Hi-LITE Mall -ELECTRICAL Incomplete Works.

Sl
No.

Location

Issue

Sub station

Earth Pit not yet commissioned and kept in an open


condition

D.G room

floor epoxy painting work is not completed and air filters


are getting choked

3
4
5

HSD service tank


area
Substation
Substation

diesel transfer pump supply socket is kept in open


condition with no enclosure.need to give proper covering .
no back up supply for 6kva ups in substation
floor epoxy painting need to do

Substation

all the ACB breakers UV RELAY not yet connected. Still


Breakers are not working Properly.

Diesel service tank


D.G room
D.G room
D.G room

need to fix a calibrated gauge scale for service tank


no illumination provided
battery charger not yet provided for all d.g s
no fire standards provided inside d,g room

8
9
10
11

12 Diesel pump

diesel transfer pump kept above a disel barrel .need to fix


on a permanent platform and permanet G.I line to be lined
to tank

13 Diesel

no permanet platform for diesel unloading and barrel are


getting damged

14 Basement 3

fresh air,exhaust,gas fan cabling work not completed and


not yet commissioned

Emergency plant
15 room

WTP electrical panel not commissioned

16 Basement -3

still on temporary connection.work under progress and


cables lying are not properly dressed

17 Basement -3

there is no power socket(single and 3 phase) connection


provided for any kind of maintanance work in future

18 Basement -3

there is no water connection point given for maintanance


in future

19 Basement -2

there is no power socket(single and 3 phase) connection


provided for any kind of maintanance work in future

20 Basement -1
21 Ground floor

exterior focussing illumination light should be provided


with a permanent power connection
entrance one ckt foot light ckt not working

GF to base 1
22 Ramp(exterior)
23 Ground floor

wall fixed foot lights are not working


UPS pm is pending

24 Ground floor

sockets with no power supply:- near PUMA shop,near


SPLASH,near DANIEL HETCHER ,near passenger lift

25 1st floor

sockets with no power supply: near MAX,near OPTIC ZONE

26 2nd floor

sockets with no power supply: near MAX,near LEE FOOT


,near wash room

27 3rd floor

sockets with no power supply: near BARBIQUE. socket


directly mounted on wall

28 Basement 1

no energy meter provided seperately for lift,escalator,fire


system,WTP

29 Terrace

no energy meter provided for chiller.

Floor
30
31 Floor
32 Cooling tower area

all floor csu are connected from common area lighting


panel MLT3B.
floor wise separate energy meter not fixed
no illumination provided

33
34
35
36
37
38

no illumintaionin in entire trerrace area and point also not


given
no lighting yet provided
IBS room debris not cleared.
not yet connected in all mall area
ventillation work not yet completed
one lift near lifestyle not yet commissioned

Terrace area
All AHU rooms
Basement 1
CCTV camera
Electrical rooms
Service lift

39 Electrical rooms
40 Substation

MLT1 electrical cabling work under progress and smoke


detecters are fixed
electrical total load balancing not completed .

41 D.G

Air compresser need to order for cleaning the radiater

42 Electrical panel
43 Stair Case No.2

electrical mats need to be placed in all electrical panels


There is no lighting supply given.

44 Exit Gate No.2

Lighting cables are provide but there is no light fixture.

45 Common

Need to purchase hydraulic ladder to repalce fuse lights.

46 Common area

Most of pillar focus LED lights are not working.

47 Substation, Electric
Rooms

Some panels CT's are not fixed.

48 Shops

Major Anchor shops not fix in Energey Meter (Fbb,I am In,


Baby Care, Malabar Fresh ) and other shops (Fazal Bag,
Paont ball).

49 Basement -3

All the Sumps need to connect with submergible pump with


starter panel to be connected to common Drain.

50 Substation

All the ABB breakers need to do preventive maintenace.

51 Pump Room
52 Parking Area

WTP pumps need to be connected with level controls.


Fire Exits signag need to fix with battery Back-Up.

e Works.

Remarks

Done

Done
Done

Done
Done

Chiller#1, Chiller#2 & MCC Panel#2 is


done. Need MCC Panel#1

Done
Done

Cabling work completed. But Smoke


detecter fixing still pending.
Under Progress.

Done

Done

24
25
26
27
28

Ground floor
1st floor
2nd floor
3rd floor
Basement 1

sockets with no power supply:near PUMA shop,near SPLASH,near DANIEL HETCHER ,near
passenger lift
sockets with no power supply: near MAX,near OPTIC ZONE
sockets with no power supply: near MAX,near LEE FOOT ,near wash room
sockets with no power supply: near BARBIQUE. socket directly mounted on wall
no energy meter provided seperately for lift ,escalater,fire system,WTP