Beruflich Dokumente
Kultur Dokumente
Gray Mullins, Ruben Sosa, Rajan Sen and Moussa Issa, University of South Florida, Tampa, FL, USA
This paper presents results from model and full-scale tests to assess the
interface bond between a cast-in-place concrete seal slab and steel H-piles in
cofferdams. Three different seal slab placement conditions - fresh water, salt
water and bentonite slurry - were evaluated and the results compared against
controls where no fluid was displaced by the concrete. Normal pile surfaces
were investigated. Additionally, the situation of soil caked piles was also tested.
In the model tests, eight 15 cm deep, W6 x 15 sections were used for two
different embedment depths of 1.5d and 2d, d being the depth of the section. In
the full-scale tests, 16 specimens 35 cm deep (W14 x 90 sections) were tested
with the embedment varied between 0.5d-2d. The results show that significant
bond stresses developed even in the worst placement condition.
Recommendations made for revising current values in specifications have
already been implemented by the Florida Department of Transportation.
INTRODUCTION
Driven Piles
(HP sections)
Pile Template
RESEARCH SIGNIFICANCE
This study provides the first set of experimental
results on the interface shear between steel
piles and seal concrete slabs cast in accordance
with construction specifications6. The results
obtained have already led to increased
allowable interface shear in the latest
specifications.7 This should result in reduced
construction costs.
Steel Piles
Cast-in-Place
Seal Slab
In-situ Soil
Hydrostatic Uplift
Pressure
OBJECTIVES
The overall goal of the study was to recommend
interface shear stress values for seal slab and
piles that could be directly used in FDOTs
design specifications. These values were to be
based on full-scale tests conducted on
specimens that had been prepared in
accordance with current FDOT specifications6
for conditions that were commonly encountered.
Variables examined were the pile embedment
depth, effect of pile surface, effect of the pile
material (steel or concrete) and the type of fluid
that was displaced by the concrete.
Single Pile
Tension Tests
Profile View
EXPERIMENTAL PROGRAM
The load transfer characteristics in seal slabs
can be simulated by conducting pullout tests as
illustrated in Figure 2 in which compressive
loads are applied to the seal slab and tensile
loads to the steel piles. Careful attention had to
be paid to the experimental set-up so that tests
could be carried out under field conditions.
Small-scale bond tests were conducted to
identify the maximum pullout lengths for a 1/3
scale pilot study. Results of the pilot study were
used to subsequently refine the apparatus and
procedures for the full-scale testing.
Varied
Embedment
Depth
Cofferdam Simulation
Four, 0.76 m high wood boxes with inside
dimensions of 1.4 m x 1.4 m were fabricated to
simulate the four placement conditions. Plastic
sheeting was used to line and seal the boxes.
Wood templates were used to properly position
each pile within the simulated cofferdams. The
piles were spaced at 3 x pile size, i.e. the center
to center distance was 45 cm. The edge
spacing from the center line to the box edge was
1.5d or 22.5 cm.
All piles were identical in length and tip
elevation; however, the two different embedment
depths of 1.5d and 2d were accommodated by
varying the bonded and debonded lengths within
the concrete. The bonded region (steel to seal
slab) was provided at the bottom of the
simulated cofferdam in all the specimens. For
the 15 cm piles, the bonded length was either
22.5 cm (1.5d) or 30 cm (2d). Above this
bonded length, the piles were debonded using a
thick layer of bitumen (Figure 3) applied up to a
height sufficiently above the anticipated upper
surface of the seal slab. The overall slab
thickness and debonded region was set such
that the bitumen extended at least 1d below the
upper seal slab surface for all specimens. This
minimum debond length was intended to
eliminate bearing stress concentrations based
on finite element modeling.
Three of the four boxes were filled with either
fresh water, 3% salt water or bentonite slurry
(Figure 3). The latter was made by mixing dry,
high yield bentonite and fresh water to achieve
slurry properties similar to those in the FDOT
specifications6. The final density achieved was
10 kN/m3 (64 pcf) with a pH of 8 and a viscosity
of 37 seconds (Marsh Cone method). The
fourth box served as a control and was therefore
not filled.
Bituminous coating
(debond region)
Figure 3: Drilling fluid pumped into
simulated cofferdam
Seal Slab Placement
Class III seal concrete specified by FDOT6 was
used. The specified 28 day strength of the seal
slab was 21MPa (3000 psi). This mix has 330 kg
of cement / m3 (560 lb of cement/cy) and a water
cement ratio of 0.51.
The concrete was
purchased from a Readi-Mix plant and was
pumped through a 76 mm (3 inch) diameter
hose. The concrete was placed from the bottom
upwards keeping the hose tip below the rising
level of concrete. This is similar in placement
and identical in effect to using a tremie pipe.
Pullout Frame
The pullout frame used is shown in Figure 4. It
consists of two telescopic sections that react
against each other via a stiffened beam and a
hydraulic jack. The pile specimen was bolted to
the tension assembly. The pullout frame
weighed 2.2 kN fully assembled and required an
overhead chain hoist to assemble and/or move.
Tension loads were measured using a load cell
positioned between the top of the jack and the
tension assembly. The stiffened beam
transferred load from the base of the jack to a
built-up column section which in turn applied
uniform compressive stress to the seal slab.
Hydraulic
Jack
Load Cell
Stif fened
Beam
Load Cell
Tension
Assembly
Compression
Assembly
Splice Plates
Control
Salt
fc
MPa
Bond
Lgth
Bond
Area
(m2)
Pull
out
Load
(kN)
Bond
Stress
(MPa)
H41
31
1.5d
0.206
611
3.01
H42
31
2d
0.274
720
2.66
H21
31
1.5d
0.206
744
3.66
H22
31
2d
0.274
563
2.08
H31
31
1.5d
0.206
336
1.66*
H32
31
2d
0.274
620
2.29
H11
31
1.5d
0.206
320
1.58
H12
31
2d
0.274
344
1.27
Water
Fresh
Water
Test Procedure
Pullout tests were commenced after the seal
slab had been cured for 72 hours in accordance
with FDOT requirements. Concrete cylinders
were tested at periodic intervals to monitor the
change in compressive strength. The tension
Specimen
Bentonite
Testing Apparatus
W14 x 90 Specimens
PilePositioning
Template
Plastic-lined
Box Forms
Supplemental
Lateral Bracing
Tension Assembly
Tension Assembly
Hydraulic Jack
Placement Conditions
One cofferdam was left dry prior to concrete
placement (control); the second was filled with
fresh water from a nearby potable source. The
third was filled with bentonite slurry which was
made by mixing dry, high yield bentonite and
fresh water. The mixing was accomplished
through the use of a shear pump. Enough
bentonite clay was added to achieve slurry
properties similar to FDOT specifications. The
final density achieved was 10 kN/m3 (65 pcf)
with a viscosity of 40 seconds (Marsh Cone
Method) and a pH of 8.
Seal Slab Placement
Seal concrete was placed using a concrete
pump truck. The concrete was pumped through
a 15 cm (6 in) diameter hose and was placed
from the bottom upwards keeping the hose tip
below the rising level of concrete. This is similar
in placement and identical in effect to the tremie
method.
2 Splice Plates
(1 shown)
Compression
Assembly (4 legs)
W14 x 90 Specimens
Test Procedure
The test setup and procedure was similar to the
pilot study involving placing a grout layer,
connecting the tension assembly to the pile,
lowering the compression assembly on to the
leveled grout surface, attach the appropriate
instrumentation, and extract the specimens.
However, some variations were adopted to
expedite the testing procedure so less variation
in concrete strength would be observed after the
72 hour FDOT curing period.
Load Cell
Hydraulic Jack
W14 x 90
Specimens
Leveling
Grout Pad
Seal Slab
Spec.
(w)
fc
MPa
Bond
Lgth
(w)
Pull
out
Load
kN
Bond
Stress
MPa
Control
SC0.5
32
0.5d
618
1.63
SC1.0A
32
1d
1018
1.34
SC1.0B
32
1d
1100
1.45
SC1.5A
32
1.5d
1140
1.00
SC.15B
32
1.5d
1187
1.04
SW0.5
27.5
0.5d
438
1.15
SW1.0A
27.5
1d
1105
1.33
SW1.0B
27.5
1d
975
1.29
SW1.5A
27.5
1.5d
1317
1.16
SW1.5B
27.5
1.5d
1116
0.98
SB1B
23.5
1d
874
1.15
SB1D
23.5
1d
466
0.62
SB2A
23.5
2d
827
0.55
SB2B
23.5
2d
767
0.50
Bentonite
SB1A
23.5
1d
629
0.83
(soilcaked)
SB1C
23.5
1d
753
0.99
Fresh
Water
Bentonite
Ave
MPa
Normalized
MPa
1.40
1.20
1.02
0.88
1.31
1.21
1.07
0.99
0.88
0.88
0.52
0.52
0.91
0.91
23.5
32
Displacement (mm)
6
8
Displacement (mm)
10
12
300
10
12
300
1200
1200
SW1.0B
1000
800
150
600
1dEmbedment
100
400
50
0
200
2dEmbedment
800
150
50
600
400
1dEmbedment
(soil caked)
200
0.00
0.10
0.20
0.30
0.40
0.50
0
0.00
0.10
0.20
0.30
0.40
Displacement (in)
10
12
300
SC0.5
1.5d Embedment
250
DISCUSSION
1200
SC1.0B
SC1.5B
1000
800
150
1d Embedment
600
100
50
400
0.5d Embedment
200
0
0.00
0
0.10
0.20
0.30
0.40
Displacement (in)
Load (kN)
200
Load (kips)
1000
SB2A
100
200
0.5dEmbedment
SB1B
1dEmbedment
Load (kN)
SW1.5B
200
SB1A
250
Load (kips)
250
0.50
0
0.50
Load (kN)
SW0.5
1.5dEmbedment
Load (kips)
Condition
Fb (kPa)
Steel
Salt/Fresh Water
1000
Bentonite
350