Beruflich Dokumente
Kultur Dokumente
% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Fire Pump Room GI installation 100% 100% 100% 100% 100% 100% DOOR NOT FIXED
Fire Alam Services
Cable Installation 100% 100% 100% 100% 100% 100%
Page 1 of 15
% Completed
Level Area Description Elv Services - BMS Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09
Installation of Control 0% 0% 0% 0% 0% 0%
Wire/Cable Installation 100% 100% 100% 100% 100% 100% To be done by ADDC
HV Panel installations 0% 0% 0% 0% 0% 0%
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
TYPE OF EQUIPEMENTS
& CABLES 07 Nos of hv switch gear panels
Panel installations 0% 0% 0% 0% 0% 0%
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
TYPE OF EQUIPEMENTS
& CABLES Termination by contractor
Panel installations 0% 0% 0% 0% 0% 0%
Telephone Room Electrical Lighting GI installation 100% 100% 100% 100% 100% 100% DOOR NOT FIXED
Page 2 of 15
TYPE OF EQUIPEMENTS
& CABLES
Telephone Room DOOR NOT FIXED
% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09
Termination by contractor
TYPE OF EQUIPEMENTS
& CABLES
Termination by BOND
Panel installations 0% 0% 0% 0% 0% 0%
Battery Room DOOR NOT FIXED
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
TYPE OF EQUIPEMENTS
& CABLES BATTERIES
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator
Electrical Power
Termination by contractor 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
Terminaton by contractor
Terminaton by contractor
Terminaton by contractor
Terminaton by BOND
All XLPE/SWA/CABLES
Electrical Power Cable Installation 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Transformer installations 0% 0% 0% 0% 0% 0%
Page 3 of 15
Electrical Power
% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
TYPE OF EQUIPEMENTS
& CABLES 02 NOS OF 2000KVA TRANSFORMERS 0% 0%
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Electrical Power
Cable Installation 0% 0% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Generator Room Wire Installation 100% 100% 100% 100% 100% 100% DOOR NOT FIXED
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
TYPE OF EQUIPEMENTS
& CABLES
4X4C 240Ssqmm XLPE/SWA/PVC 100% 100% 100% 100% 100% 100%
CABLES
BMS installations 0% 0% 0% 0% 0% 0%
BMS Trunking & Tray installation 50% 60% 60% 60% 60%
Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
BMS Room DOOR NOT FIXED; RAISED FLOOR NOT
Installation of earth rod, earth pit and CONSTRUCTED
earth cabling
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Prayer Room & Toilets Electrical Lighting GI installation 100% 100% 100% 100% 100% 100% DOORS NOT FIXED handed over to DEPA
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
Level 05
Cable Installation 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Electrical Power
Installation of SMDB-GE-02, SMDB-EPA-
O5-03 100% 100% 100% 100% 100% 100%
Termination by contractor
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
4C 185 sqmm,25SQsqmm,16sqmm
CABLES 100% 100% 100% 100% 100% 100%
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Electrical Power
Wire/Cable Installation 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
Installation of DB-L5-02 0% 0% 0% 0% 0% 0%
TYPE OF EQUIPEMENTS
& CABLES
Terminaton by contractor
Terminaton by Bond
Installation of Panel 0% 0% 0% 0% 0% 0%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Termination by contractor
TYPE OF EQUIPEMENTS
& CABLES
Termination by Bond
4c 240sqmm,4c 16sqmmXLPE/SWA/PVC
CABLES ande 1C 95sqmm,10sqmm PVC
EARTH CABLES
Page 6 of 15
% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
TYPE OF EQUIPEMENTS
& CABLES 2X4C 150sqmm,4c 16sqmm
XLPE/SWA/PVC CABLES and 1c 150sqmm 100% 100% 100% 100% 100% 100%
pvc earth cables
Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Panel Installation 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
Installation of MCC EPA PUMP CONTROL Not race day Not race day Not race day Not race day Not race day Not race day
PANELS scope scope scope scope scope scope
Termination by contractor
TYPE OF EQUIPEMENTS
& CABLES
Termination by Bond
Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Page 7 of 15
Electrical Lighting % Completed
ROOM LOCKED BY TAIYO; AFFECTING THE
Level Area Description
ETFE Room 1 Activity Description Remarks
INSTALLATION OF SMDB-ETFE
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
TYPE OF EQUIPEMENTS
& CABLES Termination by contractor
4C 95sqmm,4c 25sqmm XLPE/SWA/PVC
CABLES and 1c 50sqmm,1c 16sqmm 100% 100% 100% 100% 100% 100%
EARTH CABLES
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
TYPE OF EQUIPEMENTS
& CABLES 4C 25sqmm XLPE/SWA/PVC CABLE and 1c
16sqmm earth cable 25% 25% 75% 100% 100% 100%
Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
CCTV Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Cable Installation 0% 0% 0% 0% 0% 0%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Page 8 of 15
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Fire Alam Services GI installation N/A N/A N/A N/A N/A N/A
TYPE OF EQUIPEMENTS
& CABLES Installation of SMDB-EPA-10 100% 100% 100% 100% 100% 100%
Termination by contractor
Panel Installation 0% 0% 0% 0% 0% 0%
Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Wire Installation 0% 0% 0% 0% 0% 0%
Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Level 20 Electrical CIVIL WORKS IN PROGRESS; RAISER TO BE
Room CLEARED BY CIVIL CONTRACTOR;DOOR NOT FIXED
Fire Alam Services GI installation N/A N/A N/A N/A N/A N/A
Cable Installation 0% 0% 0% 0% 0% 0%
Installation of DB-L20-02
Termination by contractor
Termination by Bond
TYPE OF EQUIPEMENTS
& CABLES
4C 25 sqmm XLPE/SWA/PVC 25% 50% 50% 50%
GI installation 0% 0% 0% 0% 0% 0%
Installation of Lights 0% 0% 0% 0% 0% 0%
testing 0% 0% 0% 0% 0% 0%
focussing of Lights 0% 0% 0% 0% 0% 0%
programming 0% 0% 0% 0% 0% 0%
control equipment 0% 0% 0% 0% 0% 0%
GI installation 0% 0% 0% 0% 0% 0%
Electrical Lighting
Level 30 roof control room
Installation of Tray & Trunking 0% 0% 0% 0% 0% 0%
Cable Installation 0% 0% 0% 0% 0% 0%
testing 0% 0% 0% 0% 0% 0%
Installation of racks 0% 0% 0% 0% 0% 0%
ROOF PVC conduit installation 75% 75% 75% 75% 75% 75%
Page 9 of 15
% Completed
Level Area Description Activity Description Remarks
ROOF 26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09
GI installation 0% 0% 0% 0% 0% 0%
Installation of Lights 0% 0% 0% 0% 0% 0%
testing 0% 0% 0% 0% 0% 0%
focussing of Lights 0% 0% 0% 0% 0% 0%
programming 0% 0% 0% 0% 0% 0%
GI installation 0% 0% 0% 0% 0% 0%
Cable Installation 0% 0% 0% 0% 0% 0%
Installation of Lights 0% 0% 0% 0% 0% 0%
testing 0% 0% 0% 0% 0% 0%
focussing of Lights 0% 0% 0% 0% 0% 0%
programming 0% 0% 0% 0% 0% 0%
Page 10 of 15
ISSUES AFFECTING MEP PROGRESS
STATUS AS ON : 24-Sep-2009
ISSUES AFFECTING MEP SYSTEM
DU Room
Telephone Room
Battery Room
1. Interbeton installing C
channel on Trench grating
2. LV
LV Room room door size to be
increased - Affecting
installation of MDB
Transformer Room
Page 11 of 15
ISSUES AFFECTING MEP SYSTEM
Generator Room
BMS Room
FCC Room
Electrical Room 1
Electrical Room 2
Electrical Room 4
Page 12 of 15
ISSUES AFFECTING MEP SYSTEM
ETS ROOM
ETFE Room 2
Service Coridor
Level 20 Electrical Room Depa works not started Depa works not started
Page 13 of 15
ISSUES AFFECTING MEP SYSTEM
Page 14 of 15
C00000Data Date: 14-Sep-09
TARGET PROGRAMME TO COMPLETION' (Matrix Format) to meet Race Day requirement @ Welcome Pavillion
Clearance by others (as per HBO) HBO Schedule
Sl No Level Area Description Activity Description Scope 1st Fix 2st Fix Final Fix 1st Fix 2st Fix Final Fix Remarks Internal Delays/Points to be noted
Finish Finish Finish Start Finish Start Finish Start Finish
1 Level 05 Water Tank Water Tank installation Hitachi complete complete complete complete complete complete complete in progress 22-Sep-09 Clearance recived only on 10-Sep-09
Water Pump room Water Pump installation Hitachi complete complete complete complete complete complete complete complete complete Clearance recived only on 09-Sep-09
Electrical Lighting BTE complete complete complete complete complete complete complete in progress 25-Sep-09 Awaiting for materials. Required a.s.p.
Fire Alam Services BTE complete complete complete complete complete complete complete in progress 25-Sep-09
Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09 Floor Screed not done
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09 Floor Screed not done Awaiting for materials. Required a.s.p.
Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09 Floor Screed not done
HV Room HV Panel installations BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
DU Room Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Telephone Room Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Containment BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Cable Pulling BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Awaiting for materials. Required a.s.p.
Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Exaust fan Hitachi complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 29-Sep-09 Final clearance partly completed
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 29-Sep-09 Final clearance partly completed
Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 29-Sep-09 Final clearance partly completed
ETS Room Panel installations BTE - - 22-Sep-09 - - - - 4-Oct-09 16-Oct-09 No access available
Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 No access available
Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 No access available
Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 No access available
BMS Room Fixtures & fittings (Toilet) Hitachi complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 Sanitary fittings are by others
BMS installations BTE - - 22-Sep-09 - - - - 1-Oct-09 10-Oct-09 Raised Floor not yet done
Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09 Raised Floor not yet done
Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09 Raised Floor not yet done
Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09 Raised Floor not yet done
Prayer Room & Toilets Fixtures & fittings (Toilet) Hitachi complete complete 18-Sep-09 complete complete complete complete 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09
Electrical Power BTE complete complete 18-Sep-09 complete complete in progress 17-Sep-09 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09
Electrical Lighting BTE complete complete 18-Sep-09 complete complete in progress 17-Sep-09 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09
Fire Alam Services BTE complete complete 18-Sep-09 complete complete in progress 17-Sep-09 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09
Fixtures & fittings BTE - - 18-Sep-09 - - - - 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09
Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09
Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09
Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09
Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete in progress 27-Sep-09
Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete in progress 27-Sep-09
Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete in progress 27-Sep-09
Service Corridoor Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09
Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09
Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09
External Water supply Hitachi - 15-Sep-09 20-Sep-09 - - in progress 20-Sep-09 21-Sep-09 27-Sep-09 Part clearance received.
(WP to Carpark C1&C2) Fire Fighting Hitachi - 15-Sep-09 20-Sep-09 - - in progress 20-Sep-09 21-Sep-09 27-Sep-09 Part clearance received.
Electrical Power BTE complete 18-Sep-09 26-Sep-09 complete complete 19-Sep-09 24-Sep-09 27-Sep-09 7-Oct-09
Electrical Lighting (WB) BTE complete 18-Sep-09 26-Sep-09 complete complete 19-Sep-09 24-Sep-09 27-Sep-09 7-Oct-09
Electrical Power BTE complete 25-Sep-09 10-Oct-09 complete complete in progress 5-Oct-09 11-Oct-09 23-Oct-09
Electrical Lighting (WB) BTE complete 25-Sep-09 10-Oct-09 complete complete in progress 5-Oct-09 11-Oct-09 23-Oct-09