Beruflich Dokumente
Kultur Dokumente
1. Fixed costs
The fixed capital costs can be divided into direct costs and indirect costs.
Type of direct costs
Value
15,400,000
231,000
25,000,000
Equipment cost
26,875,020
4600000
16997117
4249279
849856
Equipment
Unit cost $
No. of units
Cost $
Feed drum
20000
20000
Vapourizer
5000
5000
Fired heater
6000
6000
16000
16000
Furnace
6000
6000
Scrubber
10000
10000
Cooler
6000
6000
Condenser
7500
7500
Flash Distillation
Column
25000
25000
Distillation
column
130000
Tubular
Reactor
Flow
65000
Other Equipment
9000
Total
Equipment
Cost
200500
1. Working capital
Working capital is the additional investment needed, over and above the fixed capital, to start
the plant up and operate it to the point when income is earned. It includes the following
components;
1. Start-up.
2. Initial catalyst charges.
3. Raw materials and intermediates in the process.
4. Finished product inventories.
5. Funds to cover outstanding accounts from customers.
Most of the working capital is recovered at the end of the project. The total investment
needed for a project is the sum of the fixed and working capital. The working capital
requirement for a chemical plant is generally 12% of the fixed capital cost.
Capital Cost