Beruflich Dokumente
Kultur Dokumente
VISUAL INSPECTION - At any point in the course of welding, i.e. tacking (sujecin por puntos de soldadura), root pass, filler pass or capping
pass, but particularly for the root and cap, a detailed inspection may be required.
British Standard 5289: 1976 gives guidance on tools and responsibilities together with sketches of typical defects.
The inspector at this point must a) Observe, identify and perhaps record (measure) the features of the weld.
b) Decide whether the weld is acceptable in terms of the particular levels that are permitted; defect levels may be in-house or national codes
of practice.
When the defect size is in excess of the permitted level then either a concession must be applied for (from a competent person), or the weld
rejected.
AIDS OF VISUAL INSPECTION
Illumination: Good lighting is essential.
Inspection Lenses: The magnification should not exceed 2 - 2.5 diameters. If higher magnification is required use a binocular microscope.
Optical viewing can progressively develop from eyesight, to use of a hand torch and mirror, to the addition of a magnifier and light source.
* In order to achieve accessibility, remote probe units are available which must have the following properties.
a) Large field of vision
b) Freedom from distortion of image
c) Accurate preservation of colour values
d) Adequacy of illumination
CODE OF PRACTICE - A code of practice for an inspection department should take the form outlined below. (resumir, perfilar).
It is appreciated that full implementation of the code would be extremely costly and therefore it may be necessary to reduce the amount of
inspection to less than is theoretically required.
The inspector should be familiar with: All applicable documents - Workmanship standards - All phases of good workshop practice
- Tools and measuring devices.
INSPECTION BEFORE WELDING - Before Assembly you must check:
* All applicable documents.
* Quality plan is authorised and endorsed with signature, date and company stamp.
* Application standard is up to date with the latest edition, revision or amendment. (enmienda o correccin).
* The drawings are clear, the issue number is marked and the latest revision is used.
* Welding procedure sheets (specifications) are available, have been approved and are employed in production.
* Welder qualifications with identification and range of approval are verified and that only approved welders as required are employed in
production.
* Calibration certificates, material certificates (mill sheets) and consumer certificates are available and valid. (encuadernacin).
* Parent material identification is verified against documentation and markings. (sobre, respecto a ).
* Material composition, type and condition.
* Correct methods are applied for cutting and machining.
* Identification of welding consumables such as electrodes, filler wire, fluxes, shielding and backing gases and any special requirements (e.g.
drying) are met.
* Plant and equipment are in a safe condition and adequate for the job.
* Safety permits (licencia, pase) e.g. hot work permit, gas free permit, enclosed space certificate are available and valid. (sitio o lugar
cercado).
After Assembly you must check:
* Dimensions, tolerances, preparation, fit-up and alignment are in accordance with the Approved drawings and standards.
(colocacin de las partes entre s; gap= espacio entre alas adyacentes).
* Tack welds, bridging pieces (unin de puntales por travesao), clamping and type of backing - if any used are correct.
* Cleanliness of work area is maintained.
* Preheat in accordance with procedure.
NOTE. Good inspection prior to welding can eliminate conditions that lead to the formation of defects. (llevar, ocasionar).
INSPECTION DURING WELDING
* The welding process must be monitored.
* Preheat and interpass temperatures must be monitored.
* Interpass cleaning - chipping, grinding, gouging, must be monitored. (desportillar); excavar, escoplear con gubia o formn.
* Root and subsequent run sequence.
* Essential variables such as current, voltage, travel speed to be monitored.
* Filler metals, fluxes and shielding gases are correct.
* Welding is in compliance with weld procedure sheet and application standard.
INSPECTION AFTER WELDING
* Visual inspection to be carried out to ascertain acceptability of appearance of welds. (esclarecer, descubrir).
* Dimensional accuracy to be ascertained.
* Conformity with drawings and standards requirements.
INFLUENCE OF PROCESS - Each process will give a characteristic intensity of power. Processes that offer the higher power intensity offer
advantages in fusion welding because the essential melting can be obtained without excessive heat inputs with the consequent thermal
expansion of the parent metal.
Successful welding often depends on feeding into the weld pool a filler wire which carries a deoxidant (or ferrite forming elements) hence
processes which do not use filler wire are limited in application.
HEAT INPUT - Heat input is a combination of voltage, amperage and travel speed.
Heat Input = voltage x amperage/travel speed; for example:
Weld
pass
process
Root
SMAW
Filler Metal
Class
E7010
Brand
Pipe Liner 7P+
3.2mm
Polarity
Current
(AMPS)
DCEP
Range
58 - 105
Volts
Range
(V)
17-35
Travel Speed
(mm/min)
Direction
of Welding
46 - 190
Uphill
Higher heat Input gives a larger grain size and better Bead Penetration, (With hardness, the higher the number, the harder the material e.g.
475, 450, 300, 275)
As heat input increases:
grain size increases
toughness decreases
brittleness increases
hardness decreases
incidence of cracking decreases
Toughness - resistance to bending and impact
Hardness - resistance to penetration
PREHEATING - There are four general factors that must be assessed to determine the level of preheat.
1. Material type.
2. Combined thickness.
3. Heat input potential (welding process).
4. Joint type.
INFLUENCE OF COMPOSITION - The composition of the steel and its effect on weldability may be divided into two parts:
1. Segregation effects, particularly that of sulphur - When a steel solidifies, there is a tendency for the iron to solidify fast and for the
alloying elements to be accumulated in the centre of the ingot. This configuration is retained even after prolonged and severe rolling and results
in high concentrations of sulphur in the central layers of the plate. These layers have little strength and are likely to crack if stressed.
2. The tendency of the steel to harden - The hardening characteristics of steel are mentioned in the heat treatment section. As the carbon
or alloy content of the steel increases, the likelihood of low ductility and hardened microstructures forming also increases and should stresses
exist, cracking will result.
WELD AND HAZ CRACKING - These are the main causes of cracking:
a. High levels of carbon and other alloy elements result in brittle zones around the weld.
b. High cooling rates after welding increase the hardness, which increases the susceptibility to cold cracking.
c. Joint restraint prevents contraction after welding, which can lead to internal cracking. (impedir).
d. Hydrogen in the weld bead can lead to hydrogen induced cold cracking.
e. Contaminants like sulphur and phosphorus cause segregation or solidification cracking.
f. Lamellar tearing caused by inclusions layering during rolling resulting in deterioration of the through-thickness properties. (Proceso de
laminado).
Cracking usually occurs in the unmelted areas adjacent to a weld bead (in the HAZ). This zone is made up of an area that has been heated to
above about 800C (to become austenite), and an area heated above 723C (partially transformed zone). The fully austenitic region
just adjacent to the fusion zone is often the most brittle area of the weld due to the grain growth that has occurred while the metal was at this
temperature. The grain size gradually decreases moving away from the fusion zone to the partially transformed region. Grain refinement
occurs here, which is considered beneficial, the grain size being smaller.
The composition of the steel, particularly the carbon level, determines the hardness and brittleness of both the weld and the HAZ.
On cooling, austenite transforms to ferrite. Carbon is soluble in austenite, but less so in ferrite. Iron carbides are precipitated when this
transformation takes place. These can be arranged in lamellar form (as pearlite), which gives the structure reasonable strength and ductility.
The HAZ can be the region where the highest cooling rates occur, particularly in thicker section plate. High cooling rates tend to lock the
carbides in a solid solution, forming martensite. This leads to high internal stress and hard brittle structures.
HEAT TREATMENT - Many metals must be given heat treatment before and after welding. The inspectors function is to ensure that the
treatment is given, and given correctly, to the details supplied.
5.3.2.13 Pre- and Post-heat Treatment - The methods, temperature, temperature-control methods, and ambient temperature range for
pre- and post-heat treatment shall be specified. (See 7.11) - The procedure specification shall specify the pre- and post heat treatment
practices to be followed when materials or weather conditions make either or both treatments necessary.
PREHEATING - There are four general factors that must be assessed to determine the level of preheat.
1. Material type.
2. Combined thickness.
3. Heat input potential (welding process).
4. Joint type.
The types of heat treatment available are given below. (The temperatures mentioned are for steel).
Annealing process at 920 C hold in furnace cooling: Annealing is a recrystallization that improves (softens) ductility. However when very slow
cooling is applied: decreases toughness, makes bending, etc. (easier) and lowers yield stress.
Normalising process at 920 C hold in air cool: increases toughness and improves mechanical properties. However when slow cool is applied:
relieves internal stress.
Quench, harden process at 920 C hold in quench cool: hardens carbon steels and prevent precipitation in austenitic stainless steels.
However when fast cooling (in oil or water) is applied: prevents temper brittleness, cooling after tempering and prepares metal for tempering.
Temper process at 550 C to 700 C hold in slow air cooling: increases toughness of quench steels.
Stress relief process at 500 C to 700 C hold in air cool: relief residual stresses by plastic deformation, reduces yield point and reduces
hydrogen levels. However when slow air cooling is applied: improves stability during machining and prevent stress corrosion cracking.
Pre-heating for welding is performed at 50 C to 250 C
Hydrogen soak process at 150 C holding.
When temperature is above 920 C: the grain structure and size of grain are affected. Not so below 920 C where the zone is partially
transformed and the grain structure is not affected.
The soak time is related to thickness, usually 1hr/25mm thickness.
Differing cooling rates give different properties to the metal, so the cool down rate is also critical (Possibly monitoring at a stand off from the
weld being treated). (relacin).
For preheating and hydrogen soak oxy-acetylene is not to be used due to a heat source too localized, but propane is to be used.
MONITORING THE HEAT TREATMENT The method and location of the heat treatment are important, for example in a workshop furnace or
on site using electro-blanket (cooper-heat type) equipment.
The temperature is measured with thermocouples and recorded on a chart. The main points are:
- controlled heat rise
- soak time
- temperature
- cool down rate to unrestricted
Remedy
Preheat, relieve residual stresses mechanically, minimise shrinkage stresses using back-step or block welding
sequence. Also known as back-skip welding.
Change welding current and travel speed, weld with covered electrode negative, butter the joint faces prior to welding.
Change to new electrode, bake electrodes to remove moisture (when use Basic).
Reduce root opening (root gap), or build up the edges with weld metal.
Increase electrode size, raise welding current, or reduce travel speed.
Use filler metal low in sulphur.
Change to balanced welding on both sides of joint.
Fill crater before extinguishing the arc, use a welding current decay device when terminating the weld bead (drooping
characteristic).
Base metal cracking
Causes
Hydrogen in welding atmosphere
Remedy
Use low hydrogen welding process, preheat and hold for two hours after welding or PWHT immediately
(Hydrogen soak at 150 C holding).
Hot cracking
Use low heat input; deposit thin layers; change base metal.
Low ductility
Preheat, anneal the base metal (at 920 C, hold in furnace cooling).
High residual stresses
Redesign the weldment (change joint design), change welding sequence, apply intermediate stress relief
heat treatment (at 500-700 C. hold in air cool).
High hardenability
Preheat, increase heat input, heat treat without cooling to room temperature.
Brittle phases in the microstructure
Solution heat-treat prior to welding (temper till 500-700 C).
THE WELDING PROCEDURE - A welding procedure is a way of controlling the welding operation. Purpose of procedure:
1) To prove a joint can meet design procedure - consistency coherencia,consistencia).
2) Instruction for welder
3) Ensure repeatability
Weld procedures are approved to ensure they are functional and fulfil the physical and mechanical properties necessary to reach the required
standard (to establish the essential variables for contractual obligations). (to carry out or perform a task; Cumplir, satisfacer).
Welders are approved to ensure a particular welder is capable of welding to a procedure and obtaining a result that meets specification.
The task of collecting the data and drafting the documentation is often referred to as writing a weld procedure. (esbozar=bosquejar).
In many ways this is an unfortunate term as the writing of documents is the last in a sequence of tasks.
Producing a weld procedure involves:
Planning the tasks
Collecting the data
Writing a procedure for use or for trial. (prueba, ensayo).
Making test welds
Evaluating the results of the tests
Approving the procedure of the relevant code
Preparing the documentation
In each code reference is made to how the procedures are to be devised and whether approval of these procedures is required. (concebido).
In most codes approval is mandatory and tests to confirm the skill of the welder are specified. Details are also given of acceptance criteria for
the finished joint. The approach used depends on the code, for example: (propuesta, proposicin).
BS 2633 (Class 1 arc welding of ferritic steel pipe work for carrying fluids) provides general comments on various aspects of a suitable
weld procedure.
AWS D.1.1 (Structural welding code - steel) favours more specific instructions for different joints and processes that are, in effect, prequalified procedures. (Apoyar, aprobar).
Other codes do not deal specifically with the details of the weld procedure but refer to published documentation, e.g. BS 5135 process of arc
welding carbon and carbon manganese steels.
COMPONENTS OF A WELD PROCEDURE - Items to be included in the procedure can be some of the following:
1. Parent Metal
a. Type
b. Thickness (for pipe this includes outside diameter)
c. Surface condition
d. Identifying marks
2. Welding Process
a. Type of process (MMA, TIG, SAW etc.)
b. Equipment
c. Make, brand (marca), type of welding consumables
d. When appropriate, the temperature and time adopted for drying and baking of electrodes and/or consumables
3. Joint Design
a. Welding position
b. Edge preparation
c. Method of cleaning, degreasing etc.
d. Fit up of joint
e. Jigging or tacking procedure (punteo)
f. Type of backing
4. Welding Position
a. Whether shop or site weld
b. Arrangement of runs and weld sequence (disposicin, arreglo).
c. Filler material, composition and size (diameter)
d. Welding variables - voltage, current, travel speed
e. Weld size
f. Back gouging (excavar, escoplear con gubia o formn)
g. Any specific features, e.g. heat input control, run-out length
5. Thermal Treatment
a. Preheat and interpass temperatures including method and control
b. Post weld treatment including method and control
ESSENTIAL VARIABLES - An essential variable is a variable that will influence or change the mechanical or metallurgical properties of the
welded joint - changes affecting the procedure approval. Any change in an essential variable requires a new WPS.
Essential variables include: wall thickness, joint design, process, materials, consumables, welding position, direction, heat input (voltage,
amperage, travel speed), heat treatment.
APPROVING THE PROCEDURE - When the data has been collected, the procedure must be validated by producing and testing a trail weld.
If the procedure is to be used on a fabrication, which has been designed to meet the requirements of a code, the test weld is done under the
supervision of an independent witness. The detailed arrangements for the test are subject to agreement between the contracting parties.
A number of British Standards make cross-reference to another standard which covers approval testing.
Other codes of practice include their own weld procedure/welder approval information. In general they include a standard format, which can be
used to report the results of an approval test. e.g. API figure 1
Range of approval - extent of approval - scope of approval - Provides a working range over which certain variables may alter without
requiring a new welding procedure/welder approval.
Variables include thickness (e.g. 1/2 down to 2x above), diameter (e.g. = down to above) materials (different materials can be
covered), position, process, parent plate group, and consumables.
Re-approval of a welding procedure is necessary if there is a change of any of the essential variables or considerable defect re-occurrence.
ABBREVIATIONS
WPS
PQR
WAC
WATC
WAR
WPAR
WQT
* pWPS
welding procedure specification - an approved and accepted welding procedure; an authorised document.
procedure qualification records - proof the procedure works - record of tests undertaken to qualify procedure. (emprender)
welder approval certificate - required to ensure a particular welder is capable of welding to a procedure.
welder approval test certificate.
welder approval record.
welding procedure approval record.
welder qualification test.
preliminary WPS - unauthorised (contains all essential variables and, after welding the test piece and all NDT and destructive
tests have been accepted, then the WPS can be approved).
* pWPS and WPAR give final WPS (various WPS can derive from one pWPS).
3.2.11 qualified welder A welder who has demonstrated the ability to produce welds that meet the requirements of Sections 5 or 6.
3.2.12 qualified welding procedure A tested and proven detailed method by which sound welds with suitable mechanical properties can be
produced.
DOCUMENTATION - The objectives of a procedure or welder approval test are:
a. to prove the procedure meets the necessary requirements with reference to feasibility, mechanical strength etc. (factibilidad).
b. to prove the welders are competent to work on a particular job.
If a customer queries it, evidence can and would be supplied to prove validity. (preguntar, cuestionar, poner en duda).
Approval Test Specifications call for a paper record, which can be known as:
Procedure/welder approval certificate (WAC)
Procedure/welder approval record (WAR)
Procedure/welder approval report
The following records should also be kept:
NDT reports
Records of visual examination or mechanical testing
Test pieces from destructive testing
Other records that are equally important are proof of regular employment on a job for scheduling re-tests to avoid duplication on procedure
approval. (empleo); programar, fijar.
7. Design and Preparation of a Joint for Production Welding - Piping shall be welded by qualified welders using qualified procedures.
The surfaces to be welded shall be smooth, uniform, and free from laminations, tears, scale, slag, grease, paint, and other deleterious
(residuals) material that might adversely affect the welding. The joint design and spacing between abutting ends shall be in accordance with the
procedure specification used.
5.3.2.4 Joint Design the specification shall include a sketch or sketches of the joint that show the angle of bevel, the size of the root face, and
the root opening or the space between abutting members. The shape and size of fillet welds shall be shown. If a backup is used, the type shall
be designated.
7.2 ALIGNMENT - The alignment of abutting ends shall minimize the offset between surfaces. For pipe ends of the same nominal
thickness, the offset should not exceed 1/8 in. (3 mm).
Larger variations are permissible provided the variation is caused by variations of the pipe end dimensions within the pipe purchase
specification tolerances, and such variations have been distributed essentially uniformly around the circumference of the pipe. Hammering of
the pipe to obtain proper lineup should be kept to a minimum.
7.3 USE OF LINEUP CLAMP FOR BUTT WELDS - Lineup clamps shall be used for butt welds in accordance with the procedure specification.
When it is permissible to remove the lineup clamp before the root bead is completed, the completed part of the bead shall be in approximately
equal segments spaced approximately equally around the cir-cumference of the joint. However, when an internal lineup clamp is used and
conditions make it difficult to prevent movement of the pipe or if the weld will be unduly (excessively) stressed, the root bead shall be
completed before clamp tension is released.
Root-bead segments used in connection with external clamps should be uniformly spaced around the circumference of the pipe and shall have
an aggregate length of at least 50% of the pipe circumference before the clamp is removed.
3.2.16 root bead: The first or stringer bead that initially joins two sections of pipe, a section of pipe to a fitting, or two fittings.
Generally internal lineup clamp is used for pipe to pie and pipe to pipe tie-in.
Pipe to pipe tubo con otro tubo, osea una soldadura normal sin mayor concentracin de esfuerzo en los dos tubos.
Pipe to pipe tie-in empalme, es una soldadura entre dos secciones de tubera o empalme de un tubo con una seccin de tuberas soldadas lo
cual requiere ms dedicacin y precaucin.
7.4 BEVEL
7.4.1 Mill Bevel - All mill bevels on pipe ends shall conform to the joint design used in the procedure specification.
7.4.2 Field Bevel - Pipe ends should be field beveled by machine tool or machine oxygen cutting. If authorized by the company, manual
oxygen cutting may also be used. The beveled ends shall be reasonably smooth and uniform, and dimensions shall be in accordance with the
procedure specification.
7.5 WEATHER CONDITIONS - Welding shall not be done when the quality of the completed weld would be impaired=deteriorado by the
prevailing weather conditions, including but not limited to airborne moisture, blowing sands, or high winds. Windshields may be used when
practical. The company shall decide if weather conditions are suitable for welding.
7.6 CLEARANCE - When the pipe is welded above ground, the working clearance around the pipe at the weld should not be less than
16 in. (400 mm). When the pipe is welded in a trench, the bell hole shall be large enough to provide the welder or welders with ready access
to the joint.
7.7 CLEANING BETWEEN BEADS - Scale and slag shall be removed from each bead and groove. Power tools shall be used when called for=
required in the procedure specification; otherwise, cleaning may be performed with either hand or power tools.
When semiautomatic or mechanized welding is used, surface porosity clusters, bead starts, and high points shall be removed by grinding before
weld metal is deposited over them. When requested by the company, heavy glass deposits shall be removed before weld metal is deposited
over them.
7.8 y 3.2.10 POSITION WELDING - welding in which the pipe or assembly is not rotating while the weld is being deposited
7.8.1 Procedure - All position welds shall be made with the parts to be joined secured against movement and with adequate clearance around
the joint to allow the welder or welders space in which to work.
5.3.2.16 Speed of Travel - the range for speed of travel, in inches (millimeters) per minute, shall be specified for each pass.
7.8.2 y 7.9.2 Filler and Finish Beads - for position (fixed) welding, and for roll welding the number of filler and finish beads shall allow the
completed weld a substantially uniform cross section around the entire circumference of the pipe. (escencialmente, considerablemente)
5.3.2.5 Filler Metal and Number of Beads - the sizes and classification number of the filler metal and the minimum number and sequence of
beads shall be designated. At no point shall the crown surface fall below the outside surface of the pipe, nor should it be raised
above the parent metal by more than 1/16 in. (1.6 mm).
Two beads shall not be started at the same location. The face of the completed weld should be approximately 1/8 in. (3 mm) wider than the
width of the original groove. As the welding progresses, the pipe shall be rolled to maintain welding at or near the top of the pipe. The
completed weld shall be thoroughly brushed and cleaned. (cepillado, pulido)
7.9 y 3.2.15 ROLL WELDING - welding in which the pipe or assembly is rotated while the weld metal is being deposited at or near the top
center.
7.9.1 Alignment - At the companys option, roll welding shall be permitted, provided alignment is maintained by the use of skids (deslizantes)
or a structural framework with an adequate number of roller dollies to prevent sag in the supported lengths of pipe. (doblz, combarse)
5.3.2.16 Speed of Travel - the range for speed of travel, in inches (millimeters) per minute, shall be specified for each pass.
7.10 IDENTIFICATION OF WELDS - each welder shall identify his work in the manner prescribed by the company.
7.11 y 5.3.2.13 PRE- AND POST-HEAT TREATMENT - the methods, temperature, temperature-control methods, and ambient temperature
range for pre- and post-heat treatment shall be specified. The procedure specification shall specify the pre- and post- heat treatment practices
to be followed when materials or weather conditions make either or both treatments necessary.
9.2 RIGHTS OF REJECTION - All nondestructive test methods are limited in the information that can be derived from the indications they
produce.
Fuentes de Radiacin, Rayos Gamma Ir 192.
Actividad de la fuente en Produccin. Mxima: 100 Ci y Mnimo: 40 Ci
Dimensiones Mximas de la Fuente. Diagonal: 4.2 mm
Capacidad de Contenedor: 100 Ci
Ci = curio, unidad de radioactividad. cantidad de cualquier nclido radiactivo en el que el numero de desintegraciones por segundo es 3,7 x 10
elevado al 10 becquerels.
Pantallas intensificadoras:
Material: Plomo
Espesor: Frontal 0.15 / 0.10 mm
Espesor: Posterior 0.15 / 0.10 mm.
Pelcula Radiogrfica - Se utilizara una pelcula por cada pantalla intensificadora tanto delantera como trasera.
Pelcula radiogrfica industrial AGFA- Structurix D 4 o Kodak Industrex MX de 70 mm o 100 mm. de ancho o equivalente.
Condiciones Geomtricas de la Exposicin
(DWE/SWV) Doble pared imagen simple
La fuente ser ubicada en el exterior del tubo separada (13mm) del mismo como mximo.
Se realizar 3 exposiciones por junta a 120 cada una.
La desviacin entre la fuente y la soldadura no ser superior a 5 .
El traslape ser como mnimo de 2 in (50mm). (Normalmente se deja un marco o traslape en cada extremidad de la pelcula para que la
soldadura aparezca completa).
Localizacin del (IQI) Lado de la pelcula en contacto con el tubo (4 IQI situados a 90 una de otra ).
Para el caso de calificacin de procedimientos de soldadura se podr utilizar la tcnica panormica (SWE/SWV) pared simple vista simple.
La fuente ser ubicada en el interior del tubo y en el centro.
Se realizar 1 exposicin.
Localizacin del (IQI) Lado de la pelcula en contacto con el tubo.
when the film length to be interpreted is to 5 in. (130mm), one IQI shall be placed on the film side, across the weld and located at the center
of the length to be interpreted.
Distancia mnima fuente objeto.
La distancia mnima (FFD) a radiografiar esta determinado por la siguiente frmula: D = S. t/k
Donde:
K = (geometric unsharpness factor) 0.02in. (0.5mm), para espesores de 2 in (50.8mm) o menores.
S = Tamao efectivo de la fuente (mm) size (in inches) of the effective source or focal spot.
t = Espesor de la soldadura incluyendo refuerzo ms la distancia entre la cara de la soldadura del lado de la pelcula y la pelcula.
Including reinforcement, plus the distance between the film side of the weld and the film.
- When t is determined for SWE/SWV and DWE/SWV procedures, the thickness of the single wall and its weld reinforcement shall be used.
- When t is determined for DWE/DWV procedures, the outside diameter of the weld (the OD of the pipe plus twice the average height of the
weld crown= not more than 1.6 mm) shall be used.
D = Distancia mnima (in inches) entre la fuente y el objeto, desde el lado de la fuente.
Minimum distance between the source or focal spot and the source side of the object being radiographed.
Exposicin - El clculo del Tiempo de Exposicin se determinar por formula matemtica o por el uso de reglas de clculo.
ESPESORES MXIMOS QUE PUEDEN PENETRARSE CON RAYOS X
TENSIN
TIEMPO DE
PENETRACIN (mm)
FILAMENTO
EXPOSICIN
ACERO
COBRE/LATON
BRONCE
150 KV
1 hora
50
30
20
300 KV
100
65
40
1 000 KV
200
150
150
2 000 KV
300
250
250
Densidad - La mnima densidad ser de 2.0 H&D en la soldadura y la mxima ser de 3.5 H&D en la zona de inters.
Para determinar esta densidad se utilizar un densitmetro calibrado.
11.1.10 Film Density except for small localized areas caused by irregular weld configurations:
The transmitted H&D density in the area of interest of transparent-based film shall not be <1.8 nor > 4.0.
The reflected H&D density for opaque-based film shall not be < 0.5 nor > 1.5.
Transmitted H&D densities through small localized areas may exceed these limits.
However, minimum densities shall not be less than 1.5 and maximum densities shall not exceed 4.2.
Reflected H&D density shall not be < 0.25 and shall not exceed 1.8.
Si existiese una variacin de densidad en cualquier parte del rea de inters -15% +30% de la densidad medida a travs del penetrametro
(IQI) o adyacente al alambre designado, ser necesario colocar un indicador de calidad adicional.
Radiacin secundaria - Cuando sea necesario detectar radiacin secundaria, se colocar una letra B en la parte posterior del cassette. Si una
imagen clara sobre un fondo oscuro aparece la proteccin es insuficiente y la radiografa se considera inaceptable. Una imagen oscura de la B
sobre un fondo ms claro no es causa de rechazo de la radiografa.
Definicin de imagen - La imagen en el rea de interpretacin de la radiografa estar libre de imperfecciones que alteren u oculten los
defectos. El hilo o agujero del penetrmetro que correspondan segn las Tablas I o II de este procedimiento, debe distinguirse claramente en la
imagen.
(IQI) Penetrametro son como hilos de diferente grosor que se ponen en la pelcula para saber si la radiacion que pasa es aceptable y si la
soldadura se puede ver bien; son alambres que definen la densidad de la placa radiografica; dependiendo del espesor del tubo o material de
acero se usan segn el mnimo grosor que puede ser como un cabello hasta el mayor grosor como el de una aguja grande.
En caso de radiografas de doble pared imagen simple (DWE/SWV), al menos 2 (IQI) penetrametros deben ser usados del lado pelcula, uno a
1 (25mm) antes del final o 1 al comienzo de la longitud interpretable y otro en el centro de la pelcula.
When the film length to be interpreted is > 5 in. (130 mm), two IQI placed across the weld and located on the film side shall be used.
One shall be within 1 in. (25 mm) of the end of the film length to be interpreted and the other shall be at the center of the film.
Cuando la toma sea panormica (SWE/SWV) se usarn 4 indicadores uno por cuadrante. When a complete weld is radiographed in a single
exposure using a source inside the piping, at least four IQI placed across the weld and spaced approximately equally around the circumference
shall be used.
Para radiografas de soldaduras reparadas se colocar un penetrametro en la zona de inters
When a repaired weld is radiographed, an additional IQI shall be placed across each repaired area.
Espesor de Soldadura
Pulgadas
Milmetros
0 - 0.25
> 0 - 6.4
> 0.25 0.375 > 6.4 - 9.5
> 0.375 0.50 > 9.5 -12.7
> 0.50 0.75
>12.7 - 19.10
> 0.75 - 1
>19.10 - 25.4
>1- 2
>25.4 - 50.8
Penetrametro ASTM
Set
N Hilo a ver
1-A
5
1-A o 1-B 6
1-B
7
1-B
8
1-B
9
1-B
10
11.1.12 Image Processing Area The image processing area and all accessories shall be kept clean at all times. El cuarto oscuro contar con
dos reas de clima apropiado una seca y otra hmeda donde se procesarn las pelculas adems dispondr de un Negatoscopio para lecturas
de placas hasta de 4.0 H&D. La luz roja ser filtrada para impedir el velo de las pelculas.
Marcas de posicin. Para el marcado de posicin se usarn nmeros de plomo. El candado o inicio de la Soldadura se lo marcar con el 0 en
el tubo y tambin este ser en inicio de la cinta con nmeros de plomo distribuidos en pulgadas o centmetros dependiendo de coordinacin con
la supervisin, con letras de tamao de al menos de 6 mm.
Identificacin de las Soldaduras. Para las soldaduras que hayan sido reparadas se debe volver a tomar la radiografa y al nmero de junta
se le anexara una letra R.
Cuando se trate de tiein la radiografa se identificar con una letra T.
Cuando haya existido un corte se colocar las letras CT para identificar que es nueva soldadura.
Evaluacin de las Pelculas Radiogrficas. (ASME T-238.1) La visualizacin de las placas ser realizada con iluminador de luz regulable o
negatoscopio, suficiente para lograr las densidades utilizadas e intensidad aproximada 2100 Lmenes, toda placa radiogrfica debe estar libre
de manchas e irregularidades del proceso que puedan interferir con la imagen de discontinuidades reales.
11.1.10.2 Film Viewing Equipment (illuminator or negatoscopio) shall be of the variable high intensity type and shall be capable of
viewing film densities within the range specified in 11.1.10 (film density). It shall be equipped to prevent light, coming from around the outer
edge of the radiograph or through low density portions of the radiograph, from interfering with interpretations.
11.1.10.3 Film Viewing Facilities Viewing facilities shall provide subdued background lighting of an intensity that will not cause troublesome
reflections, shadows, or glare on the radiograph.
Calificacin del procedimiento radiogrfico - Se realizar una radiografa de calificacin del procedimiento para cada uno de los sistemas
(interno y externo), colocando un indicador de imagen en el lado film y otro en el lado fuente, concordando los parmetros de observacin con
la inspeccin y registrando densidad, sensibilidad obtenida, pelcula usada, condiciones de revelado, identificacin y todos los datos
relacionados.
El procedimiento es considerado aprobado cuando las radiografas tomadas presentan:
Densidad requerida
(IQI) requerido e imagen perfectamente definida
Orificio esencial visible o Alambre visible
Libre de manchas de revelado
Sistema de identificacin perfectamente visible.
Se debe emitir un registro de la calificacin del procedimiento radiogrfico generado.
LIMITE ANUAL
2 Rem
0.10 Rem
Delimitacin de reas - En funcin de la carga de trabajo estimada para el mismo, la delimitacin para trabajadores ser hecha con 2
mRem/H. Se emplearn colimadores (material de tugsteno o plomo) para disminuir la radiacin.