Beruflich Dokumente
Kultur Dokumente
Coastal Engineering
journal homepage: www.elsevier.com/locate/coastaleng
a r t i c l e
i n f o
Article history:
Received 30 June 2013
Received in revised form 23 November 2013
Accepted 11 December 2013
Available online 7 January 2014
Keywords:
Sea level rise
Revetments
Upgrading concepts
a b s t r a c t
The paper presents a design exercise of upgrading a typical rock armoured revetment by modifying the structure
prole and adding structure elements. Several concepts of upgrading are examined. A sea level rise corresponding to the mean of the IPCC 2007 predictions is used together with a slight increase in long-term wind/wave
conditions as predicted for the North Sea by the Danish Coastal Authority. Both conditions of non-acceptable
and acceptable increase in structure crest level are considered. Moreover, a scenario for steepening of the foreshore due to morphological changes caused by increased wave impacts is included. Only desk study tools are
used for the upgrade designs. A simple comparative cost optimization analysis of the various upgrading solutions
is presented, and conclusions are given for the preferred upgrading concept valid for the case study structure. A
short discussion of the uncertainties related to upgrading design is included. The importance of physical model
tests of the structures is underlined due to insufcient desk study tools for rubble mound upgrade design.
2013 Elsevier B.V. All rights reserved.
1. Introduction
Climate change might cause sea level rise and increase in the intensity of storms. Both phenomena will increase the risk of ooding
of low lying areas, accelerate erosion of exposed soft beaches, and
cause damage to existing coastal protection structures. This makes
it necessary to upgrade the structures so they comply with the
original design performance criteria. Upgrading can be done by
modifying the structure prole and/or adding structure elements.
The 2007 report of the Intergovernmental Panel on Climate Change
(IPCC) presents six scenarios with estimated sea level rises in the
range 0.180.59 m, i.e. a mean value of 0.35 m, by the end of the 21st
century.
Figures for increase in storm intensity are not given by IPCC but are
dealt with regionally. As an example a 2% and a 5% increase in signicant
wave height are predicted for the North Sea for years 2050 and 2100
respectively, STOWASUS (2001). This is due to foreseen higher average
wind velocities. However, related to storm wind velocities a 10%
increase, which will add approximately 0.3 m to the wind generated
set-up on a at coast, is expected. On sandy coasts the higher water
levels and the larger waves generally cause steepening of the coastal
prole and subsequent accelerated retreat of the coastline.
The paper presents a design exercise of the upgrade of one of the
most commonly used types of coastal protection structures, namely revetments with a sloping seaward front armoured with randomly placed
quarry rocks. The structures are typically used in more shallow waters
with depth limited design waves. The seabed can be both erodible and
resistant.
The paper presents several concepts of upgrading for conditions of
non-acceptable and acceptable increase in structure crest level. Specic
upgrade design of a shallow water conventional revetment is performed
assuming a sea level rise corresponding to the mean of the predictions
by IPCC. The performance of the upgraded structure is assumed unchanged compared to the existing structure.
Desk study tools for the design of conventional revetment and
breakwater structures are readily available but are not covering all
performance aspects related to upgrading. An example is the effects of
adding an extra armour layer. In the present design exercises are
therefore used modications of existing formulae. This introduces
extra uncertainty for which reason it is stressed that performance of
physical model tests is a necessity for the nal evaluation of the proposed upgradings. Numerical models are not applied in the present
paper because the available models, e.g. for armour stability, have not
yet been sufciently calibrated to cover the presented concepts of
upgrading.
A simple comparative cost optimization analysis of the various
upgrading solutions is presented. Finally safety aspects related to
113
climate change motivated upgrading are discussed including the potential of application of Levels 1, 2 and 3 design procedures.
2. Concepts of upgrading
114
4. Example application
A simplied desk study of the upgrading of two rock armoured rubble mound revetments is presented. The only difference between the
two cross sections is the toe structure which, in one example, is buried
and therefore has the crest in level with the seabed and, in the other
Table 1
Design hydraulic conditions and related performance for existing revetment.
Return period (years)
10
50
100
200
2.7
710
+1.0
4.0
2.45
0.4
0.9
0.0006
0.04
3.1
811
+1.3
4.3
2.73
1.2
1.2
0.001
0.3
3.5
912
+1.8
4.8
3.01
2.0
1.6
0.002
2
3.8
913
+2.1
5.1
3.27
3.0
2.1
0.004
7
4.0
1014
+2.3
5.3
3.44
3.9
2.4
0.005
17
4.1
1315
+2.4
5.4
3.53
4.4
2.6
0.006
29
115
Table 2
Design hydraulic conditions for the upgraded structure.
Return period (years)
10
50
100
200
2.84
711
+1.25
4.25
2.67
2.93
3.26
812
+1.60
4.60
2.93
3.23
3.68
913
+2.15
5.15
3.28
3.68
3.99
914
+2.50
5.50
3.47
3.83
4.20
1015
+2.75
5.75
3.70
4.12
4.31
1316
+2.87
5.87
3.83
4.21
200 years sea state. The actual structure performs somewhat better,
cf. the overtopping values given in Table 1. However, the admissible
discharges are used for the upgraded structures. We will for simplicity only consider the average discharge in this paper, but updated
tools for maximum overtopping volumes were developed in the
Theseus project, cf. Nrgaard et al. (2014).
The design hydraulic conditions and the related structure performance for the existing structure are given in Table 1. At the time of
the design the effects of climate change were not foreseen and are
therefore not included in wave heights and water levels.
The S-values correspond to the most critical Iribarren number for
which the armour stability is minimum, i.e. the transition between
plunging and surging waves. The average overtopping discharges are
determined by the EU-project CLASH Neural Network using the upper
values of the range of wave periods.
Fig. 4. Upgrading by adding an extra armour layer. Foreshore seabed slope 1:00.
116
Fig. 5. Upgrading by adding an extra armour layer and a wave wall extending 1.00 m over the armour crest level. Foreshore seabed slope 1:30.
Fig. 6. Upgrading by adding an extra armour layer on the front slope and on the crest plus increase in existing wall height by 1.00 m to crest level + 7.50 m. Foreshore seabed slope 1:30.
crest as shown in Fig. 6, but still the wave wall has to be raised by
1.00 m. The overtopping and the wave forces on the wall will be smaller
than for the upgrade shown in Fig. 5.
The performances of the upgraded structures are given in Table 3.
From Table 3 it is seen that the upgraded structures shown in Figs. 4,
5 and 6 rather closely satisfy the performance criteria dened in Table 1
for the existing structure. The exception is the armour damage in case of
a foreshore slope of 1:30 and application of P = 0.55. Only model tests
can verify the reduction in armour stability.
If an increase of the structure crest level is not acceptable, then the
most efcient solutions would probably be to add a high berm or to
place a low crested submerged breakwater on the foreshore cf. Fig. 2,
b) and c).
The 0.1% exceedance values of the 200 years return period wave induced forces and tilting moments on the walls, shown in Figs. 5 and 6,
are estimated by the upgraded Pedersen formula (Nrgaard et al.,
2014). The formula predicts the total horizontal force on wall front, FH,
the tilting moment around base front corner, MFH, and the pressure at
the base front, pb. The formula is valid only for Iribarren numbers
Table 3
Performance of upgraded structures with buried toe.
Return period (years)
10
50
100
200
0.8 1.4
1.0 1.7
1.9
2.3
2.6
3.1
3.1
3.7
3.1
3.7
0.005
4.4
5.3
0.008
5.0
6.0
0.010
0.16
0.26
0.30
below 4.5. For larger values the limitation Ru, 0.1%/H1/3 b 2.6 is used in
the calculations. The wave induced loadings are given in Table 4.
For the design of the wave wall superstructures in the upgraded
structures a target safety factor of 1.2 against sliding and overturning
for the 200 years return period sea state is assumed. In the stability calculations the following parameter values are used:
Friction coefcient for concrete slab against quarried subsoil, = 0.6
Mass density of concrete, c = 2300 kg/m3
Effective weight of soil material, = 11,000 N/m3
Passive earth pressure coefcient for quarried materials, rough wall
(Brinch Hansen), KY = 10
The 0.1% exceedance values of FH and pb do not occur simultaneously. In the stability calculations pb is reduced by 20% compared to the
Table 4 values.
The dimensions of the upgraded wall shown in Figs. 5 and 6 correspond to Tp = 13 s and to a safety coefcient of 1.2 against sliding
and overturning. Walls designed for Tp = 16 s will have approximately
25% larger volumes.
Table 4
Estimated 0.1% wave loadings on wave walls corresponding to 200 years return period.
Figure
Tp (s)
FH (kN/m)
MFH (kNm/m)
pb (kN/m2)
13
16
13
16
13
16
167
205
119
147
135
167
263
324
170
209
218
269
73.6
73.6
59.5
59.5
59.5
59.6
6
0.07
0.08
0.05
2.2
3.2
2.8
6.9
8.7
7.9
19
25
23
34
39
36
11
117
Fig. 7. Upgrading by adding an extra armour layer and a berm in order to avoid increase in structure crest level. Foreshore seabed slope 1:30.
It is assumed that the berm has to be made of the same size of stones
as used in the armour layers in order to obtain simplicity in construction. Two layers are applied for the berm.
The cross section is shown in Fig. 7.
The overtopping performance of the structure is given in Table 5.
It should be noted that according to Van Gent et al. (2013) it is possible to reduce the size of the armour on the slope above the berm. However, if doing so, the armour crest width of 7.5 m will be slightly reduced
and overtopping slightly increased. A related optimization has not been
performed. Neither, for reasons of missing readily available formulae,
has the optimization of the berm stones with respect to stability been
studied.
4.1.5. Upgrading of revetment by placing a submerged breakwater on
the foreshore
Fig. 2 c) shows the concept of using a detached breakwater to reduce the impact on the revetment by triggering wave breaking over
the breakwater. The 200 years return period sea state, which for the
1:100 slope foreshore is given by the incident signicant wave
height Hs,i = 3.83 m, the wave period T m 1,0 = 14.5 s, and the
SWL = + 2.87 m, is used for the design of the breakwater. If gaps
in the breakwater are not rather closely spaced, the wave breaking
over the breakwater causes a pile-up of the water, which is taken
as 0.1 Hs,i = 0.38 m, estimated from Fig. 13.31 in Burcharth et al.
(2007). This gives a SWL = + 3.25 m and a water depth of 6.25 in
front of the revetment. The energy on longer frequencies in the
wave spectrum of the incident waves are somewhat reduced by
the wave transformation over the breakwater, while relatively more energy will be present at higher frequencies. However,Tm 1,0 = 14.5 s is
on the safe side assumed maintained for the transmitted waves as
overtopping is almost entirely dependent on the lower frequencies.
The transmitted signicant wave height corresponding to the admissible overtopping of 40 l/sm, cf. 4.1.1 is determined by use of the EU
CLASH Overtopping NN to be Hs,t = 3.00 m. The related wave transmission coefcient is Ct = 3.00/3.83 = 0.78.
The needed freeboard of the detached breakwater is determined
by use of the wave transmission formula by Briganti et al. (2003) to
be Rc = 2.10 m, which corresponds to a crest level of + 2.87
2.10 = + 0.77 m + 0.80 m.
The size of the rock main armour is determined by the design formula for low-crested breakwaters in shallow water by Kramer and
Burcharth (2003) to be M50 = 5.5 t. For construction reasons the
thickness of the armour layer must correspond to either two or
three layers of stones. Fig. 8 shows both a solution with two layers
placed on a high toe, in which case the needed armour layer thickness corresponds to M50 = 7.5 t, i.e. a conservative size, and a solution with two layers, in which the needed armour layer thickness
Table 5
Overtopping performance for structure upgraded by adding an armour layer and a berm.
Return period (years)
10
50
100
200
0.08
2.9
7.4
20
33
corresponds to M50 = 5.5 t. The rst solution makes easy construction directly on the seabed possible. The other solution demands
excavation for the buried lter layer and toe, but is a more stable
solution in case of further seabed erosion.
The distance between the breakwater and the revetment would be
approximately 20 m.
4.2. Existing revetment with a high toe
Fig. 9 shows an existing revetment with a toe berm extending 1.2 m
over the seabed. The increase in wave impact makes it necessary to
strengthen the toe in the upgraded structure. Upgrading by adding an
extra armour layer on the front slope and on the toe berm is an obvious
solution, but for structures in shallow water the increase in toe berm
level increases overtopping and reduces the toe armour stability as
will be demonstrated in the following. If instead the toe berm is lowered
by digging the toe into the sea bed, then smaller toe stones would be
sufcient and overtopping will be reduced. However, the construction
will be much more difcult and expensive.
In general, upgrading by adding height to a toe berm is not a very
efcient solution for structures in shallow water as the higher toe demands larger stones, and the overtopping will increase.
The design hydraulic conditions and the performance of the structure are as given in Table 1 for the structure with the buried berm
because the relative small toe berm height of 1.2 m does not change
armour stability and overtopping performances signicantly. Only the
stability of the 0.30.7 t rock toe is less. Actually the shoulder of the
toe berm is rounded in the case of foreshore slope 1:100, and is eroded/attened in the case of foreshore slope 1:30, but the toe berm is
still supporting the main armour.
4.2.1. Upgrading of revetment with high toe by adding armour layer
The performance criteria for the upgraded structure given in 4.1
and the related environmental design condition given in 4.1.1 are
maintained.
As the rst obvious concept for upgrading the addition of an armour
layer on the front slope and on the toe berm is chosen. As no applicable
formula for the inuence of a relatively high berm on the main armour
stability is available, it is assumed that the stability given in Table 3 for
the structure with a buried toe is valid. For the toe berm it would be
preferable to use only one layer of stones in order to keep the height
of the berm as low as possible. However, the stability of such a toe
would have to be determined in model tests because generic formulae
and design diagrams for the stability exist only for toe berms consisting
of two or more layers of stones. In the present desk study two-layer
berms are therefore used.
Calculations by use of the Van der Meer (1998) and the Muttray
(2013) formulae as well as data given in Fig. 2 in Baart et al. (2010)
show that berm stones of 24 t with M50 = 3.0 t, Dn50 = 1.04 m
and berm height 2.08 m will be stable in case of foreshore seabed
slope 1:100, but for foreshore seabed slope 1:30 it is necessary to
use 46 t stones with M50 = 5.0 t, Dn50 = 1.24 m and berm height
2.5 m.
118
Fig. 8. a (upper). Fig. 8b (lower). Protection of the revetment by detached breakwater. Foreshore seabed slope 1:00.
Fig. 9. Existing revetment with a high toe berm. Seabed slope 1:100.
Fig. 10. Two solutions for upgrading: One (a) by adding an armour layer on the front slope, the other (b) by adding an armour layer both on the front slope and on the crest.
Fig. 11. Upgrading by adding an armour layer on the front slope and on the crest combined with a wave wall raised to armour crest level.
119
Table 6
Performance of upgraded structures with high toe berms.
Return period (years)
Toe damage. Fig. 10. Foreshore slope 1:100
Nod (Fit to slope 1:50 data in Fig. 2 in Baart et al., 2010)
Nod (Muttray, 2013)
Toe damage. Fig. 11. Foreshore slope 1:30
Nod (Van der Meer, 1998)
Nod (Fit to slope 1:20 data in Fig. 2 in Baart et al., 2010)
Nod (Muttray, 2013)
Average overtopping discharge (l/sm)
Foreshore slope 1:100, Fig. 10 a (left)
Fig. 10 b (right)
Foreshore slope 1:30, Fig. 11
10
50
100
200
0.03
0.62
0.06
0.92
0.07
1.07
0.06
1.19
0.06
1.28
0.13
0.10
0.56
0.29
0.46
0.85
0.35
0.19
1.0
0.39
0.24
1.1
0.43
0.22
1.2
0.04
0.03
0.03
1.3
1.5
1.8
4.2
5.0
5.2
11
15
16
21
27
26
Fig. 12. Upgrading of structure with high berm by adding an armour layer and a berm in order to avoid increase in structure crest level. Foreshore seabed slope 1:30.
Table 7
Overtopping performance for structure upgraded by adding an armour layer and a berm.
Return period (years)
10
50
100
200
0.09
4.0
10
26
41
120
Fig. 13. Detached breakwater for protection of revetment. Foreshore seabed slope 1:30.
Table 8
In-place bulk volume unit construction costs for materials handled by land-based equipment.
Main armour (EUR/m3)
Shingle layer
Concrete wall
5.5 t
7.5 t
13 t
3.0 t
5.0 t
7.5 t
(EUR/m2)
(EUR/m2)
(EUR/m3)
60
65
70
55
60
65
50
30
350
Table 9
Volumes of structure parts.
Figure
4
5
6
7
8a
8b
10a
10b
11
12
13
7.5 t
Toe/berm (m3/m)
13 t
3.0 t
5.0 t
7.5 t
23.98
23.98
32.92
48.98
25.76
40.66
20.95
29.02
30.09
42.45
7.35
7.35
10.00
64.52
Filter layer
Shingle layer
Concrete wall
(m2/m)
(m2/m)
(m3/m)
2.52
2.52
2.52
7.52
23.20
23.28
6.02
6.02
6.62
7.71
28.05
4.69
4.69
4.69
9.68
26.20
26.07
4.32
4.32
4.84
7.72
30.77
11.45
6.63
7.33
The estimated construction costs are given in Table 10 as function of foreshore seabed slope, type of toe and allowable increase in structure crest level.
Table 10
Construction costs of upgrading in EUR/m of structure.
Foreshore slope
Toe type
1:100
Buried
High
1:30
Buried
High
1.825
4.525
5.483
4.525
5.483
2.197
3.850
3.376
8.553
2.721
5.833
4.727
5.548
Inuence on upgrading
Very large
Environmental changes
Water level
Wave height (wave period)
Wind velocity
Subsequent morphological changes
Structure responses, by formulae etc.
Armour stability
Toe stability
Detached breakwater stability
Overtopping
Wave wall stability
Large
Moderate
Small
x
x
x
x
x
x
x
x
x
x
x
x
121
Increase in the crest level of the revetment by adding an extra armour layer on the crest and/or installing a wave wall seems unnecessary
and not economically feasible compared to the solution described above.
Upgrading by installing a detached breakwater in front of the revetment seems signicantly more expensive than other upgrading concepts.
The overall conclusion of this specic study is that the anticipated
climate change does not impose a big problem as the structure can easily be upgraded at moderate costs.
The study reveals a lack of desk study design tools related to structure upgrading e.g. for the prediction of the stability of slopes upgraded
by adding extra armour layers, and for the prediction of the related
overtopping. At present it is absolutely necessary to perform physical
model tests along with the design work and not solely after as verication model tests.
Acknowledgement
The support of the European Commission through FP7. 20091, Contract 244104-THESEUS (Innovative technologies for safer European
coasts in a changing climate) is gratefully acknowledged as is also the
assistance of Jorgen Q. H. Nrgaard in calculating wave forces on wave
walls.
References
Baart, S., Ebbens, R.E., Nammuni-Krohn, J., Verhagen, H.J., 2010. Toe rock stability for rubble mound breakwaters. Proc. 32 International Conference on Coastal Engineering,
Shanghai, China.
Briganti, R., Van der Meer, J.W., Buccino, M., Calabrese, M., 2003. Wave transmission
behind low crested structures. Proc. Coastal Structures, ASCE, Portland, Oregon,
US.
Burcharth, H.F., Sorensen, J.D., 2000. The PIANC safety factor system for breakwaters. In:
Losada (Ed.), Proc. Coastal Structures '99, Santander, Spain. Balkema, Rotterdam,
pp. 11251144.
Burcharth, H.F., Hawkins, S.J., Zanuttigh, B., Lamberti, A. (Eds.), 2007. Environmental Design Guidelines for Low Crested Coastal Structures. Elsevier.
Ebbens, R.E., 2009. Toe structure of rubble mound breakwaters. (MSc. Thesis) Delft University of Technology, The Netherlands.
Gerding, E., 1993. Toe stability of rubble mound breakwaters. (MSc. Thesis) Delft University of Technology, The Netherlands.
Kramer, M., Burcharth, H.F., 2003. Stability of low-crested breakwaters in shallow
water short crested waves. Proc. Coastal Structures, ASCE, Portland, Oregon,
USA, pp. 137149.
Muttray, M., 2013. A pragmatic approach to rock toe stability. Coast. Eng. 82, 5663.
Nrgaard, J.H., Lykke Andersen, T., Burcharth, H.F., 2014. Distribution of individual
overtopping wave volumes in deep and shallow water wave conditions. Coast. Eng.
83, 1523.
STOWASUS, 2001. Regional storm, wave and surge scenarios for the 2100 century.
Denmark's Climate Center Report 0103. DMI.
Van der Meer, J.W., 1988. Rock slopes and gravel beaches under wave attack. Delft
Hydraulics Communication. . , No. 396.
Van der Meer, J.W., 1998. Geometrical design of coastal structures. In: Pilarczyk, K.W.
(Ed.), Dikes and revetments. Balkema, Rotterdam.
Van der Meer, J.W., d'Angremond, K., Gerding, E., 1995. Toe structure stability of
rubble mound breakwaters. Proc. Advances in Coastal Structures and Breakwaters Conference, Institution of Civil Engineers. Thomas Telford Publishing,
London, UK, pp. 308321.
Van Gent, M.R.A., Van den Boogaard, H.F.P., Pozueta, B., Medina, J.R., 2007. Neural network
modelling of wave overtopping at coastal structures. Coast. Eng. 54, 586593.
Van Gent, M.R.A., Smith, G.M., Van der Werf, I.M., 2013. Stability of rubble mound breakwaters with a berm: the upper slope. Proc. 33 International Conference on Coastal
Engineering, Santander, Spain.
Weisse, R., Bellaore, D., Menndez, M., Mndez, F., Nicholls, R.J., Umgiesser, G.,
Willems, P., 2014. Changing extreme sea levels along European coasts. Coast.
Eng. 87, 414 (in this issue).