Telephone No.
055-715-1600
Fax. No.
055-715-1604
Wdr_wondybest@21csb.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
ARA Ballast
Ballasting
De-ballasting
Ballasting and De-ballasting
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) Select a model according to the treatment capacity.
2) Check installation space to verify whether the system need to explosion-proof type or not
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Flow rate
Power
(m /h)
consumption(kW)
ARA-350
350
30
1.79
ARA-500
500
60
2.74
ARA-750
750
85
2.78
ARA-1000
1000
125
5.06
ARA-1500
1500
170
5.19
ARA-2000
2000
250
10.12
ARA-3000
3000
350
10.38
Model of system
Footprint
Dimension summary
(L x B x H)
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
Water
Treatment
Equipment
Treatment Unit
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous
(Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Yes
Yes
Yes
Neutralization Unit
Others : (PDE, PRE),
Sampling Tank
TRO Sensor Unit
Gas Sensor Unit
Control
and
Monitoring
Equipment
Conductivity Sensor
Unit
Flow Meter Unit
Others :
(LOP, AVU)
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Dissolved Oxygen Monitoring
Yes No
E/R
(Ballast or Cargo)Pump Room
Others : ECR, CCR, Up Decker
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
N/A
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
In the event of excessive flow, the flow will be controlled by a throttle valve and an alarm will
activate.
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
N/A
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
At suction side of a filter and ballast water discharge line.
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
The Machinery Team of this Society is planning to publish a Guidance for Installation of the
BWTS.
The KR's BWTS Guidance is intended to assist shipyards and ship owners in selecting
appropriate BWTS by describing the physical and mechanical properties of the BWTS,
technical aspects to be considered at the time of installation, and specific considerations
per each ship type.
In order for us to be able to complete the BWTS Guidance, we would highly appreciate it if
you could fill the questionnaire in as much as possible, and submit to us the completed
questionnaire by 30 April 2011 at the latest.
Your responses to the questionnaire are required for guidance purposes only and will not
be disclosed partly or wholly if specifically requested by the respondents.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
Techwineco
Person in Charge
Lim, Jae-dong
Telephone No.
043-271-8191
Fax. No.
043-271-8193
jdlim@techwineco.co.kr
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
TM
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
Cost saving
5) Automatic operation
6)
Global support
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) Explosion-proof type should be considered when installed in pump room.
2) Vent pipes for Hydrogen gas should be installed in a safe space.
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Instal dimensionandweight
Flow
No.
Rate
3
(m /h)
Power
ElectrolysisUnit
NeutralizationUnit
SensorUnit
Consumption
Dimension
Weight
Dimension
Weight
Dimension
Weight
(LxWxH)
(Kg)
(xH)
(Kg)
(LxWxH)
(Kg)
(kW)
200
1950x1530x1800
900
1100x1400
60
900x300x1600
80
14.4
500
2000x2000x2050
1030
1400x1900
150
900x300x1600
80
25.6
700
2150x2000x2040
1120
1500x2100
210
900x300x1600
80
32.5
1,000
2600x2400x2130
1610
1700x2200
300
900x300x1600
80
46.9
1,500
2800x2500x2400
1850
2000x2500
450
900x300x1600
80
64.2
2,000
3100x2600x2560
2390
2100x2800
600
900x300x1600
80
81.5
2,500
3200x2600x2560
2600
2200x2500
750
900x300x1600
80
99.6
3,000
3300x2700x2600
3120
2400x2800
900
900x300x1600
80
117.0
3,500
4300x2900x2650
3640
2500x3500
1050
900x300x1600
80
134.3
10
4,000
4600x3200x2700
3930
2600x3200
1200
900x300x1600
80
151.6
11
4,500
4650x3300x2800
4500
2700x3200
13510
900x300x1600
80
168.9
12
5,000
4700x3300x2800
4830
2800x3200
1500
900x300x1600
80
188.3
13
6,000
5000x3300x3000
5550
3000x3300
1800
900x300x1600
80
223.7
14
7,000
5200x3500x3200
6000
3000x4000
2100
900x300x1600
80
258.3
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
E/R
Ballast
Water
(Cargo/Ballast)
Pump Room
Treatment Unit
Neutralization Unit
On-deck
On-deck
(Hazardous
(Non-Hazardous
Area)
Area)
Explosion
Other Space
Proof Type
No
Yes
Treatment
Equipment Others : Filter
Control
and
Monitoring
Equipment
Conductivity Sensor
Unit
Flow Meter Unit
Others :
Control Panel
Yes
O
Yes
Yes
Yes
Yes
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Dissolved Oxygen Monitoring
Yes No
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
NaOCl
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
Answer
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Alarm
Shut-down
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
TRO Sensor Unit, Flow meter, Hydrogen gas dilution fan, Pressurization pump, Control
panel (network system)
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast water discharge Line, Over board line
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
No
Hydrogen, Chlorine
Toxic
Flammable
Asphyxiant
Others :
Under 2%
Yes
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
The Machinery Team of this Society is planning to publish a Guidance for Installation of the
BWTS.
The KR's BWTS Guidance is intended to assist shipyards and ship owners in selecting
appropriate BWTS by describing the physical and mechanical properties of the BWTS,
technical aspects to be considered at the time of installation, and specific considerations
per each ship type.
In order for us to be able to complete the BWTS Guidance, we would highly appreciate it if
you could fill the questionnaire in as much as possible, and submit to us the completed
questionnaire by 30 April 2011 at the latest.
Your responses to the questionnaire are required for guidance purposes only and will not
be disclosed partly or wholly if specifically requested by the respondents.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
Person in Charge
Song, Jae-keong
Telephone No.
051-728-1270~2
Fax. No.
051-728-1273
jksong@aquaeng.kr
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
TM
Electrolysis
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
Machinery Team of KR
(m /h)
100
200
300
400
500
[~55(max.)]x2
(3x3x1)x2, / (2x2x2)
[~121(max.)]x2
(3x3x1)x2, / (2x2x2)
[~158(max.)]x2
(3x3x1)x2, / (2x2x2)
[~264(max.)]x2
(4x4x1.5)x2, / (2x2x2)
600
700
800
900
1000
1500
2000
2500
3000
3500
4000
4500
5000
6000
7000
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
Proof Type
Treatment Unit
Yes
Neutralization Unit
Yes
Yes
Yes
Ballast
Water
Others :
Control
Conductivity Sensor
and
Unit
Monitoring
Equipment
Others :
- Master Control
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
an
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Dissolved Oxygen Monitoring
Yes No (I.S. Type)
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others : N/A
7-1. In the above case and where components are directly fitted in ballast pipe line, please
answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Other 1 :
Yes
Dissolved Oxygen Sensor
No
Other 2 :
Yes
No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
NaOCl
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
- Controls TRO production suitable for ballast water flow.
- If out of control, the system first activates alarm and then shut-down the system.
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
- The BWMS is installed in each ballast pump so as to give redundancy to the system.
- Pressure indicator (transmitter)
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast Water Discharge Line
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
Hydrogen
Toxic
Flammable
Asphyxiant
Others :
Yes
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
The Machinery Team of this Society is planning to publish a Guidance for Installation of the
BWTS.
The KR's BWTS Guidance is intended to assist shipyards and ship owners in selecting
appropriate BWTS by describing the physical and mechanical properties of the BWTS,
technical aspects to be considered at the time of installation, and specific considerations
per each ship type.
In order for us to be able to complete the BWTS Guidance, we would highly appreciate it if
you could fill the questionnaire in as much as possible, and submit to us the completed
questionnaire by 31 March 2010 at the latest.
Your responses to the questionnaire are required for guidance purposes only and will not
be disclosed partly or wholly if specifically requested by the respondents.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
Telephone No.
574 304-5060
Fax. No.
574 773-5889
mbb@electrichlor.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
Electrichlor EL BWTS
Ballasting
De-ballasting
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) Small piping installation from sea chest to unit and into upstream of ballast pump piping
2) Whether to install on deck on in machinery space
3) Hydrogen discharge to be piped upwards to atmosphere
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
3
(m /h)
100
.45
200
.9
300
1.35
400
1.8
500
2.25
600
2.7
700
11.25
800
3.6
900
4.05
1000
4.5
1500
6.75
2000
2500
11.25
3000
13.5
3500
15.75
4000
18
4500
20.25
5000
22.5
6000
27
7000
31.5
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
Water
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Treatment Unit
Neutralization Unit
Other Space
[If applicable, fill out the belows]
Explosion Proof
Type
Class1, Div 2
Groups C&D
Treatment Others :
Equipment
and
Monitoring
Equipment Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
N/A
TRO Sensor Unit
Gas Sensor Unit
Others : Total Chlorine Analyzer
Yes No
an
E/R
(Ballast or Cargo)Pump Room
Others : At the ballast water discharge
point
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Yes
No
Other 2 :
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
(Please describe briefly)
Sodium Hypochlorite
Toxic NO
Flammable NO
Asphyxiant NO
Others :
Gas Detection
Mechanical Vent
None
What means are provided to protect crews
Others : There is a drip tray that directs
from the leak of active substances ?
any leaks to drain
E/R
Pump Room
Dedicated space
Others : Can be installed anywhere
Mechanical Vent.
3
(Air change rate : 800m /H)
Natural Vent.
None
Others :
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
No the unit is sized for the maximum ballast water flow rate
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Redundant dosing pumps and blowers
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
Hydrogen
Toxic
Flammable - Hydrogen
Asphyxiant
Others :
.03 m /h
Yes
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
1. Please describe about your company
Company name
Person in Charge
William Burroughs
Telephone No.
Fax. No.
2. Please describe briefly about the Ballast Water Treatment System (hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
BalPure
Ballasting
De-ballasting
Others
(describe in detail)
Machinery Team of KR
Fully automated/integrated into ships ballast water control system. Instant on-
applications
3)
ballast tank.
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
3
(m /h)
250 - 750
750 1150
1150 1550
1550 2500
2500 3500
Machinery Team of KR
3500 4500
4500 - 5800
6000
7000
8000
9000
Discharge ~ 750 W
360 MAX (uptake only)
Discharge ~ 1 kW
420 MAX (uptake only)
Discharge ~ 1.25 kW
480 MAX (uptake only)
Discharge ~ 1.50 kW
540 MAX (uptake only)
Discharge ~ 1.75 kW
Each
Others :
Discharge ~ 750 W
specified
size
DC
is
optimized
with
power
source
(transformer/SCR-
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Treatment Unit
Neutralization Unit
Water
Treatment Others :
Equipment
Control
and
Monitoring
Equipment Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
an
N/A
X TRO Sensor Unit
X Gas Sensor Unit (hydrogen)
Others :
X Yes No
X E/R
X (Ballast or Cargo)Pump Room
Others :
X Mechanical Ventilation
If the monitoring equipment of sampling X Gas Detection & Alarm
type is installed in safety areas (e.g. Self-closing Gas-tight Door
E/R, Dedicated space) outside the Others :
cargo dangerous area, what kind of Hydrogen byproduct is diluted to less than
safety measures is taken against the
1% H2 in air & vented to safe location.
H2 detector is adjacent to equipment
risk of toxic or flammable gas?
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
X Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
X Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
Sodium hypochlorite generated from
electrolysis of seawater.
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
X E/R
Pump Room
Dedicated space
X Others : Can be installed anywhere on
ship to accommodate space available
X Mechanical Vent. Hydrogen produced
(byproduct) is known/Faradays laws &
dilution blowers to remove all hydrogen
safely from the degas separation vessel.
Natural Vent.
None
Others :
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ? BalPure is sized to match the ships ballast water
capacity/flow rate, etc. Design will prevent shortage of generation capacity. System is
designed to treat during ballasting for most efficient operation but active substance can be
added to each ballast tank as a post fill operation. Therefore this is not an issue.
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Machinery Team of KR
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Dual TRO sensors, dual dilution blowers, dual dechlorination (neutralization) pumps, dual
booster pumps, dual flow meters. Reliability studys over 30 years of similar manufacturing
used to formulate accurate failure analysis of components.
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast discharge line
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
Question
Answer
No.
1
No
X Yes
No
Machinery Team of KR
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
The Machinery Team of this Society is planning to publish a Guidance for Installation of the
BWTS.
The KR's BWTS Guidance is intended to assist shipyards and ship owners in selecting
appropriate BWTS by describing the physical and mechanical properties of the BWTS,
technical aspects to be considered at the time of installation, and specific considerations
per each ship type.
In order for us to be able to complete the BWTS Guidance, we would highly appreciate it if
you could fill the questionnaire in as much as possible, and submit to us the completed
questionnaire by 31 March 2010 at the latest.
Your responses to the questionnaire are required for guidance purposes only and will not
be disclosed partly or wholly if specifically requested by the respondents.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
Person in Charge
Mr Steffen Schlricke
Telephone No.
0049-421-53705225
Fax. No.
0049-421-53705442
steffen.schloericke@veoliawater.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name : CleanBallast
Ballasting
De-ballasting
Ballasting and De-ballasting
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1)
2)
3)
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
(m3/h)
100
200
300
400
Installed total power: 170 kW 3 Disc filters, each: =980;
Power consumption: 10 - 55
depth=1080; height=1300
kW/h
500
height=2000; depth=700
Rectifier: width=600;
height=2000; depth=750
Flushing pump: 600;
height=2200
All in mm indication
600
700
800
900
1000
1500
2000
2500
3000
3500
4000
Machinery Team of KR
4500
5000
6000
7000
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous
(Non-Hazardous
Area)
Area)
Treatment Unit
Neutralization Unit
Control
and
Ballast
Explosion
Other Space
Proof Type
Water
Treatment Others :
Equipment
Monitoring
Equipment Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
an
N/A
X TRO Sensor Unit
X Gas Sensor Unit
X Others :algae monitor, salinity meter
Yes X No
X E/R
(Ballast or Cargo)Pump Room
X Others : at BWTS
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
X Others : no safety measures are taken
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes
X No
Yes
X No
Yes
Yes
X No
X No
Yes
X No
Yes
X No
Yes
X No
Yes
X No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
Hydroxyl Radicals, OH*
Hypochloric acid, HOCL
Hypochlorite, OCL
Toxic
Flammable
Asphyxiant
X Others : electrochemical oxidation
Gas Detection
Mechanical Vent
What means are provided to protect crews None
X Others : N/A
from the leak of active substances ?
X E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
X Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Alarm
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
No redundancy in case of standard equipment
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
There are any recommendation by manufacture. Installation of sampling equipment has to be
installed acc. to G2.
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
Question
Answer
No.
1
No
Toxic
Flammable
Asphyxiant
X Others : oxidation
What is the generation rate of dangerous gases Less than 2% H2 of the lower
per each type of BWTS ? (e.g. 1m3/hr, etc)
explosion limit (LEL)
Please use a separate sheet if needed.
X No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
1. Please describe about your company
Company name
Person in Charge
Ralph Michael
Telephone No.
Fax. No.
ralph.michael@mahle.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
Ocean Protection System (OPS)
Ballasting
De-ballasting
Ballasting and De-ballasting
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) nothing
2)
3)
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
3
(m /h)
Variable construction (m )
100
200
~ 19
~ 12
300
~ 25
~ 18
500
~ 37
~ 26
600
~ 49
~ 32
700
~ 54
~ 35
800
~ 60
~ 40
1000
~ 77
~ 49
1500
~ 120
~ 65
2000
~ 159
~ 93
400
900
2500
3000
3500
4000
4500
5000
6000
7000
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Treatment Unit
Ballast
Neutralization Unit
Water
Treatment Others :
Equipment
and
Monitoring
Equipment Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
an
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Yes No
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
TRO Sensor Unit
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
(Please describe briefly)
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Not intended but possible.
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Not intended but possible.
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast Water Discharge Line
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
No
Toxic
Flammable
Asphyxiant
Others :
Yes
No
Questions 6 and 7: The OPS can be safely installed on-board ships with hazardous areas such
as tankers. However there are limitations as to the location of the individual system components.
By modifying system components, it can be made into an explosion proof system, such as
required for use on oil and gas carriers and chemical tankers.
Questions 8 and 12: The OPS uses no chemicals and produces no by-products. The treatment
is a physical system only. It emits light with a primary wavelength of 253.7 nm, which reaches
organisms in the water and affects their DNA directly.
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
1. Please describe about your company
Company name
Person in Charge
Louis Lombardo
Telephone No.
Fax. No.
louis.lombardo@siemens.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
SiCURE Ballast Water Management System
2) Treatment Type (e.g. electrolysis, UV, ozone, ozone+electrolysis, etc.) :
Filtration and electrochlorination with proprietary control logic.
3) In which process does the ballast water treatment occur ?
Treatment process
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
3. Please list strengths of your BWTS.
1) The production of active substance in a side stream generates several advantages as:
Low pressure drop, flexible footprint, easy to install
2) Treatment only on uptake of ballast water results in low operating expenses
3) No need of handling or storage of chemicals due to in-situ production of active substance,
no need for de-chlorination chemicals and self cleaning design (no cleaning chemicals)
4) Based on more than 35 years proven Chloropac technology guarantees for safety and
reliability
Machinery Team of KR
5) Dual Action option: The SiCURE System can be customized to be used for BWT while
ballasting and for Biofouling control of sea water pipelines for cooling water circuits during
voyage
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
No special requirements
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
(m3/h)
100
15
200
21
300
28
400
33.7
500
41
600
46
700
53
800
60
900
69
1000
73
1500
107
2000
145
2500
190
3000
216
3500
265
4000
292
4500
339
5000
368
6000
440
7000
513
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Treatment Unit
Ballast
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Neutralization Unit
Water
Treatment Others :
Equipment Filter Unit
n.a.
n.a.
n.a.
n.a.
n.a.
Control
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
and
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
Monitoring
Equipment Others :
ORP sensor
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
monitoring
Is the monitoring
explosion-proof type?
equipment
an
N/A
TRO Sensor Unit
Gas Sensor Unit
x Others : ORP sensor
Yes x No
X E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
x Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
x N/A
TRO Sensor Unit
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Not applicable
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
hypochlorite
x Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
x Others :
x E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
/H)
Natural Vent.
None
x Others : No special requirement
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Not necessary with SiCURE design
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Redundancy can be provided if requested
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
In the ballast water discharge line
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
Question
Answer
No.
1
x No
Toxic
x Flammable
Asphyxiant
Others :
Yes
No
Where are the residue gases ventilated to after Hydrogen is degassed and diluted
gas detection?
constantly during the process. No
(e.g. installation location of the gas detection unit,accumulation can occur. Gas
or safety area on the exposed weather deck)
detection not necessary.
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
1. Please describe about your company
Company name
OptiMarin AS
Pal Sanner
Person in Charge
Telephone No.
+47 51 11 45 33
Fax. No.
+47 51 12 31 03
info@optimarin.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name : OptiMarin Ballast Water Treatment System.
The patented OptiMarin Ballast System is based on solid separation (filter) as pre-t
reatment and high doses of UV irradiation for inactivation of marine organisms, viru
ses and bacteria, without affecting the normal operation of the ship. Ballast water is
treated both during ballasting and de-ballasting to ensure a dual effect.
The OptiMarin Ballast System can be fitted in new ships and retrofitted in older
ships. The MicroKill Medium Pressure UV can handle almost any flow when
multiple chambers are built into a manifold system. The components in the
OptiMarin system are flexible; the filter can be installed either horizontally or
vertically. The installation is normally in the pump room or engine room and in
close proximity to the ballast pumps. Being flexible in design, the various
components do not need to be side by side but can be installed wherever they will
fit.
Ballasting
Filtering and UV
De-ballasting
UV only
None
Machinery Team of KR
Others
None
(describe in detail)
3. Please list strengths of your BWTS.
The OptiMarin Ballast System has been tested successfully according to the
INTERNATIONAL CONVENTION FOR THE CONTROL AND MANAGEMENT
OF SHIPS BALLAST WATER AND SEDIMENTS, 2004, D2 standard by NIVA
(Norwegian Institute for Water Research). Verified by DNV:
Based on these results we have also received confirmation from the California State
Land Commission that we meet their standard for best available technologies to be
implemented starting 2010. We meet current New York state regulations and the
proposed US Coast Guard Regulations.
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) UV chambers must be installed horizontally
2) Service area for filter and UV chambers
3) Max distance between UV power cabinets and UV chambers should not exceed 25
meters. ( Pls contact Optimarin if longer distance is needed)
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Please note that the system requires 1 x UV lamp/chamber for every 167m3/hr. Each uses
approximately 38kw of power. We added numbers in parenthesis in the first column which
represents the maximum flow an OptiMarin system can handle for the requested flow.
Treatment Capacity
(m3/h)
100 (167)
Machinery Team of KR
200 (334)
76
300 (334)
76
400 (500)
114
500 (501)
114
600 (668)
152
700 (835)
190
800 (835)
190
900 (1,002)
228
1000 (1,002)
228
1500 (1,503)
342
2000 (2,004)
456
2500 (2,505)
570
3000 (3,006)
684
3500
Etc.
4000
4500
5000
6000
7000
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
We are currently not EX certified, but we are in the process of completing a feasibility study, and hope to have this completed by summer of 2010.
In the meantime, the filter is EX rated, so can be placed anywhere.
hazardous areas.
Installed Spaces
(e.g. ECU, UV chamber)
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Treatment Unit
Ballast
Neutralization Unit
Water
Treatment Others :
Equipment
Control
and
Monitoring Gas Sensor Unit
Equipment Flow Meter Unit
Machinery Team of KR
Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
See above. We do not have any ex certified equipment at the moment.
No.
Question
Answer
an
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Yes No
E/R
(Ballast or Cargo)Pump Room
Others
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
TRO Sensor Unit
Yes No
Yes No
x Yes No
Yes No
x Yes No
xYes No
x Yes No
Other 2 :
Yes No
Not Applicable
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns. We do not use any active substances, yet we exceed the IMO Ballast
Water Standards from Reg D-2.
No.
Question
Answer
None
None
No substances, so no leakage
No active substances
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Installed on all systems is a flow & pressure control valve (FPV). Should the limit be reached
this valve will restrict flow so as not to exceed the limit of the ballast water treatment system.
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Machinery Team of KR
In case of break-down/failure of the system, the OBS will shut-down and the bypass will open.
This will ensure continued safe operation of the vessel.
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
The sampling points are located within the Ballastwater lines before and after treatment.
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
Question
Answer
No.
1
No
None
None
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
1. Please describe about your company
Company name
Person in Charge
Joel C. Mandelman
Telephone No.
703-288-4694
Fax. No.
301-277-7496
joelm@nutech-o3.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
Nutech O3 Ballast Water Treatment System
Ballasting
De-ballasting
Ballasting and De-ballasting
In the ballast tank
Others
(describe in detail)
3. Please list strengths of your BWTS.
1) Meets proposed and more stringent United States Treatment Standard and IMO
Standard
2) Cost of system recovered in as little as 1 year
3) Toxicity of discharged water is within acceptable levels
4) No corrosion to ship or human exposure to ozone
Machinery Team of KR
100
200
36.2
4.2 m2
300
36.5
4.2 m2
60.4
6.6 m2
68.4
9.1 m2
1000
86.9
9.1 m2
1500
123.2
10.6 m2
2000
148.4
14.5 m2
243.5
17.0 m2
317.6
20.3 m2
5000
385.8
23.9 m2
6000
438.3
25.3 m2
613.8
36.8 m2
400
500
600
700
800
900
2500
3000
3500
4000
4500
7000
Others :
8000
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Treatment Unit
yes
Neutralization Unit
yes
Water
Treatment Ozone injector &
Equipment Pumps
yes
yes
Control
yes
and
yes
Monitoring
Equipment Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
an
N/A
x TRO Sensor Unit
Gas Sensor Unit
Others :
x Yes No
x E/R
x (Ballast or Cargo)Pump Room
Others :
x Mechanical Ventilation
x Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
x TRO Sensor Unit
x Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
(Please describe briefly)
ozone
x Toxic
Flammable
Asphyxiant
x Others : oxidant
x Gas Detection
x Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
x E/R
Pump Room
x Dedicated space
x Others : on deck in container
all 3 options available
x Mechanical Vent.
(Air change rate :
/H)
x Natural Vent.
None
Vent and blower will be sized to
accommodate whatever air change rate
is required
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Flow rate sensors will trigger alarms and automatic shut down of system
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Essential spare parts will be supplied with system, (ozone electrodes,sensing, units, flow meters,
etc)
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Ballast water discharge line
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
Question
Answer
No.
1
x No
N/A
Toxic
Flammable
Asphyxiant
Others :
N/A
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jee Jae-hoon, KR Machinery Team by phone: +82-42869-9474 or email: krmac@krs.co.kr
1. Please describe about your company
Company name
Alfa Laval
Person in Charge
Telephone No.
Fax. No.
E-mail
per.warg@alfalaval.com
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name : PureBallast
Ballasting
De-ballasting
Ballasting and De-ballasting
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
1) Space
2) Availability of power
3) Ballast pump pressure head
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
(m3/h)
100
200
300
400
500
120
1000
240
12
1500
360
15
2000
480
20
2500
600
25
60
600
700
800
900
3000
3500
4000
4500
5000
6000
7000
Others :
250
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
Water
Treatment
Equipment
Control
E/R
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Treatment Unit
Neutralization Unit
na
na
Na
na
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Others :
Filter
Cleaning-in-place
unit
and
Monitoring
Equipment
Machinery Team of KR
Others :
Control&
power distribution
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
an
X N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Yes No
E/R
(Ballast or Cargo)Pump Room
Others :
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
TRO Sensor Unit
Yes No
Yes No
X Yes No
X Yes No
X Yes No
X Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Answer
(Please describe briefly)
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Alarm
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure ?
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.) PureBallast is equipped with sampling equipment.
12. Regarding the bi-products that are generated from the ballast water treatment process,
please fill in all relevant rows.
No.
Question
Answer
1
X No
Toxic
Flammable
Asphyxiant
Others :
Yes
No
Machinery Team of KR
Questionnaire about
Ballast Water Treatment System
Korean Register of Shipping, with the objective of GLOBAL TOP+, will always do our best
to provide the costumers with quicker and better quality services.
The Machinery Team of this Society is planning to publish a Guidance for Installation of the
BWTS.
The KR's BWTS Guidance is intended to assist shipyards and ship owners in selecting
appropriate BWTS by describing the physical and mechanical properties of the BWTS,
technical aspects to be considered at the time of installation, and specific considerations
per each ship type.
In order for us to be able to complete the BWTS Guidance, we would highly appreciate it if
you could fill the questionnaire in as much as possible, and submit to us the completed
questionnaire by 30 April 2011 at the latest.
Your responses to the questionnaire are required for guidance purposes only and will not
be disclosed partly or wholly if specifically requested by the respondents.
Machinery Team of KR
Thank you for participating in the BWTS Guidance questionnaire. If you have any questions
about how to complete it, please contact Jang Jae-shik, KR Machinery Team by phone: +82-42869-9456 or E-mail: krmac@krs.co.kr
Telephone No.
+86 (0)532-68725831
Fax. No.
+86 (0)532-68725001
yujs@sunrui.net
2. Please describe briefly about the Ballast Water Treatment System(hereinafter referred to as
'BWTS') manufactured by your company.
1) Product Name :
BalClorTM
Ballasting
De-ballasting
1)
2)
3)
4)
5)
side-stream
low power consumption
low maintenance cost
flexible modular design
function unaffected by water condition
Machinery Team of KR
4. Please describe what needs to be specially considered when your BWTS is installed on
board ships.
None
5. Please fill in all applicable columns of the following table about the power consumption and
the required space.
Treatment Capacity
100
15
250018002200
200
15
250018002200
300
15
250018002200
400
25
260018002300
500
25
260018002300
600
50
290023002200
700
50
290023002200
800
50
290023002200
900
50
290023002200
1000
50
290023002200
1500
75
300026002100
2000
100
330025002200
2500
125
350029002400
3000
150
350029002400
3500
175
390028002500
4000
200
380024002600
4500
250
400028002600
5000
250
400028002600
3
(m /h)
6000
7000
Others :
Machinery Team of KR
6. In case of ships carrying dangerous cargoes (such as Oil / Chemical Tanker, Gas Carrier), please indicate the spaces where each part and
equipment of your BWTS are installed.[Put () or description in all relevant rows and columns]
Installed Spaces
(e.g. ECU, UV chamber)
Ballast
E/R
Treatment Unit
Neutralization Unit
(Cargo/Ballast)
Pump Room
On-deck
On-deck
(Hazardous (Non-Hazardous
Area)
Area)
Explosion
Other Space
[If applicable, fill out the belows]
Proof Type
Water
Treatment Others :
Equipment
and
Monitoring
Equipment Others :
Machinery Team of KR
7. In case where the BWTS is installed on board Oil/Chemical Tankers and if it is equipped with
monitoring devices which take samples from ballast pipe lines, please answer the following
questions.
No.
Question
Answer
an
N/A
TRO Sensor Unit
Gas Sensor Unit
Others :
Yes
E/R
(Ballast or Cargo)Pump Room
Others :
No
Mechanical Ventilation
Gas Detection & Alarm
Self-closing Gas-tight Door
Others :
7-1. In the above case and where components are directly fitted in ballast pipe line,
please answer the following questions.
No.
Question
Explosion
Proof Type
Answer
N/A
Yes
No
Yes No
Yes
No
Yes No
Yes No
Yes No
Yes No
Other 2 :
Yes No
Machinery Team of KR
8. If your BWTS uses active substances (e.g. Ozone, hydrogen peroxide), please fill in relevant
rows and columns.
No.
Question
Toxic
Flammable
Asphyxiant
Others :
Gas Detection
Mechanical Vent
What means are provided to protect crews None
from the leak of active substances ?
Others :
Answer
E/R
Pump Room
Dedicated space
Others :
Mechanical Vent.
(Air change rate :
Natural Vent.
None
Others :
/H)
9. Are any measures put in place for the case where the volume of ballast water exceeds the
maximum rated capacity of the BWTS ?
(e.g; Alarm, Automatic shut-down, Auto slow down, etc.)
Alarm
10. Does your BWTS have any redundancy for essential equipment and parts (e.g. TRO
sensing units, flow meter unit, etc) to keep the system running in case of failure?
No
Machinery Team of KR
11. Where are the spaces that you recommend to install sampling equipment according to BWM
Convention/Guideline G2 ?
(e.g; Ballast Water Discharge Line, etc.)
Yes
No
Hydrogen
Toxic
Flammable
Asphyxiant
Others :
Yes
No
On Deck
Machinery Team of KR
Published by
Machinery Team