Beruflich Dokumente
Kultur Dokumente
ELSEVIER
www.elsevier.com/locate/desal
Abstract
In order to investigate the possible approach to increase thermal efficiency of desalination plants, decrease water
production costs and further optimize the coupling design of a nuclear heating reactor (NHR) with the desalination
process, the coupling schemes of NHR reactors with hybrid desalination technologies were investigated. The
cogeneration operation mode was adopted in this investigation. Two coupling schemes were selected for the cogeneration mode: NHR + low-temperature MED+RO and NHR + low-temperature MED+MEDNC. Technical
specifications and economic aspects of the investigation are briefly presented in this paper.
Keywords: Nuclear heating reactor; Coupling; Hybrid desalination technologies
1. Introduction
Small- and medium-sized seawater desalination plants using a nuclear heating reactor
(NHR) coupled with a MED process could be a
suitable solution to supply potable water to some
coastal districts, islands or countries with a small
or medium population due to their perfect
inherent safety, simplicity in structure, proven
technology [ 1-3], and acceptable investment and
water costs. The results of the study of the technical and economical aspects for a desalination
*Corresponding author.
0011-9164/03/$- See front matter 2003 Elsevier Science B.V. All rights reserved
PII: S 0 0 1 1 - 9 ! 6 4 ( 0 3 ) 0 0 2 9 5 - 9
180
Table 1
Design parameters of heating reactor NHR-200 coupled
with selected hybrid desalination process
Table 2
Design parameters of a desalination plant with the
NHR-200 coupled with the LTMED and RO process
Design parameters
Values
Parameters
Operation mode
Reactor power, MWt
Pressure in the primary circuit, MPa
Core outlet temperature, C
Core inlet temperature, C
Pressure in the secondary circuit, MPa
Outlet temperature of the secondary
circuit, C
Inlet temperature of the secondary
circuit, C
Outlet steam temperature of the
steam generator, C
Inlet steam pressure in turbine, MPa
Inlet steam temperature in
turbine, C
Back pressure of the turbine, MPa
Inlet steam temperature in
LTMED, C
Electricity production, MW
Co-generation
200
3.0
223
164
3.5
165
152
147
0.416
145
0.101
100
14.42
utilization o f thermal energy at a higher temperature range would reach higher efficiency.
Therefore, the design pressure and temperature at
the primary circuit of the heating reactor were
increased to 3.0 MPa, and 223C, respectively.
All other parameters concerned with the reactor
safety features were maintained. The design
parameters of the NHR with co-generation mode
are listed in Table 1 for the two coupling
schemes that were selected: (a) NHR + low
tempera-ture MED+RO and (b) NHR + low
temperature MED+MED/VC.
The technical specifications and economic
aspects of the investigation are briefly presented
in this paper.
Values
200
147
0.416
145
330
0.101
14.42
100
75
126,000
21,000
6
36,000
12,000
3
1000
8
100
181
I
/!tITlll
-x,
r
_
Fig. 1. Coupling scheme of the NHR with LTMED and RO processes. 1 reactor core, 2 primary heat exchanger, 3 steam
generator, 4 steam turbine, 5 RO unit, 6 LTMED unit.
LTMED process, but part of the pre-heated brine
from LTMED was used as the feed seawater to
the RO units. The produced electricity by the
turbine generator of the nuclear plant was used to
supply power to the motor of the high-pressure
pump in the RO unit and the nuclear power plant
itself.
The total capacity of the selected RO process
depends on the maximum electricity production
of the NHR plant, and the number of RO unit
depends on the available unit capacity of RO
process. Design parameters of the hybrid
desalination plant with LTMED and RO process
are listed in Table 2. The distribution method for
the electricity cost and heat charge in the cogeneration plant was considered as following.
The total steam cost of the co-generation nuclear
plant should be divided into two parts: total
annual electricity cost for the RO process and
heat charge for the MED process. Here the
electricity price is assumed as 0.044 US$/kWh.
Based on this electricity price and the total
electricity production of the nuclear plant, the
total annual electricity cost was deducted from
182
Table 3
Results of preliminary economic analysis for the coupling scheme of the NHR-200 with the LTMED and RO processes
Parameters
Values
200
8
130.24
48
13.28
143.52
12.47
4.1
4.73
0.52
22.09
2,601,720
113,687,280
5,002,240
6.568
Desalination process:
Total capacity, m3/d
Capacity per unit, m3/d
Number of desalination units
Specific investment, US$/m 3
Investment per unit, MUS$
Total investment of desalination plant, M US$
BOW per unit, MUS$
Total investment including BOW, MUS$
Availability, %
Total production per day, m3/d
Annual water production, m3/y
Time of operation, y
Interest, %
Depreciation of capital cost, US$/m3
Operational costs:
Membrane replacement, US$/m 3
O&M labour & materials cost, US$/m3
Chemicals, US$/m3
Steam price, US$/t
Steam consumption per unit, t/h
Steam charge per 1 m3 of product, US$/m 3
Electricity price, US$/kWh
Electricity consumption, kWh/m3
Electricity charge per 1 m3 of product, US$/m 3
Labor, US$/m 3
Total operational costs, US$/m3
Total water cost, US$/m3
RO
LTMED
36,000
12,000
3
790
9.48
28.44
126,000
21,000
6
809.5
16.0
96.0
1.0
102.0
95
119,700
43,690,500
20
7
0.22
95
34,200
12,483,000
20
8
0.22
0.025
0.0374
0.065
0.044
3.01
0.133
0.014
0.318
0.538
0.02
0.05
6.568
55
0.41
0.044
1.59
0.06
0.01
0.55
0.77
183
Table 4
Design parameters of a desalination plant with the
NHR-200 coupled with LTMED and MED/VC processes
Parameters
Values
200
147
0.416
145
330
0.101
14.42
100
75
126,000
21,000
6
36,000
4,000
9
F
i
Se~w~ ter
If ....I.........
.~
Brine o~t
Fig. 2. Coupling scheme of NHR with LTMED and MED/VC. 1 reactor core, 2 primary heat exchanger, 3 steam generator,
4 steam turbine, 5 steam compressor, 6 VC/MED unit, 7 LTMED unit.
184
Table 5
Results of preliminary economic analysis for the coupling scheme of the NHR-200 with the LTMED and MED/VC
processes
Parameters
Values
200
8
130.24
48
13.28
143.52
12.47
4.1
4.73
0.52
22.09
2,601,720
113,687,280
5,002,240
6.568
Desalination process:
Total capacity, m3/d
Capacity per unit, m3/d
Number of desalination units
Specific investment, US$/m3
Investment per unit, MUS$
Total investment of desalination plant, MUS$
BOW per unit, MUS$
Total investment including BOW, MUS$
Availability, %
Total production per day, m3/d
Annual water production, m3/y
Time of operation, y
Interest, %
Depreciation of capital cost, US$/m3
Operational costs:
Maintenance
Chemicals, U S $ / m 3
MED/VC
LTMED
36,000
4,000
9
85O
4.0
27.0
0.4
30.0
95
34,200
12,483,000
20
7
0.23
126,000
21,000
6
809.5
16.0
96.0
1.0
102.0
95
119,700
43,690,500
20
7
0.22
0.02
0.05
6.568
1.3
0.07
0.044
8.00
0.352
0.01
0.502
0.732
0.02
0.05
6.568
55
0.41
0.044
1.59
0.06
0.01
0.55
0.77
185
Acknowledgements
This paper is based on research work
supported by the CRP of the International Atomic
Energy Agency.
References
[1] D. Wang and D. Dong, The 5 MW nuclear heating
test reactor, Nuclear Power Engineer-ing, 11(5)
(1990) 8-14 (in Chinese).
[2] D. Dong, S. Wu and D. Zhang, Comprehensive
utilization of the nuclear heating reactor, J. Tsinghua
Univ. (Science and Technology), 34(ES2) (1994)
32-38.
[3] Nuclear Desalination Project in Morocco, IAEATECDOC-898, Aug. 1996, pp. 105-106.
[4] S. Wu and D. Dong, Seawater desalination plant
using nuclear heating reactor coupled with MED
process,Nuclear Sci. Techniques, 11(1)(2000) 6-12.
[5] S. Wu and W. Zheng, Coupling of nuclear heating
reactor with desalination process, Desalination, 142
(2002) 187-193.