Beruflich Dokumente
Kultur Dokumente
(Pr001)
Issue No.
THIRD ISSUE
AUTHOR
HSSE Manager
Date
Signature
23/01/2012
REGISTERED COPY
No.
This document is the property of Majan Electricity Company. Neither the whole nor any part of
this document may be disclosed to others or reproduced, stored in a retrieval system, or
transmitted in any form by any means (electronic, mechanical, reprographic recording or
otherwise) without prior written consent of the owner.
VERSION 3 BY MJEC,OMAN
CONTENTS
1.
INTRODUCTION
2.
3.
GENERAL PROVISIONS
3.01
DUTIES
3.02
OBJECTIONS
3.03
STATUTORY REGULATIONS
3.04
STANDARD FORMS
3.05
3.06
3.07
FAILURE OF SUPPLY
3.08
ADMITTANCE TO STATIONS
3.09
VARIATION OF RULES
3.10
APPLICATION OF RULES
3.11
4.
4.1
ACCESS
4.2
SWITCHING PROCEDURES
4.3
4.4
4.5
EARTHING
4.6
4.7
Page 2
VERSION 3 BY MJEC,OMAN
5.
5.1
INITIATION OF DOCUMENTS
5.2
5.3
5.4
6.
6.1
6.2
6.3
6.4
6.5
6.6
6.7
7.
7.1
GENERAL
7.2
7.3
SAFETY PRECAUTIONS
8.
8.1 GENERAL
8.2 LIVE LINE TOOLS AND EQUIPMENT
8.3 SAFETY PRECAUTIONS
Page 3
VERSION 3 BY MJEC,OMAN
APPENDICES
APPENDIX A - ELECTRICAL SAFETY DOCUMENTS
A1. ELECTRICAL PERMIT TO WORK
A2. SANCTION FOR TES T
A3. LIMITATION OF ACCESS
APPENDIX B - CERTIFICATE OF AUTHORIZATION
APPENDIX C - APPROVED DEVICES FOR USE IN MJEC
APPENDIX D - FIRST AID FOR ELECTRIC SHOCK
APPENDIX E - WORKING AND ACCESS CLEARANCE
APPENDIX F - SWITCHING PROGRAM FORMAT
APPENDIX G - GUIDANCE FOR ACTIVITIES IN THE VICINITY OF OVERHESD LINES
APPENDIX H - SAFE STEPS TO BE OBSERVED WHILE EXECUTING SWITCHING PROGRAM AND
ISSUING E PTW
APPENDIX I - SWITCHING PROGRAM & E PTW AUDIT CHECKLIST
APPENDIX G - GPTW
APPENDIX K - USER-COMMENT FORM
Page 4
VERSION 3 BY MJEC,OMAN
References
1234-
Page 5
VERSION 3 BY MJEC,OMAN
1. INTRODUCTION
Majan Electricity Company was established on 1st May, 2005, and it's licensed by the Authority
for Electricity Regulation, Oman, to distribute and supply Electricity in the governorates of
North Al-Batinah, Al-Dhahirah and Buraimi of the Sultanate of Oman, as per the SECTOR LAW
promulgated under the royal decree 78/2004.
The Majan Electricity Company Electrical Safety Rules (MJEC ESRs) are intended for the use of
the employees of MJEC and its contractors who may be concerned with the operation of, or
work on, MJEC HIGH VOLTAGE and associated LOW VOLTAGE electrical systems. These are in
addition to the generally applicable safety requirements of MJEC, together with the MJEC
Health, Safety, and Security and Environment procedures/standards.
The application of these Rules is mandatory.
The HSSE Manager is the custodian of this document. The authority for revision of these Rules
rests within his responsibility.
These Rules shall apply to all MJEC Electrical distribution system in areas where it is licensed to
distribute and supply Electricity.
Registered copies of these rules shall be issued to all authorized employees of MJEC and its
contractors. Unregistered copies of these Rules may be issued to any other concerned bodies
and persons for information.
Before making reference to this document, it is the user's responsibility to ensure that any
hard copy, or electronic copy, is current. For assistance, contact the MJEC HSSE department.
Users are encouraged to participate in the continuous improvement of this document by
providing constructive feedback. Please complete the format given on the appendix K and
send to MJEC HSSE department.
Page 6
2.
VERSION 3 BY MJEC,OMAN
2.01
APPARATUS
2.01.1
2.01.2
2.02
2.03
CERTIFICATE OF AUTHORIZATION
It is a form of identification issued by the FUNCTION HEAD to appoint MJEC or
contractor staff to a level of electrical authorization. The CERTIFICATE OF
AUTHORIZATION in a form of license shall state the area of the electrical system
to which it applies. (See Appendix B)
2.04
DANGER - a risk of bodily injury or loss of life or health from shock, burn,
asphyxiation or other cause.
2.05
DEAD - at or about zero voltage and disconnected from any LIVE system.
2.06
DISTRIBUTION CODE
Rules in relation to the Connection to, Operation and maintenance of and
changes to the Distribution Systems of Licensed Distributors. The Distribution
Code applies to all persons who are connected to and/or use or may use the
Distribution Systems of Licensed Distributors.
2.07
Page 7
VERSION 3 BY MJEC,OMAN
EARTHING
2.08. 1
2.08.2
2.08.3
CIRCUIT MAIN EARTH (CME) - which is applied with the knowledge of the
REMOTE CONTROL PERSON before an ELECTRICAL PERMIT TO WORK or
SANCTION FOR TEST is issued. An approved portable earth may be used as CME,
refer to section 4.5.3
2.08.4
2.09
2.09.2
Page 8
VERSION 3 BY MJEC,OMAN
2.09.3
2.10
ELECTRICAL PERSONS
A person (MJEC or contractors employee)) who has been appointed by the
FUNCTION HEAD to any of the electrical authorization levels defined below in
2.10.1/2/3/4 and 5.
MJEC contractors employees will have only limited switching authority, within
the scope of their contract. FUNCTION HEAD shall specify the limitation in the
COA (license card).
2.10.1
2.10.2
2.10.3
2.10.4
Page 9
2.10.5
VERSION 3 BY MJEC,OMAN
2.10.6
2.11
FUNCTION HEAD The HSSE Manager or any other line manager designated
by General Manager as the custodian of MJEC ELECTRICAL SAFETY RULES.
FUNCTION HEAD shall have the authority to interpret, revise, permit
exceptions, and lay down procedures to follow MJEC ELECTRICAL SAFETY
RULES. FUNCTION HEAD shall assess and appoint the persons under sections
2.10.1, 2, 3, 4, 5 and 6 or delegate any other person to carry out the above
mentioned function.
2.12
GRID CODE
Grid Code is the document referred to in the Sector Law (Articles 22 & 23)
containing rules for Transmission and Dispatch License granted by the
Regulatory Authority to the Oman Electricity Transmission Company SAOC
(Transco) under that Law.
2.13
2.14
ISOLATION, ISOLATED
Page 01
VERSION 3 BY MJEC,OMAN
KEY SAFE - an Approved device for the secure retention of all keys used to lock
means of isolation, earthing or other safety devices necessary for the issue of an
ELECTRICAL SAFETY DOCUMENT.
2.16
2.17
2.18
2.19
NOTICES
2.19.1
2.19.2
2.19.3
2.20
SAFETY DISTANCE
The distance from the nearest LIVE HIGH VOLTAGE exposed conductor or from
an insulator supporting a HIGH VOLTAGE conductor, that shall be maintained to
avoid DANGER.
2.21
SAFETY PADLOCKS
Locks of an APPROVED type with a unique key, which shall be used to lock
switches, etc, at points of ISOLATION where the APPARATUS being worked on
Page 00
VERSION 3 BY MJEC,OMAN
could be made LIVE in error. Only one key shall be supplied for each lock.
2.22
2.23
SECTOR LAW -The law for the regulation and privatization of the electricity and
related water sector promulgated by Royal Decree 79/2004.
STANDARD ELECTRICAL PADLOCKS
Locks of an APPROVED standard type fitted to prevent access by unauthorized
persons to power stations, substations or electrical APPARATUS not subject to an
ELECTRICAL SAFETY DOCUMENT. This type of lock shall fit the electrical master
key system.
2.24
2.25
2.26
2.27 General Permit To Work (GPTW), is a permit to be raised for all work types done
on
or adjacent to MJEC network , specifying the type of work to be done, exact location, and all
safety documents must be attached to it e.g. EPTW, LOA , SFT. GPTW must be attached with
JOB SAFETY PLAN (JSP) indicating all hazards associated with work activities, safety controls
and emergency procedures in case of incident. Refer to Appendix N
Page 02
2.27
VERSION 3 BY MJEC,OMAN
ABBREVIATIONS
AE
ADDITIONAL EARTH
AEP
AP
APPOINTED PERSON
CEP
CME
CN
CAUTION NOTICE
COA
CERTIFICATE OF AUTHORIZATION
CP
LCP
RCP
DCC
HSSE
DN
DANGER NOTICE
EN
EARTHED NOTICE
EPTW
ESRs
HV
HIGH VOLTAGE
IEC
LLW
LOA
LIMITATION OF ACCESS
LV
LOW VOLTAGE
MJEC
SAEP
SCADA
SFT
SOP
Page 03
VERSION 3 BY MJEC,OMAN
SP
SAFETY PADLOCK
GPTW
JSB
Page 04
General Provisions
3.01
Duties
VERSION 3 BY MJEC,OMAN
It is the duty of all persons who may be concerned with the operation of, and work on
the systems and apparatus of Majan Electricity Company (MJEC) to make themselves
thoroughly conversant with the statutory requirements and safety rules governing any
work they may have to undertake on these systems and apparatus. Ignorance of the
statutory requirements and rules will not be accepted as an excuse for neglect of duty.
All persons who may be concerned with the operation of, and work on the systems and
apparatus of a MJEC shall make themselves conversant with the treatment for electric
shock, information regarding treatment is given in Appendix 'D'
3.02
Objections
Any person objecting on operational or safety grounds to any instructions given to him
regarding the operation of HV or LV APPARATUS or work on electrical equipment shall
make these objections clearly known to the person issuing them.
This person shall then have the matter investigated and if necessary referred to a higher
authority for a decision before proceeding.
3.03
Statutory Regulations
All Statutory Regulations in force in the Sultanate of Oman shall be complied with at all
times, including the provisions of the SECTOR LAW.
MAJAN ELECTRICITY COMPANY ELECTRICAL SAFETY RULES (MJEC ESRs) forms part of
MJEC Health, Safety, Security and Environment manual ( In addition to any statutory
requirements, these Safety Rules shall be complied with.
Page 05
3.04
VERSION 3 BY MJEC,OMAN
Standard Forms
Specimen forms and documents are shown in Appendix 'A'
3.05
3.06
3.07
Failure of supply
A failure of supply from whatever cause, to or from any part of the high voltage systems
shall be immediately reported to REMOTE CONTROL PERSON (RCP) During failures of
supply, all apparatus, equipment and conductors shall be regarded as being LIVE until
isolated and proved DEAD.
3.08
Admittance to Stations
No persons shall enter any Substation, Switching Station or any other operational area
belonging to a MJEC without a pass or written authorization. In the case of WORK
PARTY, the person in charge shall have a pass (LIECENCE CARD).
3.09
Variation of rules
In exceptional circumstances, function head shall, authorize in writing or by electronic
message, waiver or modifications to sections of MJEC ELECTRICAL SAFETY RULES.
Page 06
3.10
VERSION 3 BY MJEC,OMAN
Application of Rules
These rules shall apply to all work on or in close proximity of, the power systems of
MJEC. At the interface with other licensed entities for transmission and distribution of
power the rules shall at all times be applied in accordance with the provisions of:
Operating Code 6 (Safety Coordination) of the Grid Code; and
Operating Code 5 (Safety Coordination) of the Distribution Code.
These rules shall not apply to any work on or in close proximity of, the APPARATUS
operating at voltages below 50Volts, such as batteries.
3.11
3.11.01
General
The authorization of staff to LCP, RCP SAEP, AEP, CEP and AP operating and
working under the scope of these Rules shall follow the definitions given in
section 2.10. All such persons shall attend prescribed Electrical Safety Rules
course and pass the learning outcome assessment with no less than 70% marks.
3.11.02
The COA shall be valid for three years (3 years) from the date of issue. It shall be
valid only during the tenure of employment for MJEC employees and tenure of
contract and or employment with the contractor for contractor employees.
Invalid COA shall be returned to MJEC HSSE department.
Page 07
VERSION 3 BY MJEC,OMAN
4.
4.1
Access
4.1.1
4.1.2
Locking arrangements
Two types of APPROVED STANDARD PADLOCKS shall be used to control access to
enclosures or cubicles containing LIVE conductors.
Level 1
Used for locking switch yards with exposed conductors and for locking field
switches and other switchgears in service as required operationally. Master keys
shall only be issued to AEP.
Level 2
For substation entrance, building doors and all other areas except areas having
exposed HV apparatus master keys shall be issued to all authorized persons who
need access to such areas for any work/inspection to be done.
4.2
SWITCHING Procedures
4.2.1
General
4.2.1.1
All HV SWITCHING shall be carried out with the agreement of the REMOTE
CONTROL PERSON at DISTRIBUTION CONTROL CENTRE. In cases of emergency where DANGER
to persons, environment or major damage to property exists then the AEP shall instruct
Appointed Person at DCC to do the required isolation in coordination with RCP.
4.2.1.2
4.2.1.3
When the RCP gives agreement for HV SWITCHING to be carried out, the AEP
Page 08
VERSION 3 BY MJEC,OMAN
who execute the program in the site shall communicate directly with RCP at
every stages of the switching program.
AEP is required to inform RCP on the actual time of executing of every switching
item immediately after the completion of work with appropriate communication
means.
AEP shall carry with him the approved switching program in the site.
SWITCHING to the RCP's consent, shall be carried out without undue delay.
In case of circumstances where the switching program cannot be carried out for
a reason or so, then LCP must be contacted for approval of such changes.
4.2.1.4
4.2.1.4
4.2.1.6
4.2.1.7
When switchgear or any other HV APPARATUS shows any sign of distress, its
condition shall be reported immediately to the RCP and it shall be examined
before a decision is made about further operation.
4.2.2
4.2.3
Page 09
VERSION 3 BY MJEC,OMAN
In all cases when emergency SWITCHING has been carried out, the LCP for the
electrical system concerned shall be informed as soon as possible of any action
taken. The LCP shall report to RCP
in accordance with an APPROVED procedure.
4.2.4
4.3
4.3.1
4.3.1.1
Switched off from all points of supply, made DEAD and proven DEAD by
checking each phase of the circuit in an approved manner.
4.3.1.2
ISOLATED and all steps taken to secure with SAFETY PADLOCKS from all
points of supply, including where practicable voltage and auxiliary
transformers, common neutral equipment and any other source from
which the APPARATUS and conductors may become LIVE and CAUTION
NOTICES attached at all points of ISOLATION. The keys for the SAFETY
PADLOCKS shall be placed in a KEY SAFE or another APPROVED security
method shall be used.
4.3.1.3
4.3.1.4
Page 21
4.3.1.5
VERSION 3 BY MJEC,OMAN
Or
4.3.1.6
Released for testing by the issue of a SANCTION FOR TEST to an AEP who
shall be accompanied by another AEP or CEP during the progress of the
testing.
4.3.1.7
4.3.2
4.3.3
For LIVE LINE WASHING, reference to section 7 to be followed and the safety
distance to be maintained as per 4.6 sections.
4.4
4.4.1
General Rules
The consequence of shock or serious burn from short circuit associated with
LOW VOLTAGE systems may be serious or in some circumstances, fatal. For all
work in general rules under section 4.4.2 shall apply.
It is not always possible or operationally practical to make DEAD or earth LOW
VOLTAGE APPARATUS for certain type of work and testing. For work on or
testing of LIVE LOW VOLTAGE APPARATUS rules under section 4.4.3 shall apply.
Lockable ISOLATION by opening switches or withdrawal of fuses or links, may not
be possible for some LOW VOLTAGE APPARATUS such as Main feeder pillar or LV
switch board on the secondary side of an HV/LV transformer, and then rule 4.4.4
shall apply.
If work is carried out on the ISOLATED circuits of an LV APPARATUS with adjacent
circuits live rule 4.4.5 shall apply.
4.4.2
4.4.2.1
For all work on or testing of all LV APPARATUS the following precautions shall
be taken.
Switched off from all possible points of supply and made DEAD.
Page 20
VERSION 3 BY MJEC,OMAN
4.4.2.2
4.4.2.3
4.4.2.3
Proved DEAD with an APPROVED voltage testing device suitable for the
rated voltage of the circuit. The voltage testing device shall be checked
before and after use to check it is working correctly.
4.4.2.4
4.4.2.5
4.4.3
4.4.3.1
4.4.3.2
4.4.3.3
4.4.3.4
For testing voltage and current, APPROVED electrical rubber gloves and
instruments shall be used. They shall be inspected and confirmed to be
free of any defects before every use.
4.4.3.5
4.4.4
4.4.4.1
Work on LV switch boards and feeder pillars where lockable ISOLATION is not
possible.
Switch off and ISOLATE HV windings of the transformer feeding the LV
windings and connections (including incoming switchboard units), prove
dead and apply CIRCUIT MAIN EARTH to the ISOLATED HV circuits and or
Page 22
VERSION 3 BY MJEC,OMAN
4.4.5
The CEP who is to be in charge of the work, shall be made fully aware by
AEP of the nature and extent of the work to be done, and understands
the precautions that he and his WORKING PARTY shall take to avoid
DANGER from LIVE APPARATUS. The CEP shall be accompanied by
another person during the progress of the work.
Work near LIVE LV APPARATUS.
4.4.5.1
4.4.5.2
When verbal instructions are not considered sufficient AEP should issue a
LIMITATION OF ACCESS to the CEP.
4.5
EARTHING
4.5.1
General
4.5.1.1
4.5.1.2
4.5.1.2
4.5.2
4.5.2.1
4.5.3
Page 23
VERSION 3 BY MJEC,OMAN
4.5.3.2
Ensure that each phase of the circuit is DEAD (only an HV testing device
suitable for the rated voltage of the circuit shall be used). The APPROVED
voltage testing device shall be checked before and after use to check it is
functioning correctly
4.5.3.3
Examine the portable EARTHING leads prior to use to ensure that they are
in good condition.
4.5.3.4
4.5.3.5
EARTH and short circuit all phases even if work is to be carried out on one
phase only.
4.5.3.6
4.5.3.7
4.5.3.8
Page 24
4.6
VERSION 3 BY MJEC,OMAN
4.6.1
Safety Distances
4.6.1.1
The SAFETY DISTANCE (designated 'X' in below given Table 1 and Diagram
1) shall be maintained at the respective system voltages between any
part of the person or object and the nearest LIVE HV conductor.
4.6.1.2
Not exceeding 11 kV
0.9 m
1.2 m
1.8 m
4.6.2
Approach of Persons
4.6.2.1
No person shall, except, for the provision of Rule 4.6.2.2, allow any part
of his body to approach exposed HV conductors or insulators supporting
such conductors within the SAFETY DISTANCES specified in Rule 4.6.1,
unless the conductors have been made DEAD, ISOLATED and EARTHED
and an ELECTRICAL PERMIT TO WORK or SANCTION FOR TEST has been
issued.
4.6.2.2
Page 25
VERSION 3 BY MJEC,OMAN
X
X
DIAGRAM 1
30cm
30cm
Page 26
VERSION 3 BY MJEC,OMAN
4.6.3
Testing of Conductors
4.6.3.1
4.6.3.2
When exposed HV conductors are ISOLATED but not yet proved DEAD the
only objects which shall approach them or the insulators supporting
them, within the SAFETY DISTANCES specified in Rule 4.6.1 shall be
APPROVED voltage testing devices.
4.6.4
4.6.4.1
When work is to take place in the vicinity of LIVE HV conductors the AEP
shall, taking into account the nature and location of the work and the
tools or objects to be used, determine how the SAFETY DISTANCES
specified in Rule 4.6.1 have to be maintained by the persons working.
4.6.4.1
Note:
Page 27
4.7
VERSION 3 BY MJEC,OMAN
4.7.1
4.7.2
4.7.3
The AEP shall ensure that when a HV test voltage is being applied to
APPARATUS, adequate precautions are taken to guard the APPARATUS to
prevent DANGER. These precautions shall include:
4.7.3.1
4.7.3.2
4.7.3.3
4.7.3.4
Page 28
VERSION 3 BY MJEC,OMAN
5.
5.1
Initiation of Documents
5.1.1
5.1.2
A SANCTION FOR TEST shall be agreed by the LCP and issued by a SENIOR
AUTHORIZED ELECTRICAL PERSON SAEP to an AEP under whose approval the
testing is initiated, before any testing is carried out on any HV APPARATUS after
it has once been connected to and remains part of an HV system.
5.1.3
5.1.4
5.1.5
5.2
5.2.1
Page 29
VERSION 3 BY MJEC,OMAN
5.2.2
5.2.3
The person in charge to whom a SANCTION FOR TEST is issued shall be an AEP,
who shall retain the SANCTION FOR TEST in his possession at all times, and
remain on site, whilst tests are being made.
5.2.4
5.2.5
5.3
5.3.1
5.3.2
The APPARATUS ISOLATED and EARTHED for testing under the terms of a
SANCTION FOR TEST shall not be connected to the system without the
agreement of the LCP. The recipient of the SANCTION FOR TEST shall be
responsible for coordinating all testing operations on the ISOLATED APPARATUS
and for ensuring safety during the tests. He may, without reference to the LCP,
remove and replace EARTHS as necessary and carry out tests including making
LIVE the APPARATUS concerned from a testing supply. This does not mean that
the recipient of the SANCTION FOR TEST has to carry out the tests personally,
but that they shall be carried out under his direct supervision.
5.4
5.4.1
When work on APPARATUS for which an ELECTRICAL PERMIT TO WORK has been
issued is completed, the recipient shall sign the clearance and return the
ELECTRICAL PERMIT TO WORK to an AEP who shall cancel it and inform the RCP.
5.4.2
Where more than one ELECTRICAL PERMIT TO WORK has been issued for work
on HV APPARATUS associated with the same CIRCUIT MAIN EARTHS, the RCP
shall ensure that all such ELECTRICAL PERMITS TO WORK have been cancelled
before the CIRCUIT MAIN EARTHS are removed.
Page 31
VERSION 3 BY MJEC,OMAN
5.4.3
When testing on APPARATUS for which a SANCTION FOR TEST has been issued is
completed, the recipient shall sign the clearance and return the SANCTION FOR
TEST to a SAEP for cancellation.
5.4.4
A circuit under SANCTION FOR TEST shall have all CIRCUIT MAIN EARTHS
restored prior to cancellation unless agreement was reached with the LCP at the
time of issue to accept the cancellation of the SANCTION FOR TEST without these
EARTHS in position.
5.4.5
The SAEP, before canceling the SANCTION FOR TEST shall enter under
"Exceptions" the changes of state of EARTHING of the circuit and then inform the
LCP of the cancellation and of the operational state of the circuit.
5.4.6
When work for which a LIMITATION OF ACCESS has been issued is completed,
the recipient shall sign the clearance and return the LIMITATION OF ACCESS for
cancellation to an AEP.
5.4.7
When work for which a LIMITATION OF ACCESS under section 5.1.4 is canceled,
then the RCP shall be informed.
5.5
General requirements
5.5.1
5.5.2
All Electrical safety documents forms are printed in a book form and are pre
numbered and its issue is controlled.
2 copies are made - White and
Yellow (card). The white copies are generally retained in the book, Yellow card is
issued to document recipient, the first white original returned to DCC for
archiving.
5.5.3
Cancelled and completed original white copy is archived for two years in
separate files.
5.5.3
5.5.3.1
5.5.3.2
5.5.3.3
5.5.3.4
5.5.3.5
Page 30
5.5.3.6
6.
VERSION 3 BY MJEC,OMAN
6.1
6.1.1 General
6.1.1.1
6.1.1.2
6.1.2
6.1.2.1
A clearance certificate shall be issued prior to starting any work in the vicinity of
an overhead line or passing under the line of vehicles higher than 5.5 meter
above ground where goal posts have not been erected. The certificate can only
be issued by the MJEC area distribution engineer who is an AUTHORISED
ELECTRICAL PERSON. On roads where goal posts have been erected,
Page 32
VERSION 3 BY MJEC,OMAN
vehicles/equipment with a height lower than the sign posted maximum does not
require a Clearance certificate.
6.1.2.2
The driver or person in charge on site shall carry a copy of the authorised
Clearance Certificate, including route map/ situation sketch as supplied with the
certificate.
(See Appendix G for detailed guidance)
6.1.3
Identification of circuits
6.1.4.1
No CEP shall climb any such pole supporting LIVE conductors except
under the direct supervision of an AEP, who shall ensure that the person
does not ascend to a position in which it is possible for him to bring any
part of his body or working tool within the SAFETY DISTANCES specified in
Rule 4.6.
6.1.4.2
6.1.5
Page 33
VERSION 3 BY MJEC,OMAN
6.1.5.1
6.1.5.2
6.1.5.3
The AEP shall from the ground directly supervise all such persons
climbing or working on the towers or structures.
6.1.6
Clearance
2.5m
2.6m
2.8m
3.0m
Page 34
6.1.7
VERSION 3 BY MJEC,OMAN
4.6m
Work on single or double circuit HIGH VOLTAGE overhead lines with all
conductors DEAD
For work on HV conductors the AEP in addition to the procedures called for in
Rule 4.3 shall:-
6.1.7.01
6.1.7.02
6.1.7.03
If, from the point of work the conductors can be seen to be EARTHED,
avoid checking with the APPROVED voltage testing device.
6.1.7.04
Issue the CEP holding the ELECTRICAL PERMIT TO WORK with portable
EARTHING leads that shall be used as ADDITIONAL EARTHS.
6.1.7.05
Page 35
VERSION 3 BY MJEC,OMAN
If the WORKING PARTY leaves the line at any time, check when they
come back, that they have returned to the same line and that all EARTHS
adjacent to the point of work, are still in position before allowing work to
start again.
Check that all members of the WORKING PARTY are off the line before
removing all the ADDITIONAL EARTHS.
Sign the 'Clearance section' of the ELECTRICAL PERMIT TO WORK.
6.1.8
6.1.8.1
6.1.8.2
At the point of work personally identify the circuit to be worked on, and
instruct the WORKING PARTY how to obtain safe access, up the tower or
structure, to the circuit's DEAD conductors.
6.1.8.3
Attach an APPROVED green flag at ground level on the DEAD circuit side
of the face of the tower or structure showing the safe access approach.
6.1.8.4
Attach a DANGER NOTICE at ground level on the LIVE circuit side of the
face of the tower or structure.
6.1.8.5
6.1.8.6
6.1.8.7
Ensure that these APPROVED red flags are attached so that all members
of the WORKING PARTY are aware that no part of their bodies or working
tools shall go beyond them and come within the SAFETY DISTANCES
specified in Rule 4.6.
Page 36
VERSION 3 BY MJEC,OMAN
6.1.8.8
6.1.8.9
The CEP holding the ELECTRICAL PERMIT TO WORK shall ensure that until
the work is finished and the rest of the WORKING PARTY have descended
to the ground, the conductors remain EARTHED at the point of work and
the APPROVED red and green flags and DANGER NOTICES are kept in
position.
6.1.9
6.1.9.1
6.1.10
6.1.10.1
Where tree branches are in contact with an overhead line, the provisions
of 4.3 shall apply before work commences to remove the branches from
the overhead line.
6.1.10.2
Where branches are free of contact with the overhead line and have
clearance well above the SAFETY DISTANCE as per section 4.6, but may
come into contact with it after being cut, the work may be carried out
under a LIMITATION OF ACCESS and sections 4.3.1.3, 4.3.1.4 and 4.3.1.5
shall not apply.
6.1.11
LV Overhead lines
6.1.11.1
General
When all conductors can be made dead precautions under Rule 4.4 shall
be taken in addition to those under Rule 6.1.1.
6.1.11.2
Exposed conductors
Before work is commenced on exposed low voltage overhead lines which
have been made DEAD, the conductors including the neutral shall be
Page 37
VERSION 3 BY MJEC,OMAN
Page 38
VERSION 3 BY MJEC,OMAN
6.2
6.2.1
6.2.1.1
Ensure that no person touches or cuts into the insulation which covers
the conductor, unless the conductor is DEAD, ISOLATED and EARTHED.
Page 39
6.2.1.2
6.2.2
VERSION 3 BY MJEC,OMAN
Before issuing the ELECTRICAL PERMIT TO WORK to the CEP, identify the
cable to be worked on at the point of work, and prove it dead by
APPROVED spiking equipment or other APPROVED means.
Work on LV Cables
For work on LV cables, the CEP in addition to the procedures called for in Rule
4.4 shall
6.2.2.1
Take all reasonably practicable steps to prevent the cable being made
LIVE in error during the course of work.
6.2.2.1
Keep any SAFETY PADLOCK keys, withdrawn fuses or links in a safe place
during the course of work.
6.2.2.1
Before the start of the work, clearly identify the cable at the point of
work to the person in charge of the work.
6.2.3
6.2.3.1
6.2.3.2
6.2.3.3
If in the view of the AEP the cables should be made DEAD, he may state
so in the Excavation clearance.
6.2.3.4
Page 41
6.3
6.3.1
VERSION 3 BY MJEC,OMAN
For work on HV transformers, the AEP in addition to the procedures called for in
Rule 4.3 shall take the following precautions.
6.3.1.1
6.3.1.2
6.3.1.3
6.3.2
Page 40
6.4
6.4.1
VERSION 3 BY MJEC,OMAN
6.4.1.1
6.4.1.1
Discharge its conductors to EARTH, but they need not remain connected
to EARTH.
6.4.2.
6.4.2.1
Ensure that the section of the busbars on which work is to be carried out
are made DEAD and ISOLATED from all points of supply from which it can
be made LIVE.
6.4.2.2
6.4.2.3
Attach CAUTION NOTICES at all points where the busbars can be made
LIVE.
6.4.2.4
6.4.2.5
Test with an APPROVED voltage testing device that the busbars are dead,
checking the voltage testing device before and after use.
6.4.2.6
EARTH the busbar at the point of testing and where practicable lock the
CIRCUIT MAIN EARTH in position. Attach an EARTHED NOTICE to the
circuit breaker or EARTHING device.
Page 42
VERSION 3 BY MJEC,OMAN
6.4.2.7
Test with an APPROVED voltage testing device every spout where work is
to be carried out, checking the voltage testing device before and after
use.
6.4.2.8
6.4.2.9
6.4.4
6.4.4.1
For any equipment containing SF6 gas the relevant Code of Practice must be
available at the point of work stating the method of dealing with the gas and
associated compounds. The apparatus shall bear an APPROVED NOTICE stating
that it contains Sulfur Hexafluoride (SF6).
6.4.4.1
6.4.5
(i)
The apparatus shall be isolated from all sources of supply of gas, purged
in accordance with the codes of practice and the associated receivers and
pipe work left open to the atmosphere.
(ii)
The valves shall be locked by safety locks and the keys shall be placed in
the appropriate KEY SAFE.
(iii)
(v)
6.4.5.1
6.4.5.2
Page 43
VERSION 3 BY MJEC,OMAN
of the fuse to EARTH. The EARTH switch shall be padlocked and an EARTHED NOTICE attached.
6.5
6.5.1
6.5.1.1
Identify the area where work may be carried out safely and ensure that
SAFETY DISTANCES called for in Rule 4.6 are maintained by the WORKING
PARTY and the tools and equipment they are to use. If no ELECTRICAL
PERMIT TO WORK or SANCTION FOR TEST is issued for adjacent
APPARATUS in the substation, then he shall issue a LIMITATION OF
ACCESS to the CEP in charge of the work, specifying how the SAFETY
DISTANCES from LIVE conductors shall be maintained during the course
of the work.
6.5.1.1
6.5.1.1
Ensure that ladders required for the work shall be of an APPROVED type
and be kept secure with a STANDARD ELECTRICAL PADLOCK when not in
use. When ladders are used to gain access to DEAD APPARATUS, subject
to an ELECTRICAL PERMIT TO WORK, these shall be locked in position
with a STANDARD ELECTRICAL PADLOCK or by any other APPROVED
means such that they cannot be removed unauthorized.
6.5.1.1
Ensure that if ladders, scaffolding, cranes etc, are to be used, that the
position that they shall be placed and the route through the substation to
that position shall first be agreed. Scaffolding and cranes, etc., shall be
connected to the substation EARTH system as soon as they are in position
for work to take place.
Page 44
VERSION 3 BY MJEC,OMAN
6.6
6.6.1
Physical Danger
Serious bodily harm can be suffered by persons working on HV APPARATUS such
as tap-change gear, circuit breakers, etc, due to the automatic or remote control
feature being operated in error.
6.6.2
Precautions
For work on remotely or automatically controlled HV APPARATUS such as tapchange gear, circuit breakers, disconnectors, etc., the AEP before work
commences shall:-
6.6.2.1
Ensure that all remote control and automatic features are made so that
they cannot be operated and, where practicable, secure with SAFETY
PADLOCKS and CAUTION NOTICES.
6.6.2.1
Page 45
VERSION 3 BY MJEC,OMAN
6.7
6.7.1
For work on HV static capacitors the AEP in addition to the procedures called for
in Rule 4.3 shall:-
6.7.1.1
6.7.1.2
6.7.1.3
6.7.2
Page 46
7.
VERSION 3 BY MJEC,OMAN
7.1
General
7.1.1.
Contractors are selected to carry out LIVE LINE WASHING in MJEC. They shall
have proven LIVE LINE WASHING procedures, adequately trained and
experienced staff and all the necessary well maintained equipment to carry out
such work.
7.1.3
RCP shall agree not to reclose the line without permission from the AEP in charge
of live line washing.
7.1.2
The AEP before initiating LIVE LINE WASHING shall ensure that the Contractor's
Supervisor has the necessary evidence and certificates on site to satisfy him that
the requirements of Rule 7.1.1 are met.
7.1.3
The LIVE LINE WASHING and the safety of the team shall be the responsibility of
the Contractor's Supervisor, who shall ensure that the work is carried out
correctly and is present all the time the washing is taking place in accordance
with the Rules in this Section 7.0.
7.2
7.2.1
7.2.2
The equipment shall have a nozzle which is such that the water ejected by it
breaks into a spray before reaching the insulator being washed.
7.2.3
The nozzle and metal parts of the equipment shall be bonded together to EARTH
by a suitable EARTHING lead which is not less than 70 mm2 copper equivalent in
cross-section.
7.3
Safety precautions
7.3.1
The AEP shall inform the RCP of the location of the LIVE LINE WASHING to be
carried out by the Contractor. The AEP shall inform the RCP when the LIVE LINE
WASHING is started and notify completion.
7.3.2
The AEP shall issue a LIMITATION OF ACCESS to the Contractor's CEP who is in
charge of the LIVE LINE WASHING. The LIMITATION OF ACCESS shall state the
name of the circuit, its identification or symbol and any precautions taken by the
AEP.
Page 47
VERSION 3 BY MJEC,OMAN
7.3.3
The contractor CEP shall normally remain on site throughout the LIVE LINE
WASHING taking place on wood pole overhead lines.
7.3.4
The AEP shall remain on site throughout the LIVE LINE WASHING taking place in
substations or on double circuit overhead lines.
7.3.5
The water being used for LIVE LINE WASHING shall have a resistivity of more
than 2500 ohms-cm (conductivity less than 400 micro Siemens). This shall be
constantly monitored as a rise in the water temperature increases its
conductivity. The water quality monitoring shall be done using an automatic
monitoring device fitted with an audible alarm signal.
7.3.6
When no connection to a fixed EARTH plate is available on site for the bonding
called for in Rule 7.2.3, the Contractor's Supervisor shall have a temporary
EARTH electrode installed and check that its resistance is adequate for the
operator's safety before commencing any LIVE LINE WASHING.
7.3.7
The safety clearance necessary between the hose operator and LIVE conductors
will depend on the system voltage, the method of washing and the efficiency of
the breakup of the jet of water. The safety clearance necessary shall be agreed
between the Contractor's Supervisor and the AEP depending on the Contractor's
methods, equipment and experience.
7.3.8
The LIVE LINE WASHING shall not commence in unfavorable conditions such as
high winds as this would affect the direction of the water jets. LIVE LINE
WASHING shall stop in the event of a local lightning risk
7.3.9
Only one phase insulator shall be washed by the same jet. No other LIVE
conductor at a lesser distance than the one being washed shall be sprayed in
error.
7.3.10
The Contractor's supervisor shall be responsible for ensuring that the LIVE LINE
WASHING operator wears any protective clothing necessary for this work.
Page 48
VERSION 3 BY MJEC,OMAN
experienced staff and the necessary well maintained LIVE LINE tools and equipment to
carry out such work.
8.1.2
The AEP before initiating LIVE LINE WORK shall ensure that the Contractor's
Supervisor has the written procedures, the necessary evidence and certificates on site
to satisfy him that the above requirements are met.
8.1.3
The LIVE LINE WORKING and the safety of the team shall be the
responsibility of the Contractor's Supervisor, who shall ensure that the procedure is
carried out correctly and is present throughout the procedure to ensure that it is in
accordance with the Rules in this Section 8.0.
8.2 LIVE LINE TOOLS AND EQUIPMENT
8.2.1
LIVE LINE tools and equipment shall be kept in a clean and dry condition
and immediately before use be inspected by the Contractor's Supervisor to ensure
they are clean, dry and in sound condition.
8.2.2
A clear mark shall be maintained on every LIVE LINE tool and equipment
where appropriate, indicating the limit of the safe handling distance which shall not be
less than as indicated in Table 2 below.
Up to and including 33 kV
1.5 m
2.1 m
Page 49
VERSION 3 BY MJEC,OMAN
Page 51
VERSION 3 BY MJEC,OMAN
these parts during LIVE LINE WORK. This examination shall extend to include adjacent
spans and supports on both sides of the point of work.
8.3.9
Before any pole is climbed it shall be sounded. No pole badly impaired by
decay or damage shall be climbed until the Contractor's Supervisor is satisfied that he
has made it safe for climbing, alternatively access to the top of the pole shall be by
suitable means independent of the pole.
8.3.10
Before displacing conductors adequate precautions shall be taken to
avoid DANGER and to ensure the safety of third persons, Safe clearances shall also be
maintained between the line and other APPARATUS and objects.
8.3.11
No vehicle or person other than members of the LIVE LINE WORKING
team shall be allowed in the near vicinity of the point of work while the work is in
progress without the consent of the Contractor's Supervisor in charge of the LIVE LINE
WORK. Temporary markers may be erected to ensure this requirement is met.
8.3.12
No person shall climb, move or work in such a position to bring any part of
his body, clothing or any working tool, other than LIVE LINE WORKING tools or
equipment, within the distances as indicated in Table below. This distance shall be
marked on the structure. Refer to section 4.6
SAFE DISTANCE
Not exceeding 11 kV
0.9 m
1.2 m
1.8 m
8.3.13
The Contractor's Supervisor shall be responsible for ensuring all personnel
of the LIVE LINE WORKING team wear the protective clothing and equipment
necessary for this work.
8.3.14
The AEP shall inform the RCP when the HV live line work is completed and the LOA
is canceled.
Page 50
VERSION 3 BY MJEC,OMAN
NO.
WORK LOCATION:
Page 52
VERSION 3 BY MJEC,OMAN
2. RECEIPT
I hereby declare that I accept responsibility for carrying out the work on the apparatus detailed
on this Permit and that no attempt will be made by me or by the men under my supervision to
carry out work on any other apparatus.
Signed ...................... Time ....................... Date ..
Signed ................. Time ....................... Date ...........
being the CEP, License Card No. (
Page 53
VERSION 3 BY MJEC,OMAN
3. CLEARANE
I hereby declare that the work for which this Permit was issued is now completed / not
completed, and that all men under my supervision have been withdrawn and warned that it is no
longer safe to work on the apparatus specified on this Permit and that all gear, tools and
additional earthing connections are clear. (Delete where applicable)
Signed ................. Time ....................... Date ...........
being the CEP in charge of the work.
4. CANCELLATION OF PERMIT
This EPTW is hereby cancelled and I have informed the following
at
control.........................................................................................
.............. (Name)
Signed
...............................
Time
.......................
Date
............................ is being Authorized Electrical Person possessing authority to cancel
this EPTW.
CANCELLATION AND OPERATIONAL STATE NOTIFIED TO (REMOTE CONTROL PERSONRCP)..................................................
Page 54
VERSION 3 BY MJEC,OMAN
No.
WORK LOCATION:
Page 55
VERSION 3 BY MJEC,OMAN
2. RECEIPT
I accept responsibility for the testing of the APPARATUS detailed on this SANCTION TO TEST and
for taking precautions to prevent danger...
Signed ....................... Time ..................... Date ...
Signed ........................... Time ......................... Date ...........
being the AEP, License Card No. (
3. CLEARANCE
All persons under my charge have now been withdrawn and warned that it is no longer safe to
work on the APPARATUS detailed on this SANCTION-FOR-TEST. ALL ADDITIONAL EARTHS have
been removed. The testing is *COMPLETE/INCOMPLETE The operational state of the apparatus
is the same as at the time of this issue of this SANCTION FOR TEST apart from the exceptions
noted below.
Exception (if none, state none)
(Delete where applicable)
Signed ................... Time ....................... Date .............
being the AEP in charge of the work.
4. CANCELLATION OF PERMIT
This SFT is hereby cancelled and I have informed the following at
(Name) Local Control Person
Signed ................. Time .......................... Date ................ being a
Senior Authorized Electrical Person possessing authority to cancel this SFT
Page 56
VERSION 3 BY MJEC,OMAN
LIMITATION OF ACCESS
AREA:
No.
WORK LOCATION:
1. ISSUE
TOEMPLOYED BY......................... .
Permission is given to carry out the work described below which is in the vicinity of LIVE
conductor:WORK SITE:
______________________________________________________________________________
WORK TO BE DONE:
______________________________________________________________________________
NO OTHER WORK SHALL BE CARRIED OUT
LIVE APPARATUS:
______________________________________________________________________________
PRECAUTIONS THAT MUST BE TAKEN WHEN WORK IS CARRIED OUT:
____________________________________________________________________________
SAFETY PRECAUTIONS FOR WORK ON LOW VOLTAGE APPARATUS:
______________________________________________________________________________
KEY SAFES/SAFETY PADLOCK NOS: ______________________________ *(if applicable)
Issued with knowledge of ..................REMOTE/CONTROL PERSON, RCP
Signed ............. Time .................. Date ............
being an authorized electrical Person, License Card No. (
LOA
Page 57
VERSION 3 BY MJEC,OMAN
2. RECEIPT
I accept responsibility for carrying out the work in accordance with this LIMITATION OF ACCESS
and no other work will be done by me or the persons under my charge.
Signed .................... Time .............. Date .............
being the CEP , License Card No. (
3. CLEARANCE
All persons under my charge have now been withdrawn and warned that it is no longer
permitted to carry out work specified on this LIMITATION OF ACCESS
Signed ............................ Time ...... Date ........
being the CEP in charge of the work.
4. CANCELLATION OF PERMIT
This LIMITATION OF ACCESS is now cancelled. I have informed the following *(IF APPLICABLE)
LOCAL/CONTROL PERSON-LCP
.................................................................. (Name)
Signed .......................... Time .......... Date........................ being an
AUTHORIZED ELECTRICAL PERSON possessing authority to cancel this LOA
Page 58
VERSION 3 BY MJEC,OMAN
APPENDIX.B
CERTIFICATE OF AUTHORISATION
PHOTO
Page 59
VERSION 3 BY MJEC,OMAN
APPENDIX C
APPROVED SAFETY DEVICES FOR MJEC
DEVICE
SPECEFICATION
APPLICATION
Rule 2.20.1
Rule 2.20.2
Larger size can be used for
Same as above + of one more substation fences, doors,
size 300x450 mm
switch yards etc.
AE LABEL PLASTIC
Rule 4.5.3.8
Same as above
Rule 4.5.3.9
Page 61
VERSION 3 BY MJEC,OMAN
KEY SAFE
2
H
O
OK
S
IN
EA
CH
BO
X
http://www.boddingtonselectrical.com
Rule 2.22
SAFETY PADLOCK
00100BBI
STANDARD
ELECTRICAL
PADLOCK LEVEL 1
Rule 2.20.3
00A0110
Duplicate keys to be
destroyed and locks for
each location shall be
numbered with area
prefixes. Eg IB 001 (for
Ibri area)
Rule 2.24
Master Keyed. All keys have
sequential
numbers
engraved with suffix A
Page 60
VERSION 3 BY MJEC,OMAN
Rule 2.24
STANDARD
ELECTRICAL
0000110
PADLOCK LEVEL 2
SAFETY
HARNESS
Code:E2 - * - * - *
ELECTRICAL
RUBBER GLOVES (HV)
EXAMPLE: E2-14-B-11 is
Class 2, 14" length, black
and size 11
website
Meets or exceeds ASTM Refer
D120 and IEC 903 standards ordering:
Class 4 Gloves (33kV)
before
http://www.aplussafety.ne
t/products
Code:E4 - * - * - *
36,000vac max use voltage
Proof tested at 40,000vac
SAFETY HELMET
Page 62
VERSION 3 BY MJEC,OMAN
PFISTERER
KP TEST 5
MODEL 257a
or
PFISTERER
KP TEST 5
CAT No. 930.140.620
MULTIMETERS:
Note: AVO shall only be
BECKMANN HD 110
used with fused leads
FLUKE
AVO
Or any other make having
international certification label
like CE, KEMA, UL
Set consisting 3 conductor Rule 4.5.3
clamps and one earth clamp,
Cable size 70 mm2 copper.
http://www.thew.com.au/earth
ing.html
Page 63
VERSION 3 BY MJEC,OMAN
Class 00 Gloves
LV GLOVES
Code:E00 * - * - *
http://www.aplussafety
.net/products
D120
color
and
IEC
903
and
size
standards
EXAMPLE: E00-11-R-10
Code:GK00 - * - * - *
http://www.mitchellinstru
ment.com
10FT Hydraulic Cable Spike
Mitchell Part Number: SAL24322
Page 64
VERSION 3 BY MJEC,OMAN
Code:
AS1000HAT
10cal/cm2
before
w/
Page 65
VERSION 3 BY MJEC,OMAN
APPENDIX D
FIRST AID FOR ELECTRIC SHOCK
What to do:
1. Switch off the main switch.
2. Break the contact between electrical source and patient using dry non-conductive
object like wooden stick.
3. Call for help.
4. If breathing and heartbeat has stopped begin Cardio pulmonary resuscitation (C.P.R)
5. If breathing, but unconscious : Recovery Position
6. Treat any Burns
7. Treat for Shock
8. Secure the area by suitable barriers like caution tape to prevent others contacting live
apparatus.
Do not:
1. Touch the patient directly.
2. Panic or go near the area if high voltage electricity is suspected.
Page 66
VERSION 3 BY MJEC,OMAN
Airway
Tilt head back, lift chin up to open airway. Listen for breathing.
BREATHING
If not breathing, pinch nose and cover the
mouth with yours and blow until you see
the chest rise. Give 2 breaths. Each breath
should take 1 second. If chest doesn't rise,
open airway again.
Page 67
VERSION 3 BY MJEC,OMAN
Circulation
If the victim is still not breathing normally,
coughing or moving, begin chest
compressions. Pump the chest 30 times.
Place the heel of one hand in the center of
the chest and your other hand on top of it.
Push down on the chest 1 to 2 inches 30
times right between the nipples. Pump at
the rate of 100/minute, faster than once
per second (16 in 10 seconds).
Repeat A - B - C
Until
help
arrives
or
the
victim
begins
breathing.
If there are two rescuers, one does the breathing and one does the compressions - CPR
steps and ratios remain the same.
Page 68
VERSION 3 BY MJEC,OMAN
Recovery
If breathing and pulse OK, recovery position
ensures the prevention of tongue falling back and
blocking the airway.
Place the patient on their back.
Lift the chin to ensure the Lift the chin to ensure
the airway is open. Patient's arm on your side
should be positioned so as to make a right angle
with his body, with elbow bent and palm facing
out.
Patient's other arm on opposite side should be
placed across the chest, with back of their hand
against the cheek on your side of the patient.
Pull up the patient's knee point (side away from
you) as it bends with the foot flat on the ground.
Roll over the patient in this position towards your
side.
By tilting the patient's head back ensure that the
airway is open. The uppermost leg should be
adjusted in such a way that the hip and knee are
at right angles.
In case of a fall from height, do not move the patient
if a spinal injury is suspected.
Just remember
to save a life!
Page 69
VERSION 3 BY MJEC,OMAN
Burns
1. The affected area should be immediately kept under cold running water for 10 mins.
Helps to dissipate the localized high heat and reduces further burns by cooling off
the skin and tissues.
2. Remove clothing, watch and other jewelry
from the affected area.
Do not :
1. Burst skin blisters.
2. Remove skin.
3. Apply creams, lotions on the burns.
Reassure, loosen any tight clothing, and keep area warm and airy.
If the cause can be removed such as - bleeding / burns.
If no fracture make the patient lies down and raise and support his legs.
If unconscious place in recovery position.
Monitor and the casualty.
Do not:
1. Feed the patient by mouth in spite of thirst.
2. Make the patient stand up or walk or run.
3. Allow the patient to smoke
Page 71
VERSION 3 BY MJEC,OMAN
Page 70
VERSION 3 BY MJEC,OMAN
The Working and Access Clearances given in the following Tables of this
Appendix are derived from the SAFETY DISTANCES 'X' (Table 1) specified in Rule
4.6.1 with the addition of 'Application Factors' suitable for the particular activity
to be undertaken in the vicinity of exposed LIVE HIGH VOLTAGE conductors.
2.0
Appendix E1 specifies the Working and Access Clearances for work on overhead
line poles when work is to be undertaken with the conductors LIVE.
3.0
Appendix E2 specifies the Working and Access Clearances for work in substations
containing exposed LIVE HIGH VOLTAGE conductors.
4.0
IMPORTANT NOTE
This Appendix has been produced and added to these Rules to give AUTHORISED
ELECTRICAL PERSONS operational guidance, when they are issuing ELECTRICAL
SAFETY DOCUMENTS, in the types of situations covered in appendices E1, E2 and
E3.
The Working and Access Clearance figures given should be used as a minimum
requirement, and should be increased if practicable in all such situations.
The importance of the AUTHORISED ELECTRICAL PERSONS understanding the
intention of Rule 4.6 is essential when using the Clearances given in this
Appendix E
Page 72
VERSION 3 BY MJEC,OMAN
APPENDIX E2
WORKING AND ACCESS CLEARANCES FOR WORK IN SUBSTATIONS CONTAINING EXPOSED LIVE HIGH VOLTAGE
CONDUCTORS RULE 4.6.4 ; 6.1.4
X = SAFETY DISTANCE
X = SAFETY DISTANCE
A = X+A F
LIMIT MARKER
WORKING PLATFORM
LEVEL
LADDER OR CLIMBER
KV
A- MTR
SCAFFOLDING /PLATFORM
KV
B - MTRS
Page 73
VERSION 3 BY MJEC,OMAN
S
11
1.2
11
3.0
33
1.5
33
3.3
APPENDIX E2
WORKING AND ACCESS CLEARANCES FOR WORK IN SWITCH YARDS RULE 4.6.4 ; 6.5.1
SAFE AREA
BOUNDRY
EXPOSED
LIVE
CONDUCTOR
X = SAFETY DISTANCE
B= X+A F
2100mm= APPLICATION
FACTOR (AF)
VERTICAL
LIMIT
AF=1500mm
ELEVATION
Page 74
VERSION 3 BY MJEC,OMAN
APPENDIX E3
HIGH VOLTAGE LIVE LINE WORK ON WOOD POLE OVERHEAD LINES
A
AF = 300mm
X = SAFETY DISTANCE 300M
2100mm= AF
11KV
0.9M+2.1M= 3M
33KV
1.2M+2.1M= 3.3M
11KV
0.9M+0.3M= 1.2M
33KV
1.2M+0.3M= 1.5M
Page 75
VERSION 3 BY MJEC,OMAN
ZONE
START DATE
EST.COMP.
DATE
LOCATION
START TIME
EST.COMP TIME
NET WORK TO BE
MADE DEAD
PURPOSE
INTERRUPTION
FROM
LOAD
INTERRUPTED(A)
TO
NO
YES
NO
DEPARTMENT .
ACTION PARTY
NAME
SIGNATURE
STATUS
PERSON IN CHARGE:
SAEP/ AEP
CHECKED BY:
RCP
PERMISSION TO
PROCEED BY:
LCP
Page 76
VERSION 3 BY MJEC,OMAN
SWITCHING PROGRAM
ITEM
SUBSTATION
CIRCUIT
OR UNIT
PROG. REF NO
OPERATION
OPERATOR
TIME
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
RETURN ON COMPLETION TO CONTROL CENTER
BY______________________DATE:__________________
Page 77
VERSION 3 BY MJEC,OMAN
SHEET NO OF
APPENDIX G
GUIDANCE FOR ACTIVITIES IN THE VICINITY OF OVERHESD LINES
This guidance addresses:
General Requirements
1.1
Passage Underneath Overhead Power Lines crossing roads, tracks or right of way.
1.1.1 Clear sign-posting (including maximum allowable height indication signs) and a suitable
type of goal post arrangement on either side of the overhead line at the entrance of
roads, tracks or right of way, wherever the line crosses the roads, tracks or right of way
shall be provided. The safety clearances between the cross bars and the lowest
conductor shall be in accordance with Section 1.3. Due to changes in road conditions
MJEC shall frequently updates the sign posts to reflect the actual goal post height.
1.1.2
Wood poles shall be used in the construction of safety barriers and goal posts. On sign
posted roads, goal posts shall be erected with a minimum horizontal distance from the
overhead power line of 75 metres. This enables vehicles which are too high and hit the
goal post, to stop safely before reaching the overhead line crossing.
1.1.3 The responsible person for the vehicle or other plant moving or working underneath the
power lines shall submit the clearance certificate not less than 48 hrs to allow enough
time for the Area AUTHORIZED ELRCTRICAL PERSON to conduct site visit if required.
1.1.4 When high loads, travels long distance and crosses overhead lines through a number of
locations, the mobilisation team (and prior to mobilisation ) shall conduct crossing
points survey and submit to the issuer of clearance certificate with following details:
Line tag
Pole number a crossing location
Voltage type
Height if applicable
Page 78
VERSION 3 BY MJEC,OMAN
1.2.1 If work is to take place underneath or within 5 meters of a live overhead line, then the
safety clearances given in Section 2.3 shall be applied. Suitable means should be put in
place, where necessary, to ensure that safety clearances are maintained. This is
particularly important if cranes and jibs, or similar equipment are to be used.
1.2.1 If verbal instructions are not considered sufficient by the AUTHORISED ELECTRICAL
PERSON, then he shall issue a LIMITATION OF ACCESS to COMPETENT ELECTRICAL
PERSON (CEP) who shall remain at the work location and oversee the work activities. If
the CEP is not in charge of the work, then it shall be made clear to the person in charge
that the CEP is on site to enforce the safety precautions and the safety clearances called
for on the LIMITATION OF ACCESS. The CEP shall be given full authority to stop the
work if it is considered unsafe.
1.2.2 If the work, or passage of vehicles, is such that the safety clearances cannot be
reasonably maintained in practice and there is a danger of personnel, materials, or
vehicles infringing the safety clearances, then the overhead line shall be made dead,
isolated and earthed. In this case an ELECTRICAL PERMIT TO WORK (EPTW) shall be
issued to a CEP, who will remain onsite to ensure safety of personnel involved. It shall
be stated in the 'Work Description Section of EPTW that the High Voltage overhead line
has been made safe so that passage / work can take place near / under the earthed
conductors, but no work shall be carried out on the conductors themselves.
1.2.3 At all other sites subjected to passage underneath overhead power lines (e.g., access
roads to construction sites), goal posts and safety barriers shall be erected at an
absolute minimum horizontal distance of 6 meters from the overhead line to ensure
that mobile plant crosses under the overhead line via the goal posts (ref Figure 2).
Page 79
1.3
VERSION 3 BY MJEC,OMAN
Safety Clearances
1.3.1 The minimum vertical safety clearance to the lowest conductor of the overhead line,
beyond which no person or object can approach shall be:
33kV
11kV
1.2 meters
0.9 meters
1.3.2 The following factors shall be taken into account when deciding the safety clearances.
1.4
Has the ground level been raised in any way which could reduce the design
clearances of overhead line?
Check the area under the line for humps or bumps which could reduce safety
clearances.
1.5
1.5.1 If major construction activity involving earth moving and other heavy plant, is to take
place below live overhead line, where possible overhead power lines should be made
dead. If this is not practicable, then strict precautions shall be enforced whilst work is in
progress.
1.5.2 The safety precautions for such work shall be closely supervised by the Area Distribution
representative who shall ensure that a minimum vertical safety clearance of 3.5 meters
is maintained at all times. Figures 2 and 3 illustrate methods that can be adopted, using
goal posts and safety barriers, to assist in promoting safe working practices.
Page 81
VERSION 3 BY MJEC,OMAN
Page 80
VERSION 3 BY MJEC,OMAN
Page 82
Figure
Example
VERSION 3 BY MJEC,OMAN
of
the
Use
of
Tensioned
ropes
Page 83
VERSION 3 BY MJEC,OMAN
No.
MAJAN ELECTRICITY COMPANY
CLEARANCE CERTIFICATE FOR WORK IN THE VICINITY OR PASSAGE UNDER O/H LINES
1.
WORK/PASSAGE DETAILS
The following information shall be completed by the person applying for the clearance:
a)
Originating Party..................................................................................
b)
c)
Type of Work..........................................................................................................
d)
e)
f)
Details of work.........................................................................................................
g)
h)
i)
Signature:
**Originator.
Date:
Page 84
VERSION 3 BY MJEC,OMAN
2.
CLEARANCE
a)
b)
________________________________________________________________________
3.
WORK COMPLETION
I hereby declare that the work/passage as stated above is completed/cancelled and this
certificate may be cancelled.
Date...............................
**Person in charge on Site
4.
CANCELLATION
This certificate is cancelled. No further work/passage is allowed.
Date..............................
** State name and sign.
NOTE: USE ONLY ORIGINAL SHEETS OF THIS CERTIFICATE. FAXED COPIES NOT ALLOWED.
White - Originator ; Blue - Person in charge on site/ driver
Pink
Page 85
VERSION 3 BY MJEC,OMAN
APPENDIX H
Safe Steps to be observed while executing switching program and issuing E PTW
1. Switching Program must be prepared as specified in ESRs with all necessary info and to
be attached with updated single line diagram, then to be sent to DCC to get it checked
from RCP and then approved by LCP. AEP is to make sure that DCC has the final copy of
approved switching program
(After being reviewed by RCP, corrections made, signed by LCP)
2. AEP is required to keep the approved switching program document along with him on
site during work & inform RCP before starting the Switching program & during the
execution of the program and when restoring supply with all details.
3. As first step in executing the switching program, AEP is to Switch off and identify all
possible points of supply as per approved switching program.
4. Once above is done, AEP is to Isolate, establish physical gap between live and dead
points
5. After that, AEP is to TEST VOLTAGE to ensure the system (equipment) to be worked on is
dead & proved to be dead using proper voltage tester.
6. Then, AEP to APPLY Safety Padlock(Lock out all live systems and never assume)
7. Then, AEP to APPLY CN (Put caution notices at points of Isolation) lock & maintain key
safe.
8. Then, AEP to APPLY DN (put danger notices at nearby exposed live equipment), put
suitable barricade mean around nearby live equipment.
9. Then AEP to APPLY EARTH (Identify the points of Earthing and apply CMEs)
10. Then, AEP to APPLY EN (Put Earthing notices at points of earth )
11. AEP is to BREIF the CEP on the work to be done, make him aware of all isolation points,
earthling, etc., and inform him where he needs to apply AE if required.
12. Then AEP to ISSUE EPTW to CEP, & shall make sure that he has understood what has
been written in the permit. The permit needs to be written in clear writing with ink and
in capital letters.
13. The CEP shouldnt allow his crew enter/attended restricted work area until the area/site
is made to be safe and EPTW is issued by AEP.
14. CEP is to Receive EPTW and signs it after making sure that he understood its content
and conditions as specified.
15. CEP is to brief his crew on the work to be done and conduct tool box talk & must adhere
to EPTW and GPTW procedure.
For emergency cases and outages toll box talk should be sufficient.
16. CEP is to Apply Additional Earth at dead points of work.
17. CEP has to supervise his crew during execution of the work and must observe that all
safety precautions are in place all times.
18. Once work is done, CEP is to Remove additional earth
19. CEP is to Clear EPTW and GPTW.
20. AEP is Cancel EPTW and GPTW and should inform RCP accordingly.
Page 86
VERSION 3 BY MJEC,OMAN
Item
Yes /No
Remarks
Has the AEP notified RCP before work gets started &
Is APPROVED switching program available at the site with AEP?
Has the AEP done the Switch off and identified all possible points of
supply as per approved switching program?
Has the AEP Isolated & established physical gap between live and dead
points?
Page 87
VERSION 3 BY MJEC,OMAN
Has the AEP Tested the voltage, to ensure the system (equipment) to be
worked on was dead & proved to be dead, using proper voltage tester?
Has the AEP APPLIED Safety Padlock (Lock out all live systems and never
assumed)?
HAS the AEP APPLIED DN (put danger notices at nearby exposed live
equipment)? Has he barricaded the live area with suitable mean?
10
Has the AEP APPLIED EARTH (Identified the points of Earthing and
applied CMEs)?
11
12
Has the AEP ISSUED E-PTW to CEP, & made sure that CEP understood
what was written in the permit?
13
Is E PTW clearly written with ink & in capital letters and filled with all
required info? Are all boxes filled?
14
Has the AEP BREIFED the CEP on the work to be done, made him aware
of isolation points, earthing , etc, & informed him where he needs to
apply AE as required?
15
Has the CEP Received EPTW and signed it after making sure that he
understood its content and conditions as specified?
Page 88
VERSION 3 BY MJEC,OMAN
16
Has the CEP briefed his crew on the work to be done and conducted
tool box talk & did he adhere to E PTW requirement?
17
18
Has CEP and his crew executed the work and observed that all safety
precautions were in place all times?
19
Has the CEP Removed additional earth once work was done?
20
Has the CEP Cleared EPTW once confirmed the work is done?
21
22
23
24
25
26
Has the AEP submitted canceled EPTW & Switching program to DCC?
27
Has RCP archived EPTW, Switching Program, SLDs and other safety
documents?
Page 89
VERSION 3 BY MJEC,OMAN
28
Has the RCP reviewed any deviation done while executing the work and
highlighted any HSSE non conformances?
29
Page 91
VERSION 3 BY MJEC,OMAN
PLAN, discuss with him the hazards and HSSE controls, then he should endorse the JOB SAFETY
PLAN. He should retain the white copy of the GPTW form, while the blue color should be
handed over to the applicant and to be kept at the work site.
If the work is to be done in the MJEC network, assets and facilities, then normally the MJEC
Responsible Engineer, refer to him as issuer, is the area/zone distribution engineer.
In case if the applicant is not the one who will execute the work at site but his foreman , who is
called PTW holder, then it is the responsibility of the GPTW applicant to make sure that his
PTW holder understood the work hazards and HSSE controls. He should discuss these in person
with him.
The permit holder (who can be the applicant himself or his foremen) should fill section C in
GPTW form, please refer to GPTW form.
The PTW holder should only sign once he knows the work to be done, the hazards associated
with work activities and HSSE controls. Then before work starts he should discuss the hazards
and HSSE controls with his work party. He should make sure that his work party understood
these. Then he can proceed on the work execution.
Once the work is complete or in case it is incomplete due to certain circumstances he should fill
in section D of the GPTW accordingly.
Then PTW holder or the applicant must submit the GPTW to MJEC Responsible Engineer (the
issuer) to fill in section E and cancel the GPTW accordingly.
System Archiving:
Once the GPTW is canceled the Responsible Engineer (issuer) should retain the GPTW for a
period of six months then the canceled GPTW can be disposed off.
Page 90
VERSION 3 BY MJEC,OMAN
GPTW Form
no
---Regio
n:
-----------
Walay
at:
---------------
:
Applicant
------------------
:Contact
------
---------------
: Work
:location
-----------------------
:
Description of work to be carried out:
............
/
.
/
/
to
:
Contractor Name: ...
:
Name of person in charge :....
:
Page 92
VERSION 3 BY MJEC,OMAN
Name of Applicant:
:
Signature:...
:
---------------------------Department:
: ----
---------------------Signature:
:
.
I acknowledge receive of permit and understood work hazards and associated safety controls
Name of Holder: : Signature:.
:
Page 93
VERSION 3 BY MJEC,OMAN
-------------------------------Name:
: --------
/
--------------------Department:
: -
---------------------Signature:
:
Page 94
VERSION 3 BY MJEC,OMAN
HAZARDS
CONTROLS
Tick if
provided
CONTROLS
Tick if done
CONTROLS
Tick if done
B. Safety HAZARDS
1. Electrical HAZARDS
HAZARDS
2. Construction HAZARDS
HAZARDS
Page 95
VERSION 3 BY MJEC,OMAN
CONTROLS
Tick if done
CONTROLS
Tick if done
CONTROLS
Tick if done
D. Environmental Hazards
HAZARDS
In case of Emergency (accident at work site and a help is required), the following to be done:
Page 96
VERSION 3 BY MJEC,OMAN
I hereby confirm that above HAZARDS are being recognized for this work and all controls will be
in place during the work execution. In case of Emergency, the above Emergency steps will be
initiated accordingly.
The above will be discussed with the work party during tool box talk.
Name of Permit applicant:
Sign:
Date:
Date:
Date:
Page 97
VERSION 3 BY MJEC,OMAN
APPENDIX K
User-Comment Form
User-Comment Form
If you find something that is incorrect, ambiguous or could be better in this
document, write your comments and suggestions on this form. Send the form to
the FUNCTION HEAD, who besides acknowledging will issue necessary revisions.
Page number:
Heading Number:
Figure Number:
Comments:
Suggestions:
Position:
Signature:
Date:
Phone:
Page 98