Federal Register / Vol. 71, No.

144 / Thursday, July 27, 2006 / Rules and Regulations 42593

DEPARTMENT OF ENERGY requirements.1 The COOP Plan is C. Consistency of State Action With
designed to ensure that the Commission Reliability Standard
Federal Energy Regulatory is able to quickly restore its ability to 4. If the date by which a Commission
Commission perform essential functions should such determination under FPA § 215 as to
conditions occur.2 The rule temporarily whether a State action is inconsistent
18 CFR Part 376 suspends filing requirements and with a reliability standard is required to
ensures that deadlines for Commission be made falls during a period when the
[Docket No. RM06–19–000, Order No. 680] actions that fall during the period the COOP Plan is activated, the
plan is in operation are met, thereby effectiveness of the State action will be
Commission Procedures During providing continuity in the conduct of deemed to be stayed pending further
Periods of Emergency Requiring the Commission’s business and action by the Commission.
Activation of Continuity of Operations certainty to parties with business before
Plan the Commission.3 D. Tolling of Time Periods for
Commission Action
Issued July 20, 2006. II. Discussion
5. The rule also tolls for purposes of
AGENCY: Federal Energy Regulatory A. Acceptance and Suspension of further consideration the time periods
Commission, DOE. Pending Filings Requiring Commission for certain Commission actions that will
ACTION: Final rule. Action by a Date Certain be required during the emergency.
These include the:
2. The rule provides for the
SUMMARY: In this rule the Commission • 60-day period for acting on requests
establishes procedures with regard to acceptance and suspension, during
for Exempt Wholesale Generator or
filing and other requirements if the emergencies that disrupt normal
Foreign Utility Company status;
Commission is required to implement operations and communications and • 60-day period for acting on
its Continuity of Operations Plan in require activation of the COOP Plan,4 of interlocking directorate applications;
response to an emergency situation that pending filings upon which the • 90-day period for acting on requests
disrupts communications to or from the Commission would be required to act by for certification of qualifying facility
Commission’s headquarters or which a date certain during the period of status;
otherwise impairs headquarters emergency. The effective date(s) of such • 60-day period for acting on holding
operations. The rule temporarily filings shall be the date(s) requested, to company and transaction exemptions
suspends filing requirements and be effective subject to refund and further and waivers;
ensures that deadlines for Commission order of the Commission. These include • 180-day period for acting on public
actions that fall during the period the filings made pursuant to: utility and holding company
plan is in operation are met, thereby • Section 4 of the Natural Gas Act; applications for dispositions,
providing continuity in the conduct of • Section 205 of the Federal Power considerations, or acquisitions;
the Commission’s business and Act; and • 150-day period for acting on
certainty to parties with business before intrastate pipeline applications for
• Section 6(3) of the Interstate
the Commission. approval of proposed rates;
Commerce Act. • Period ending 60 days prior to the
EFFECTIVE DATE: The rule will become
B. Electric Reliability Organization Electric Reliability Organization’s (ERO)
effective July 20, 2006.
Penalties fiscal year for acting on the ERO’s
FOR FURTHER INFORMATION CONTACT: John budget;
Clements, Office of the General Counsel, 3. If the date on which a penalty • 60-day period for acting on
Federal Energy Regulatory Commission, imposed by an Electric Reliability notifications that a Reliability Standard
Room 101–57, 888 First St., NE., Organization pursuant to FPA § 215 may conflict with a function, rule,
Washington, DC 20426, 202–502–8070. would take effect falls during a period order, tariff, rate schedule or agreement;
SUPPLEMENTARY INFORMATION: Before when the COOP Plan is activated, • 60-day period for acting on
Commissioners: Joseph T. Kelliher, review of such penalty by the applications for review of a penalty
Chairman; Nora Mead Brownell, and Commission will be deemed to be imposed by the ERO for violation of a
Suedeen G. Kelly. initiated and the penalty shall be stayed reliability standard;
pending further action by the • 45-day Protest period for protesting
I. Introduction Commission. Prior Notice Filings, and the 30-day
1. The Federal Energy Regulatory period for resolving and filing to
Commission (Commission) is amending
1 The emergency conditions which might trigger withdraw such Protests; 5
its regulations to modify certain filing
activation of the COOP Plan are not identical to • 30-day period for acting on requests
‘‘emergency conditions’’ as heretofore defined in 18
requirements and establish procedures CFR 376.201. One of the revisions discussed below
for rehearing;
to be effective during emergencies modifies that section to cover the emergency • Time periods prescribed in 18 CFR
affecting the Commission that require it conditions that would trigger activation of the 385.714–715 for acting on interlocutory
to implement its Continuity of
COOP Plan. appeals and certified questions.
2 More information concerning the COOP Plan
Operations Plan (COOP Plan). The can be found on the Commission’s Web site at E. Suspension of Certain Requirements
COOP Plan was developed to address www.ferc.gov/coop.asp.
6. Disruptions to normal operations
emergency conditions lasting up to 30 3 Activation of the COOP Plan affects

communications with headquarters only, and does and communications during an


days during which Commission
not affect communications required to be made
headquarters operations may be directly to the Commission’s Regional Offices. 5 The result of these suspensions is that no
temporarily disrupted or
jlentini on PROD1PC65 with RULES

4 Not all disruptions of communications with the facilities subject to the prior notice provisions of the
communications may be temporarily Commission’s headquarters will require activation Commission’s blanket certificate regulations not
unavailable, either of which may of the COOP Plan and the triggering of these finally authorized prior to the activation of the
regulations. For instance, a brief outage of eLibrary COOP Plan shall be constructed during its
prevent the public or the Commission that prevents entities from making electronic filings activation in the absence of specific authorization
from meeting regulatory or statutory would not trigger activation of the COOP Plan. by the Commission.

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00027 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
42594 Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations

emergency that require activation of the G. Suspension of Proceedings Before on completion of dam safety work, in a
COOP Plan could make compliance Administrative Law Judges manner consistent with the
with some Commission statutes, 9. The rule also suspends all hearings, maintenance of environmental
regulations, or orders difficult or prehearing conferences, settlement protections. The Commission will
impossible. This rule suspends those conferences, and meetings before further ensure that its personnel are
requirements during the emergency. The administrative law judges while the available to respond to and address:
affected regulatory requirements include COOP Plan is activated. Plant accidents or reportable incidents
mandatory filings, submissions, and at LNG facilities; dam safety, public
notifications, as well as voluntary H. Delegations of Authority safety, and security incidents at
notices, contacts, or reports to the 10. This rulemaking also revises the jurisdictional hydropower projects; and
Commission. They include: Commission’s rules regarding regional and interregional bulk power
• Filings to comply with Commission emergency operations to ensure that systems incidents and emergencies,
orders, including orders issued by delegations of authority will remain including blackouts. Alternate channels
administrative law judges; effective in the event the COOP Plan is of communication will include
• Filings required to be made by a activated. The revisions clarify measures to ensure that these activities
date certain under the Commission’s § 376.206 of the Commission’s can go forward unhindered.
regulations or orders; regulations to specify with more Regulatory Flexibility Act Certification
• Motions to intervene and protests, particularity what persons will be
and notices of intervention; authorized to exercise delegated 13. The Regulatory Flexibility Act of
authority in the event the officials to 1980 (RFA) 8 generally requires a
• Comments responding to proposed
whom delegations are made under Part description and analysis of final rules
rulemakings or technical conferences;
375 are unavailable. Section that will have significant economic
• Responses to data requests; 376.204(b)(2) also is being revised to impact on a substantial number of small
• Self-reports of violations; update the list of officials designated to entities.9 The Commission is not
• Responses to staff audit reports; act on behalf of the Commission in the required to make such an analysis if a
• Contacts with the Commission’s event of an emergency. Finally, the rule would not have such an effect. This
Enforcement Hotline; definition of ‘‘emergency condition’’ Final Rule merely temporarily suspends
• Accounting filings required by the contained in § 376.201 is being revised or waives certain filings and other
Commission’s Uniform Systems of to include specifically any condition requirements. Therefore, this Final Rule
Accounts; and that necessitates activation of the COOP will not have a significant economic
Plan. impact on a substantial number of small
• Forms, reports, and submissions entities and no regulatory flexibility
required to be filed by a date certain. I. Related Matters
analysis is required.
7. The rule also grants certain relief 11. The COOP Plan includes
with respect to the Commission’s procedures to inform the public when Information Collection Statement
Standards of Conduct for Transmission the COOP Plan is activated, when 14. Office of Management and Budget
Providers that are also affected by the alternate channels of communication (OMB) regulations require OMB to
emergency affecting the Commission. are established, when normal operations approve certain information collection
Specifically, such Transmission and communications are resumed, and requirements imposed by agency rule.10
Providers may, for 30 days, delay the length of any grace period to comply This Final Rule contains no new
compliance with the requirement of with requirements that were suspended information collections. Therefore, OMB
§ 358.4(a)(2) of the regulations 6 to during the emergency. A press release review of this Final Rule is not required.
report to the Commission each will be sent to major wire services,
emergency that resulted in any industry press, and appropriate Environmental Analysis
deviation from the Standards of metropolitan area radio stations
Conduct within 24 hours of such announcing that the Commission has 15. The Commission is required to
deviation. Unless the emergency activated the COOP Plan. The prepare an Environmental Assessment
prevents the Transmission Provider Commission’s alternative Web site or an Environmental Impact Statement
from posting information on the OASIS (http://www.fercalt.gov) will be for any action that may have a
or Internet Web site, the Transmission activated and a notice that the COOP significant adverse effect on the human
Provider must comply with those Plan has been activated will be environment. Included in the exclusion
posting requirements. The 30-day prominently displayed thereon. The are rules that are clarifying, corrective,
period may be extended as necessary. alternative Web site will act as a or procedural or that do not
resource for the press, industry, and substantially change the effect of the
F. Intention Not To Act
general public. An additional press
85 U.S.C. 601–12.
8. The rule provides that, during the release will be sent to appropriate media
9 The RFA definition of ‘‘small entity’’ refers to
emergency conditions that require outlets when the COOP Plan is
the definition provided in the Small Business Act,
activation of the COOP Plan, the deactivated and the Commission’s which defines a ‘‘small business concern’’ as a
Commission will not initiate an headquarters constituted, and business which is independently owned and
enforcement action under § 210(h)(2) of appropriate modifications made to the operated and which is not dominant in its field of
the Public Utility Regulatory Policies alternative Web site. operation. 15 U.S.C. 632. The Small Business Size
Standards component of the North American
Act of 1978.7 Applicants may, as a 12. Finally, during periods when the Industry Classification System defines a small
consequence, bring their own COOP is activated, the Commission will electric utility as one that, including its affiliates,
enforcement actions in the appropriate continue to act on requests to ensure is primarily engaged in the generation,
jlentini on PROD1PC65 with RULES

courts. continued construction of essential transmission, and/or distribution of electric energy


for sale and whose total electric output for the
natural gas facilities with sensitive preceding fiscal years did not exceed 4 million
6 18 CFR 358.4(a)(2). construction timelines, on MWh. 13 CFR 121.201.
7 16 U.S.C. 824a–3(h)(2). Commencement of Service requests, and 10 5 CFR 1320.12.

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00028 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations 42595

regulations being amended.11 This rule By the Commission. any Office or Division, or officer in
is procedural in nature and therefore Magalie R. Salas, charge of a regional office, is not
falls under this exception; consequently, Secretary. available and capable of carrying out his
no environmental consideration is ■ In consideration of the foregoing, the or her functions, such functions are
necessary. Commission amends part 376, Chapter I, delegated to staff members designated
Title 18, Code of Federal Regulations, as by the Chairman to perform such
Document Availability functions. If no staff member so
follows:
designated is available and capable of
16. In addition to publishing the full
PART 376—ORGANIZATION, MISSION, carrying out their functions, such
text of this document in the Federal
AND FUNCTIONS; OPERATIONS functions are delegated to the next
Register, the Commission provides all subordinate employee in the Office or
interested persons an opportunity to DURING EMERGENCY CONDITIONS
Division of the highest grade and
view and/or print the contents of this ■ 1. The authority citation for part 376 longest period of service in that grade.
document via the Internet through the continues to read as follows: If no subordinate employee of the Office
Commission’s Home Page (http:// Authority: 5 U.S.C. 553; 42 U.S.C. 7101– or Division is available and capable of
www.ferc.gov) and in the Commission’s 7352; E.O. 12009, 3 CFR 1978 Comp., p. 142. carrying out their functions, such
Public Reference Room during normal functions are delegated to the
business hours (8:30 a.m. to 5 p.m. ■ 2. In § 376.201, paragraph (a)(3) is Commission employee of the highest
Eastern time) at 888 First Street, NE., revised and paragraph (a)(4) is added to grade and longest period of service in
Room 2A, Washington, DC 20426. read as follows: that grade who is available and capable
17. From the Commission’s Home § 376.201 Emergency condition defined. of carrying out their functions.
Page on the Internet, this information is * * * * * ■ 5. Section 376.209 is added to read as
available in the eLibrary. The full text (a) * * * follows:
of this document is available on (3) At a time specified by the § 376.209 Procedures during periods of
eLibrary in PDF and Microsoft Word authority of the President; or emergency requiring activation of the
format for viewing, printing, and/or (4) At such time that the Continuity of Operations Plan.
downloading. To access this document Commission’s Continuity of Operations (a)(1) The Commission’s Continuity of
in FERRIS, type the docket number Plan is activated; and Operations Plan is activated during
excluding the last three digits of this * * * * * emergency conditions lasting up to 30
document in the docket number field. ■ 3. In § 376.204, paragraphs (b)(2)(ii), days during which Commission
18. User assistance is available for (b)(2)(v), (b)(2)(vi), (b)(2)(viii), (b)(2)(ix) headquarters operations may be
eLibrary and the Commission’s Web site and (b)(2)(x) are revised to read as temporarily disrupted or
during normal business hours. For follows: communications with the Commission’s
assistance, please contact Online headquarters may be temporarily
§ 376.204 Delegation of Commission’s unavailable, either of which may
Support at 1–866–208–3676 (e-mail at authority during emergency conditions.
FERCOnlineSupport@FERC.gov), or the prevent the public or the Commission
* * * * * from meeting regulatory or statutory
Public Reference Room at (202) 502– (b) * * * requirements. The provisions of this
8371, TTY 202–502–8659 (e-mail at (2) * * * paragraph are effective upon activation
public.referenceroom@ferc.gov). (ii) Director of the Office of Energy of the Plan. The Commission will notify
Effective Date and Congressional Markets and Reliability; the public that the Plan has been
Notification * * * * * activated by sending a press release
(v) Director of the Office of announcing that fact to major wire
19. These regulations are effective on Enforcement; services, industry press, and appropriate
July 20, 2006. The provisions of 5 U.S.C. (vi) Deputy Directors, Office of Energy metropolitan area radio stations
801 regarding Congressional review of Markets and Reliability, in order of announcing that the Commission has
Final Rules do not apply to this Final seniority; activated the Plan. The Commission’s
Rule, because the rule concerns agency * * * * * alternative Web site (http://
procedure and practice and will not (viii) Deputy General Counsels, in www.fercalt.gov) will be activated and a
substantially affect the rights of non- order of seniority; notice that the Plan has been activated
agency parties. The Commission finds (ix) Associate General Counsels and will be prominently displayed thereon.
that notice and public procedure are Solicitor, in order of seniority; The alternative Web site will act as a
unnecessary because no new burden or (x) Assistant Directors and Division resource for the press, industry, and
regulatory requirement is imposed on heads, Office of Energy Markets and general public. An additional press
regulated entities or the general public. Reliability; Assistant Directors and release will be sent to appropriate media
For the same reason, the Commission Division heads, Office of Energy outlets when the Plan is deactivated and
finds good cause to waive the customary Projects; Assistant General Counsels; the Commission’s headquarters
30-day notice period before the effective and Assistant Directors and Division constituted, and appropriate
date of this Final Rule. heads, Office of Enforcement; in order of modifications made to the alternative
seniority. Web site.
List of Subjects in 18 CFR Part 376 * * * * * (2) During periods when the
■ 4. Section 376.206 is revised to read Continuity of Operations Plan is
Civil defense, Organization and
as follows: activated, the Commission will continue
functions (Government agencies).
to act on requests to ensure continued
jlentini on PROD1PC65 with RULES

11 Regulations Implementing the National


§ 376.206 Delegation of functions of construction of essential natural gas
certain Commission staff members. facilities with sensitive construction
Environmental Policy Act, Order No. 486, 52 FR
47897 (Dec. 17, 1987), FERC Stats. & Regs. When, by reason of emergency timelines, on Commencement of Service
Regulations Preambles 1986–1990 ¶ 30,783 (1987). conditions, the Secretary, Director of requests, and on completion of dam

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00029 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1
42596 Federal Register / Vol. 71, No. 144 / Thursday, July 27, 2006 / Rules and Regulations

safety work, in a manner consistent with may conflict with a function, rule, § 215 as to whether a State action is
the maintenance of environmental order, tariff, rate schedule or agreement; inconsistent with a reliability standard
protections. The Commission will (9) 60-day period for acting on is required to be made falls during a
further ensure that its personnel are applications for review of a penalty period when the COOP Plan is
available to respond to plant accidents imposed by the ERO for violation of a activated, the effectiveness of the State
or reportable incidents at LNG facilities, reliability standard; action will be deemed to be stayed
and address dam safety, public safety, (10) 45-day Protest period for pending further action by the
and security incidents at jurisdictional protesting Prior Notice Filings, and the Commission.
hydropower projects. Alternate 30-day period for resolving and filing to (h) Suspension of Evidentiary
channels of communication will include withdraw such Protests; Hearings. During periods when the
measures to ensure that these activities (11) 30-day period for acting on Continuity of Operations Plan is
can go forward unhindered. requests for rehearing; and activated, all hearings, prehearing
(b) Standards of conduct for (12) Time periods for acting on conferences, settlement conferences,
transmission service providers. During interlocutory appeals and certified and meetings before administrative law
periods when the Commission’s questions. judges are suspended.
Continuity of Operations Plan is (d) Suspension of certain (i) Enforcement Actions. During
activated, a Transmission Provider requirements. During periods when the periods when the Continuity of
affected by the same emergency Commission’s Continuity of Operations Operations Plan is activated, the
affecting the Commission may, for 30 Plan is activated, requirements for the Commission will not initiate an
days, delay compliance with the following filings, submissions, and enforcement action under section
requirement to report to the notifications are suspended. 210(h)(2) of the Public Utility
Commission each emergency that (1) Filings to comply with Regulatory Policies Act of 1978.
resulted in any deviation from the Commission orders, including orders
[FR Doc. E6–11990 Filed 7–26–06; 8:45 am]
standards of conduct within 24 hours of issued by administrative law judges;
(2) Filings required to be made by a BILLING CODE 6717–01–P
such deviation. If the emergency
prevents a Transmission Provider from date certain under the Commission’s
posting information on the OASIS or regulations or orders;
(3) Motions to intervene and protests, DEPARTMENT OF HEALTH AND
Internet Web site, the Transmission
and notices of intervention; HUMAN SERVICES
Provide may, for 30 days, also delay
(4) Comments responding to proposed
compliance with the requirements of Food and Drug Administration
rulemakings or technical conferences;
§ 358.4(a)(2) of this chapter to post this
(5) Responses to data requests;
information on the OASIS or Internet 21 CFR Part 866
(6) Self-reports of violations;
Web site, as applicable. Upon (7) Responses to staff audit reports;
application by any such Transmission [Docket No. 2006N–0276]
(8) Contacts with the Commission’s
Provider, the Commission may extend Enforcement Hotline; Medical Devices; Immunology and
these periods. (9) Accounting filings required by the Microbiology Devices; Classification of
(c) Tolling of time periods for Commission’s Uniform Systems of Fecal Calprotectin Immunological Test
Commission action. The Commission Accounts; and Systems
tolls, for purposes of further (10) Forms required to be filed by a
consideration, the time period in which date certain. AGENCY: Food and Drug Administration,
the Commission must act on the (e) Acceptance and Suspension of HHS.
following matters if the time period Rate Filings. When the date by which ACTION: Final rule.
during which the Commission would the Commission is required to act on
ordinarily be required to act closes SUMMARY: The Food and Drug
filings made pursuant to section 4 of the
during the period when the Continuity Natural Gas Act, sections 205 of the Administration (FDA) is classifying
of Operations Plan is activated: Federal Power Act, and section 6(e) of fecal calprotectin immunological test
(1) 60-day period to act on requests the Interstate Commerce Act falls during systems into class II (special controls).
for Exempt Wholesale Generator or periods when the Continuity of The special control that will apply to
Foreign Utility Company status; Operations Plan is activated, such these devices is the guidance document
(2) 90-day period for acting on filings shall be deemed to be accepted entitled, ‘‘Class II Special Controls
requests for certification of qualifying and suspended and made effective on Guidance Document: Fecal Calprotectin
facility status; the requested effective date, subject to Immunological Test Systems.’’ The
(3) 60-day period for acting on refund and further order of the agency is classifying these devices into
interlocking directorate applications; Commission. class II (special controls) in order to
(4) 60-day period for acting on Public (f) Electric Reliability Organization provide a reasonable assurance of safety
Utility Holding Company Act Penalties. If the date on which an and effectiveness of these devices.
exemptions and waivers; Electric Reliability Organization Elsewhere in this issue of the Federal
(5) 180-period for acting on imposes a penalty under Federal Power Register, FDA is announcing the
applications under § 203 of the FPA; Act § 215 would take effect falls during availability of a guidance document that
(6) 150-day period for acting on a period when the COOP Plan is will serve as the special control for
intrastate pipeline applications for activated, review of such penalty by the these devices.
approval of proposed rates; Commission shall be deemed to be DATES: This rule is effective August 28,
(7) Period ending 60 days prior to the initiated and the penalty shall be stayed 2006. The classification was effective
Electric Reliability Organization’s (ERO) pending further action of the April 26, 2006.
jlentini on PROD1PC65 with RULES

fiscal year for acting on the ERO’s Commission. FOR FURTHER INFORMATION CONTACT:
budget; (g) Consistency of State action with Deborah Moore, Center for Devices and
(8) 60-day period for acting on reliability standard. If the date by which Radiological Health (HFZ–440), Food
notifications that a Reliability Standard a Commission determination under FPA and Drug Administration, 2098 Gaither

VerDate Aug<31>2005 16:25 Jul 26, 2006 Jkt 208001 PO 00000 Frm 00030 Fmt 4700 Sfmt 4700 E:\FR\FM\27JYR1.SGM 27JYR1

Das könnte Ihnen auch gefallen