Beruflich Dokumente
Kultur Dokumente
An experimental program on pretensioned wing-shaped members has investigated the evolution of prestressing stresses and
camber during the different stages of concrete hardening.
The result allowed the careful evaluation of prestress losses in
the first three weeks during concrete placement and curing,
emphasizing the influence of temperature history on prestress
losses and calibrating parameters for the prediction of camber
growth.
Calculations based on Eurocode2 equations compared
favorably with the data, indicating that these equations can
be applied to prestressed wing-shaped members made of selfconsolidating concrete as investigated in the present work.
98
restressed concrete wing-shaped members are frequently used in the construction of long-span roofs
in precast concrete buildings. Roofs spanning over
30m (100ft) are built by assembling a number of these
thin-walled members, which may be placed side by side or
with a certain transverse spacing, often rather wide, covered by ribbed slabs with curved shape. Figure1 shows
an example of a roof comprising curved ribbed slabs
supported by adjacent wing-shaped members resting on a
main I-girder. The ease of fabrication of the wing-shaped
members is comparable to that of a double tee but more
difficult than an I-girder. Nevertheless, the use of wingshaped members allows for better aesthetic results and for
roofs having smaller mass with the consequent benefits in
relation to seismic risk. To optimize the design of these
thin-walled members and take advantage of their loadcarrying capacity, prestressing is extensively used.
The exploitation of the mechanical properties of the materials, the prestress force necessary to ensure an appropriate
load-carrying capacity, and the requirement for in-service
camber for aesthetic and functional reasons necessitate
monitoring of prestress and camber. Inaccurate prediction
of the camber can lead to unsatisfactory service conditions.
Checking and monitoring of prestress loss and camber
growth and investigations of the parameters that could affect them have primarily focused on bridge girders.
99
Amount
460
992
747
Water, kg/m3
185
0.7
0.40
Sample
Concrete age
16 hours (release)
1 day
28 day
35.1
50.0
54.7
46.1
49.5
49.3
45.4
50.0
n/a
Average
42.2
49.8
52.0
33,048
n/a
n/a
33,199
n/a
n/a
33,786
n/a
n/a
Average
33,344
n/a
n/a
Abutment
Wing-shaped member
Casting bed
Abutment
Hydraulic jacks
Casting bed
Experimental setup
Length, m
Strands
pi, MPa
T1
16.9
1 0.6in. + 12 0.5in.
1400
T2
19.8
1 0.6in. + 14 0.5in.
1500
T3
18.9
11 0.6in. + 2 0.5in.
1450
101
710 mm
2490 mm
Strands debonding
2.5 m
2.0 m
1.5 m
1.0 m
3 2 1
3 2 1
upp
4
e
fac
r
r su
3 2 1
Figure 4. Cross sections and prestressing strands of the wing-shaped members tested in this project from top to bottom: tests1, 2, and 3. Note: 1mm = 0.0394in.;
1m = 3.28ft.
102
two displacement transducers for measuring the vertical displacement, placed in the mean longitudinal
plane, at 1/4 and 1/2 of the span length
three thermocouples, two embedded in the fresh concrete and the third to measure ambient temperature.
Channel 8
Section 4
Section 1
Section 5
Section 3
Section 2
Channel 10
Channel 7
Strand 7
Strand 5
Strand 3
Strand 1
Channel 12
Channel 11
Channel 4
Channel 2
Channel 15
Channel 14
Channel 9
Channel 1
Channel 13
Strand 8
Strand 6
Strand 4
Strand 2
Section 4
Section 1
Section 5
Section 3
Section 2
Channel 19
Channel 18
Channel 17
Strand 8
Strand 6
Strand 4
Strand 2
Strand 7
Strand 5
Strand 3
Strand 1
Channel 22
Channel 21
Channel 34
Section 4
Section 1
Section 5
Section 3
Section 2
Channel 33
Strand 8
Strand 6
Strand 4
Strand 2
Strand 7
Strand 5
Strand 3
Strand 1
Section 4
Section 1
Section 5
Section 3
Section 2
Displacement transducers
Ambient
Strand 8
Strand 6
Strand 4
Strand 2
Strand 7
Strand 5
Strand 3
Strand 1
0.4 m
0.8 m
L/4
Concrete bulb
=
Concrete bulb
=
L/4
1.5 m
L/2
Thermocouples
Figure 5. Positions of sensors. Note: L = total length of prestredded element. 1 mm = 0.0394 in.; 1 m = 3.28 ft.
PCI Journal | J a n u a r y Fe b r u a r y 2015
103
Figure 6. Electrical-resistance surface-bonded strain gauges glued to prestressing strands after application of waterproof coatings.
104
a second tensioning. For example, strand1 gained a prestress of roughly 40MPa (6ksi) from 1325MPa (192ksi)
at the end of the first tensioning phase to about 1365MPa
(198ksi) at the end of the second tensioning phase.
Figure10 shows the history of the tensile stress measured
during the hardening phase up to prestress transfer of test3.
Concrete deformation
Two strain gauges embedded in the concrete close to
strand1 made it possible to monitor the evolution of deformation in the concrete at sections1 and 3 (Fig.11).
During the first phase (about 2hours) a rather limited
shortening occurred, followed by a longer phase of elongation, resulting from shrinkage and thermal effects. It is
possible to observe a different behavior between the strain
gauge placed at midspan (section1) and that placed close
to the anchoring head (section3). In the first case the elongation increased for the first 9hours and then remained
almost constant. The elongation measured by the second
strain gauge started to slowly decrease after 5hours. After-
Figure 7. Anchoring heads and load cells mounted on prestressing strands1 and 6.
ward, the release of the strands produced an abrupt shortening due to elastic deformation of the concrete on transfer
of prestress. As expected, the shortening was greater at
section3 due to the smaller bending moment produced by
the self-weight of the element.
For longer periods, the effect on concrete deformation of the
daily temperature variation was superimposed on the effects
of creep and shrinkage; the combined effect produced a
gradual but continuous increase of the deformation.
After the removal of the upper formwork, it was also possible to install the electrical-resistance surface-bonded strain
gauges on the extrados of the concrete surface. Figure11
shows the deformation measured by the uppermost strain
gauge (channel19 of Fig.5) and confirms that the section
is fully in compression at prestress transfer.
Camber monitoring
Some camber is always desirable at the serviceability limit
state in slender members such as these. Camber can be easily measured in the factory and can also be used to check
105
Calibration of design
parameters
The adjustment of some nominal parameters assumed in the
design phase, such as the factors that influence the evaluation of the prestress loss in the short- and long term and those
involved in the assessment of camber growth, was conducted,
taking into account the experimental results. These parameters are treated separately in the following sections.
Prestress loss
Immediate losses In the case of prestressing strands
106
tensioned individually between the abutments interconnected by the casting bed, the elastic deformations of the whole
pretensioning system produced a prestress loss that cannot
be evaluated with sufficient precision. The experimental
measurements provided the data to evaluate this prestress
loss. In fact, the prestress loss of the first tensioned strand
caused by the elastic deformation of the casting bed produced by the tensioning of the remaining strands was measured by load cells and electrical-resistance surface-bonded
strain gauges. Table4 reports the values of these losses.
After the tensioning of a number n of strands, each having nominal area Ai, with initial prestressing tension pi,
Eq.(1) can estimate the final tension of the first strand (assuming no load eccentricity), similar to the prestress loss
produced by elastic shortening in posttensioned beams for
the sequential jacking steps.
where
(1)
Figure 10. Test3: tensile stress in strands as measured in the first 20hours by load cells (top and middle); and magnification of stress-time curves measured in first
hour after tensioning by electrical-resistance surface-bonded strain gauges (bottom). Note: 1MPa = 0.145ksi.
PCI Journal | J a n u a r y Fe b r u a r y 2015
107
The experimental findings allowed the evaluation of the summation in the right-hand-side member of Eq.(1), thus permitting the evaluation of the average prestress loss of Eq.(2).
In tests1, 2, and 3, the average prestress losses were equal
to 29.5, 31.1, and 25.3MPa (4.3, 4.5, and 3.7ksi), respectively, close to 2% of the initial prestress. This loss can be
introduced directly in the calculations or can be significantly reduced by a second tensioning of the strands as
done, for example, in test3, where about 40MPa (5.8ksi)
was recovered in strand1 (Fig.9).
By observing the force variations measured by load cells
and electrical-resistance surface-bonded strain gauges
glued to the strands, it was possible to quantify the prestress loss due to wedge draw-in at the fixed anchorage.
The two measurements were in perfect agreement. Table5
shows the measured values of these losses. In particular,
although new wedges and new cylinders were used during the tests, the following different average losses were
observed for the 0.5 and 0.6in (13and 15mm). diameter
strands fwed,0.5 and fwed,0.6:
fwed,0.5 = 40.3MPa (5.84ksi)
fwed,0.6 = 24.5MPa (3.55ksi)
The prestress losses for the relaxation of the strands were
quantified following EuroCode215 for low-relaxation
strands (Class2):
Figure 11. Test2: short-term (top) and long-term (bottom) concrete deformation as a function of time (hours and days, respectively).
where
(2)
Table 4. Experimental prestress loss due to elastic deformation of casting bed and abutments used for pretensioning strands
Pretension strand
pi, MPa
Strand number
Strand area,
mm2
Ai, mm2
Prestress loss,
MPa
T1
1400
139
12
99
64.4
T2
1500
139
14
99
66.9
T3
1450
139
10
139
56.2
Element
Note: Ai = nominal area of ith strand; n = number of strands; pi = initial prestressing tension. 1mm = 0.0394in.; 1MPa = 0.145ksi.
108
According to ACI435R, the prestress losses for the relaxation of the strands can also be evaluated as follows:
where
t = time from initial tensioning
fpy = yielding tensile strength of prestressing steel
These equations refer to the losses that would occur at
20C (68F). To take into account actual test conditions,
where the hydration reaction of the cement produced a
temperature increase in the strands, an equivalent time teq
was calculated on the basis of the following equation15 with
temperature expressed in C:
where
teq = equivalent time for temperatures above 20C (68F)
Tmax = maximum temperature
T(ti) = constant temperature occurred for a duration ti
ti = duration of the ith constant temperature T(ti)
Table6 shows the theoretical values of the prestress losses
due to steel relaxation.
Prestress losses can also take place due to thermal variations in the steel due to heat of hydration. EuroCode2
provides the following simplified formula for steam curing:
Ntemp = 0.5ApEpc(Tmax T0)
where
Strand
number
Prestress loss,
MPa
T1
139
29.4
T2
139
21.8
Ap
Ep
T2
99
40.3
T2
99
37.5
T0
= ambient temperature
T2
99
43.5
T3
139
25.1
T3
139
21.9
Although in this case no steam curing was used, significant temperature variations were recorded during concrete
109
where
where
cs = cd + ca
where
cd(t) = ds(t,ts)khcd,0
= creep coefficient
ts
kh
110
ca(t) = as(t)ca()
where
KCR = coefficient equal to 2.0 for pretensioned members
Ec = elastic modulus of concrete
fcs = stress in concrete at centroid of reinforcement immediately after transfer
The theoretical values of the deflection due to the selfweight sw and to the prestressing force with unbonded
tendons pr were also calculated using Eq.(5) and (6).
Ep
p ,c + s + r =
( t , t0 ) c ,Qp + cs E p + 0.8 pr
Ecm
E p Ap
Ac 2
zcp 1 + 0.8 ( t , t0 )
1+
1 +
Ecm Ac
Ic
(3)
(5)
where
where
c,Qp
Ecm
pr
= absolute value of variation of stress in tendons
due to relaxation of prestressing steel
Ac
Ic
zcp
+
x
A
e
p
,
i
pg
,
i
,
,
fin
dt
i
Ecj I i =1
2l
2
8 2
2
2
2
2
pr
x
l
l xin , dt ,i x fin , dt ,i
n
+ x fin , dt ,i + in , dt ,i
=
Ap,i e pg ,i 8 2
Ecj I i =1
2
l
2
where
pr = prestressing tension
Ap,i = area of ith strand
epg,i = eccentricity of ith strand
(4)
An indication of the soundness of the evaluation of the prestressing losses following prestress transfer can be obtained
The permanent deflection due to creep caused by the selfweight, which was the only sustained load acting on the
wing-shaped element during the experimental tests, has
111
pi, MPa
Tmax, C
Tmed, C
teq, hours
T2
1500
56
43
T3
1450
37
26
Element
ACI435R
1286
38.9
26.9
59
18.5
13.1
Note: teq = equivalent time; Tmax = maximum temperature; Tmed = mean temperature; pi = initial prestressing tension. 1MPa = 0.145ksi;
C = 5/9(F 32).
T2
26
26.5
T3
22
22.4
Test
The theoretical values obtained by Eq.(5) and (6) overestimated both displacements: 38.8 and 45.6mm (1.53 and
1.79in.), at release and after 12days, or +11% in both
cases. Camber growth was measured on 10elements with
different lengths and prestressing forces (Table11) at
transfer and at 14days.
Strand area,
mm2
T1
139
82.7
T2
139
90.0
T3
139
113.0
Element
Prestress
loss, MPa
Strand 0.6in.
Summer
244.5
228.7
Winter
229.0
213.2
where
Figure14 shows the debonding and transfer lengths. Because
Table 10. Experimental total immediate prestress loss
Element
Strand number
, MPa
T2
1500
1260
240
T3
1450
1216
234
T3
1450
1206
244
Ap,i
i th strand
x in,deb,i x in,tr,i
x in,dt,i
x fin,tr,i
x fin,deb,i
x fin,dt,i
Figure 14. Debonding length and transfer length. Note: Ap,i = area of ith strand; pg,i = eccentricity of ith strand; xfin,deb,i = abscissa of ith strand after final debonding;
xfin,dt,i = abscissa of ith strand after final debonding and transfer length; xfin,tr,i = final transfer length of ith strand; xin,deb,i = abscissa of ith strand after initial debonding;
xin,dt,i = abscissa of ith strand after initial debonding and transfer length; xin,tr,i = initial transfer length of ith strand.
Conclusion
In this research project, an experimental investigation and
a number of theoretical analyses were conducted to gain
firsthand information on the actual prestress losses and
camber growth in the first weeks following casting of prestressed, pretensioned wing-shaped concrete members.
The results of the analysis provided the following information:
Table 11. Length, prestressing strands, initial prestressing, concrete strength at release, camber at release, and camber at 14days
Length, m
Strands
pi, MPa
fcj, MPa
rel, mm
14, mm
M1
17.8
1 0.6in. + 12 0.5in.
1500
45.1
22.1
35.1
M2
17.8
1 0.6in. + 12 0.5in.
1500
45.1
22.1
32.0
M3
17.8
1 0.6in. + 12 0.5in.
1500
46.4
25.9
32.0
M4
17.8
1 0.6in. + 12 0.5in.
1500
46.4
25.9
32.0
M5
17.8
1 0.6in. + 12 0.5in.
1500
45.6
26.9
32.0
M6
17.8
1 0.6in. + 12 0.5in.
1500
45.6
29.0
34.0
M7
17.8
1 0.6in. + 12 0.5in.
1500
50.7
22.1
35.1
M8
17.8
1 0.6in. + 12 0.5in.
1500
50.7
22.9
33.0
M9
17.8
1 0.6in. + 12 0.5in.
1500
47.7
22.1
32.0
M10
11.9
1 0.6in. + 12 0.5in.
1500
46.8
17.0
21.1
Element
Note: fcj = compressive strength of concrete at release; rel = camber due to prestress and prestress loss at release; 14 = camber at 14days;
pi = initial prestressing tension. 1mm = 0.0394in.; 1m = 3.28ft; 1MPa = 0.145ksi.
PCI Journal | J a n u a r y Fe b r u a r y 2015
113
Appropriate corrective actions are proposed as well to reduce as much as possible the prestress loss during concrete
casting, curing, and hardening, and suitable values for the
design parameters have been calibrated to correctly predict
prestress losses and camber growth.
Acknowledgments
The Authors are grateful to Manini Prefabbricati S.p.A.
(S. Maria degli Angeli, Perugia, Italy) and in particular
to Paolo Manni and Graziano Baldograni for the valuable
support in organizing the experimental phase of this work.
References
1. Stallings, J. M., R. W. Barnes, and S. Eskildsen.
2003. Camber and Prestress Losses in Alabama HPC
Bridge Girders. PCI Journal 48 (5): 216.
2. Al-Omaishi, N., M. K. Tadros, and S. J. Seguirant.
114
fpu
fpy
h0
Ic
Notation
k h
Ac
KCR
Afw
ldeb
= debonding length
A i
Ap
= number of strands
Ap,i
RH
= relative humidity
c1
c2
t0
epg,i
teq
Ec
Eci
ts
T0
= ambient temperature
Ecj
Tmax
= maximum temperature
Ecm
Tmed
= mean temperature
Ep
Eps
T(ti)
fc
fck
fcj
fcm
fcs
fcsd
xfin,tr,i
115
xin,tr,i
cd
= drying shrinkage
zcp
cd,0
cs
as
SH
ds
= time-dependent coefficient for drying shrinkage
14
pr
1000
rel
1,fin
sw
pr
c,Qp
fpCR
pi
fpR
pr
= prestressing tension
fpSH
= creep coefficient
= temperature increase
116
pr
ca
= autogenous shrinkage
Abstract
Prestressed concrete wing-shaped members are frequently used in the construction of long-span roofs in
precast concrete buildings. Roofs spanning more than
30m (100ft) are built by assembling a number of these
thin-walled members. To optimize their design and take
advantage of their potential load-carrying capacity, the
transfer of large forces from the pretensioned strands to
the concrete is critical. Information on the evolution of
these forces and of the ensuing deformations is necessary, not only in the long run, but also immediately after
concrete casting and during the first few weeks.
The Department of Civil and Environmental Engineering of the University of Perugia in Italy and a major
prefabrication firm of central Italy have completed an
experimental program on pretensioned wing-shaped
members to investigate the evolution of prestressing
stresses and of camber during the different stages of
concrete hardening.
The result allowed the careful evaluation of the prestress losses that occur in the first three weeks during
concrete placement and curing to emphasize the influence of the temperature history on the development of
prestress losses and to calibrate suitable parameters for
the prediction of camber growth.
Numerical comparisons based on Eurocode2 are also
performed to check the reliability of the numerical
procedure adopted by the authors and to ascertain
whether using self-consolidating concrete (as in the
manufacture of the specimens tested in this project)
makes any sizeable difference with respect to the predictions based on Eurocode2, which refers to ordinary
concrete.
Keywords
Camber, prestress loss, self-consolidating concrete,
temperature, wing-shaped members.
Review policy
This paper was reviewed in accordance with the
Precast/Prestressed Concrete Institutes peer-review
process.
Reader comments
Please address and reader comments to journal@pci
.org or Precast/Prestressed Concrete Institute, c/o PCI
Journal, 200 W. Adams St., Suite 2100, Chicago, IL
60606. J
117