Beruflich Dokumente
Kultur Dokumente
Atlantic Yards
Date
6/16/2014
Location
B2
Weekday
Monday
Client
ESD
Report #
338
Contract #
6717
Weather
Sunny, Warm
Project
Project #
STV Representative:
2114659
Bill King
Temp. L/H
Wind Speed
Work hours
8:30-5:00
Precip
64/82
Slight (14 mph gusting to 19 mph)
0"
140
930
132
0.151
1.1
Information previously requested: From FCR, week of 6/13, Skanska's environmental consultant's 2nd report re mold including
potential of it in insulation which would then have to be removed, FCR will send copy to STV once they see the report - they are still waiting.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
On 5/1/14
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 -
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; utility lines not lining up; utility lines not installed in mods either on purpose or for another
reason.
Previous Information received: Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close,
less than 1+1/8" from gasket plate to adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel cau ks the 'crucifix',
where 4 mods meet, to seal any openings.
FCR stated on 6/3/14 that mods installed starting (the week of) 6/9 will be floors 6-9.
Final mold report due from Skanska's environmental consultant on 6/6. FCR still waiting at end of week ending 6/13.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
1 of 2
Previous observations: Front faade is 33-35' from the ped walkway. Flatbush faade is 12' from the edge of the sidewalk shed. Height
exceeds 2 X the distance between the building and the ped crosswalk at Flatbush across Dean.
Manpower on Site
25-30
Navillus
Stearns
10
J SuporTrucking
MEP trades
0-5
Other
5-10
William King
6/16/2014
2 of 2
Date
Atlantic Yards
Date
6/17/2014
Location
B2
Weekday
Tuesday
Client
ESD
Report #
339
Contract #
6717
Weather
Sunny, Warm
Project
Project #
STV Representative:
2114659
Bill King
Temp. L/H
Wind Speed
Work hours
8:30-5:00
Precip
71/88
Slight (15 mph gusting to 19 mph)
0"
147
930
133
0.158
1.1
Information previously requested: From FCR, week of 6/13, Skanska's environmental consultant's 2nd report re mold including
potential of it in insulation which would then have to be removed, FCR will send copy to STV once they see the report - they are still waiting.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
On 5/1/14
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; utility lines not lining up; utility lines not installed in mods either on purpose or for another
reason.
Previous Information received: Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close,
less than 1+1/8" from gasket plate to adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel cau ks the 'crucifix',
where 4 mods meet, to seal any openings.
FCR stated on 6/3/14 that mods installed starting (the week of) 6/9 will be floors 6-9.
Final mold report due from Skanska's environmental consultant on 6/6. FCR still waiting at end of week ending 6/13.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
At Navy Yard Wed., 10/16, FCR stated that first mods would arrive on site in late December/early January and that there would be a backlog
of 30-40 (1-2 floors worth) to 80 (3 floors worth) mods completed at that time which it was felt would be sufficient for production to keep
ahead of erection so there would be no downtime during mod erection at the B2 site.
1 of 2
Manpower on Site
25-30
Navillus
Stearns
J SuporTrucking
MEP trades
0-5
Other
5-10
William King
6/17/2014
2 of 2
Date
Atlantic Yards
Date
6/18/2014
Wednesday
Location
B2
Weekday
Client
ESD
Report #
340
Contract #
6717
Weather
Project #
STV Representative:
2114659
Bill King
Temp. L/H
Wind Speed
Work hours
8:30-4:30
Precip
79/88
19 mph gusting to 30 mph
0"
153
930
134
0.165
1.1
Information previously requested: From FCR, week of 6/13, Skanska's environmental consultant's 2nd report re mold including
potential of it in insulation which would then have to be removed, FCR will send copy to STV once they see the report - they are still waiting.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
On 5/1/14
.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 -
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; utility lines not lining up; utility lines not installed in mods either on purpose or for another
reason.
Previous Information received: Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close,
less than 1+1/8" from gasket plate to adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel cau ks the 'crucifix',
where 4 mods meet, to seal any openings.
FCR stated on 6/3/14 that mods installed starting (the week of) 6/9 will be floors 6-9.
Final mold report due from Skanska's environmental consultant on 6/6. FCR still waiting at end of week ending 6/13.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
Paper documenting DOB's approval (signed 2/2/14) of no sidewalk shed on Dean received on 3/21/14.
1 of 2
Previous observations: Front faade is now less than 33-35' from the ped wa kway due to the 6th floor Dean St. transfer beam facade
protruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush faade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Manpower on Site
25-30
Navillus
Stearns
J SuporTrucking
MEP trades
0-5
Other
5-10
William King
6/18/2014
2 of 2
Date
Atlantic Yards
Date
6/19/2014
Thursday
Location
B2
Weekday
Client
ESD
Report #
Contract #
6717
Weather
341
High Overcast, Cooler, Nice
Project #
STV Representative:
2114659
Bill King
Temp. L/H
Wind Speed
Work hours
8:30-5:00
Precip
69/80
Slight (11 mph)
0"
159
930
135
0.171
1.2
Additional New Observations: Mods going in smoothly, as viewed from rooftop. Asked Skanska whether MG McGrath had any
problems with gaskets as installed on any of the 6th floor mods. Skanska responded there was one mod of concern. Took measurements to
send to the designers/plant to see if something is off. Something has been off on the line of mods (western section).
Pail placed under leak in bedroom of 1 bdrm unit on 3rd floor 7/8 full and still there. Surrounding floor still wet. Shop vac present but
perhaps not yet used. Mentioned this in email to FCR.
New Information received: Brace frame will be for 2 days after completion of 7th floor which will be either a week from today or a week
from Friday - so that brace frame work would start either Fri., 6/27 or Mon., 6/30.
Read Skanska ec's report no. 2, sent by FCR at end of day on 6/17.
New Information requested: In email response to FCR's SS, who sent the 2nd report by Skanska's environmental consultant, asked
whether any type of air monitoring can take place to measure potentially high mold spore counts in a unit where any mold is not visible, i.e in
upper or inner layer of wal board in ceiling/wall. Cited leak day on 6/13, after e.c's most recent site visit, when subsequent leak damage is
not that evident.
Information previously requested: On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether
mold may be suspected. No response to date.
On 5/1/14
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; utility lines not lining up; utility lines not installed in mods either on purpose or for another
reason.
Previous Information received: Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close,
less than 1+1/8" from gasket plate to adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel cau ks the 'crucifix',
where 4 mods meet, to seal any openings.
FCR stated on 6/3/14 that mods installed starting (the week of) 6/9 will be floors 6-9.
Final mold report due from Skanska's environmental consultant on 6/6. FCR still waiting at end of week ending 6/13.
4/8: Jury is still out on gaskets which may be under increasing stress under weight of additional floors.
1 of 2
Previous observations: Front faade is now less than 33-35' from the ped wa kway due to the 6th floor Dean St. transfer beam facade
protruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush faade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Manpower on Site
25-30
Navillus
Stearns
J SuporTrucking
MEP trades
0-5
Other
5-10
William King
6/19/2014
2 of 2
Date
Atlantic Yards
Date
6/20/2014
Location
B2
Weekday
Friday
Client
ESD
Report #
342
Contract #
6717
Weather
Project
Project #
STV Representative:
2114659
Bill King
63/82
Temp. L/H
Wind Speed Slight winds picking up a little in p.m.
Work hours
7:45-4:30
Precip
0"
165
930
136
0.177
1.2
Additional New Observations: Mods going in smoothly, as viewed from rooftop and at street level. Will ask Skanska and MG McGrath
what the concern was with the one previously installed 6th floor mod that seemed to be of concern on 6/19.
Pail that was placed under leak in bedroom of 1 bdrm unit on 3rd floor that was 7/8 full was finally removed. Surrounding floor still damp.
Shop vac present.
Noticed some mold on drywall in a closet of the large studio at the northwest corner of the building on either the 4th or 5th floor.
Wa ked project with new Hirani safety inspector Dino Colalillo
New Information received: Skanska's primary safety concern is making sure ironworkers are properly tied off on the roof when they
should be.
Information previously requested: Read Skanska ec's report no. 2, sent by FCR at end of day on 6/17. In 6/19 email response to
FCR's SS, who sent the 2nd report by Skanska's environmental consultant, asked whether any type of air monitoring can take place to
measure potentially high mold spore counts in a unit where any mold is not visible, i.e in upper or inner layer of wallboard in ceiling/wall.
Cited leak day on 6/13, after e.c's most recent site visit, when subsequent leak damage is not that evident.
On 6/6/14 sent pictures of installed/discolored dry wall cross sections to Skanska to ask whether mold may be suspected. No response to
date.
On 5/1/14
t.
2/27/14 - Copies of sketches or drawings of roof fixes (of John Dolan, Skanska). No response.
1/20/14 -
Information to be requested: More information on quality issues noticed with the mods - exterior: torn gaskets, dents and scratches to
the faade; interior: lack of completeness of mods; utility lines not lining up; utility lines not installed in mods either on purpose or for another
reason.
Previous Information received: Brace frame will be for 2 days after completion of 7th floor which will be either a week from today or a
week from Friday - so that brace frame work would start either Fri., 6/27 or Mon., 6/30.
Allowable gasket tolerances: up to 1/2" out of allignment - otherwise warranty is void. Also, if too close, less than 1+1/8" from gasket plate to
adjoining gasket plate or more than 2+1/8" between plates then warranty void. Joel caulks the 'crucifix', where 4 mods meet, to seal any
openings.
FCR stated on 6/3/14 that mods installed starting (the week of) 6/9 will be floors 6-9.
1 of 2
Previous observations: Front faade is now less than 33-35' from the ped wa kway due to the 6th floor Dean St. transfer beam facade
protruding 1-2' closer to the street than the 1st-5th floor facade. Flatbush faade is 12' from the edge of the sidewalk shed. Height exceeds
2 X the distance between the building and the ped crosswa k at Flatbush across Dean.
Contract changes, claims, deficiencies, RFI's, RFP's reported to STV by FCR: None
Manpower on Site
25-30
Navillus
Stearns
J SuporTrucking
MEP trades
0-5
Other
5-10
William King
6/20/2014
2 of 2
Date