WELCOME PAVILION DAILY REPORT FOR RACE DAY

% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Instllation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Switch & Lights 0% 0% 0% 0% 0% 0%

Water Pump room DOOR NOT FIXED

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Fire Alam Services
Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Break Glass 0% 0% 0% 0% 0% 0%

Installation of Smoke Detector 0% 0% 0% 0% 0% 0%

Water pump control panel,

4c 16sqmm XLPE/SWA/PVC CABLE 100% 100% 100% 100% 100% 100%


TYPE OF EQUIPEMENTS INSTALLATION
& CABLES 1C 16sqmm PVC(G/Y) CABLE
INSTALLATION 100% 100% 100% 100% 100% 100%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

GI installation 100% 100% 100% 100% 100% 100%


GRP Water tank room Electrical Lighting DOOR NOT FIXED
Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

GI installation 100% 100% 100% 100% 100% 100%


Fire Alam Services
Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Smoke Detector 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Pump Room GI installation 100% 100% 100% 100% 100% 100% DOOR NOT FIXED
Fire Alam Services
Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Break Glass 0% 0% 0% 0% 0% 0%

Installation of Smoke Detector 0% 0% 0% 0% 0% 0%

Installation of Trunking 100% 100% 100% 100% 100% 100%


Elv Services - BMS
Cable Laying 100% 100% 100% 100% 100% 100%

Page 1 of 15
% Completed
Level Area Description Elv Services - BMS Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

Installation of Control 0% 0% 0% 0% 0% 0%

Fire pumps control panels-06nos

Diesel engine panels--03nos


TYPE OF EQUIPEMENTS
& CABLES
4c 185sqmm,4c 150sqmm,4c 35sqmm 100% 100% 100% 100% 100% 100%

4C 10 sqmm XLPE/SWA/PVC CABLES


INSTALLATIONS 100% 100% 100% 100% 100% 100%

1C 95 sqmm,1c 70sqmm,1c 16sqmm,1c


10sqmm PVC(G/Y) CABLES 100% 100% 100% 100% 100% 100%

DOOR NOT FIXED

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Power GI installation 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100% To be done by ADDC

HV Panel installations 0% 0% 0% 0% 0% 0%

Installation of earth rod, earth pit and


earth cabling 25% 25%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%


HV Room
Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

TYPE OF EQUIPEMENTS
& CABLES 07 Nos of hv switch gear panels

3c 95sqmm HV CABLES,and incoming HV


CABLES

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Panel installations 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%


DU Room DOOR NOT FIXED
Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

Installation of SMDB-DU PANEL 40kw

TYPE OF EQUIPEMENTS
& CABLES Termination by contractor

4C 50sqmm XLPE/SWA/PVC CABLE

1C 25sqmm PVC(G/Y) CABLE

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Panel installations 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Telephone Room Electrical Lighting GI installation 100% 100% 100% 100% 100% 100% DOOR NOT FIXED

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 100% 100% 100% 100% 100% 100%

Page 2 of 15
TYPE OF EQUIPEMENTS
& CABLES
Telephone Room DOOR NOT FIXED

% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

Installation of DB-ETISALAT PANEL 10KW

Termination by contractor
TYPE OF EQUIPEMENTS
& CABLES
Termination by BOND

4c 16sqmm XLPE/SWA/PVC CABLE

1C 16sqmm PVC(G/Y) CABLE

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Panel installations 0% 0% 0% 0% 0% 0%
Battery Room DOOR NOT FIXED

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

TYPE OF EQUIPEMENTS
& CABLES BATTERIES

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Cable Installation 90% 90% 90% 90% 100% 100%

Installation of Socket/Isolator
Electrical Power

LV Panel installations 15% 20% 50% 75% 90% 90%

Installation of DB-SER-01 100% 100% 100% 100% 100% 100%

Termination by contractor 0% 0% 0% 0% 0% 0%

Termination by BOND 100% 100% 100% 100% 100% 100%

Installation of earth rod, earth pit and 35% 35%


earth cabling

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0% IBY INSTALLING C CHANNEL ON THE TRENCH


LV Room GRATING; DOOR
HIEGHT TO BE INCREASED

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

Installation of 02nos MDB 65% 100% 100%

Terminaton by contractor

Installation of 02nos CAPACITOR BANK 100% 100% 100%

Terminaton by contractor

Installation of 01no ATS PANEL 100% 100% 100%

TYPE OF EQUIPEMENTS Terminaton by contractor


& CABLES

Installation of DB-SER-02(not arrived) 0% 0% 0%

Terminaton by contractor

Terminaton by BOND

1C 14no 630sqmm XLPE/AWA/PVCCABLE

All XLPE/SWA/CABLES

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Electrical Power Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Transformer installations 0% 0% 0% 0% 0% 0%

Page 3 of 15
Electrical Power

% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

Installation of earth rod, earth pit and


earth cabling 25% 25%

PVC conduit installation 100% 100% 100% 100% 100% 100%


Transformer Room
Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

TYPE OF EQUIPEMENTS
& CABLES 02 NOS OF 2000KVA TRANSFORMERS 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Electrical Power
Cable Installation 0% 0% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Generator installations 100% 100% 100% 100% 100% 100%

Installation of earth rod, earth pit and


earth cabling 50% 50%

installation of SMDB GE-1 and


transformer acb. 60% 60%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Generator Room Wire Installation 100% 100% 100% 100% 100% 100% DOOR NOT FIXED

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

02 nos of 800kva FG.WILSON


GENERATORS

TYPE OF EQUIPEMENTS
& CABLES
4X4C 240Ssqmm XLPE/SWA/PVC 100% 100% 100% 100% 100% 100%

CABLES

BMS installations 0% 0% 0% 0% 0% 0%

BMS Trunking & Tray installation 50% 60% 60% 60% 60%

Elv Services - BMS BMS Cable installation 0% 0% 0% 0% 0%

External services from Car park 1 (C1)


UPVC Duct installation 0% 0% 50% 75% 75%

External services from Car park 2 (C2)


UPVC Duct installation 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
BMS Room DOOR NOT FIXED; RAISED FLOOR NOT
Installation of earth rod, earth pit and CONSTRUCTED
earth cabling

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

Trunking and cable tray for ELV 50% 50% 50%

Fire Alam Services Page 4 of 15


% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Installation of Tray & Trunking N/A N/A N/A N/A N/A N/A

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Prayer Room & Toilets Electrical Lighting GI installation 100% 100% 100% 100% 100% 100% DOORS NOT FIXED handed over to DEPA

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%
Level 05
Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

Fixtures & fittings

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%


FCC Room DOOR NOT FIXED
Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%
Electrical Power
Installation of SMDB-GE-02, SMDB-EPA-
O5-03 100% 100% 100% 100% 100% 100%

Termination by contractor

Installation of DB-UPS, DB-L5EM1, DB-L5-


05 100% 100% 100% 100% 100% 100%

Termination by contractor 50% 50% 50% 50% 50%

Termination by Bond (DB-L5-EM1) 100% 100% 100% 100% 100% 100%

Installation of earth cable and earthbar 15% 15%

Electrical Room 1 DOOR NOT FIXED

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services


Page 5 of 15
% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

UPS PANEL 50% 75% 75% 75% 75%

4C 185 sqmm,25SQsqmm,16sqmm
CABLES 100% 100% 100% 100% 100% 100%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%
Electrical Power
Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Panel 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Installation of earth cable and earthbar 25% 25%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%


Electrical Room 2 DOOR NOT FIXED
Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

Installation of SMDB-EPA-01 100% 100% 100% 100% 100% 100%

Terminaton by contractor 75% 100 100% 100% 100%

Installation of DB-L5-02 0% 0% 0% 0% 0% 0%
TYPE OF EQUIPEMENTS
& CABLES
Terminaton by contractor

Terminaton by Bond

4C,185sqmm ,4C 16sqmm


XLPE/SWA/PVC CABLES 60% 100% 100% 100% 100% 100%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 65% 65% 65% 65% 65% 65%

Installation of Tray & Trunking 0% 0% 0% 0% 0% 0%


Electrical Power
Wire/Cable Installation 75% 75% 75% 75% 75% 75%

Installation of Panel 0% 0% 0% 0% 0% 0%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Installation of earth cable and earthbar 0% 0%

PVC conduit installation 100% 100% 0% 0% 0% 0%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%


IBY SCAFOLDING OBSTRUCTING MEP PROGRESS;
Electrical Room 3 DOOR NOT FIXED
Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 0% 0% 0% 0% 0% 0%

Cable Installation 80% 80% 80% 80% 80% 80%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

Installation of DB-WATER FEATURE,DB-


L5-06,DB-L5-07

Termination by contractor
TYPE OF EQUIPEMENTS
& CABLES
Termination by Bond

4c 240sqmm,4c 16sqmmXLPE/SWA/PVC
CABLES ande 1C 95sqmm,10sqmm PVC

EARTH CABLES

PVC conduit installation 100% 100% 100% 100% 100% 100%

Page 6 of 15
% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

GI installation 100% 100% 100% 100% 100% 100%

Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of SMDB-EPA-05-04 100% 100% 100% 100% 100% 100%


Electrical Power
Termination by contractor 75% 75% 100% 100% 100% 100%

Installation of DB-L5-03 100% 100% 100% 100% 100% 100%

Termination by contractor 100% 100% 100% 100% 100% 100%

Termination by Bond (DB-L5-03) 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Installation of earth cable and earthbar 25% 25%


Electrical Room 4 DOOR NOT FIXED

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

TYPE OF EQUIPEMENTS
& CABLES 2X4C 150sqmm,4c 16sqmm
XLPE/SWA/PVC CABLES and 1c 150sqmm 100% 100% 100% 100% 100% 100%
pvc earth cables

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Panel Installation 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%

ETS ROOM NO ACCESS; DOOR NOT FIXED


Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

Installation of MCC EPA PUMP CONTROL Not race day Not race day Not race day Not race day Not race day Not race day
PANELS scope scope scope scope scope scope

Termination by contractor
TYPE OF EQUIPEMENTS
& CABLES

Termination by Bond

4C 120sqmm,4c 50sqmm XLPE/SWA/PVC


CABLES and 1c 70sqmm,1c 25sqmm earth Not race day Not race day Not race day Not race day Not race day Not race day
cables scope scope scope scope scope scope

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Panel Installation 100% 100% 100% 100% 100% 100%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%


ETFE Room 1 ROOM LOCKED BY TAIYO; AFFECTING THE
INSTALLATION OF SMDB-ETFE
Wire Installation 100% 100% 100% 100% 100% 100%

Page 7 of 15
Electrical Lighting % Completed
ROOM LOCKED BY TAIYO; AFFECTING THE
Level Area Description
ETFE Room 1 Activity Description Remarks
INSTALLATION OF SMDB-ETFE
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

Installation of SMDB-ETFE 100% 100% 100% 100% 100% 100%

TYPE OF EQUIPEMENTS
& CABLES Termination by contractor
4C 95sqmm,4c 25sqmm XLPE/SWA/PVC
CABLES and 1c 50sqmm,1c 16sqmm 100% 100% 100% 100% 100% 100%
EARTH CABLES

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%


Electrical Power
Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 90% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%


ETFE Room 2 DOOR NOT FIXED
Wire Installation 100% 100% 100% 100% 100% 100%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

TYPE OF EQUIPEMENTS
& CABLES 4C 25sqmm XLPE/SWA/PVC CABLE and 1c
16sqmm earth cable 25% 25% 75% 100% 100% 100%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

Electrical Power Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Wire/Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation 100% 100% 100% 100% 100% 100%

Wire Installation 100% 100% 100% 100% 100% 100%


Service Coridor
Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation 100% 100% 100% 100% 100% 100%

Cable Installation 100% 100% 100% 100% 100% 100%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation 100% 100% 100% 100% 100% 100%

CCTV Installation of Tray & Trunking 100% 100% 100% 100% 100% 100%

Cable Installation 0% 0% 0% 0% 0% 0%

Installation of field devices 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation N/A N/A N/A0 N/A0 N/A0 N/A0

Installation of Tray & Trunking 0% 0% 0% 40% 75% 75%


Electrical Power
Cable Installation 50% 50% 100% 100% 100% 100%

Panel Installation 100% 100% 100% 100% 100% 100%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

Page 8 of 15

CIVIL WORKS IN PROGRESS; RAISER TO BE


% Completed
Level Area Description Activity Description Remarks
26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation N/A N/A N/A N/A N/A N/A


CIVIL WORKS IN PROGRESS; RAISER TO BE
Level 10 Electrical CLEARED BY CIVIL CONTRACTOR;DOOR NOT FIXED
Room Wire Installation 50% 50% 60% 75% 75% 75%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation N/A N/A N/A N/A N/A N/A

Cable Installation 30% 30% 40% 40% 40% 40%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

4c 185Sqmm XLPE/SWA/PVC & 1C 95


sqmm G/Y PVC 100% 100% 100% 100%

TYPE OF EQUIPEMENTS
& CABLES Installation of SMDB-EPA-10 100% 100% 100% 100% 100% 100%

Termination by contractor

PVC conduit installation 100% 100% 100% 100% 100% 100%

GI installation N/A N/A N/A N/A N/A N/A

Installation of Tray & Trunking 0% 0% 15% 50% 50% 50%


Electrical Power
Cable Installation 0% 0% 25% 25% 50% 50%

Panel Installation 0% 0% 0% 0% 0% 0%

Installation of Socket/Isolator 0% 0% 0% 0% 0% 0%

PVC conduit installation 100% 100% 100% 100% 100% 100%

Electrical Lighting GI installation N/A N/A N/A N/A N/A N/A

Wire Installation 0% 0% 0% 0% 0% 0%

Installation of Light/Switches 0% 0% 0% 0% 0% 0%
Level 20 Electrical CIVIL WORKS IN PROGRESS; RAISER TO BE
Room CLEARED BY CIVIL CONTRACTOR;DOOR NOT FIXED

PVC conduit installation 100% 100% 100% 100% 100% 100%

Fire Alam Services GI installation N/A N/A N/A N/A N/A N/A

Cable Installation 0% 0% 0% 0% 0% 0%

Installation of Fire alarm field devices 0% 0% 0% 0% 0% 0%

Installation of DB-L20-02

Termination by contractor

Termination by Bond
TYPE OF EQUIPEMENTS
& CABLES
4C 25 sqmm XLPE/SWA/PVC 25% 50% 50% 50%

1C 16sqmm PVC(G/Y) CABLE

PVC conduit installation 75% 75% 75% 75% 75% 75%

field control equipment 0% 0% 0% 0% 0% 0%

GI installation 0% 0% 0% 0% 0% 0%

Installation of Tray & Trunking 0% 0% 0% 0% 0% 0%


Level 20 roof Electrical Lighting (WB)
Cable Installation 0% 0% 0% 0% 0% 0%

Installation of Lights 0% 0% 0% 0% 0% 0%

testing 0% 0% 0% 0% 0% 0%

focussing of Lights 0% 0% 0% 0% 0% 0%

programming 0% 0% 0% 0% 0% 0%

PVC conduit installation 75% 75% 75% 75% 75% 75%

control equipment 0% 0% 0% 0% 0% 0%

GI installation 0% 0% 0% 0% 0% 0%
Electrical Lighting
Level 30 roof control room
Installation of Tray & Trunking 0% 0% 0% 0% 0% 0%

Cable Installation 0% 0% 0% 0% 0% 0%

testing 0% 0% 0% 0% 0% 0%

Installation of racks 0% 0% 0% 0% 0% 0%

ROOF PVC conduit installation 75% 75% 75% 75% 75% 75%

Page 9 of 15
% Completed
Level Area Description Activity Description Remarks
ROOF 26-Sep-09 27-Sep-09 28-Sep-09 29-Sep-09 30-Sep-09 1-Oct-09

field control equipment 0% 0% 0% 0% 0% 0%

GI installation 0% 0% 0% 0% 0% 0%

Installation of Tray & Trunking 0% 0% 0% 0% 0% 0%


Level 30 roof Electrical Lighting (WB)
Cable Installation 0% 0% 0% 0% 0% 0%

Installation of Lights 0% 0% 0% 0% 0% 0%

testing 0% 0% 0% 0% 0% 0%

focussing of Lights 0% 0% 0% 0% 0% 0%

programming 0% 0% 0% 0% 0% 0%

location marking of lights and field


control equipment 100% 100% 100% 100% 100% 100%

PVC conduit installation 50% 50% 50% 50% 50% 50%

field control equipment 0% 0% 0% 0% 0% 0%

GI installation 0% 0% 0% 0% 0% 0%

Electrical Lighting (WA


& WE) Installation of Tray & Trunking 0% 0% 0% 0% 0% 0%

Cable Installation 0% 0% 0% 0% 0% 0%

Installation of Lights 0% 0% 0% 0% 0% 0%

testing 0% 0% 0% 0% 0% 0%

focussing of Lights 0% 0% 0% 0% 0% 0%

programming 0% 0% 0% 0% 0% 0%

Page 10 of 15
ISSUES AFFECTING MEP PROGRESS
STATUS AS ON : 24-Sep-2009
ISSUES AFFECTING MEP SYSTEM

AREA DESCRIPTION LIGHTNING REMARKS


ELECTRICAL POWER ELECTRICAL LIGHTING ROOF LIGHTING PROTECTION & ELV SERVICES FIRE FIGHTING WATER SUPPLY
EARTHING

Water Pump room

Fire Pump Room

HV Room Interbeton installing C


channel on Trench grating

DU Room

Telephone Room

Battery Room

1. Interbeton installing C
channel on Trench grating
2. LV
LV Room room door size to be
increased - Affecting
installation of MDB

Transformer Room

Page 11 of 15
ISSUES AFFECTING MEP SYSTEM

AREA DESCRIPTION LIGHTNING REMARKS


ELECTRICAL POWER ELECTRICAL LIGHTING ROOF LIGHTING PROTECTION & ELV SERVICES FIRE FIGHTING WATER SUPPLY
EARTHING

Generator Room

BMS Room

Prayer Room & Toilets

FCC Room

Electrical Room 1

Electrical Room 2

IBY scafolding blocking MEP


Electrical Room 3
works

Electrical Room 4

Page 12 of 15
ISSUES AFFECTING MEP SYSTEM

AREA DESCRIPTION LIGHTNING REMARKS


ELECTRICAL POWER ELECTRICAL LIGHTING ROOF LIGHTING PROTECTION & ELV SERVICES FIRE FIGHTING WATER SUPPLY
EARTHING

ETS ROOM

Room Locked; SMDb cannot


ETFE Room 1
be installed

ETFE Room 2

Service Coridor

Level 10 Electrical Room Depa Works in progress Depa Works in progress

Level 20 Electrical Room Depa works not started Depa works not started

Level 20 (Roof Uplights)

Level 30 (Roof Uplights)

Page 13 of 15
ISSUES AFFECTING MEP SYSTEM

AREA DESCRIPTION LIGHTNING REMARKS


ELECTRICAL POWER ELECTRICAL LIGHTING ROOF LIGHTING PROTECTION & ELV SERVICES FIRE FIGHTING WATER SUPPLY
EARTHING

Awaiting Nelons studs from


Roof Taiyo

Excavation to be done for


External Corridor Earth pits EP1 , EP2, EP3,
EP4, EP5 & EP6

External Connetion between Excavation not started by


welcome pavilion & carparks IBY

Page 14 of 15
C00000Data Date: 14-Sep-09

TARGET PROGRAMME TO COMPLETION' (Matrix Format) to meet Race Day requirement @ Welcome Pavillion
Clearance by others (as per HBO) HBO Schedule
Sl No Level Area Description Activity Description Scope 1st Fix 2st Fix Final Fix 1st Fix 2st Fix Final Fix Remarks Internal Delays/Points to be noted
Finish Finish Finish Start Finish Start Finish Start Finish

1 Level 05 Water Tank Water Tank installation Hitachi complete complete complete complete complete complete complete in progress 22-Sep-09 Clearance recived only on 10-Sep-09

Water Pump room Water Pump installation Hitachi complete complete complete complete complete complete complete complete complete Clearance recived only on 09-Sep-09

Final Clearance recived only on 09-Sep-09; Door installation not yet


Electrical Power BTE complete complete complete complete complete complete complete in progress 25-Sep-09
done; Atleast temperory door required.

Electrical Lighting BTE complete complete complete complete complete complete complete in progress 25-Sep-09 Awaiting for materials. Required a.s.p.

Fire Alam Services BTE complete complete complete complete complete complete complete in progress 25-Sep-09

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

Clearance recived only on 03-Sep-09; No access was available till


Fire Pump Room Fire Pump installation Hitachi complete complete complete complete complete in progress 30-Sep-09 1-Oct-09 5-Oct-09
05-Sep-09

Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09 Floor Screed not done

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09 Floor Screed not done Awaiting for materials. Required a.s.p.

Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09 Floor Screed not done

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

HV Room HV Panel installations BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

DU Room Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

Telephone Room Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

LV Room LV Panel installations BTE 20-Sep-09 - - - - 21-Sep-09 1-Oct-09

Containment BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Cable Pulling BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09
Awaiting for materials. Required a.s.p.
Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

Transformer Room Transformer installations BTE - - 20-Sep-09 - - - - 2-Oct-09 14-Oct-09

Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Exaust fan Hitachi complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 1-Oct-09

Generator Room Generator installations BTE - - complete - - - - complete complete

Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 29-Sep-09 Final clearance partly completed

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 29-Sep-09 Final clearance partly completed

Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete 21-Sep-09 29-Sep-09 Final clearance partly completed

ETS Room Panel installations BTE - - 22-Sep-09 - - - - 4-Oct-09 16-Oct-09 No access available

DB installations BTE - - 22-Sep-09 - - - - 4-Oct-09 16-Oct-09 No access available

Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 No access available

Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 No access available

Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 No access available

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

BMS Room Fixtures & fittings (Toilet) Hitachi complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09 Sanitary fittings are by others

BMS installations BTE - - 22-Sep-09 - - - - 1-Oct-09 10-Oct-09 Raised Floor not yet done

Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09 Raised Floor not yet done

Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09 Raised Floor not yet done

Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09 Raised Floor not yet done

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

Prayer Room & Toilets Fixtures & fittings (Toilet) Hitachi complete complete 18-Sep-09 complete complete complete complete 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09

Electrical Power BTE complete complete 18-Sep-09 complete complete in progress 17-Sep-09 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09

Electrical Lighting BTE complete complete 18-Sep-09 complete complete in progress 17-Sep-09 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09

Fire Alam Services BTE complete complete 18-Sep-09 complete complete in progress 17-Sep-09 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09

Fixtures & fittings BTE - - 18-Sep-09 - - - - 19-Sep-09 29-Sep-09 Clearance recived only on 14-Sep-09

Temp. AC Hitachi - - - - - - - 20-Sep-09 28-Sep-09

ETFE Room DB installations BTE - - 22-Sep-09 1-Oct-09 9-Oct-09

Panel installations BTE - - 22-Sep-09 1-Oct-09 9-Oct-09

Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09

Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09

Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 30-Sep-09

Electrical Rooms Panel installations BTE - - 20-Sep-09 28-Sep-09 6-Oct-09

Electrical Power BTE complete complete 20-Sep-09 complete complete complete complete in progress 27-Sep-09

Electrical Lighting BTE complete complete 20-Sep-09 complete complete complete complete in progress 27-Sep-09

Fire Alam Services BTE complete complete 20-Sep-09 complete complete complete complete in progress 27-Sep-09

Service Corridoor Electrical Power BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09

Electrical Lighting BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09

Fire Alam Services BTE complete complete 22-Sep-09 complete complete complete complete 23-Sep-09 3-Oct-09

External Water supply Hitachi - 15-Sep-09 20-Sep-09 - - in progress 20-Sep-09 21-Sep-09 27-Sep-09 Part clearance received.

(WP to Carpark C1&C2) Fire Fighting Hitachi - 15-Sep-09 20-Sep-09 - - in progress 20-Sep-09 21-Sep-09 27-Sep-09 Part clearance received.

2 Level 20 Slab Handover by Taiyo Taiyo 18-Sep-09 - - - - - - - -

Electrical Power BTE complete 18-Sep-09 26-Sep-09 complete complete 19-Sep-09 24-Sep-09 27-Sep-09 7-Oct-09

Electrical Lighting (WB) BTE complete 18-Sep-09 26-Sep-09 complete complete 19-Sep-09 24-Sep-09 27-Sep-09 7-Oct-09

Electrical Room Handover of Electrical room Interbeton - - 22-Sep-09 - - - - 19-Sep-09 7-Oct-09

3 Level 30 Handover by Taiyo Taiyo 25-Sep-09 - - - - - - - -

Electrical Power BTE complete 25-Sep-09 10-Oct-09 complete complete in progress 5-Oct-09 11-Oct-09 23-Oct-09

Electrical Lighting (WB) BTE complete 25-Sep-09 10-Oct-09 complete complete in progress 5-Oct-09 11-Oct-09 23-Oct-09

Clearance by Taiyo after completion of


4 Roof Taiyo 25-Sep-09
bracket works, backbox etc.

Electrical Lighting (WA & WE) BTE - - 25-Sep-09 - - - - 26-Sep-09 26-Oct-09

5 Overall Testing & commissioning - - - - - - - - 13-Oct-09 28-Oct-09