Sie sind auf Seite 1von 7

The Details of Equipments to be erected

SLNo
1

Description of the Equipment


Ring Main Units

Sectionalisers

FPIs

Name of the
Town where
the Equipment
to be erected
Vijayawada
Guntur
Nellore
Total
Vijayawada
Guntur
Nellore
Total
Vijayawada
Guntur
Nellore
Total

Quantity to be
erected (In Nos)
150
100
75
325
150
100
75
325
100
100
50
250

Price Schedule for erection of RMU,Sectionalisers and FPIs with associated equipment under turnkey basis (R-APDRP
PART B)
in Vijayawada , Guntur and Nellore Towns
BID DOCUMENT No.SIP- 49 /2015-16
(This section consists of the following schedules)

S.No.

Qty.

325

Schedule
Code No.

Description

Estimated rates in Rs.


Material

Labour

Total
Amount

supply and erection of Ring main Units with associated


equipment

S1

215035714

16300928

231336642

supply and erection of sectionalisers with associated


equipment

S2

211347227

3409601

214756828

S3

16633750

6260750

22894500

TOTAL

443016691

25971279

468987970

WELFARE CESS @1 %

4430167

259713

4689880

SERVICE TAX @ 14 % ON LABOUR CHARGES

3635979

3635979

GRAND TOTAL

447446858

29866971

477313829

Nos.
2

325

Nos.
250 supply and erection of FPIs with associated equipment
Nos.

file:///var/www/apps/conversion/tmp/scratch_4/280552938.xlsx

SIP-49-205-16

RMU

S1-Price Schedule for Erection of RMU with associated equipment


Proposed amount in Rs.
Total unit
Amount for
Amount for
rate
Material
Labour
(Col.5+6)
(Col.2X5)
(Col.2X6)
7
8
9

S.
No.

Qty.

Description of Item

Unit

3
Supply and erection of 3 way 11KV motorised RMU including
transportation complete as per specification(SCADA /DMS
Compatable)

Each

5276867.76

2128.95

529816.71

527687.76

2128.95

529816.71

Consruction of plinth for RMU:


Excavation of pit of size 2.1MX1.2MX0.6M,filling with sand for
150mm dept,laying bed concrete with CC(1:4:8) USING 40mm
HBG metal for 150mm,construction of plint as per drawing (2
Supports) with RR Masanory of size0.837 Cum,and plastering
all around the outer side with CM (1:5) 12 mm Thick and white
washing 2coats including cost and trasnsport of all material
and labour charges for all operation incidential charges etc.,
complete as directed by the engineer incharge.

Each

3839.99

3123.15

6963.14

3839.99

3123.15

6963.14

60

Supply, laying, testing and commissioning of 11KV 185Sq.mm


XLPE armoured cable including tranportation from incoming
poles to RMU and RMU to outgoing poles and with proper
clamping arrangements from poles and forming cable trench
including of providing of suitable glands and lugs wherever
necessary with identifications clearly marked on it.

Each

1056.78

212.33

1269.11

63406.80

12739.50

76146.30

18

Supply, making end terminations, testing and commissioning


of 11KV, 3cx185Sqmm, XLPE armoured cable with heat
shrinkable cable end termination kits suitable for indoor and
outdoor type

Each

3334.50

1675.80

5010.30

60021.00

Supply and erection of . 80mm dia 6mm thick 2.54Mtrs. long


CI earth pipe including excavation of pit, earthing with No.8 GI
wire, supply and refilling the pit with bentonite powder and soil
with ratio 1:4 and giving connections etc., as per departmental
standards

Each

3346.40

1000.35

4346.75

6692.80

Unit Rate for Unit Rate


material
for labour

30164.40

2000.70

Total Amount
(Col.8+9)
10

90185.40

8693.50

RMU
Total

661648.35

50156.70

711805.05

SECTIONLIZER

S2-Price Schedule for Erection of sectionlisers with associated equipment


S.
No.

Qty.

Description of Item

Unit

Unit Rate for


material

Unit Rate
for labour

Proposed amount in Rs.


Total unit
Amount for
Amount for
rate
Material
Labour
(Col.5+6)
(Col.2X5)
(Col.2X6)
7
8
9

Total Amount
(Col.8+9)
10

Supply of sectiionaliser(SCADA Compatable) including


galvonised mounting frame for mounting to PSCC
Poles,cables for incoming and out going, Terminal
connectors for connecting incoming and outgoing cables,
control cable etc.,

Each

613548.00

2128.95

615676.95

613548.00

2128.95

615676.95

Supply & Erection of 12.5 M Spun poles including


transport, loading, unloading and pit excavation (pit size 0.9
X0.9 X2.1Mtrs.) in all soils except which require blasting Each
(excluding cost of concreting of pole) (Wherever
necessary as per the field conditions)

13338.00

4139.63

17477.63

13338

4139.63

17477.63

Pole Concreting (pit size 0.9 X0.9 X2.1Mtrs.) for 12.5Mt


Each
spun Pole

5697.00

1596.00

7293.00

0.00

0.00

0.00

Supply and erection of 11 kv 200 Amp TT AB switch with


post type insulators on already erected 12.5M Spun pole
along with 75X40X6mm MS channel for supporting AB
switch pipe and .U Clamps with 50X6mm, Back clamp with Each
50X6mm MS flat, . MS angle 50X50X6mm for supporting
AB switch including bolts, nuts & washers for givinig
connection to sectionlizers

13231.36

1675.80

14907.16

13231.36

1675.80

14907.16

129.00

34.00

163.00

1161.00

306.00

1467.00

388.00

40.00

428.00

2328.00

240.00

2568.00

3346.40

1000.35

4346.75

6692.80

2000.70

8693.50

Supply and erection of 11KV Pin insulators and hardware


Each
complete as per specification
Supply and erection of 11KV 45KN composite polymer
Each
insulators & Hard ware as per specification
Supply and erection of . 80mm dia 6mm thick 2.54Mtrs.
long CI earth pipe including excavation of pit, earthing with
No.8 GI wire, supply and refilling the pit with bentonite Each
powder and soil with ratio 1:4 and giving connections etc.,
as per departmental standards

Total

650299.16

10491.08

660790.24

SECTIONLIZER

FPI

S3-Price Schedule for Erection of FPI with associated equipment


S.
No.

Qty.

Description of Item
3
Supply and erection of FPI including transportation complete
as per specification(SCADA /DMS Compatable)
Total

Unit
4
Each

Proposed amount in Rs.


Unit Rate
Total unit
Amount for
Amount for
Unit Rate for
for
rate
Material
Labour
labour
material
(Col.5+6)
(Col.2X5)
(Col.2X6)
5
6
7
8
9
66535.00

25043.00

91578.00

66535.00
66535.00

25043
25043.00

Total Amount
(Col.8+9)
10
91578
91578.00

Das könnte Ihnen auch gefallen