MEMORIA DE CALCULO CASETA

1.1
1.2
1.3
1.4
1.5
1.6
1.7

limpieza y descapote (M2) = 18 *20 = 360m2


cerramiento provisional (M2) =18+18+20+20 =76ml
campamento provisional (m2) = 6*8 =48m2
localizacin y replanteo (M2) = 2.50*3.75 =9.37m2
red provisional acueducto (Mes) = 3meses
red provisional energa (Mes) (segn duracin de obra)
red provisional alcantarillado (Ml) = 11ml

2.1 Excavacin manual


- zapatas
- viga de cimentacin
- tubos
- caja de inspeccin

ZAPATAS
0.6*0.6*0.8 = 0.28m3
0.28m3*4zapatas = 1.12m3

TUBOS 2
(0.89+1.04)0.30*0.70 = 0.48M3
TUBO 3
2.19*0.30*0.70 = 0.45M3
VIGAS #1
(1.7*0.20*0.5)2vigas
(0.17m3)2vigas = 0.34m3
VIGAS # 2
(2.90*0.20*0.5)2vigas
(0.29)2vigas = 0.59m3
CAJADE INSPECCION
1*1*0.80 = 0.8M3
SUMA = 1.12+0.45+0.34+0.59+0.8 = 3.78M3

2.2 RELLENO
-ZAPATAS (relleno zapatas +relleno columnas)
1.12m3 (0.432+0.025)
1.12m3- (0-457m3) = 0.663m3
VIGAS 0.34+0.59 (Relleno vigas #1 +Relleno viga#2
(0.93m3)-(0.136+0.232) (0.93)-(0.368) = 0.562m3
- CAJA- o.8m3-(relleno de caja)
O.8m3-(0.7) = 0.1m3
- TUBOS- (0.48+0.45)-(ocupacin tubo)
(0.93)-(0.019) = 0.91m3
SUMA = 0.663+0.562+0.1+0.911 = 1.4161M3

2.3 RELLENO DE SOBRANTES


SUMA = 0.457+0.368+0.7+0.019 = 1.544m3

2.4 SOLADO. (Zapata y vigas)


(0.6*0.6)+ (0.2*1.17)+ (0.2*0.9)
(0.36*4Zapatas)+ (0.34*2vigas)+ (0.58*2vigas)
(1.44)+ (0.68) + (1.16) = 3.28m2
0.14

0.14

3. REFUERZOS
0.7

3.1 Refuerzos 3/8

0.14

0.19

Estribos
0.14

Vigas

.columnas

Despiece estribos
de vigas.

0.7

.vigas

Despiece estribo
de columna

0.7

3.2 Refuerzos

0.14

.losa cubierta
1.76
Despiece viga#1
refuerzo.

0.7

0.7

2.96
Despiece viga#2
refuerzo.

3.1 REFUERZOS 3/8 = 0.56kg

estribos columna

- estribos columna

SUMAS= 7+19+14+19+14+7 = 80cm = 0.80mL

- estribo vigas

H =3.5M

- mallas

3.5/0.15=24+1=25 estribos*columnas
25*4Olumnas = 100
0.80*100=80---0.56g*80= 44.8kg

VIGAS # 1

0.1

0.1

SUMA= 7+14+14+14+14+7 = 0.70Ml


1.70/0.150 12+1= 13 Estribos*Viga
13*2Vigas= 26estribos
0.70*26=18.2--- 18.2*0.56 = 10.19kg

3.52

3.50

VIGA #2
-

7+14+14+14+14+7 = 0.70ml
2.90/0.15=20+1= 21 Estribos*viga
21*2vigas = 42 0.70* 42 = 29.2ml
29.4*0.56 = 16.46kg

MALLA Refuerzos verticales y horizontales


0.50*8= 4m*4= 16ml
16*0.56= 8.96kg
SUMA 3/8= 44.8+10.19+16.46+8.96 = 80.41Kg

0.2

0.2

3.2 REFUERZOS =1kg


. Vigas
. Columnas
. Losa cubierta
VIGA #1

VIGA #2

1.90ml*4=7.6ml*2vigas = 15.2

3.10*4=12.4*2Vigas = 24.8ml

15.2*1kg = 15.2kg

24.8*1kg = 24.8kg

COLUMNA
SUMA= 0.10+3.52+0.20+0.20+3.50.0.10 = 7.62ml
7.62*2= 15.24ml
15.24*4columna =60.69ml
60.69*1kg = 60.69kg

LOZA CUBIERTA
-

4ML * 2= 8ML8*2Lozas = 16ml


16*1kg = 16kg

SUMA =15.2+24.8+60.69+16 = 116.69kg

4. ESTRUCTURA CONCRETO.
4.1 Columnas (0.25*0.20*3.50)4columnas
(0.175)4Columnas = 0.7m3

4.2 Vigas #1 (0.20*0.20*1.70)2vigas


(0.068)2vigas = 0.136m3
Vigas #2 (0.20*0.20*0.29)2 vigas
(0.116)2vigas = 0.232m3

4.3 Caja de inspeccin (1*1*0.07)4muros


(0.07)4muros = 0.28m3

SUMA = 0.136M3 + 0.232M2


= 0.269M3

4.4 Cubierta (2.10*2.95*0.1)2lozas


(0.6)2lozas = 1.23m3

4.5 Zapatas (0.6*0.6*0.3)4zapatas


(0.108)4zapatas = 0.432m3

SUMA= 0.7+0.136+0.232+0.28+1.23+0.432 = 3.01 m3

5. IMPERMEABILIZACIONES.
- Zapatas
- Vigas
- Caja de inspeccin
- Cubierta

ZAPATAS = (0.6*0.3)4capas
(0.18)4caras
0.72m2 * 4 zapata = 2.96m2

VIGA #1 (0.2*2.20)4Caras
(0.44)4cras
(1.76*2vigas)= 3.52m2
VIGA #2 (0.2*3.25)4Caras
(0.65)4Caras
2.6*2 vigas = 5.2m2

SUMA = 2.96+3.52+5.2 = 11.68

CAJA DE INSPECCON (1*0.7)4Caras


(0.7m2)4Caras = 2.8m2

CUBIERTA (2.10*2.95)2Losas
(6.195) 2Losas = 12.39m2

6. DESAGUES EN TIERRA
. Tierra sanitaria
-

3=2.19ml
2=2.29ml
Codo 3=(1unidad)45
Codo 2= (2unidad)45
YEE 2= (2unidad)

7. INSTALACIONES HIDROSANITARIA
7.1 Punto hidrulico = (3unidades)
7.2 Bajantes aguas negras = (unidad)

8. INSTALACIONES ELETRICAS
8.1 Salida de lmparas = (3 unidades)
8.2 Salida de toma corriente = (3unidades)
8.3 Salida para tv = (1 unidades)

9. MAMPOSTERIA
9.1 Muro ladrillo farol (fachada)
-- 8.04m2+3.43m2+9.83m2 = 28.16m2

9.2 Calados 0.20m2+ 1.89m2 + 0.81m2 = 3m2

SUMA = 2.96+3.52+5.2+2.8+12.39
= 26.87M2

10. REPELLOS / REVOQUE / PAETES

10.1Muros / exterior
= 5.26m2+9.18m2+7.29m2+2.46m2 = 24.29m2
-

Interiores

5.26m2+9.18m2+7.29m2+2.46 = 24.29m2

SUMA = 24.29m2+24.29m2 = 48.38m2

10.2 cielo razo


- (2.10*1.75) 2 losas
(3.67m2)2 losas = 7.35m2

11. BASES Y PISOS


-- Losa bloquelon arcilla = 9.1m2
-- Mortero nivelacin losa = 12.04m2
-- Borde ducha = 1.50ml

12. METALES Y CARPINTERIA


-- Perfil metlico losa bloquelon arcilla = 11.6ml
-- Puerta aluminio = 1.95m2

-- puerta bao = 1.60m2

-- Marco aluminio =5.20ml

-- Marco =4.20ml

13. ENCHAPE
13.1 Enchape para bao cermico
-- granito gris 30*30 (revestimiento)
-- 21 m2+3.15m2+2.17m2 = 7.42m2

14. ESTUCO Y PINTURA


- estuco muros (interior) = 48.38m2
-Estuco cielo Razo = 7.35 m2
- Pintura muros exteriores koraza = 24.29m2
- pintura carpintera metlica en esmalte
= puerta = 1.95 + = puerta baos = 1.60= SUMA
= merco = 5.2ml+ =marco= 4.80ml = SUMA
- Pintura muro 2manos = 24.29m2ra
- Pintura cielo Razo 2 manos = 7.35m2

15. APARATOS SANITARIOS


- Sanitario mazdra redondo corona 0 (1unidad)
- Lavamanos ovalin blanco (42*16) corona (1unidad)
- ducha sencilla corona = (1unidad)

16. ESPEJOS Y VIDRIOS


-- Espejo baos (2.70*0.50)

17. EQUIPO Y HERRAMIENTAS


-- equipo menor (martillo, cerrucho , palas . etc) = das
-- equipo de compactacin = das
-- equipo de fontanera = das

18. ASEO Y LIMPIEZA


-- ASEO GENERAL DURANTE OBRAS =468