Sie sind auf Seite 1von 51

Gwalior Shivpuri Toll Road Project

Gwalior-Shivpuri 4-Laning Project for NH-3 of the


National Highways Authority of India under NHDP
Phase-IV

Monthly Progress Report

September2014
Submitted By

Essel Gwalior Shivpuri Toll Roads Pvt Ltd


SEPTEMBER 2014 IPAGE 1 OF 51
51

Gwalior Shivpuri Toll Road Project

Scope and objective of the Report


This report is being prepared as part of the monthly submissions by the Concessionaire,
Essel Gwalior Shivpuri Toll Roads Pvt Limited, for the execution of the Gwalior-Shivpuri
4-Laning Project for NH-3 of the National Highway Authority of India (NHAI) under NHDP
Phase-IV.
This report is prepared in order to brief the progress about the key developments of the
project during the month of September 2014 and to highlight key issues concerning the
project.
Information being provided in this report supplements the daily, weekly, and other routine
exchanges and correspondence between the Concessionaire and the NHAI.
For the purpose of improved project monitoring, the project has been divided into the
following three sections:
Section-I

from Km. 0+000 to Km. 40+000 (40 km)


(Gwalior to Charairehant)

Section-II

From Km. 40+000 to Km. 80+000 (40 km)


Charairehant to Karaiahamedpur)

Section-III

From Km. 80+000 to Km. 125+300 (45.3 km)


(Karaiahamedpur to Shivpuri)

Period Covered in this Report

September 2014

Monthly Progress Report Number

Nine

SEPTEMBER 2014 IPAGE 2 OF 51


51

Gwalior Shivpuri Toll Road Project

Figure 1: Project Alignment Map

SEPTEMBER 2014 IPAGE 3 OF 51


51

Gwalior Shivpuri Toll Road Project

Table of Content

SEPTEMBER 2014 IPAGE 4 OF 51


51

Gwalior Shivpuri Toll Road Project

Table of Content

Table of Content ................................................................................................................ 5


List of Tables...................................................................................................................... 6
List of Figures .................................................................................................................... 6
Executive Summary .......................................................................................................... 7
1. Background and Project Details ............................................................................. 10
1.1. Project Overview ................................................................................................. 10
1.2. Project Contract Details ...................................................................................... 12
1.3. General Contract Details ..................................................................................... 13
1.4. Salient Project Features ...................................................................................... 13
1.5. Contractual Project Milestones .......................................................................... 14
2. Right of WayStatus................................................................................................... 16
2.1. Land Acquisition ................................................................................................. 16
2.2. Shifting of Utilities and Electrical HT/LT Lines ................................................ 17
2.3. R&R Activities ...................................................................................................... 18
2.4. Tree Cutting ......................................................................................................... 18
3. Progress Briefing Contractor Activities .............................................................. 20
3.1. Pre-Construction Activities ................................................................................ 20
3.2. Construction Activities ....................................................................................... 23
3.2.1. SECTION I: Chainage0 to 40 km .................................................................... 23
3.2.2. SECTION II:Chainage40 to 80 km ................................................................. 23
3.2.3. SECTION III:Chainage 80 to 125.3 km .......................................................... 23
4. Physical Progress of Work ...................................................................................... 25
4.1. Physical Progress of Work.................................................................................. 25
4.1.1. Highway (LHS) .................................................................................................. 25
4.1.2. Highway (RHS) ................................................................................................. 26
4.1.3. Maintenance of Existing Carriageway ............................................................ 26
5. FinancialProgress of Work ...................................................................................... 28
6. Construction Programme ........................................................................................ 31
7. Quality Control and Quality Assurance .................................................................. 33
7.1. Material ................................................................................................................ 33
7.2. Source Approval of Materials ............................................................................. 34
7.2.1. Cement............................................................................................................... 34
7.2.2. Admixtures ........................................................................................................ 35
7.2.3. Steel ................................................................................................................... 35
7.2.4. Bitumen ............................................................................................................. 35
8. Environment and Safety .......................................................................................... 37
9. Actions required from NHAI ................................................................................... 39
10
Appendices .......................................................................................................... 40
Appendix A: Organization Chart .................................................................................... 41
Appendix B: List of Plants, Machinery and Equipments .............................................. 42
Appendix C: Chainage-wise progress ............................................................................ 43
Appendix D: Project Cash Flow Statement (Planned) .................................................. 44
Appendix E: Project Progress Photographs ................................................................. 45

SEPTEMBER 2014 IPAGE 5 OF 51


51

Gwalior Shivpuri Toll Road Project

List of Tables
Table 2.1-1: Status of Land Acquisition ..................................................................................... 16
Table 2.2-1: Status of Utility Relocation .................................................................................... 17
Table 2.3-1: Status of R&R Activities ......................................................................................... 18
Table 2.4-1: Status of Tree Cutting ............................................................................................. 18
Table 3.1-1: Status of Design and Drawings-Highway ............................................................. 21
Table 3.1-2: Status of Design and Drawings Structures ......................................................... 21
Table 4.1.1-1: Progress of Highway Construction (LHS) .......................................................... 25
Table 4.1.2-1: Progress of Highway Construction (RHS) ......................................................... 26
Table 4.1.3-1: Status of Maintenance of Existing Carriageway ................................................ 26
Table 6-1: Program for the Total Project Scope (Highways) ................................................... 31
Table 6-2: Program for the Major Project Components (Structures) ..................................... 31
Table 7.1-1: Status of Construction Material ............................................................................. 33
Table 7.2-1: Source of Procuring Material ................................................................................. 34

List of Figures
Figure 1: Project Alignment Map
Figure 2: Typical Highway Cross Section
Figure 3: Financial Progress - Planned vs Achieved

3
11
29

SEPTEMBER 2014 IPAGE 6 OF 51


51

Gwalior Shivpuri Toll Road Project

Executive Summary
Following summarises the project overview and key highlights of the project up to and
including the month of September 2014.
1. Total project site area is 745 Ha. Out of this the Concessionaire has been handed over
approximately629 Ha till the end of August2014, or approximately 84 % of the site. No
additional areas have been handed over during the current month.
2. A total of 116 Ha or 16 % is not handed over. Out of the area not given possession,
approximately 80 Ha is awaiting clearance and approval from the forest authorities,
and 16 Ha from the wildlife authorities, respectively. In addition, an area of 20 Ha
comprising public and private land is also not yet handed over to the concessionaire
pending its acquisition by the NHAI. As a consequence, a total project length of about 40
kmsdoes not have vacant access to 100% Right of Way.
3. The Contractor, M/sPan India Infrastructure Pvt Ltd (PIIPL) has mobilised on the site
for execution of Highways and structures. Execution of Works is mainly progressing in
the following locations:
a. Chainage 0 to 25 km, 40 to 70 km and 100 to 120 km: Clearing & Grubbing
activities have been completed for a road length of about 95.10km. and this
includes both the Left and Right hand sides of the carriageway
b. Excavations completed for major bridge foundations at Chainage Km 61, Km
57& km 53,for 5 nos box culverts. Excavation has also been done for one Hume
Pipe Culvert (HPC), for which the bedding &pipe-laying has also been
completed .A total of 225 nos electrical poles have been procured and shifting of
75 nos has been completed.
4. Following major equipment and relevant manpower have mobilised on the site:
a. One (1) no. each of RMC, Hot-mix, WMM and Stone Crusher Plants have been set
up and commissioned at both the Mohana and Kheria camps.
b. Major camps have been set up at Mohana and Kheria for the staff, engineers and
labourers working on the project. Concessionaires organisation chart is
attached at Appendix A.
5. Financial progress of the works is Rs 518.07crores in terms of expenditure incurred
towards the project, which amounts to over 32.34% of the total estimated project cost
of Rs 1,601.77 crores.
During the month, bills for approx.Rs 53 lakhs have been raised to NHAI for the
maintenance works carried out on the project, as required by NHAI and directed
through IE.
6. To achieve the scheduled 4-laning date of 11th November 2015 in accordance with the
Concession Agreement, target dates have been worked out for completing the highway
works and all related structures mid-August 2015. Based on these target dates, a barchart has been prepared which indicates the schedule for completion of the various

SEPTEMBER 2014 IPAGE 7 OF 51


51

Gwalior Shivpuri Toll Road Project

structures and road sections. Monitoring of the project activities will henceforth be
done based on this bar chart program.
7. The targeted completion dates for the various broad elements of the project as per this
bar-chart program are :

Major Bridges

: June30, 2015.

Road Over Bridges

: August 15, 2015

Minor Bridges

: May 30, 2015

Pipe & Box Culverts

: July 22, 2015

Vehicular Under Pass

: End November 2014

Pedestrian Under Pass

: May 23, 2015

Toll Plazas & Misc.

:End May 2015

All Highway construction work has also been targeted for completion by mid-August
2015.
Whereas all effort will be made to achieve these target dates, they are subject to
reasonable modifications considering ground conditions & any unforeseen
contingencies.

SEPTEMBER 2014 IPAGE 8 OF 51


51

Gwalior Shivpuri Toll Road Project

Background and Project


Details

SEPTEMBER 2014 IPAGE 9 OF 51


51

Gwalior Shivpuri Toll Road Project

1.
1.1.

Background and Project Details

Project Overview
National Highways Authority of India has taken up four laning of NH-3 under NHDP
Phase IV to be constructed between Gwalior to Shivpuri for a design length of
125+300 Kms. The project road stretch is a part of Agra-Gwalior-Shivpuri-IndoreMumbai Road.
The Concession has been awarded to M/s Essel Gwalior-Shivpuri Toll Roads Pvt
Limited for a concession period of 29 years. The Concessionaire has achieved
financial closure on December 13, 2012 and having complied with all the conditions
precedent as stipulated in the Concession Agreement. The Authority has declared
the appointed date as May 16, 2013. Accordingly, the project construction
completion date is scheduled as November11, 2015.
The Gwalior to Shivpuri 4-Laning Project consists of construction of four lane road
between Gwalior and Shivpuri on NH-3 from Km.15+600 (NH-75) to km.236+000
(NH-3). Major towns and developed areas along the route are Ghatigaon, Mohana
and Karaiahamedpur. Land use along the road is of a mixed nature, with presence of
agricultural, forest, vacant & interspersed built up land areas.
The proposed development includes construction of 5.65 km of re-alignment, which
will be new construction in the ghat section, 36.9 km long by-passes& 82.75km
length of road along the existing alignment, which requires widening and
strengthening as well as new carriageway construction. The road alignment
generally encounters plain & rolling terrain & also passes through Forest areas, and
also areas of Son Bird Sanctuary & Madhav National Park.
As of date approximately 84 % of the ROW required for development has been
handed over to the Concessionaire. As a first priority, works have been taken up for
the highways near the Gwalior, Mohana and Shivpuri bypasses, for major bridges at
Km 57 & Km 61 and for 5 box culverts. Clearing and Grubbing activities have
advanced on both the LHS and RHS.
Project offices and laboratories for quality control of the works have been set up
and Plants for the production of aggregates, concrete, hot mix, have been
commissioned. The detailed survey for road and structures has been completed and
the EPC contractor has mobilised at site.
The cross section of the road along the route is designed to generally consist of
bituminous concrete placed on top of layers of bituminous macadam, GSB, WMM,
Sub-base and subgrade layers. A typical cross-section is shown below:

SEPTEMBER 2014 IPAGE 10 OF 51


51

Gwalior Shivpuri Toll Road Project

Figure 2: Typical Highway Cross Section

Major structures along the project alignment include 4 Major Bridges, 49 Minor
Bridges, 71 nos. Box-Culverts, 3 Road Over Bridges (ROBs), 9 nos. Pedestrian
Under Passes (PUPs) and one Vehicular Under Pass (VUP). Seventy five (75) Pipe
Culverts will be placed at appropriate locations for drainage purposes. Also
included in the project are the constructions of service roads near urban areas,
Truck lay byes, Bus bays and Toll Plazas.

SEPTEMBER 2014 IPAGE 11 OF 51


51

Gwalior Shivpuri Toll Road Project

1.2.

Project Contract Details


The following tables summarize the technical and contractual details of the project
and the contact details of key stakeholders and their personnel:
Name of Work

Four Laning of Gwalior-Shivpuri from Km


15+600 (NH-75) to km 236+000
(NH-3) in the state of MP, on DBFOT basis
under NHDP Phase IV

Name of Employer

National Highways Authority of India (NHAI)


Narender Nagar, Chhatri Road
Shivpuri (M.P.)- 473551

Name of Concessionaire

Essel Gwalior Shivpuri Toll Roads Pvt Ltd.


Kohinoor City 513, A-Wing,
Off. LBS Road, Kurla (W),
Mumbai 400070
Tel: +91-22-66012323
Fax: +91-22-66012300
Contact Person: Mr.Kaushik Pal, COO

Independent Engineer

M/s CDM Smith Inc


C/o Aditya Kumar Parasar, Patel Nagar,
Near MoniSagar Gate No 4, TV Tower Road
Shivpuri, M.P. - 473551
Team Leader Mr Ashok Goyal
(Tel 0 91652 76115)

EPC Contractor

Pan India Infrastructure Pvt. Ltd


Kohinoor City 513, A-Wing,
Off. LBS Road, Kurla (W),
Mumbai 400070
Tel: +91-22-66012323
Fax: +91-22-66012300

Design Consultant

Contact Person: Mr.Jayant Torvi, VP (Roads)

: National

I.D.C. Projects. & Asia Infrastructure Advisory


Services

: M/S CDM

SEPTEMBER 2014 IPAGE 12 OF 51


51

Gwalior Shivpuri Toll Road Project

1.3.

General Contract Details


Some salient features of the Construction Contract are noted below:

1.4.

Length of Road (Design


Length)

125.300 Km.

Total Capital Cost

Rs. 1,601.77 Crores

Total Project Cost

Rs. 1,055 Crores (as per concession agreement)

Date of Concession
Agreement

September 9. 2012

Concession Period

29 Years

Appointed Date

May 16, 2013

Construction Period

910 days from Appointed date

Completion Date

November 11, 2015

Amount of liquidated
damages as per CA

0.1% of the amount of Performance Security


For delay of each day until such Milestone is
achieved.

Salient Project Features


Besides the construction of new carriageways and widening and strengthening of
existing carriageways, the following table summarises the major elements of the
project construction:
Major Bridge

4 Nos

Minor Bridge

49 Nos.

ROB

3 Nos.

Cattle/Pedestrian Underpass

9 Nos.

Vehicular Underpass

1 No.

No. of Box Culverts

71 Nos.

No. of Pipe Culverts

75 Nos.

Truck lay byes

2 Nos.

Major Intersections

6 Nos.

Minor Intersections

30 Nos.

Bus Bays

13 Nos.

Toll Plaza

2 Nos.

4 - Lane Divided Carriage Way

2 x 7.60m

1.5 m Width Paved Shoulder

2 x 1.50 m

SEPTEMBER 2014 IPAGE 13 OF 51


51

Gwalior Shivpuri Toll Road Project

2.00 m Width Earthen/Granular Shoulder

2 x (1.00 to 2.00) m Central Median

Urban/ Built up /Rural Section

12.0m & 4.5m & 2.50m

Built up Section

7.0 m

Approaches of VUP/ Flyover

7.0 m

Footpath / Sidewalk / Built

1.5 m

Service Road

up Section

1.5.

Contractual Project Milestones

Following is a listing of the Key Project Milestones:


Mile
Stone

Description

Target Date &


Amount

Mile
Stone -I

Commencement of Highway Construction and


not less than 10 % expenditure of the Total

November 11,
2013 &

th

Mile
Stone -II

Capital Cost on 180 day from the Appointed


Date

160.00 Cr.

Commencement of all Bridges Construction and


not less than 30 % of the Total Capital Cost on

May 15,2014
& 481.00 Cr

th

365 day from the Appointed Date


Mile
Stone -III

Commencement of all Project Facilities and

May 15,2015

not less than 70% expenditure of the Total

& 1121.00 Cr.

th

Capital Cost on 730 day from the Appointed


Date
Scheduled
4 Laning
date

Scheduled four laning date shall occur on 910


day from the Appointed Date

th

November 11,
2015
& 1601.77 Cr.

SEPTEMBER 2014 IPAGE 14 OF 51


51

Gwalior Shivpuri Toll Road Project

Right of Way Status

SEPTEMBER 2014 IPAGE 15 OF 51


51

Gwalior Shivpuri Toll Road Project

2. Right of WayStatus
2.1.

Land Acquisition
As per the Concession Agreement, the project requires a Right of Way (ROW) of
60.0 metres. Accordingly, the Status of Land availability as on April 30, 2014 is
summarised in the table below. The current status tabulated below shows, that out
of a total of 745 Ha, the land available for work is over 629 Ha (Approx. 84%).
The balance land area not currently available for the project comprises about 80 Ha
of Forest and 16 Ha of wildlife authority land. However out of 80Ha forest land,
NHAI has obtained stage approval for 64.25 Ha. This is an in principle approval
where by the forest authorities have prima facie reviewed & accepted the proposal.
Another 20 Ha of revenue and private land is in the process of acquisition, wherein
the declaration of acquisition by NHAI as per section 3-D of the NHAI Act, is yet to
be made.
Table 2.1-1: Status of Land Acquisition
Description

Sr.
No.

Land
Acquisition
Area in Ha.

Remarks

Land
available for
work in Ha.

Land Not
Cleared/
Encumbra
nce in Ha.
7.765

3D under
process

80.289

Stage-I
approval
acquired(
64.259)

12.371

3D under
process

Private Land Vested


with Central Govt. as per
3a Notifications

263.776

256.011

Clear land of Existing


Road Carriageway
available

238.06

238.060

Reserve /Protected
forest formal approval
from MOEF

80.289

Reserve/ Protected
forest (Not Requiring
Diversion of Land

Govt. land to be
transferred

147.379

Wild life land

15.540

Total

745.044

629.079

115.965

100%

84.43%

15.56%

135.008

15.540

SEPTEMBER 2014 IPAGE 16 OF 51


51

Gwalior Shivpuri Toll Road Project

2.2.

Shifting of Utilities and Electrical HT/LT Lines


To proceed with the project construction, several utilities are required to be shifted
under the supervision of the respective authorities. These include a water supply
line, hand pumps, besides Electrical lines, , as shown in the table below.
Table 2.2-1: Status of Utility Relocation
Sr.No

Authority

Description

Unit

Total
Scope

Work
Done

Balance

MPMKVV

Electric lines

Km

58

Nil

58

MPPHE

Water supply
line

Km

1.5

Nil

1.5

MPPHE

Hand Pumps

No

43

35

Estimates for shifting of the above Electric lines have been prepared. The estimated
cost is approximately Rs. 6.73crores under the Gwalior Section and Rs 7.60 crores
for works under the Shivpuri divisions of MP MKVV. The current estimates are
based on the 2012 SOR and the same is being revised based on the SOR for the year
2014.
Estimates have been done for the shifting of the water supply pipeline & related
items mentioned above. The PHE department of the Shivpuri division has
completed the shifting of all the 17 nos hand pumps. For the Gwalior division, the
shifting of 18 nos. hand-pumps has been completed, out of a total of 26 nos, and the
rest are in progress.

SEPTEMBER 2014 IPAGE 17 OF 51


51

Gwalior Shivpuri Toll Road Project

2.3.

R&R Activities
The following structures coming within the ROW already handed over to the
Concessionaire are being demolished after resolving the related rehabilitation and
payment issues.

Table 2.3-1: Status of R&R Activities

2.4.

Particulars

Total

Total No. of Temples/Mazaar

22

Total Nos.Shifted

Balance

22

Tree Cutting
Table 2.4-1: Status of Tree Cutting

Particulars

Unit

Total

Permission obtained

Trees to be cut

No

17700

4599

Cutting completed

No

600

Balance

No

17100

The Concessionaire has initiated the process for payment of deposit to the Tree
Authority to cut the trees coming within the ROW. The trees for which cutting has
not commenced are lying within the forest and wildlife land, for which a the Stage
II approval is still awaited.
A detailed list of obstructions and encumbrances has been prepared and these are
being removed progressively in the areas already handed over.

SEPTEMBER 2014 IPAGE 18 OF 51


51

Gwalior Shivpuri Toll Road Project

Progress Briefing
Contractors Activities

SEPTEMBER 2014 IPAGE 19 OF 51


51

Gwalior Shivpuri Toll Road Project

3.
3.1.

Progress Briefing Contractor Activities

Pre-Construction Activities
a) Resource Mobilisation
Materials:

Material Procurement has been done to a large extent.

Aggregates to the extent of 67%, GSB- 41% and RCC Hume Pipes-40% have
already been procured / manufactured for the project works.

The total tonnage of aggregates corresponding to the above is about 19 lakh


MT, GSB is approximately 6.5 lakh MT,

The number of Hume pipes of various diameters available at site is over


1400.

Plant & Equipment:

Two nos plants each are mobilised and commissioned for RMC, Hot-Mix,
WMM and Stone crushing, at Mohana & Kheria towns. Site offices and
Quality Control Laboratories have also been set up.

Mobilization of man power, vehicles, equipment and plants by EPC


Contractor has advanced to a great degree.

A detailed list of Plant, Machinery and Equipment is attached in Appendix


B.

The Plan and Profile, as well as the Pavement Designs for the entire 125.30 km
project length has been completed and reviewed by the Independent Engineer (IE).
Construction Methodology submitted to the IE in January 2014 has been reviewed
and accepted.
b) Surveys
The Design Consultants have completed the pre-design survey works and have
obtained an inventory of highways and structures. Geo-technical investigations for
minor and major bridges, as well as for ROBs, etc, have been completed and all the
required data for designs has been obtained.

SEPTEMBER 2014 IPAGE 20 OF 51


51

Gwalior Shivpuri Toll Road Project

Table 3.1-1: Status of Design and Drawings-Highway


Sl
No

Description

Unit

Total
Scope

Design
completed

Review By IE

Good For Construction


(GFC) Drawing Issued

Sch. B
1

Pavement Design

Km

125.300

125.300

125.30

Nil

Plan & Profile

Km

125.300

125.300

125.3

75.0

Typical Cross
Sections

Type

11

11

11

Nil

Major Intersections

No

Nil

Nil

Minor
Intersections

No

30

Nil

Nil

Toll Plazas (Typical


Details)

No

Nil

Nil

Toll Plaza (Aid


Posts)

No

Nil

Nil

Truck Lay Bye

No

Nil

Nil

Bus Bay with Bus


Shelter

No

13

Nil

Nil

10

Road Signs

Km

Nil

Nil

11

Street Lighting

Km

Nil

Nil

12

Land Scaping

Km

& Plantation

Median,
GSI
location,
At grade
island &
Toll
plaza
location

Nil

Table 3.1-2: Status of Design and Drawings Structures


Sr.
No

Description

Unit

Total
Scope

Design
completed

Reviewed by
IE

Good for Construction


Drawing
Issued

Sch. B
1

Rail Over Bridge

No

Nil

Nil

MJB

No

Nil

MNB

No

49

49

49

Nil

VUP

No

Nil

PUP

No

03

Pipe Culverts

No

75

75

75

Nil

Box Culverts

No

71

71

71

Nil

SEPTEMBER 2014 IPAGE 21 OF 51


51

Gwalior Shivpuri Toll Road Project

c) Authority Approvals
Railways
Included in the project alignment are three nos. ROBs at Chainage km 2+050,
km 109+900 and at km 121+040 respectively. The General Arrangement
drawings (GADs) of these were submitted to the relevant Railway Authorities
and all the three GADs were approved by them vide their letters dated August
20, 2012 and May 24, 2012
Ministry of Environment & Forests
Environmental clearance for the project has been granted by the Ministry of
Environment & forest onMay10, 2013. The National Wild Life Board (NWLB)
clearance for both the Madhav National Park, as well as SON bird sanctuary is
awaited. Stage I forest clearance for 64.259 Ha has been obtained on
November 21, 2013
In addition to the above, following permissions / clearances / licenses /
approvals have been acquired for the project:

Quarrying permission from the State Govt

Permission of Village Panchayat & Pollution Control Board for installation of


stone crusher, asphalt plant and use of borrow area

License for the use of explosives for quarrying

State Govt permission to draw water from river / reservoir

License from Inspector of Factories or other competent authority for setting


up batching plant

State Govt permission for cutting of trees.

SEPTEMBER 2014 IPAGE 22 OF 51


51

Gwalior Shivpuri Toll Road Project

3.2.

Construction Activities

Out of the clear fronts available to the Concessionaire within the ROW and along the
alignment, work has commenced at various locations in each of the three sections along the
alignment. Up to and including this month, the construction works have progressed as
mentioned below:
3.2.1. SECTION I: Chainage 0 to 40 km
a)

Highway

Clearing and Grubbing work has been completed for a length of 36.8 km on
the Left Hand Side in this section, up to and including this month.

3.2.2. SECTION II:Chainage 40 to 80 km


a)

b)

Highway

Clearing and Grubbing work has been completed for a length of 3 km


between chainages Km 74+000 to Km 77+000, on the Left hand side. The
total length of road for which this item has been executed in this section is
now 38.3 km, up to and including this month.

Embankment construction has commenced in this section during this month


and the placement of the first layer for a total length of 1.11 km has
commenced between the chainages of Km 46 to Km 61.

Structures

Foundation Excavations have been completed for all abutments and piers,
during this month, at the Major Bridge site at km 61.

For the Major Bridge at Km 57, excavation for all foundations have been
completed except for Pier P3 and P4 in the river-bed portion, on both the
LHS and the RHS.

Work has also commenced at five nos box culvert locations at Km 50+745 ,
59+645, 60+055, 60+881 and 63+765

3.2.3. SECTION III: Chainage 80 to 125.3 km


a)

Highway

No Clearing and Grubbing work was done in this section during the month
of September 2014. The total length of road for which this activity has been
achieved so far in this section is 20 km.

The detailed Chainage-wise progress in Appendix C

SEPTEMBER 2014 IPAGE 23 OF 51


51

Gwalior Shivpuri Toll Road Project

Physical Progress of
Work

SEPTEMBER 2014 IPAGE 24 OF 51


51

Gwalior Shivpuri Toll Road Project

4.
4.1.

Physical Progress of Work

Physical Progress of Work


The following tables summarize the quantum of work achieved towards the
construction of the various elements of the highway, both LHS & RHS

4.1.1. Highway (LHS)


Table 4.1.1-1: Progress of Highway Construction (LHS)
Sr.
No.

Achieved
Description

Unit

Total
Scope

August14

In
September
-14

Total
Up to
Date
Qty.

Achieved
%

Up to

Tree Cutting

km

125.30

20.0

10.0

30.0

23.90

Clearing and
Grubbing

Km

125.300

61.30

3.00

64.30

51.3

Embankment

Km

125.300

Sub grade

Km

125.300

GSB

Km

125.300

WMM

Km

125.300

DBM

Km

125.300

BC

Km

125.300

Road Furniture

km

125.300

SEPTEMBER 2014 IPAGE 25 OF 51


51

Gwalior Shivpuri Toll Road Project

4.1.2. Highway (RHS)


Table 4.1.2-1: Progress of Highway Construction (RHS)
Description

Sr.
No.

Unit

Total
Scope

Achieved
Up to

In

August -14

September
-14

Total Up
to Date

Achieved
%

Tree Cutting

km

125.300

20.0

10.0

30.0

23.90

Clearing and
Grubbing

Km

125.300

30.80

30.80

24.58

Embankment

Km

125.300

Sub grade

Km

125.300

GSB

Km

125.300

WMM

Km

125.300

DBM

Km

125.300

BC

Km

125.300

Road Furniture

km

125.300

4.1.3. Maintenance of Existing Carriageway


The existing carriageway maintenance like pot holes, patch work etc. is in progress
along the project Highway, as required
Table 4.1.3-1: Status of Maintenance of Existing Carriageway
Sr. No.

Description

Unit

Total

Up to
August 14
0

In
September
-14

Total Up
to Date
Qty.

2.00

2.00

133

6.30

14.0

20.30

Km

133

133

133

SDBC

Km

133

80

86

Structures
repair/culvert

No

146

10

10

Earthwork in
shoulder

Km

133

GSB

Km

133

WMM

Km

BM

5
6

SEPTEMBER 2014 IPAGE 26 OF 51


51

Gwalior Shivpuri Toll Road Project

Financial Progress of
Work

SEPTEMBER 2014 IPAGE 27 OF 51


51

Gwalior Shivpuri Toll Road Project

5.

Financial Progress of Work

Up to and including the month of September 2014, there has not been any
progress related payments to contractors engaged on the project.

During the month, bills were submitted to NHAI for the following works done
by the Concessionaire :
Maintenance works.Rs53 lakhs (approx.)

The approximate costs incurred on the project till date areRs518.07Crores as


against the planned expenditure of Rs 657 Crores. Hence, the achieved financial
cumulative progress is. 32.34 % against the cumulative targeted progress of
41.02 % as per the financial programme.

The above expenditure has been incurred on setting up the various plants and
equipment for the project, procurement and production of aggregates and
materials, and also to set up the camps at various places along the alignment.

The concessionaire has worked out the planned cash flow details for the entire
project duration and these are attached at Appendix D

A snapshot of the S-Curve up to and including this period shown below,


indicates that the actual financial progress is presently lagging behind the
planned figure by Rs 139 crores. As most of the initial physical mobilisation has
been completed, this shortfall will now have to be largely covered through
progress payments to the contractors, executing the project works

SEPTEMBER 2014 IPAGE 28 OF 51


51

Gwalior Shivpuri Toll Road Project

Figure 3: Financial Progress - Planned vs Achieved

SEPTEMBER 2014 IPAGE 29 OF 51


51

Gwalior Shivpuri Toll Road Project

Construction program

SEPTEMBER 2014 IPAGE 30 OF 51


51

Gwalior Shivpuri Toll Road Project

6.

Construction Programme

Based on the requirements of the Concession Agreement (C.A.), the total scope of highway
works for the project falls into the following broad categories for which the start and
completion dates have been targeted as shown below :
Table 6-1: Program for the Total Project Scope (Highways)

Description

Start Date

End Date

New Carriageway Construction (82.75 km)

September 9, 2014

August 15,
2015

Widening &Construction. of existing C/way


(82.75 km)

October 02, 2014

July 11, 2015

Construction of Bypasses (36.9 km)

January 01, 2015

June 02, 2015

May 17, 2015

August 15,
2015

Construction of Re-Alignment portion


(5.65 km)

The above scope has been broken down into various heads and the completion of these
items including the carriageway construction, has been targeted for completion by
August15, 2015. :
The various structures to be constructed as part of the project and their planned start and
end dates are shown in the table below :
Table 6-2: Program for the Major ProjectComponents (Structures)

Description

Start Date

End Date

Major Bridges at Ch. 53+782, 57+915 &


61+827

September 01, 2014

April 09, 2015

Major Bridge at Ch. 83+678

September 01, 2014

June 30, 2015

ROBs at
121+040

Ch.

2+050,

109+900

and September 01, 2014

August 15, 2015

Minor Bridges (49 nos)

September 01, 2014

May 30, 2015

Pipe Culverts (75 nos.)

September 01, 2014

April 22, 2015

Box Culverts (71 nos.)

September 01, 2014

July 22, 2015

PUPs (9nos.)

September 01, 2014

May 23, 2015

VUP ( 1no.)

September 01, 2014

November 27, 2014

Toll Plaza Construction

March 01, 2015

May 30, 2015

Miscellaneous works

September 01, 2014

April 29, 2015

SEPTEMBER 2014 IPAGE 31 OF 51


51

Gwalior Shivpuri Toll Road Project

Quality Control and


Quality Assurance

SEPTEMBER 2014 IPAGE 32 OF 51


51

Gwalior Shivpuri Toll Road Project

7.
7.1.

Quality Control and Quality Assurance

Material
Construction materials like aggregates, sand, GSB are being produced by stone
crusher located at the Mohana & Kheria towns. Materials are being tested in the
Contractors Laboratory as per MoRTH Specifications and Indian Standard Codes.
A site laboratory has been set up with all equipment required for testing soil, GSB,
WMM, Bitumen, aggregate and concrete. GSB material, soil samples from borrow
areas, aggregates, cement and bitumen are being tested regularly. Trial mix design
for concrete with different admixtures is also in progress.
Production and stocking of aggregates, procurement of all other construction
materials is in progress. The following table shows the up to date position:
Table 7.1-1: Status of Construction Material
SR.

ITEMS

UNIT

SCOPE

No.

Cumulative
QTY
Procured
up to
August-14

QTY
procured
during
month of
September

-14

Cumulative
QTY
procured
up to
September
- 14

AGGREGATES

MT

2855500

1898067

1898067

66.47%

STEEL

MT

17187

BITUMEN

MT

55000

CEMENT

MT

136000

GSB

MT

1560000

635860

635860

40.76%

RCC Hume pipe

(a)

1200mm Dia

No.

570

248

248

43.50%

(b)

1000mm Dia

No.

820

500

500

60.97%

(c )

600mm Dia

No.

2250

695

695

30.88%

Furthermore, Concrete Mix Designs for different grades have been finalised during
this month. These designs are now available for grades M15, M20, M25&, M30.

SEPTEMBER 2014 IPAGE 33 OF 51


51

Gwalior Shivpuri Toll Road Project

7.2.

Source Approval of Materials


The following sources of materials have been approved by Concessionaire.
Table 7.2-1: Source of Procuring Material

Material

Sr.
No

Source

Remarks

Coarse Aggregate

Mohana & Kheria

Fine Aggregate

Mohana & Kheria

GSB

Mohana & Kheria

Stone Dust

Mohana & Kheria

Test results
conform to
Specification

Steel

TATA Tiscon Fe500 D

Test results
submitted to
NHAI/IE

Materials conform
to Specification

SAIL Fe500D
RINL TMT
JSPL TMT
6

Admixture

Fosroc

Test results
submitted to
NHAI/IE

Cement

Jaypee & Vikram Premium, ACC

Test results
submitted to
NHAI/IE

(OPC 43), Shree Ultra(OPC 43),


Ultra Tech(OPC 43) & Ambuja
OPC 43 Grade
8

Bitumen (VG-30)

To be submitted

Emulsion (RS-1 &


SS1)

To be submitted

10

Curing Compound

Fosroc

Test results
submitted to
NHAI/IE

11

Water

Bore Well Mohana Camp

Test results
submitted to
NHAI/IE

Bore Well Kheria Camp

7.2.1. C
SEPTEMBER 2014 IPAGE 34 OF 51
51

Gwalior Shivpuri Toll Road Project

ement
Sample material tested at EPC contractors lab & results are found confirming to
specifications. & have to be submitted for third party testing.

7.2.2. Admixtures
Sample material tested at EPC contractors lab & results are found confirming to
specifications. & have to be submitted for third party testing.
7.2.3. Steel
Sample material tested at EPC contractors lab & results are found confirming to
specifications. & have to be submitted for third party testing.
7.2.4. Bitumen
Sample material tested at EPC contractors lab & results are found confirming to
specifications. & have to be submitted for third party testing

SEPTEMBER 2014 IPAGE 35 OF 51


51

Gwalior Shivpuri Toll Road Project

Environment and Safety

SEPTEMBER 2014 IPAGE 36 OF 51


51

Gwalior Shivpuri Toll Road Project

8.

Environment and Safety

Various issues related to environment and safety, such as traffic management,


safety signages, disposal of waste materials and oil spillage, housekeeping, area
barricading and traffic management, etc, are being taken care of during the
execution of the project. .

At the quarry and crushing plants, regular sprinkling of water by tankers is being
done for dust abatement.

As mentioned earlier in this report, cutting of trees coming within the road
alignment will be necessary. The required compensatory tree plantation
programme will be taken up in hand as per the guidelines of MoEF approval, which
is under review.

A detailed Environment Management Application Plan (EMAP)has been prepared


and submitted to the Independent Engineer (IE) on 14th August 2014 and
conditionally approved.

SEPTEMBER 2014 IPAGE 37 OF 51


51

Gwalior Shivpuri Toll Road Project

Action required from


NHAI

SEPTEMBER 2014 IPAGE 38 OF 51


51

Gwalior Shivpuri Toll Road Project

9.

Actions required from NHAI

Concessionaire requests NHAI to take early action on the following issues :


1. Procurement of the Site : NHAI is requested to procure the balance 15.57% of the
land so as to provide the concessionaire vacant access to 100% Right of Way. This
procurement, which was to be completed by 12th August 2013, is still pending.
2. Applicable permits : NHAI is requested to secure the stage-II forest clearance for
about 80 Ha of land, which has been pending since the Appointed date.
3. Shifting of Electrical utility : NHAI is requested to approve estimates of electrical
utility shifting and deposit the required supervision charges with the respective
departments.
4. Shifting of EHT Line : A total of five EHT lines would be required to be shifted in
order to proceed with the project construction. NHAI is requested to deposit the
supervision charges with the concerned department.
5. Site to be free of encumbrances : NHAI is requested to provide the site free from all
encumbrances, This is pending since 12th August 2013.

SEPTEMBER 2014 IPAGE 39 OF 51


51

Gwalior Shivpuri Toll Road Project

10 Appendices

Appendix A

Organization Chart

Appendix B

List of Plant, Machinery and Equipment

Appendix C

Chainage-wise progress

Appendix D

Project Cash Flow Statement

Appendix E

Project Progress Photographs

SEPTEMBER 2014 IPAGE 40 OF 51


51

Gwalior Shivpuri Toll Road Project

Appendix A: Organization Chart

SEPTEMBER 2014 IPAGE 41 OF 51


51

Gwalior Shivpuri Toll Road Project

Appendix B: List of Plants, Machinery and Equipments


Sr.
No

350 TPH

Crusher Plant (
with sand
classifier unit)
Crusher Plant

Condition of
Equipment
working/
breakdown
Working

250 TPH

Working

Kheria

HMP

200 TPH

Working

Mohana &
Kheria

WMM Plant

200 TPH

Working

RMC Plant-

60cum/hr

Working

Excavator

Working

Loader

Working

Grader

Working

JCB backhoe

Working

10

Hydra

Working

11

Hywa (Tippers)

14

Working

12

Weigh Bridge

Working

13

Tandem Roller

Working

14

Vibratory Roller

Working

15

PTR Roller

Working

16

Apollo Sensor
Paver

Working

17

Tractor

Working

18

Bitumen Sprayer

Working

19

Needle Vibrators

Working

20

Welding Machine

Working

21

Dewatering pump

Working

22

Air Compressor

Working

Plant &
Equipment

Capacity
/ Make

Min.
Requirement

Mobilized

Location

Mohana

SEPTEMBER 2014 IPAGE 42 OF 51


51

Gwalior Shivpuri Toll Road Project

Appendix C: Chainage-wise progress

Clearing and Grubbing


LHS
Upto Previous Month

This Month

August -14

September-14

From

To

0+500

15+400

14.9

14.900

15+400

22+400

7.00

7.000

47+000

67+000

50+000

54+100

54+100

57+000

77+000

79+400

108+000

Length (KM)

From

To

Total up to
date

Length (KM)

Length(KM)

20.00

20.000

4.1

4.100
2.9

2.900
74+000

77+000

3.00

5.400

2.40
10.0

118+000
Total

10.000

61.30

3.00

64.300

Clearing and Grubbing


RHS
Upto Previous Month

This Month

July-14

August -14

From

To

0+500

15+400

14.90

14.90

54+100

57+000

2.90

2.90

60+000

63+000

108+000

118+000

Total

Length (KM)

From

To

Total up to
date

Length (KM)

Length (KM)

3.00
10.00

30.80

10.00

0.00

30.80

SEPTEMBER 2014 IPAGE 43 OF 51


51

Gwalior Shivpuri Toll Road Project

Appendix D: Project Cash Flow Statement (Planned)

SEPTEMBER 2014 IPAGE 44 OF 51


51

Gwalior Shivpuri Toll Road Project

Appendix E: Project Progress Photographs

Clearing and Grubbing Operation

Grading of Embankment at Ch 63+000

SEPTEMBER 2014 IPAGE 45 OF 51


51

Gwalior Shivpuri Toll Road Project

Rolling of Embankment at Ch 63+000

Laying of Hume Pipe for Culvert at Ch 51+250

SEPTEMBER 2014 IPAGE 46 OF 51


51

Gwalior Shivpuri Toll Road Project

Transit Mixers at Ch 59+150

Hot Mix Plant (200TPH) at Mohana camp

SEPTEMBER 2014 IPAGE 47 OF 51


51

Gwalior Shivpuri Toll Road Project

Batching Plant (60cum) with cement store at Mohana camp

Rolling of Embankment at Ch 61+000

SEPTEMBER 2014 IPAGE 48 OF 51


51

Gwalior Shivpuri Toll Road Project

Shifting of Electrical Poles

Testing Laboratory at Mohana camp

SEPTEMBER 2014 IPAGE 49 OF 51


51

Gwalior Shivpuri Toll Road Project

Maintenance work of Existence Road

Maintenance work of Existence Road

SEPTEMBER 2014 IPAGE 50 OF 51


51

Gwalior Shivpuri Toll Road Project

Ready Mix Concrete Plant at Ch 58+950

SEPTEMBER 2014 IPAGE 51 OF 51


51

Das könnte Ihnen auch gefallen