Running head: ORION SYSTEMS

ORION Systems Case Study


Group Earth
Kirk Baringer
Meagan Beeman
Allison Benton
Yolanda Boyd
Thomas Guess
Southwestern College
Joel Light, Ph. D.
MGMT 505 Project Management Fundamentals
January 22, 2012

ORION SYSTEMS
1
Introduction
ORION Systems (ORION) has 7,000 employees and is a detachment of a large aerospace
company (Gray & Larson, 2011). ORION was recently awarded a government contract to build
high speed light rail trains. It is essential that ORION delivers an on time quality product to
ensure they will continue to win government contracts in the future. The new government
contract, known as Jaguar, will be headed by ORIONs project manager, Mike Rosas. Mike
realizes the challenges ahead for the company due to increased industry competition. This
resulted in higher expectations from the customers which includes faster delivery expectations,
better quality products, sufficient support after the project is completed, and overall lower
product cost (Gray & Larson, 2011). ORION has all of the tools to succeed, however their
current operation might require changes before new product implementation.
ORIONs current structure includes assigning projects to team members delegated by the
Vice President of Operations. ORION currently uses the matrix arrangement where team
members are either working on a full-time or part-time basis while performing normal job duties
(Gray & Larson, 2011). ORIONs concept of project management prior to Jaguar only involved
the design of a prototype which was then manufactured and delivered to the customer. The
companys structure included a project, planning/control, electronics system engineer, and
mechanics system engineer managers (Gray & Larson, 2011). Most of ORIONs work was
completed by 12 to 20 design teams consisting of 5 to 15 engineers who were led by a team
leader. ORION is facing some key changes in their structure in preparation for the Jaguar
project.

ORION SYSTEMS
2
Recommendations
ORION must be thorough with its planning and execution while following a time line to
effectively complete the Jaguar project. A recommendation for the company is to first decide if
they are going to continue with the matrix system or choose a different project management
structure for the company. ORION should use the balanced matrix approach with an alteration
of some of the team members working full time on the project until completion. The functional
managers will have the power to determine how to meet their requirements, while the project
manager still has the final power on decisions (Gray & Larson, 2011). The project will need
more functional managers in addition to the four already in place. The balanced matrix will
allow the functional managers to oversee their assigned teams to ensure completion by
monitoring progress, making vital decisions, and being held accountable for their divisions
success.
The project manager should also study the information learned in the major assessment to
avoid potential issues. The project team must work better with the manufacturing department to
ensure communication is open to improve the instructions, and design a friendlier model of
manufacturing (Gray & Larson, 2011). ORION must be more proactive with quality defects and
deal with the issues before product production is initiated. This can be accomplished by
addressing quality concerns during the design stage. Also, ORION needs to address issues with
product support after the final product is delivered. A customer expects the manufacturer to be
able to trouble shoot problems and help with issues after the product is delivered. ORION has
had trouble with this in the past. ORION should use a number of full-time team members to help
deal with issues such as lack of project ownership, and keeping team members up to date on the

ORION SYSTEMS
3
project development. With these recommendations implemented ORION will be able to deliver
an on-time quality product to its customers.
New Master Plan and Organizational Chart
ORION Systems should think about keeping its current matrix organizational structure.
Matrix organizations work well in dealing with governmental contracts, because the government
works on a project to project basis (Wright Jr., 1979). However, ORION is currently operating
under a functional matrix system. Under this system the project manager is limited to just
coordinating the efforts of each functional group and lacks the authority to make key decisions
(Larson & Gobeli, Matrix Management: Contradictions and Insights, 1987). This system ranks
high in a lot of areas but features weak project integration (Larson & Gobeli, Matrix
Management: Contradictions and Insights, 1987). ORION Systems should move more towards a
balanced matrix system. This system will feature efficient use of resources which is essential
when resources are spread across several projects at one time. This system will also produce
greater flexibility and better information flow. The greatest advantage of a balanced matrix
system is better project integration.
Projects should never be considered complete until the product or service is provided to
the customer. ORIONs project teams will need to be involved in the project until the product
reaches the customer. They will also need to have continued support for the customer after the
product is delivered. The ultimate goal of every project is to provide a quality product or service
to an organizations customers and this is not the case with the way ORION currently executes
its projects. For this to occur, ORION needs to involve more functional managers in the process.
ORIONs project teams will no longer be just involved in design and prototype development.

ORION SYSTEMS
4
They will also be involved in the manufacturing process as well. In this way functional
managers who oversee key manufacturing process need to be added to the project team. The key
here is each functional manager should still be held responsible for all aspects of their functional
areas and responsible for decisions relating to their specialties. However, the project manager
should still have overall decision making authority in all areas of the project.
There currently is no quality assurance function or department within ORIONs project
management process. If quality is such an issue why has this requirement never been identified
in the past? ORION should quickly implement some sort of quality assurance (QA) program to
ensure the highest quality product is being delivered. A company can be made or broken by the
quality of its product, and the QA department would guarantee and aid in lower product defects.
During the design phase changes were being made that were not in the best interest of the
customer. This would result in delays and poor customer satisfaction. The QA department will
make sure every aspect of the project will have the interests of the customer in mind.
The last change required to the master plan in place at ORION is its pay system. The
project team needs to know they are all working together towards success and that every activity
within the project process is just as important as the next. Currently design engineers are paid
higher than other employees, and it appears to other project team members that these engineers
run the show. A good hard look needs to be accomplished by management to eliminate this
issue. The type of conflict this issue can breed can cause great damage to the morale and
motivation within the organization. This will prevent projects from running smoothly and
possibly impact their success.

ORION SYSTEMS
5
A new chain of command needs to be established by adding additional functional
managers. A clear line of authority needs to be recognized that establishes the project manager
as the ultimate decision authority with a project. The current chart has just one supervisor who
falls directly under the project manager. According to the major assessment of probable
problems and the increased demand from the government due to completion the master plan
would reflect these changes. The initial plan of five to seven years would be shortened to three
to four (Gray & Larson, 2011). Also, there would be a longer duration of documentation/training
program, and building the product line to ensure fewer problems.
Implemented Changes
With Rosass plan, several changes were made that created an improved project approach
to project management. The process in which a project is completed will be more streamlined
with Rosass approach. First, there will be seven managers who will oversee the project to the
end and coordinate with each other compared to the original four who were just responsible for
the design and development of a new product (Larson & Gray, 2011). Under the new project
management system, teams will be responsible for designing, developing, constructing and
testing a specific subsystem of the project (Larson & Gray, 2011). By creating teams and placing
most of the product development on each team, this improves product reliability and completion
time.
One major overhaul to the management of the project was a newer master plan which
would be implemented by ORION. By having an improved master plan, it aides in creating an
organizational culture; one that shares in a management focus, unit integration, control, conflict
tolerance, team emphasis and member identity (Gray & Larson, 2011). This contrasts to the

ORION SYSTEMS
6
previous management of projects in which each unit working on the project had their own
identity. The newer master plan also decreases the chances of an implementation gap occurring
and reducing the overall cost of the project. By using Rosass Jaguar master plan, a total of two
to three years of time have been shaved off the traditional master plan ORION previously used.
Also, by using the new plan ORION will be able to cut back on the scope creep that occurred on
past projects.
Impact of Implemented Changes
In the past ORION has managed projects according to the industry trends and norms. But
because of increased competition for government contracts the change is vital for a bid at more
contracts in the future. The changes recommended would directly improve completion time,
product reliability, and lead to overall cost reduction (Gray & Larson, 2011). These three key
issues were identified in previous project reviews and need to be implemented to maintain
ORION Systems competitive advantage into the future. ORION has had some issues with the
way the projects were handled in the past; the new method should improve quality, increase
customer support, and cut down on the projects total time to completion (Gray & Larson, 2011).
The biggest change implemented involved abandoning the traditional sequential approach
to product development and implementing a concurrent approach (Gray & Larson, 2011). This
new approach creates parallel paths of activities, which will shorten the amount of time required
to complete a series of activities during the project. However, this new approach could result in
possible conflicts in managing resources. To counter this possibility the number of teams
performing core work will be increased to 35 teams, and each individual team will consist of at
least 50% permanently assigned personnel. This will help build strong project ownership from

ORION SYSTEMS
7
permanently assigned members which will hopefully help inspire superior performance from
other team members.
Staffing teams with these permanently assigned personnel will also prevent delays due to
loss of focus or readjustment time required by team members who have to shuffle from project to
project. Scope creep has also led to delays in the past, but future design refinements must now
be closely coordinated between manufacturing and the Integrated Logistical Support (ILS)
teams. This way production can begin immediately following the completion of the Production
Readiness Review (PRR) and reduce the number of changes which are inconsistent with the
demands of the customer. Unnecessary changes can reduce the quality and reliability of the
finished product (Gray & Larson, 2011).
Reliability has been another issue that has plagued ORION Systems in the past.
Reliability of products is directly linked to quality management. In the past project teams were
only responsible for designing and developing a product. Now project teams will be responsible
for the product from cradle to grave. Teams will be responsible for overseeing all aspects of the
product from design to final customer delivery. This will help eliminate the sense of passing the
buck to another department that was present in past projects. Project teams simply passed off
responsibility for the final product to manufacturing. Three new positions have been created to
help improve reliability and quality issues.
The newly created Production Manager will be responsible for raising production issues
during the design phase which will help further eliminate scope creep. The ILS Manager
position will be responsible for all activities requiring project and customer support. Finally, a
Quality Assurance (QA) Manager has been added to implement a quality program which will

ORION SYSTEMS
8
enhance the reliability, availability, and maintainability of the product (Gray & Larson, 2011).
The creation of the QA Manager position might be the biggest change toward improving product
reliability and quality. Still, individual team leaders will be held responsible for the quality of
their subsystems.
Costs in general will be reduced if all the recommended changes are implemented.
Reducing scope creep will eliminate unnecessary changes which result in delays and increased
costs. Improved owners manuals and ownership training will reduce costs associated with
customer service. The implementation of concurrent engineering will allow production and
documentation work to be conducted at the same time other core development is occurring which
will accelerate project completion, reduce production costs, and contribute to higher customer
satisfaction (Gray & Larson, 2011).
Support for Changes
When implementing change in companies there are likely to be some opposition from
employees. ORION should avoid common pitfalls of implementation such as lack of planning,
training, and communication that leads to ineffective change (Jick & Peiperl, 2011). Rosas put
together a very ambitious plan to make the Jaguar project a success for ORION and for the
government. It appeared he did this in an effort to address many of the issues that were cultural
in nature to ORION. The new improvements should help the new project be more efficient.
The project team managers and team leaders would be in favor of the project plan,
because it gives them the opportunity to lead parts of the project. All employees should be
briefed prior to the planed roll-out so they understand their expectations and responsibilities.
Within the current scheme at ORION, they use the matrix approach to project management. This

ORION SYSTEMS
9
approach would use the same people on multiple projects which does not allow for dedicating
personnel to a single project. While this will be welcomed by the team it may not mesh with the
current culture of the organization.
Rosas was also implementing some quality improvement methodologies to his plan
which would add quality and value of the final product. Quality improvement practitioners see a
focus on the customer as the starting point, and indeed, the reason detre, of the whole quality
philosophy (Hill & Jones, 2010). The government/customer will appreciate the method that
Rosas is trying to employ, because it will address the organizational cultural issues at ORION
which include: Higher than expected production costs, quality concerns, problems with
customer support, lack of strong project ownership, and scope creep.
The ORION organization and leadership is accustomed to having many projects going
on at the same time and using the matrix approach to project management. The senior leadership
and or the board of directors are not going to appreciate Rosas ideas. His idea to dedicate
employees to a project team does not mesh with the culture. There could be dissention from all
levels with this project. But the new changes should bring higher productivity, eliminate looming
issues, and hopefully secure more government bids in the future.
Conclusion
It was very apparent after reviewing the situation at ORION Systems that changes were
indeed required to bring about improvements in project completion times, quality, reliability, and
project costs. Changes do not always require a change in organizational structure; however
ORION did need to reassess how it did business (Wright Jr., 1979). It is very well known that
matrix type organizational structures work well with government contracts, so the matrix system

ORION SYSTEMS
10
in place will suffice for now. A reassessment was conducted by Mike Rosas will produced
changes that will bring about much needed improvements in the way the company operated.
When these changes are implemented by ORION Systems the future will be paved with project
success after success as we will see with the Jaguar project.

ORION SYSTEMS
11
References:
Hill, C. W., & Jones, G. R. (2008). Strategic Management: An Integrated Approach. Boston:
Houghton Mifflin.
Jick, T. D., & Peiperl, M. A. (2011). Managing change. New York, NY: McGraw-Hill Irwin.

Larson, E. W., & Gobeli, D. H. (1987). Matrix Management: Contradictions and Insights.
California Management Review, 29(4), 126-138.
Larson, E. W., & Gray, C. F. (2011). Project Management The Managerial Process. New York:
McGraw-Hill/Irwin.
Wright Jr., N. H. (1979). Matrix management: A prime for the administrative manager.
Management Review, 68(4), 58.