Beruflich Dokumente
Kultur Dokumente
Faster Procurement
Procurement Process Study Report
Contents
1
2
3
4
5
6
Executive Summary
Introduction
Scope
Approach
The Macro Environment
The Critical Path Model
6.1
The Critical Path in IT-enabled Business Change Projects
6.2
Stage 0 Pre-Advertisement Preparation
6.3
Stage 1 advertisement to Proposals
6.4
Stage 2 Proposals to Negotiation
6.5
Stage 3 Negotiation to Award
7 The Critical Path in PFI Construction Related Projects
8 Application of Lean Principles
9 Opportunities from e-Procurement solutions
10
Conclusions
11
Acknowledgments
Annex A Process Recommendations
Annex B - CP for IT-enable Projects
Annex C - CP for Construction Projects
3
4
4
5
5
8
8
11
13
15
16
18
20
20
21
21
22
26
27
Page 2
Executive Summary
1.1
In December 2003 the Cabinet Office Regulatory Impact Unit and OGC
published a joint report entitled, Making A Difference Reducing
Bureaucracy in Central Civil Government. This captured a concern of
the procurement community that there was insufficient guidance from
OGC on actions that could be taken to reduce procurement timescales.
An action1 was published in the report for OGC to carry out a study of
the procurement process between advertisement and award to identify
such actions.
1.2
1.3
1.4
This report represents the current state of play in looking at how the
procurement process can be developed and improved for the benefit of
projects. The annexes include two critical path (CP) diagrams to
illustrate the activities required for a procurement using the Negotiated
Procedure for an IT-enabled project and for a Construction PFI project.
They were compiled with the advice and experience from departmental
Centres of Excellence and projects, and several OGC areas: Property
and Construction, Consultancy, Procurement, Best Practice and Legal.
1.5
The report will be posted on the OGC web site. Feedback on the
approach and suggestions for improvements will be sought in order to
develop the ideas still further.
OGC, in consultation with departments and industry, will carry out a study of the procurement
process, to identify further actions that departments can take to streamline the process and to reduce
planned procurement timescales OGC and Cabinet Office RIU, Making A Difference Reducing
Bureaucracy in Central Civil Government. December 2003.
Page 3
Introduction
2.1
2.2
There are two primary drivers behind the work. Firstly, concerns that
delays at the tendering stage could delay the achievement of a
departments objectives. Secondly to address suppliers concerns
about the effects on bid costs of elongated procurement timescales.
2.3
Previous work has focused on the external issues which impact upon
the time tendering takes such as skills and capabilities, approach to
risk, cultural issues, leadership and commitment. Where this work
differs is that it seeks to examine the internal or process related
issues, the actual activities that take place between advertisement and
award.
2.4
These issues are not new. The Total Acquisition Process Services
Guide published in 1995 was based on five underlying principles, one
of which was, procurement procedures should meet Departments
needs for short procurement timescales and an acceptable demand on
resources, and Industrys need for a cost-efficient bid process. That
there is still concern about these issues demonstrates that more needs
to be done to embed good practices.
Scope
3.1
The focus of this work is large complex projects, in the context of the
government-wide target2 to make procurement timescales more
predictable and to reduce the average time for government projects
between the OJEU advertisement and award of contract by 25%, on
projects currently taking more than a year.
3.2
Departments to work with OGC to make procurement timescales more predictable and to reduce the
average time for government projects between the OJEU notice and award of contract by 25%, on
projects currently taking more than a year, taking 2002/3 as the baseline. OGC and Cabinet Office RIU,
Making A Difference Reducing Bureaucracy in Central Civil Government. December 2003.
Page 4
3.3
4.1
4.2
4.3
5.1
5.2
Page 5
5.3
5.4
5.5
5.6
Page 6
Project
Conception
Requirement
Development
Project
Initiation
Award
Handover to
Contract Mgr
Transition
Period
Advert
Project
Closure
Implementation
Procurement
Figure 1. Simple Tendering in a linear Project
5.7
Vendor
Appraisal
Project Conception /
Identification of Need
or Recompetition
Project
Initiation
Contract
Management
Requirement
Development
Market Sourcing
Benefits
Realisation
Strategic
Procurement
Cycle
Implementation
Transition
Period
Identification of Key
Commercial Issues
Early Supplier Engagement /
Feasibility Testing
Award of
Contract
Tendering
OJEU
Advert
5.8
5.9
Page 7
6
6.1
Feasibility Study
Development of Requirements
Evaluation of Proposals
Contract Management
Project Review
Page 8
6.1.4 It is the very large procurement projects that risk having a procurement
timetable extending beyond 12 months, risking delays to the delivery of
major government programmes and resulting in large bid costs for
suppliers. Bid costs can be in excess of 1million. Part of the reason
that these projects can take so long is that the complexity of the
requirement means it is difficult to pin down sufficiently to enable
successful pricing by potential suppliers without a degree of discussion
and agreement between the client and supply side. In these
circumstances the European Public Procurement Directives provide for
such discussion by way of the Negotiated Procedure. The use of the
Negotiated Procedure is exceptional and should not be considered the
norm.
6.1.5 The Negotiated Procedure provides the outline framework within which
most of these large complex procurement projects are carried out.
Within this framework a good deal of variations are possible, including
such options as: the use of a study period; provision for outline
proposals; and, the use of preferred bidder status. These options can
add time to an already lengthy process. Preferred bidder status may
reduce timescales but has a significant risk of reducing competitive
pressure and is best avoided on IT-enabled projects. However the
need for such options may be obviated by better preparation before
OJEU advertisement, e.g. thorough development of requirements;
understanding the related commercial issues; and identifying
appropriate financial models.
6.1.6 A new consolidated procurement directive has been adopted which
member states have to implement by 31 January 2005. This will
include a new procedure, the competitive dialogue procedure, which
will be available when the nature of the requirement means that the
open or restricted procedures would not be appropriate. The new
procedure will allow contracting authorities to enter into discussions
with bidders on aspects of the procurement, such as the best technical
or financial solution to meet their needs. When the directive is
implemented the competitive dialogue procedure should be used in
preference to the negotiated procedure. As with the negotiated
procedure, there will be a requirement for a minimum of three tenderers
to enter into the competitive dialogue. Timescales are the same, with
37 days for expressions of interest and no set time for the competitive
dialogue itself. However there will be reductions from the 37 days for
procurements where the OJEU notices are compiled and transmitted
electronically and where tender documentation is available on line.
6.1.7 The critical path being examined here is based on a simple or
standard interpretation of the Negotiated Procedure. It is intended to
represent the timescale in which most complex procurements could be
carried out. Naturally there will be those which are faster and those
which take longer to ensure they result in a sound and deliverable
Page 9
Page 10
6.2
Page 11
See also: Market Sounding Guidance to be found in the SDTK on the OGC web site
Page 12
6.3
6.3.1 In the negotiated procedure there are only two timescales imposed by
the EU Directives (negating the popular myth that it is the imposition of
EU timescales that results in long procurements!), a minimum period of
37 days from the date of despatch of the advertisement to the Official
Journal to the close of Expressions of Interest (EOIs). The other is the
requirement to publish an award notice in the official journal within a
maximum of 48 days after award of contract.
6.3.2 In more straightforward procurements it may be that enough technical
criteria can be specified in the advertisement to enable the client to
select suppliers. However, more usual in large and complex
procurements is the use of some form of Pre-Qualification
Questionnaire (PQQ) to gather enough information about each supplier
to enable the client to make a decision about which suppliers to take
forward.
6.3.3 The use of a web site to publish the PQQ information required could
help to reduce the time it takes to gather this information by alerting
suppliers to the information requirements earlier. A reference to the
web site can be given in the advertisement narrative enabling suppliers
to submit this information alongside their EOI rather than the client
waiting for the deadline for receipt of all EOIs before sending out PQQ
information requests. This has been done successfully on a number of
projects although the approach may carry an element (albeit small) of
risk.
6.3.4 Client organisations will be keen for suppliers to register interest early.
One way of achieving this would be to require the suppliers to complete
a simple registration form on the web site which would be automated to
respond with the sending out of the PQQ information request. An
alternative to this would be to refer to an email address in the
advertisement narrative, which suppliers would then apply to for the
PQQ information request. The disadvantage of this approach being that
it relies on someone in the client organisation manually checking and
responding to applications from suppliers which takes time and
removes a resource from other work.
6.3.5 A concern about this approach may be that any supplier which does
not become aware of the advertisement until shortly before the closing
date may not have sufficient time before the deadline to retrieve the
PQQ information request, collate the information and submit it. It is
recommended that the deadline for receipt of PQQ information be set
at 7 days after the deadline for receipt of EOIs in response to the
advertisement.
6.3.6 Evaluation of PQQ information should not take a significant amount of
time. Information requested at this stage can only be in relation to track
Page 13
Process Recommendation 8
Consider referencing the PQQ in the OJEU advertisement with a web link to
an automated registration and response to enable suppliers to rapidly access
the PQQ information request.
Process Recommendation 9
Where the above approach to PQQ is adopted, the deadline for receipt of
PQQ responses should be set at 7 days after the deadline for receipt of EOIs.
Page 14
6.4
6.4.1 Once the project board has approved the long list decision, invitations
to submit proposals can be issued to a minimum of 3 bidders.
6.4.2 While suppliers are preparing proposals a considerable amount of work
is taking place to build up their understanding of the requirement and
the business and technical environment in which the solution must
operate. It is usual for each supplier at this stage to undertake a series
of meetings with directors, the business unit staff, IT technical staff, key
stakeholders and the commercial team. Wherever possible such
meetings should be run in parallel by encouraging the suppliers bid
teams to use only the appropriate people in each meeting. For example
a commercial and technical meeting can be run in parallel with the legal
and commercial team attending the former and the technical team the
latter. A suppliers entire bid team can then come together outside of
engagement between the parties to review progress. This can help to
reduce what can be a long process.
6.4.3 It has also been suggested that the use of a specific individual in the
client organisation to co-ordinate correspondence, meeting notes etc
for each supplier can be a useful way of coping with the inevitable
complexity of carrying out such a process with a number of bidders.
6.4.4 Another time-consuming issue is the handling of specific questions
raised by suppliers and making responses available to all bidders to
ensure fairness and equal treatment between bidders. Questions such
as this can arise not only within specific meetings but also result in
numerous emails and phone calls that require tracking, response and
corresponding information to other bidders. A solution is to use an
electronic web-based bulletin board that can be securely accessed by
each supplier to enable them to post questions or issues for
clarification. These can then be considered and responded to by the
client-side team and if appropriate responses posted for all bidders to
see. Time can be saved in this way and in addition an audit trail of
clarification questions and answers created.
6.4.5 Investigation suggests 60 days is reasonable in most cases.
6.4.6 This is followed by a formal evaluation of proposals and usually
indicative pricing. At this stage of evaluation it is usual to include
suppliers presentation of their proposals and where appropriate
external site visits during an indicative 31 day evaluation period.
6.4.7 This is followed by a second project board approval point as this is an
opportunity to deselect any bidders that at this point are clearly not
going to be in a position to provide a competitive solution. This should
take no more than 7 days and result in an agreed list of bidders to
invite to negotiate.
Page 15
Process Recommendation 10
Run suppliers clarification meetings in parallel wherever possible to enable
more rapid exploration of issues in specific areas.
Process Recommendation 11
Assign a different individual in the client organisation to co-ordinate
correspondence, meeting notes etc for each supplier.
Process Recommendation 12
Use a Q&A electronic bulletin board to deal with clarification questions and
answers during clarification and proposal development.
6.5
Page 16
Page 17
Process Recommendation 13
Use the Decision Map Key Commercial Principles to identify and prioritise the
key commercial issues in consultation with bidders and tackle these at the
outset of negotiations.
Process Recommendation 14
Use standard contract terms/model agreements and precedent clauses
developed by OGC.
Process Recommendation 15
Develop and use a consistent departmental approach to provide a common
look and feel to contract negotiation. This should explore options for tackling
key commercial issues.
Process Recommendation 16
Develop a standard or typical approach to drafting a services schedule to the
contract.
6.5.11 There is a legal requirement to post an Award Notice in the Official
Journal within 48 days of the award of contract. Background research
associated with this work to measure the tendering period of major
procurement projects has demonstrated that a significant number of
projects do not post an award notice despite the legal requirement to
do so.
Initial work carried out by this team to break down tendering timescales
on construction related PFI contracts has shown that there are
significant differences compared with complex IT-enabled projects.
Currently there are clear reasons, as documented below, that PFI
procurement takes longer than 12 months. 18 months is more typical.
More work is required if opportunities to reduce this typical timescale
are to be identified and this can only be done in close liaison with
Industry. Feedback suggests that there is some appetite in Industry to
tackle the issue.
7.2
Page 18
In the two projects under 12 months the build elements were both
straightforward new builds, less than 25 million in value, with
established site ownership, surveyed and subjected to Environmental
Impact Assessment (EIA) prior to competition, and with outline planning
permission approved. While a timescale of less than 12 months
appears possible on occasional straightforward new builds, it is not
usual. Experience suggests that where externalities do not intervene it
is reasonable to expect PFI construction projects to complete the
tendering process in no more than 18 months.
7.4
7.5
The key difference is that up to 70% of the total capital outlay by the
supplier is in the design phase. This outlay includes architects,
surveyors, project management and so on. Under current processes
this design work is done by the contractor at their own risk before
award of contract. Consequently it is usual to use preferred bidder
status in PFI Construction projects to select a single preferred
contractor as early as possible. Then to allow that contractor to carry
out the detailed design work with a reduced risk of not being awarded
the contract (notwithstanding the significant work at this stage to
consider the full extent of the service beyond construction). This
approach is more workable in PFI construction than in IT procurement
because a great deal more of the input costs are quantifiable and
consequently quite detailed bills of quantities can be worked up at an
earlier stage in the design process. As a result around 90% of the final
price is known before moving to a single supplier in preferred bidder
status. However for the preferred bidder around 50% - 60% of the
design cost is incurred in the stage between notification of preferred
bidder status and award of contract. Therefore during the competitive
stage and before the preferred bidder is announced, suppliers are
expected to outlay around 10-20% of the total capital cost at significant
risk of not winning the business. It quickly becomes apparent that
without the use of the preferred bidder option few if any contractors
would bid for the business.
7.6
7.7
Page 19
projects into very large deals can provide better value for money in the
long run, however the complexities of running a procurement for a
multi-site contract can result in additional time spent at the tendering
stage. This may still however result in less overall procurement time,
and less duplication of effort, than if such a deal had been broken down
into a number of smaller procurements.
7.8
One proposal discussed within OGC at the outset of this work was that
we consider whether the principles of lean-thinking had anything to
offer the Faster Procurement work in terms of process efficiency.
8.2
8.3
8.4
It seems likely that if the Lean principles have something to offer public
procurement, it will be in the lower to medium complexity
procurements. This is where issues are sufficiently broad ranging to
make automation not practical but where there is still a strong element
of process. The emphasis on removal of waste is universally relevant
and should not be forgotten in any procurement project.
Page 20
9.2
While they will not replace face to face meetings on these projects,
these solutions can help with handling the development and iterations
of the requirement, the posting and sharing of clarification questions
and responses, and the development and review of contractual
documentation.
9.3
9.4
The value for money benefits and timesaving offered by greater use of
e-procurement systems are significant and OGC has already done
much work to promote the use of such systems. Implementation of eprocurement systems in departments depends on a greater
understanding and appreciation of the benefits at both ends of the
scale; low value commodity purchases as well as high value, high risk
complex projects.
10
Conclusions
10.1
10.2
A key point to emerge from this work is the need to ensure much
greater integration between procurement and project management on
these complex projects. The perception of procurement as little more
than the tendering stage of a procurement project may be a significant
factor in failures to consider key commercial and evaluation issues prior
to engagement with the market.
10.3
11
Acknowledgments
11.1
Thanks are due to a great many people who have contributed thoughts,
ideas and experiences to enable this study to be carried out. Particular
thanks must go to Turner and Townsend Group as the source of much
of the PFI Construction knowledge, experience and ideas discussed.
Page 21
Early use of the Decision Map to consider key commercial issues before formally
commencing tendering.
Use Prior Information Notices in the Official Journal to alert the market to upcoming
requirements.
Obtain assurance of business and financial approval before advertisement placement.
7
8
Consider referencing the PQQ in the OJEU advertisement with a web link to an
automated registration and response to enable suppliers to rapidly access the PQQ
information request.
Where the above approach to PQQ is adopted, the deadline for receipt of PQQ
responses should be set at 7 days after the deadline for receipt of EOIs.
10
Run suppliers clarification meetings in parallel wherever possible to enable more rapid
exploration of issues in specific areas.
11
12
Use a Q&A electronic bulletin board to deal with clarification questions and answers
during clarification and proposal development.
13
14
15
Use the Decision Map Key Commercial Principles to identify and prioritise the key
commercial issues in consultation with bidders and tackle these at the outset of
negotiations.
Use standard contract terms/model agreements and precedent clauses developed by
OGC.
Develop and use a consistent departmental approach to provide a common look and
feel to contract negotiation. This should explore options for tackling key commercial
issues.
Develop a standard or typical approach to drafting a services schedule to the contract.
16
Issue advert
Issue Qualification Criteria
Assumptions:
58 days
Draft documentation should be prepared before advert to ensure process runs smoothly
Refer to report for outline of pre-advert activities necessary before readiness to proceed
Times are elapsed defined as in European Directive 92/50/EEC
37 day
Key:
(< 12 months)
Clarification, hold
open days, reply
to questions
7dy
Milestone - Deadline for receipt of suppliers proposals
60 days
Parallel activity
31 days
Programme/Project activity
Issue ITNs & notify any de-selected bidders
7dy
Project Board
approval to proceed
7dy
120 days total
14 days
Evaluation of proposals
An opportunity to de-select further
any unsuitable proposals
7dy
Deadline for BAFOs
Debrief
unsuccessful
candidates
Project Board
approval to proceed
7dy
Finalise
evaluation
model
7dy
Evaluation Decision
21 days
Project Board
approval of
BAFO invites
Award of Contract
Supplier
preparation
& submission
of BAFOs
3dy
14d
Gateway 3
Investment Decision
Stage 1
Stage 2
Stage 3
7dy
48 days
Stage 0
Debrief unsuccessful
candidates
Post Award
Notice
Issue advert
Issue Qualification Criteria
Assumptions:
Deadline for receipt of EOIs (unless accelerated)
Draft documentation should be prepared before advert to ensure process runs smoothly
Refer to report for outline of pre-advert activities necessary before readiness to proceed
Times are elapsed defined as in European Directive 92/50/EEC
37 day
7dy
45d
Finalise docs, hold
open days, provide
MOIs
Key:
5dy
7dy
Deadline for receipt of Proposals
Evaluate EOIs
and / or PQQs
(< 18 months)
Parallel activity
100 days
Programme/Project activity
50 days
Project Board
approval to proceed
Debrief unsuccessful
candidates
90 days total
Evaluation of BAFOs
30dys
7dy
90 days
Evaluation decision
Project Board approval of
Preferred bidder decision
160 days
3dy
Award of
Contract
7dy
48 days