Beruflich Dokumente
Kultur Dokumente
OVERVIEW
Electricity market
1.
Overview
The primary objective of German energy regulation is the supply of
electricity (and natural gas) for society as a whole that is as secure,
affordable, consumer-friendly, efficient and environmentally
sustainable as possible. To that end, the regulation of the energy
supply networks aims to ensure effective and undistorted
competition in the supply of energy and at securing a long-term
efficient and reliable operation of energy supply networks.
Furthermore, in order to protect the climate and the environment,
as well as to conserve fossil fuels, German energy policy promotes
the generation of electricity from renewable energy sources.
Recent trends
The German "energy transition" (Energiewende), proclaimed
shortly after the nuclear incident in Fukushima in March 2011, has
been one of the main drivers for recent developments and trends in
the electricity sector in Germany. The Energiewende:
global.practicallaw.com/5-524-0808
The revised EEG entered into force on 1 August 2014 (see Question
24).
In order to attract investments into the German offshore grid, the
German Energy Industry Act (Energiewirtschaftsgesetz (EnWG))
was amended in December 2012. The EnWG was amended to
provide for a more structural approach to its development, and for
a new liability regime in the case of delays in the construction, or
interruptions of the operation, of offshore grid connection lines.
After over a year in practice, the legislative changes have provided
guidelines to investors in offshore infrastructure projects, and the
overall capacity of the offshore grid has been raised to 8 gigawatts
(in the North Sea) by 2019.
The offshore grid and onshore transmission and distribution grids
require substantial investment to accommodate the increasing and
highly volatile generation of "green energy". Since the production
centres (primarily in the north and east) have moved away from the
consumption centres (primarily in the west and south), new
infrastructure projects, including direct current high-voltage power
lines, rank high on the political agenda (see Questions 14 and 17).
Finally, as electricity from renewable energy sources also benefits
from a priority connection and access to the grid (see Question 7),
the increase of green electricity pushes conventional power plants
with high marginal costs (in particular, modern gas-fired power
plants) out of the market. The ongoing discussions of a potential
move from energy-only markets to some form of "capacity
markets" is expected to gain momentum in 2014 (see Question 24).
Regulatory structure
2.
Regulatory framework
This article was first published in the Energy and Natural Resources Multi-Jurisdictional Guide 2014
and is reproduced with the permission of the publisher, Thomson Reuters.
The law is stated as at 1 September 2014.
Country Q&A
Generation
Regulatory authorities
The main regulatory authorities are the:
Transmission
Merger control.
ELECTRICITY COMPANIES
Main companies
3.
global.practicallaw.com/energy-mjg
50Hertz.
Amprion.
TenneT TSO.
TransnetBW.
Distribution
German distribution system operators (DSOs) are typically owned
by municipalities. This accounts for the large number of 869
electricity DSOs in Germany in 2014. While the "Big Four" have
managed to acquire shares in numerous DSOs through
privatisation efforts by the municipalities in the past, the German
distribution market has seen a reverse trend in recent years. This is
due to municipalities, often guided by the will of the local people,
increasingly attempting to regain sole control over the DSOs
(Rekommunalisierung). Secondly, the Federal Cartel Office also
tends to prohibit new acquisitions by the "Big Four" in order to
ensure the success of the liberalisation efforts on the transmission
and generation level.
Supply
The liberalisation of the supply market has been even more
pronounced than the liberalisation of the transmission market.
Under the EnWG and the Ordinance on Electricity Network Access
Unbundling requirements
In accordance with the transposed EU unbundling requirements,
electricity grid operators on both the transmission and distribution
level must comply with legal, operational and informational
unbundling as well as unbundling of accounts. In addition,
electricity TSOs are subject to either full ownership unbundling or
must ensure that the grid operation is independent of both
electricity production and supply within a vertically integrated
energy utility (independent transmission operator (ITO)). In
Germany, a third unbundling model (independent system operator
(ISO)), provided by EU regulation, is of no practical relevance (see
Question 2).
Foreign ownership
4.
Import of electricity
5.
Fossil fuels
While both Germany and the EU are committed to decreasing
carbon dioxide emissions, fossil fuels are currently still the main
source for electricity generation (55.7%). They are expected to
remain important in the medium term due to the German nuclear
phase-out and the challenges of renewable energy sources (that is,
their volatility in production and insufficient transmission
capacities, see Question 8).
Nuclear fission
In Germany, since the 1970s the policy on nuclear power has been
controversial and subject to many changes in recent years. In
2000, the federal government and the operators of the German
nuclear power plants agreed on a complete nuclear phase-out,
prohibiting the construction of new plants and limiting the
generation of the existing plants to maximum quantities. In 2010,
the then federal government substantially increased the maximum
quantities, effectively extending the lifetime of the existing nuclear
power plant fleet.
However, as an immediate reaction to the Fukushima catastrophe
in March 2011, the federal government issued a moratorium
ordering the immediate shut-down of the seven oldest as well as
one additional nuclear power plant which was, at the time,
temporarily out of order due to safety issues. At the same time, the
2010 extension of nuclear power in Germany was withdrawn,
reinstating the complete phase-out from nuclear power by 2022.
Both measures have provoked a number of legal proceedings by
operators of nuclear power plants which are currently pending
before German courts. In 2014, nine nuclear power plants are still
in operation in Germany with the next plant to be shut down in
2015.
Renewable energy
Renewable energy sources accounted for 24% of German electricity
generation in 2013. It marked yet another historic high following
the overall trend of increasing importance of renewable energy
sources in the German energy mix (growing from 6% in 2000 to
20% in 2011 and 23% in 2012).
Based on the overall electricity generation, the share of the
renewables was spread over the various sources as follows:
Biomass, 6.7%.
global.practicallaw.com/energy-mjg
Country Q&A
Country Q&A
Photovoltaics, 4.7%.
7.
9.
Government policies/incentives
Under the current EEG, electricity generation from renewable
sources enjoys, in particular, the following privileges:
A permit under the Federal Emission Control Act (BundesImmissionsschutzgesetz (BImSchG)), including an
However, the permit under the BImSchG (if required) includes any
building permits and/or installation-related water permits.
11.
global.practicallaw.com/energy-mjg
ELECTRICITY TRANSMISSION
Authorisation and operating requirements
14. What are the authorisation requirements to construct
electricity transmission networks?
In general, the construction of transmission networks is subject to a
two-pronged authorisation process. Based on a regional land use
planning procedure under the Federal Spatial Planning Act
(Raumordnungsgesetz), a planning approval procedure under the
EnWG takes place. The approval of the plan substitutes all other
public-law permissions (Konzentrationswirkung). For both, the
authorities of the federal states are competent to approve the
plans. Therefore, projects which cover more than one federal state
necessitate the co-ordination of different state authorities.
For the construction of electricity transmission networks and to
support the German energy transition (Energiewende), two further
Acts were recently implemented:
While the EnLAG left the two-pronged approach under the EnWG
unchanged, it allows several named projects to skip the usual
necessity analysis procedure (Bedarfsanalyse) under the EnWG.
Furthermore, it shortens the legal recourse for actions to only one
instance
at
the
Federal
Administrative
Court
(Bundesverwaltungsgericht). By contrast, the NABEG introduced a
simplified permitting procedure for spatial planning and
established a special planning approval procedure for certain other
projects. Most importantly, under the NABEG, the Federal Network
Agency (BNetzA) is the competent authority for both procedures.
Rates
16. How are the rates and conditions for the transmission of
electricity regulated?
While the conditions for access to electricity transmission grids are
governed by the Ordinance on Access to the Electricity Supply Grid
(Stromnetzzugangsverordnung (StromNZV)), the rates for such
access are regulated in the Ordinance on Tariffs for Access to the
Electricity Supply Grid (Stromnetzentgeltverordnung (StromNEV))
and
the
Ordinance
on
Incentive
Regulation
(Anreizregulierungsverordnung (ARegV)).
In 2009, the previous ex ante cost-oriented regulation of the grid
access tariffs was to a large extent replaced by an incentive
regulation (Anreizregulierung). It aims to enhance efficiency among
the grid operators. Different from the previous static cost-based
tariff regime, the incentive regulation stresses dynamic efficiencies.
Within a regulatory period (of five years), grid operators are allowed
to collect the economic benefits resulting from efficiency gains.
However, during the next regulatory period the benefit resulting
from the improvement in efficiency must be passed on to the
customers through a decrease in grid access tariffs.
For each grid operator, the Federal Network Agency (BNetzA)
defines a revenue cap (Erlsobergrenze) for each calendar year of a
regulatory period. For electricity TSOs, the first regulatory period
ended on 31 December 2013 and the second regulatory period
extends from 1 January 2014 to 31 December 2018.
global.practicallaw.com/energy-mjg
Country Q&A
Country Q&A
ELECTRICITY DISTRIBUTION
Authorisation and operating requirements
17. What are the authorisation requirements to construct
electricity distribution systems?
The authorisation requirements for the construction of electricity
distribution systems are generally the same as for transmission
systems (see Question 14). However, distribution network operators
do not benefit from either the Federal Network Expansion Act
(EnLAG) or Federal Network Expansion Acceleration Act (NABEG)
procedures as those are reserved for projects on the transmission
level.
18. What are the authorisation and the main ongoing
requirements to operate electricity distribution systems?
The requirements to operate distribution systems in Germany are
equivalent to those for transmission systems (see Question 15) with
the exception that distribution system operators do not need to be
certified by the Federal Network Agency (BNetzA).
Under the Energy Industry Act (EnWG), distribution system
operators (DSOs) are responsible for the safety and reliability of
their grids. They are also generally responsible for (smart) metering
to monitor both electricity consumption and effective utilisation
periods. Larger DSOs also have to annually report the current state
of their grids and the impact of the expanding renewable energy
sources to the competent regulatory authority. As regards the
latter, DSOs are obligated to grant both priority connection and
access to operators of renewable energy facilities under the EEG
(see Question 7).
Rates
19. How are the rates and conditions for the distribution of
electricity regulated?
Consumer
Conditions of sale are subject to the guidelines on business
processes
for
the
electricity
supply
of
customers
(Geschftsprozesse zur Kundenbelieferung mit Elektrizitt (GPKE)).
In order to encourage competition, the GPKE provides, in
particular, rules for transparent billing and for changes of supplier.
In addition, basic suppliers (see Question 20) must publish their
basic tariff and supply household customers in accordance with the
Ordinance
on
Electricity
Basic
Supply
(Stromgrundversorgungsverordnung (StromGVV)).
Wholesale
The rates and conditions for access to distribution systems are
generally equivalent to those for transmission systems (see
Question 16). However, under the current incentive regulation
scheme, investments on the distribution level are treated
differently from the transmission level. In addition, tariffs for
electricity distribution systems are calculated by taking into
account a quality element reflecting network reliability and
network performance.
ELECTRICITY SUPPLY
Authorisation and operating requirements
global.practicallaw.com/energy-mjg
TAX ISSUES
18% for the EEG levy (EEG-Umlage), for additional costs arising
from the fixed feed-in tariff scheme for electricity generated
from renewable sources (see Question 7).
REFORM
24. What reform proposals are there for the regulation of the
electricity sector?
The reform of the Renewable Energies Act (EEG) (see Question 1)
entered into force on 1 August 2014. In addition, the Federal
Minister of Economic Affairs and Energy, Sigmar Gabriel, has
announced that the political debate concerning capacity markets
will be initiated shortly after the conclusion of the EEG reform.
Furthermore, in the course of 2014, the Federal Network Agency
(BNetzA) will present an evaluation report on the incentive
regulation. The report will also contain suggestions by the
regulator with respect to the further evolution of the incentive
regulation. This will mark the first step towards the revision of the
incentive regulation prior to the beginning of the third regulatory
period (for gas network operators) in 2018.
global.practicallaw.com/energy-mjg
Country Q&A
Country Q&A
ONLINE RESOURCES
W www.clearingstelle-eeg.de/english
Description. This is an official up-to-date website in English with information on renewable energy sources.
W http://bmwi.de/EN/root.html
Description. This is the up-to-date English website of the Federal Ministry for Economic Affairs and Energy. Apart from general
information on German energy policy, the website especially provides content on the Energiewende.
W http://www.bundesnetzagentur.de/cln_1422/EN/Home/home_node.html
Description. This is the official up-to-date English website of the Federal Network Agency. Apart from general information on electricity
regulation, the site contains numerous recent statistics.
W www.gesetze-im-internet.de
Description. This is the official up-to-date website of the Federal Ministry of Justice with all texts of legal acts (in German).
Hengeler Mueller
Hengeler Mueller
T
F
E
W
T
F
E
W
Restrepo Rodrguez).
Uwer).
global.practicallaw.com/energy-mjg