Sie sind auf Seite 1von 3

Part Design and Construction of Viaduct of Length 6.

583 Km from Noida city


Activity ID

Classic WBS Layout

Activity Name

Original Start
Duration

09-Sep-15 18:11
Finish

Total
Float

130.00w
10-Aug-15
Part Design and Construction of Viaduct of Length 6.583 Km from Noida
city

04-Feb-18

0.00w

0.00w 10-Aug-15

10-Aug-15

130.00w

0.00w 10-Aug-15

10-Aug-15

0.00w

0.00w 10-Aug-15

10-Aug-15

0.00w

0.00w 10-Aug-15

10-Aug-15

130.00w

AWARD OF THE WORK


Commencement Date
A1000

Date of commencement

Area Handover by Clients


AH1010

Handing over of area for preliminary activities for Viaduct

0.00w 10-Aug-15

10-Aug-15

0.00w

AH1020

Handing over of area for preliminary activities for Stations

0.00w 10-Aug-15

10-Aug-15

130.00w

AH1030

Handing over of area for Casting yard

0.00w 10-Aug-15

10-Aug-15

130.00w

AH1040

Handing over of test pile location - Viaduct

0.00w 10-Aug-15

10-Aug-15

1.47w

AH1050

Handing over of test pile location - Station

0.00w 10-Aug-15

10-Aug-15

0.00w

AH1060

Handing over of hindrance free area for construction for Phase 1

0.00w 10-Aug-15

10-Aug-15

130.00w

AH1070

Handing over of hindrance free area for construction for Phase 2

0.00w 10-Aug-15

10-Aug-15

130.00w

AH1080

Handing over of hindrance free area for construction for Phase 3

0.00w 10-Aug-15

10-Aug-15

130.00w

20.50w 10-Aug-15

31-Dec-15

109.50w

6.00w 10-Aug-15

20-Sep-15

122.60w

6.00w 10-Aug-15

20-Sep-15

122.60w

7.40w 10-Aug-15

30-Sep-15

122.60w

7.40w 10-Aug-15

30-Sep-15

122.60w

15.50w 10-Aug-15

26-Nov-15

114.50w

INITIAL ACTIVITIES
Surveying
S1010

Initial survey of the Alignment

Geo Technical Investgation


GT1010

Geo-Technical Investigation

Utilities & Trees


UT1010

Trees identification

7.40w 10-Aug-15

30-Sep-15

77.10w

UT1040

Approval of tree cutting and (or) transplantation (Arranged by DMRC)

6.00w 24-Aug-15

04-Oct-15

114.50w

UT1050

Tree cutting and (or) transplantation

7.50w 05-Oct-15

26-Nov-15

114.50w

15.50w 14-Sep-15

31-Dec-15

1.47w

6.80w 14-Sep-15

30-Oct-15

1.47w

Initial Pile Load Test


IP1010

Test Pile - Viauduct

IP1020

Test Pile - Station

5.90w 19-Sep-15

30-Oct-15

0.00w

IP1030

Initial pile load test - Viaduct

11.50w 12-Oct-15

31-Dec-15

1.47w

IP1040

Initial pile load test - Station

10.50w 17-Oct-15

30-Dec-15

0.00w

52.90w 10-Aug-15

13-Aug-16

77.10w

52.90w 10-Aug-15

13-Aug-16

77.10w

52.90w 10-Aug-15

13-Aug-16

77.10w

51.90w 10-Aug-15

06-Aug-16

78.10w

ENGINEERING
Design & Drawing
Viaduct
Submission of Design & Drawings
S.D.1010

Submission of Span Configuration pier location

0.30w 14-Sep-15

15-Sep-15

77.10w

S.D.1020

Submission of Span Configuration pier location with vertical alignment

2.10w 15-Sep-15

30-Sep-15

121.70w

S.D.1030

Submission of design, drawing for foundation

18.00w 26-Oct-15

28-Feb-16

3.47w

S.D.1040

Submission of design, drawing for Sub-Structure

40.00w 31-Oct-15

06-Aug-16

77.10w

S.D.1050

Release of design, drawing for Segment casting

Approval of Design & Drawings

5.20w 10-Aug-15

15-Sep-15

124.80w

47.60w 15-Sep-15

13-Aug-16

77.10w

A.D.1060

Approval of Span Configuration pier location

2.10w 15-Sep-15

30-Sep-15

122.60w

A.D.1070

Approval of Span Configuration pier location with vertical alignment

2.00w 22-Sep-15

06-Oct-15

121.70w

A.D.1080

Approval of design, drawing for foundation

18.00w 02-Nov-15

06-Mar-16

100.00w

A.D.1090

Approval of design, drawing for Sub-Structure

40.00w 07-Nov-15

13-Aug-16

77.10w

13.50w 02-Sep-15

05-Dec-15

113.10w

For Station by Client


A.D.1110

Release of details/drawings for foundations -Station

4.00w 31-Oct-15

28-Nov-15

1.00w

A.D.1120

Release of details/drawings for Substructure -Station

4.00w 07-Nov-15

05-Dec-15

113.10w

A.D.1130

Release of details/drawings for Superstructure -Station

MOBILIZATION
Installations

2.00w 02-Sep-15

16-Sep-15

124.60w

26.00w 10-Aug-15

07-Feb-16

104.00w

17.10w 10-Aug-15

07-Dec-15

112.90w

IS.1120

Precasting Yard Installation

16.00w 10-Aug-15

29-Nov-15

114.00w

IS.1130

First batching plant mobilization/installation

10.00w 10-Aug-15

19-Oct-15

112.90w

IS.1140

Second batching plant mobilization/installation

10.00w 28-Sep-15

07-Dec-15

112.90w

KD.V. 010

KEY DATE 1 : SUBMISSION OF CONSTRUTION PROGRAMME, ESTABLISHING


0.00w
SITE OFFICE

13-Sep-15

125.00w

KD.V. 020

KEY DATE 2 : COMMISIONING OF 1ST BATCHING PLANT

0.00w

19-Oct-15

119.90w

KD.V. 040

KEY DATE 4 : COMMISIONING OF 2ND BATCHING PLANT

0.00w

07-Dec-15

112.90w

24.00w 24-Aug-15

07-Feb-16

32.00w

Enabling Works
E.W.1150

Fabrication of shuttering sets (Pile cap/Pier/Pier Cap)

24.00w 24-Aug-15

07-Feb-16

32.00w

E.W.1160

Fabrication of shuttering sets (Segment casting)

12.00w 24-Aug-15

15-Nov-15

40.00w

KD.V. 030

KEY DATE 3: COMPLETION FO 1ST FORMAWORK OF BOX GIRDER PRODUCTION


0.00w LINE FOR ENGINEER'S
22-Nov-15 APPROVAL
41.00w

CONSTRUCTION

116.10w 14-Nov-15

04-Feb-18

0.00w

78.00w 28-Dec-15

25-Jun-17

32.00w

A1120

Segment Casting

70.00w 28-Dec-15

30-Apr-17

40.00w

A1130

Parapet Casting

70.00w 22-Feb-16

25-Jun-17

32.00w

KD.V. 060

KEY DATE 6 :START OF CASTING OF BOX GIRDERS/SEGMENT

28-Dec-15

110.00w

103.00w 07-Dec-15

26-Nov-17

10.00w

71.03w 07-Dec-15

17-Apr-17

41.97w

Precasting Works

Elevated Viaduct
Viaduct - Phase 1 ( CH: 0000 - 2100 , TOTAL 2100 M of viaduct)

0.00w

KD.V. 050

KEY DATE 5 :COMPLETION OF 1ST WORKING PILE

0.00w

07-Dec-15

113.00w

KD.V. 070

KEY DATE 7 :START OF LAUNCHING OF BOX GIRDERS/SEGMENT

0.00w

28-Apr-16

92.47w

KD.V. 080

KEY DATE 8 :START OF LAUNCHING OF PARAPETS

0.00w

09-Jun-16

86.47w

KD.V. 090

KEY DATE 9 :PARTIAL ACCESS OF THE VIADUCT ( MINIMUM 2 KM IN ONE0.00w


STRETCH) FOR LAYING
17-Apr-17
TRACK

P1. 1010

Piling

20.53w 07-Dec-15

28-Apr-16

1.47w

P1. 1020

Pile Caps

23.00w 04-Jan-16

12-Jun-16

6.00w

P1. 1030

Pier

27.00w 25-Jan-16

31-Jul-16

6.00w

P1. 1040

Pier Caps

32.00w 22-Feb-16

02-Oct-16

6.00w

P1. 1050

Segment launching

39.00w 28-Apr-16

26-Jan-17

1.47w

P1. 1060

Parapet Erection

39.00w 09-Jun-16

09-Mar-17

1.47w

P1. 1070

Miscellaneous works

28.00w 29-Sep-16

13-Apr-17

1.47w

72.00w 14-Dec-15

30-Apr-17

40.00w

Viaduct - Phase 2 (CH:2100.00- ch: 4666.611 , TOTAL 2566.71 Meter of viaduct)

41.97w

P2. 1080

Piling

25.00w 14-Dec-15

05-Jun-16

10.00w

P2. 1090

Pile Caps

28.00w 11-Jan-16

24-Jul-16

10.00w

P2. 1100

Pier

33.00w 08-Feb-16

25-Sep-16

10.00w

P2. 1110

Pier Caps

39.00w 07-Mar-16

04-Dec-16

10.00w

Page 1 of 3

TASK filter: All Activities


Oracle Corporation

Part Design and Construction of Viaduct of Length 6.583 Km from Noida city
Activity ID

Activity Name

Classic WBS Layout


Original Start
Duration

09-Sep-15 18:11
Finish

Total
Float

P2. 1120

Segment launching

38.00w 02-May-16

22-Jan-17

40.00w

P2. 1130

Parapet Erection

42.00w 13-Jun-16

02-Apr-17

40.00w

P2. 1140

Miscellaneous works

30.00w 03-Oct-16

30-Apr-17

40.00w

99.30w 01-Jan-16

26-Nov-17

10.00w

Viaduct - Phase 3 (CH: 4666.61 - 6820.843 , TOTAL 2154.23 Meter of viaduct)


KD.V. 100

KEY DATE 10 :FULL ACCESS OF THE VIADUCT INCLUDING G.I.HANGERS 0.00w


FOR LAYING OF TRACK
17-Jul-17
AND CABLE28.90w

P3. 1080

Piling

28.00w 01-Jan-16

15-Jul-16

65.30w

P3. 1090

Pile Caps

32.00w 29-Jan-16

09-Sep-16

65.30w

P3. 1100

Pier

36.00w 26-Feb-16

04-Nov-16

65.30w

P3. 1110

Pier Caps

42.00w 07-Mar-16

25-Dec-16

58.00w

P3. 1120

Segment launching

42.00w 02-May-16

19-Feb-17

10.00w

P3. 1130

Parapet Erection

48.00w 27-Jun-16

28-May-17

10.00w

P3. 1140

Miscellaneous works

48.00w 26-Dec-16

26-Nov-17

10.00w

116.10w 14-Nov-15

04-Feb-18

0.00w

55.00w 15-Jan-17

04-Feb-18

0.00w

0.00w 15-Jan-17

15-Jan-17

55.00w

0.00w

15-Jan-17

55.00w

07-May-17

39.00w

Stations
KEY DATE FOR STATION
KEY DATE 1
KDS. 010

PARTIAL ACCESS TO E&M CONTARCTOR

10.00w 26-Feb-17

KEY DATE 2
KDS. 02010

FOR ANY TWO STATIONS

0.00w

26-Feb-17

49.00w

KDS. 02020

FOR NEXT ANY TWO STATIONS

0.00w

02-Apr-17

44.00w

KDS. 02030

FOR BALANCED TWO STATIONS

0.00w

07-May-17

39.00w

6.00w 18-Jun-17

30-Jul-17

27.00w

KEY DATE 3
KDS. 3010

FOR ANY TWO STATIONS

0.00w

18-Jun-17

33.00w

KDS. 3020

FOR NEXT ANY TWO STATIONS

0.00w

25-Jun-17

32.00w

KDS. 3030

FOR BALANCED TWO STATIONS

0.00w

30-Jul-17

27.00w

3.00w 18-Jun-17

09-Jul-17

30.00w

KEY DATE 4
KDS. 4010

FOR ANY TWO STATIONS

0.00w

18-Jun-17

33.00w

KDS. 4020

FOR NEXT ANY TWO STATIONS

0.00w

25-Jun-17

32.00w

KDS. 4030

FOR BALANCED TWO STATIONS

0.00w

09-Jul-17

30.00w

3.00w 14-May-17

04-Jun-17

35.00w

KEY DATE 5
KDS. 5010

FOR ANY TWO STATIONS

0.00w

14-May-17

38.00w

KDS. 5020

FOR NEXT ANY TWO STATIONS

0.06w 29-May-17

29-May-17

35.94w

KDS. 5030

FOR BALANCED TWO STATIONS

0.00w

04-Jun-17

35.00w

21-May-17

37.00w

11.00w 05-Mar-17

KEY DATE 6
KDS. 6010

FOR ANY TWO STATIONS

0.00w

05-Mar-17

48.00w

KDS. 6020

FOR NEXT ANY TWO STATIONS

0.00w

09-Apr-17

43.00w

KDS.6030

FOR BALANCED TWO STATIONS

0.00w

21-May-17

37.00w

0.00w 04-Feb-18

04-Feb-18

0.00w

0.00w

04-Feb-18

0.00w

KEY DATE 7
A1170

KD3: COMPLETION OF ENTIRE WORK AS PER CONTRACT

59.00w 14-Nov-15

31-Dec-16

0.00w

P1. 1080

Piling

12.00w 14-Nov-15

06-Feb-16

0.00w

P1. 1090

Pile Caps

13.00w 12-Dec-15

12-Mar-16

0.00w

P1. 1100

Pier

13.00w 09-Jan-16

09-Apr-16

0.00w

P1. 1110

Arm at consourse slab

32.00w 06-Feb-16

17-Sep-16

0.00w

P1. 1120

Concourse Slab

32.00w 06-Feb-16

17-Sep-16

0.00w

P1. 1130

Arm at Track Slab

32.00w 02-Apr-16

12-Nov-16

0.00w

P1. 1140

Track Slab

32.00w 02-Apr-16

12-Nov-16

0.00w

P1. 1150

Platform slab & Misc Struture

32.00w 02-Apr-16

12-Nov-16

0.00w

P1. 1160

Finishing Work

39.00w 02-Apr-16

31-Dec-16

0.00w

59.00w 28-Nov-15

14-Jan-17

55.10w

Station - 34

Station - 52
P1. 1980

Piling

12.00w 28-Nov-15

20-Feb-16

14.10w

P1. 1990

Pile Caps

13.00w 26-Dec-15

26-Mar-16

23.10w

P1. 2000

Pier

13.00w 23-Jan-16

23-Apr-16

23.10w

P1. 2010

Arm at consourse slab

32.00w 20-Feb-16

01-Oct-16

23.10w

P1. 2020

Concourse Slab

32.00w 20-Feb-16

01-Oct-16

23.10w

P1. 2030

Arm at Track Slab

32.00w 16-Apr-16

26-Nov-16

30.10w

P1. 2040

Track Slab

32.00w 16-Apr-16

26-Nov-16

55.10w

P1. 2050

Platform slab & Misc Struture

32.00w 16-Apr-16

26-Nov-16

55.10w

P1. 2060

Finishing Work

39.00w 16-Apr-16

14-Jan-17

55.10w

62.00w 12-Dec-15

18-Feb-17

50.10w

Station - 62
P1. 2070

Piling

12.00w 12-Dec-15

05-Mar-16

14.10w

P1. 2080

Pile Caps

13.00w 09-Jan-16

09-Apr-16

14.10w

P1. 2090

Pier

13.00w 06-Feb-16

07-May-16

14.10w

P1. 2100

Arm at consourse slab

32.00w 05-Mar-16

15-Oct-16

14.10w

P1. 2110

Concourse Slab

32.00w 05-Mar-16

15-Oct-16

14.10w

P1. 2120

Arm at Track Slab

32.00w 30-Apr-16

10-Dec-16

28.10w

P1. 2130

Track Slab

32.00w 30-Apr-16

10-Dec-16

28.10w

P1. 2140

Platform slab & Misc Struture

32.00w 30-Apr-16

10-Dec-16

50.10w

P1. 2150

Finishing Work

42.00w 30-Apr-16

18-Feb-17

50.10w

76.00w 13-Feb-16

29-Jul-17

27.10w

Station - 59
P1. 2160

Piling

12.00w 13-Feb-16

07-May-16

44.10w

P1. 2170

Pile Caps

13.00w 19-Mar-16

18-Jun-16

43.10w

P1. 2180

Pier

13.00w 16-Apr-16

16-Jul-16

43.10w

P1. 2190

Arm at consourse slab

32.00w 03-Sep-16

15-Apr-17

27.10w

P1. 2200

Concourse Slab

32.00w 03-Sep-16

15-Apr-17

27.10w

P1. 2210

Arm at Track Slab

32.00w 29-Oct-16

10-Jun-17

27.10w

P1. 2220

Track Slab

32.00w 29-Oct-16

10-Jun-17

27.10w

P1. 2230

Platform slab & Misc Struture

32.00w 29-Oct-16

10-Jun-17

27.10w

P1. 2240

Finishing Work

39.00w 29-Oct-16

29-Jul-17

27.10w

78.00w 27-Feb-16

26-Aug-17

23.10w

Station - 61
S62. 1610

Piling

12.00w 27-Feb-16

21-May-16

36.10w

S62. 1620

Pile Caps

13.00w 02-Apr-16

02-Jul-16

35.10w

Page 2 of 3

TASK filter: All Activities


Oracle Corporation

Part Design and Construction of Viaduct of Length 6.583 Km from Noida city
Activity ID

Activity Name

Classic WBS Layout


Original Start
Duration

09-Sep-15 18:11
Finish

Total
Float

S62. 1630

Pier

13.00w 30-Apr-16

30-Jul-16

35.10w

S62. 1640

Arm at consourse slab

34.00w 17-Sep-16

13-May-17

23.10w

S62. 1650

Concourse Slab

34.00w 17-Sep-16

13-May-17

23.10w

S62. 1660

Arm at track slab

34.00w 12-Nov-16

08-Jul-17

30.10w

S62. 1670

Track Slab

34.00w 12-Nov-16

08-Jul-17

30.10w

S62. 1680

Platform slab & Misc Struture

34.00w 12-Nov-16

08-Jul-17

30.10w

S62. 1690

FInishing Work

39.00w 26-Nov-16

26-Aug-17

23.10w

85.00w 12-Mar-16

28-Oct-17

14.10w

Station - Electronic City


P1. 1710

Piling

12.00w 12-Mar-16

04-Jun-16

27.10w

P1. 1720

Pile Caps

13.00w 16-Apr-16

16-Jul-16

26.10w

P1. 1730

Pier

13.00w 14-May-16

13-Aug-16

26.10w

P1. 1740

Arm at consourse slab

34.00w 01-Oct-16

27-May-17

14.10w

P1. 1750

Concourse Slab

34.00w 01-Oct-16

27-May-17

14.10w

P1. 1760

Arm at Track Slab

34.00w 26-Nov-16

22-Jul-17

28.10w

P1. 1770

Track Slab

34.00w 26-Nov-16

22-Jul-17

28.10w

P1. 1780

Platform slab & Misc Struture

34.00w 26-Nov-16

22-Jul-17

28.10w

P1. 1790

Finishing Work

42.00w 07-Jan-17

28-Oct-17

14.10w

130.00w 10-Aug-15

04-Feb-18

0.00w
1.47w

HANDING OVER
A1140

Handing over of viaduct

40.00w 20-Apr-17

25-Jan-18

A1150

Handing over of station

53.10w 28-Jan-17

04-Feb-18

0.00w

KD.S.070

KEY DATE 7 : STATION: COMPLETON OF ENTIRE WORK AS PER CONTRACT.


0.00w

10-Aug-15

130.00w

KD.V.110

KEY DATE 11: VIADUT: COMPLETION OF ENTIRE WORK AS PER CONTRACT


0.00w

25-Jan-18

1.47w

Page 3 of 3

TASK filter: All Activities


Oracle Corporation

Das könnte Ihnen auch gefallen