Sie sind auf Seite 1von 2

72350 Federal Register / Vol. 72, No.

244 / Thursday, December 20, 2007 / Notices

competing development application must be filed by providing the original j. Deadline for filing comments,
must submit to the Commission, on or and the number of copies provided by protests, and motions to intervene: 60
before a specified comment date for the the Commission’s regulations to: The days from the issuance date of this
particular application, either a Secretary, Federal Energy Regulatory notice.
competing development application or a Commission, 888 First Street, NE., All documents (original and eight
notice of intent to file such an Washington, DC 20426. An additional copies) should be filed with: Kimberly
application. Submission of a timely copy must be sent to Director, Division D. Bose, Secretary, Federal Energy
notice of intent to file a development of Hydropower Administration and Regulatory Commission, 888 First
application allows an interested person Compliance, Federal Energy Regulatory Street, NE., Washington, DC 20426.
to file the competing application no Commission, at the above-mentioned Comments, protests, and interventions
later than 120 days after the specified address. A copy of any notice of intent, may be filed electronically via the
comment date for the particular competing application or motion to Internet in lieu of paper; see 18 CFR
application. A competing license intervene must also be served upon each 385.2001(a)(1)(iii) and the instructions
application must conform with 18 CFR representative of the Applicant on the Commission’s Web site under the
4.30 and 4.36. specified in the particular application. ‘‘e-Filing’’ link. The Commission
o. Notice of Intent—A notice of intent s. Agency Comments—Federal, state, strongly encourages electronic filings.
must specify the exact name, business and local agencies are invited to file Please include the project number (P–
address, and telephone number of the comments on the described application. 13041–000) on any comments or
prospective applicant, and must include A copy of the application may be motions filed.
an unequivocal statement of intent to obtained by agencies directly from the The Commission’s Rules of Practice
submit, if such an application may be Applicant. If an agency does not file and Procedure require all intervenors
filed, either a preliminary permit comments within the time specified for filing documents with the Commission
application or a development filing comments, it will be presumed to to serve a copy of that document on
application (specify which type of have no comments. One copy of an each person in the official service list
application). A notice of intent must be agency’s comments must also be sent to for the project. Further, if an intervenor
served on the applicant(s) named in this the Applicant’s representatives. files comments or documents with the
public notice. Commission relating to the merits of an
p. Proposed Scope of Studies Under Kimberly D. Bose, issue that may affect the responsibilities
Permit—A preliminary permit, if issued, Secretary. of a particular resource agency, they
does not authorize construction. The [FR Doc. E7–24661 Filed 12–19–07; 8:45 am] must also serve a copy of the document
term of the proposed preliminary permit BILLING CODE 6717–01–P on that resource agency.
would be 36 months. The work k. Description of Project: The
proposed under the preliminary permit proposed project using the Pearl River
would include economic analysis, DEPARTMENT OF ENERGY Valley Water Supply District’s Ross
preparation of preliminary engineering Barnett Dam and operated in a run-of-
plans, and a study of environmental Federal Energy Regulatory river mode would consist of: (1) A new
impacts. Based on the results of these Commission 100-foot long, 125-foot wide, 50-foot
studies, the Applicant would decide [Project No. 13041–000] high concrete powerhouse; (2) three
whether to proceed with the preparation 400-foot-long, 12-foot-diameter steel
of a development application to BPUS Generation Development, LLC; penstocks; (3) a new intake east of the
construct and operate the project. Notice of Application Accepted for spillway and a new tailrace on the east
q. Comments, Protests, or Motions to Filing and Soliciting Motions To bank of the existing stilling basin; (4)
Intervene—Anyone may submit Intervene, Protests, and Comments three turbine/generator units with a
comments, a protest, or a motion to combined installed capacity of 24
December 13, 2007.
intervene in accordance with the megawatts; (5) a new 2.2-mile long
requirements of Rules of Practice and Take notice that the following above ground transmission line
Procedure, 18 CFR 385.210, .211, .214. hydroelectric application has been filed extending northwest from the
In determining the appropriate action to with the Commission and is available switchyard near the powerhouse to the
take, the Commission will consider all for public inspection: existing Church Street substation owned
a. Type of Application: Preliminary
protests or other comments filed, but by Mississippi Power & Light; and (6)
Permit.
only those who file a motion to appurtenant facilities. The proposed
b. Project No.: 13041–000.
intervene in accordance with the c. Date filed: September 28, 2007. Ross Barnett Project would have an
Commission’s Rules may become a d. Applicant: BPUS Generation average annual generation of 54
party to the proceeding. Any comments, Development, LLC. gigawatt-hours.
protests, or motions to intervene must e. Name of Project: Ross Barnett l. This filing is available for review at
be received on or before the specified Hydroelectric Project. the Commission in the Public Reference
comment date for the particular f. Location: Pearl River in Rankin Room or may be viewed on the
application. County, Mississippi. It would use the Commission’s Web site at
r. Filing and Service of Responsive Pearl River Valley Water Supply http://www.ferc.gov using the
Documents—Any filings must bear in District’s Ross Barnett Dam. ‘‘eLibrary’’ link. Enter the docket
all capital letters the title g. Filed Pursuant to: Federal Power number excluding the last three digits in
‘‘COMMENTS’’, ‘‘NOTICE OF INTENT Act, 16 U.S.C. 791(a)–825(r). the docket number field to access the
TO FILE COMPETING APPLICATION’’, h. Applicant Contact: Mr. Jeffrey M. document. For assistance, call toll-free
‘‘COMPETING APPLICATION’’, Auser, P.E., BPUS Generation 1–866–208–3676 or e-mail
sroberts on PROD1PC70 with NOTICES

‘‘PROTEST’’, and ‘‘MOTION TO Development, LLC, 225 Greenfield FERCONLINESUPPORT@FERC.GOV.


INTERVENE’’, as applicable, and the Parkway, Suite 201, Liverpool, NY For TTY, call (202) 502–8659. A copy is
Project Number of the particular 13088, (315) 413–2700. also available for inspection and
application to which the filing refers. i. FERC Contact: Robert Bell, (202) reproduction at the address in item h
Any of the above-named documents 502–4126. above.

VerDate Aug<31>2005 20:08 Dec 19, 2007 Jkt 214001 PO 00000 Frm 00010 Fmt 4703 Sfmt 4703 E:\FR\FM\20DEN1.SGM 20DEN1
Federal Register / Vol. 72, No. 244 / Thursday, December 20, 2007 / Notices 72351

m. Competing Preliminary Permit— protests or other comments filed, but a. Type of Application: Preliminary
Anyone desiring to file a competing only those who file a motion to Permit.
application for preliminary permit for a intervene in accordance with the b. Project No.: 13043–000.
proposed project must submit the Commission’s Rules may become a c. Date Filed: September 28, 2007.
competing application itself, or a notice party to the proceeding. Any comments, d. Applicant: BPUS Generation
of intent to file such an application, to protests, or motions to intervene must Development, LLC.
the Commission on or before the be received on or before the specified e. Name of Project: New Savannah
specified comment date for the comment date for the particular Bluff Lock and Dam Hydroelectric
particular application (see 18 CFR 4.36). application. Project.
Submission of a timely notice of intent r. Filing and Service of Responsive f. Location: Savannah River in
allows an interested person to file the Documents—Any filings must bear in Richmond County, Georgia, and Aiken
competing preliminary permit all capital letters the title County, South Carolina. It would use
application no later than 30 days after ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT the U.S. Army Corps of Engineers’ New
the specified comment date for the TO FILE COMPETING APPLICATION’’, Savannah Bluff Lock and Dam.
particular application. A competing ‘‘COMPETING APPLICATION’’, g. Filed Pursuant to: Federal Power
preliminary permit application must ‘‘PROTEST’’, and ‘‘MOTION TO Act, 16 U.S.C. 791(a)–825(r).
conform with 18 CFR 4.30 and 4.36. INTERVENE’’, as applicable, and the h. Applicant Contact: Mr. Jeffrey M.
n. Competing Development Project Number of the particular Auser, P.E., BPUS Generation
Application—Any qualified application to which the filing refers. Development, LLC, 225 Greenfield
development applicant desiring to file a Any of the above-named documents Parkway, Suite 201, Liverpool, NY
competing development application must be filed by providing the original 13088, (315) 413–2700.
must submit to the Commission, on or i. FERC Contact: Robert Bell, (202)
and the number of copies provided by
before a specified comment date for the 502–4126.
the Commission’s regulations to: The j. Deadline for filing comments,
particular application, either a Secretary, Federal Energy Regulatory
competing development application or a protests, and motions to intervene: 60
Commission, 888 First Street, NE., days from the issuance date of this
notice of intent to file such an Washington, DC 20426. An additional
application. Submission of a timely notice.
copy must be sent to Director, Division All documents (original and eight
notice of intent to file a development of Hydropower Administration and
application allows an interested person copies) should be filed with: Kimberly
Compliance, Federal Energy Regulatory D. Bose, Secretary, Federal Energy
to file the competing application no Commission, at the above-mentioned
later than 120 days after the specified Regulatory Commission, 888 First
address. A copy of any notice of intent, Street, NE., Washington, DC 20426.
comment date for the particular competing application or motion to
application. A competing license Comments, protests, and interventions
intervene must also be served upon each may be filed electronically via the
application must conform with 18 CFR representative of the Applicant
4.30 and 4.36. Internet in lieu of paper; see 18 CFR
specified in the particular application. 385.2001(a)(1)(iii) and the instructions
o. Notice of Intent—A notice of intent s. Agency Comments—Federal, state,
must specify the exact name, business on the Commission’s Web site under the
and local agencies are invited to file ‘‘e-Filing’’ link. The Commission
address, and telephone number of the comments on the described application.
prospective applicant, and must include strongly encourages electronic filings.
A copy of the application may be Please include the project number (P–
an unequivocal statement of intent to obtained by agencies directly from the
submit, if such an application may be 13043–000) on any comments or
Applicant. If an agency does not file motions filed.
filed, either a preliminary permit comments within the time specified for
application or a development The Commission’s Rules of Practice
filing comments, it will be presumed to and Procedure require all intervenors
application (specify which type of have no comments. One copy of an
application). A notice of intent must be filing documents with the Commission
agency’s comments must also be sent to to serve a copy of that document on
served on the applicant(s) named in this
the Applicant’s representatives. each person in the official service list
public notice.
p. Proposed Scope of Studies Under Kimberly D. Bose, for the project. Further, if an intervenor
Permit—A preliminary permit, if issued, Secretary. files comments or documents with the
does not authorize construction. The [FR Doc. E7–24662 Filed 12–19–07; 8:45 am] Commission relating to the merits of an
term of the proposed preliminary permit BILLING CODE 6717–01–P
issue that may affect the responsibilities
would be 36 months. The work of a particular resource agency, they
proposed under the preliminary permit must also serve a copy of the document
would include economic analysis, DEPARTMENT OF ENERGY on that resource agency.
preparation of preliminary engineering k. Description of Project: The
plans, and a study of environmental Federal Energy Regulatory proposed project using the U.S. Army
impacts. Based on the results of these Commission Corps of Engineers’ New Savannah Bluff
studies, the Applicant would decide Lock and Dam and operated in a run-of-
[Project No. 13043–000]
whether to proceed with the preparation river mode would consist of: (1) A new
of a development application to BPUS Generation Development, LLC; 30-foot long, 30-foot wide, 30-foot high
construct and operate the project. Notice of Application Accepted for concrete powerhouse; (2) an intake
q. Comments, Protests, or Motions to Filing and Soliciting Motions To channel and tailrace channel on the
Intervene—Anyone may submit Intervene, Protests, and Comments South Carolina side of the river,
comments, a protest, or a motion to opposite the existing lock; (3) two
sroberts on PROD1PC70 with NOTICES

intervene in accordance with the December 13, 2007. turbine/generator units with a combined
requirements of Rules of Practice and Take notice that the following installed capacity of 7 megawatts; (4) a
Procedure, 18 CFR 385.210, .211, .214. hydroelectric application has been filed new 10,981-foot long above ground
In determining the appropriate action to with the Commission and is available transmission line extending from the
take, the Commission will consider all for public inspection: switchyard near the powerhouse south

VerDate Aug<31>2005 20:08 Dec 19, 2007 Jkt 214001 PO 00000 Frm 00011 Fmt 4703 Sfmt 4703 E:\FR\FM\20DEN1.SGM 20DEN1